Comments of the Illinois Commerce Commission in support of PJM Interconnection, L.L.C.’s 07/31/2026 filing
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3380-000
ILLINOIS COMMERCE COMMISSION
COMMENTS
Pursuant to the Notice of Filing issued August 3, 2026, setting August 21st as the Comment date in this docket, the Illinois Commerce Commission (“ICC”) respectfully submits these comments in support of PJM Interconnection, L.L.C.’s (“PJM”) July 31, 2026, filing proposing revisions to the Open Access Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish a Reliability Backstop Procurement (“RBP”) addressing resource adequacy and large loads.1 The ICC submitted a notice of intervention in this docket on August 5, 2026, and, therefore, it is a party in this docket. The ICC generally supports PJM’s proposal to implement a one-time, supplemental procurement of new capacity to address the identified resource adequacy shortfall that aligns with the National Energy Dominance Council/PJM Governors’ Principles and the Commission’s recognition of the need for action. The proposed one-time actions strengthen regional resource adequacy. While appropriately recognizing that implementation may require complementary state action to ensure that RBP costs are allocated to the appropriate retail loads, the ICC does
1 1 PJM Interconnection L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, Docket No. ER26-3380-000 (July 31, 2026) (“Backstop Filing”).
PDF page 2
2
have some implementation concerns, particularly for retail access states like Illinois. The ICC recommends that the Commission require sufficient mitigation efforts to protect against cost shifts to or any negative impacts on existing ratepayers, impose no new obligations upon the states, and require PJM to provide the clarifications, transparency, and access to data as discussed herein.
I. COMMENTS
A. The Core Elements of PJM’s Reliability Backstop Procurement Proposal are
Generally a Just and Reasonable Approach to Assigning Costs While Maintaining Reliability
Given the time constraints under which PJM is operating, PJM’s RBP proposal is a reasonable path forward to secure much needed capacity for the footprint. As PJM notes in its transmittal letter, capacity shortfalls have appeared over the last two capacity auctions.2 PJM’s market faces a host of difficulties in meeting its capacity needs, most notably a sudden increase in load due to rapid and large data center growth in the footprint in addition to persistent interconnection delays for new generation, supply constraints, and permitting and siting delays. To address this capacity shortfall, PJM developed a plan to bring more generation online. At its core, PJM’s recommendation is a two-phase procurement process. The first phase is bilateral contracting, followed by central procurement. PJM’s development of a more robust bilateral matchmaking phase, with assistance from Charles River Associates, is a particularly well-designed method for meeting capacity needs. Bilateral contracts provide new load with an opportunity to purchase capacity and address the shortfall to which they directly contributed. Further, bilateral contracting protects ratepayers and assigns costs directly to those most
2 Backstop Filing, at 7, 27.
PDF page 3
3
responsible for cost increases. As we understand it, this bilateral matching process has already begun and is ongoing.
The second phase is the proposed RBP to address the capacity shortfall. PJM is setting the procurement target based on the region-wide Unforced Capacity megawatt (“MW”) quantity that cleared short of the Reliability Requirement in the July 2026 Base Residual Auction for the 2028/2029 Delivery Year. Resource eligibility requirements for the RBP ensure that the procurement is more likely to bring on new generation by outlining what resources can participate in the procurement. New resources included those that have not committed their capacity previously, uprates with an affiliated increase in Capacity Injection Rights, and incremental capacity created by utilizing Supplemental Interconnection Service. PJM’s RBP approach has two particularly insightful features. First, PJM’s RBP methodology insists on only new generation participating. This prevents existing generation resources from being purchased away from extant load. Second, PJM’s approach also makes full use of the existing transmission system. This allows new resources to come online more quickly, showing PJM’s awareness of the time constraints under which they are operating. In addition to these core features, PJM’s RBP solution includes a number of other beneficial aspects. For instance, the ICC appreciates the Large Load Registry, which will improve transparency in the backstop procurement processes, which PJM filed separately in Docket No. ER26-3515-000 on August 13, 2026. Additionally, PJM set an appropriate definition for New Large Loads as end-use customer load that has a cumulative peak load quantity greater than or equal to 50 MW. The ICC also appreciates PJM’s attempt to mitigate gaming by New Large Load customers. PJM clarified in its definition that if a load increases its peak demand after June 1, 2027, including any new incremental load that causes an existing load
PDF page 4
4
to meet the Large Load definition, the new large load definition applies. This should discourage gaming by New Large Load customers.
While PJM’s general procurement strategy makes sense, the proposal does not include measures to mitigate errors in forecasting and related prices. It is hard to overstate the significant increase in load forecast compared to prior years. After years of nearly flat load growth, PJM expects load growth to average 5.3% over the next 10 years and 3.4% over 20 years. By 2036, total PJM energy is forecasted to be over 1.4 million GWh - a nearly 600,00 GWh increase.3 Historically, PJM tended to over-procure capacity: from the 2018/2019 to the 2022/2023 planning years, PJM purchased 8,066MW-11,912MW of excess capacity each Planning Year. This was excess capacity in the order of 5-8% over PJM’s Installed Reserve Margin (IRM).4 When forecasts are off, even by a small percentage, the error has a significant impact on both the amount of MWs needed and prices for capacity.
The PJM proposal does not include any mechanism to moderate any potential error, such as cost reconciliation. Even where overall cumulative regional forecasts remain roughly accurate, failure to accurately forecast the locations where such growth will materialize may significantly mean the wrong zones are shouldering the costs. Further only offering 15-year contracts may compound the impact of forecasting errors. Longer contracts will likely attract new generation. Such long contracts can lock ratepayers into contracts with high prices that may come down over time as supply increases. The procurement price cap assuages some concerns but not all. PJM should have pursued a way to mitigate forecast error’s impact and a range of
3 PJM, PJM Load Forecast Report, posted January 14, 2026, p. 8, https://www.pjm.com/- /media/DotCom/library/reports-notices/load-forecast/2026-load-report.pdf4 Monitoring Analytics, State of the Market Report for PJM, Volume 2: Detailed Analysis, March 10, 2022, Table 5- 7, p. 313
PDF page 5
5
contract periods for the central procurement to better balance reliability needs against affordability concerns.
In addition, PJM’s proposed new term and approach, “RBP Obligation” or “RBO,” will impose new obligations on the states to assess the state and/or Relevant Electric Retail Regulatory Authority (“RERRA”)-determined allocation of RBP UCAP MW to Load Serving Entities within each Electric Distributor’s zone/area. PJM should provide clarification as to how it envisions states making those determinations and whether and how PJM plans to assist states in that process. PJM proposes to “empower” states by imposing on them an obligation to “submit RBP RBOs, which PJM would then apply to the allocation of RBP Charges” to load serving entities (“LSEs”).5 Given the timing and the lack of implementation details, particularly for retail access states like Illinois, PJM’s proposal will take time to develop. Moreover, it is unclear how states, particularly retail access states like Illinois, would be able to assign wholesale capacity costs to retail load in the manner PJM proposes, particularly without an appropriate rider or retail tariff sheet to do so through the LSEs. It is unclear whether it may be necessary to conduct a rulemaking proceeding, a legislative change, or create a new customer classification for large loads, in order to properly assign these costs at the retail level. This will also take time to develop. While the Virginia proposal to develop model state tariff provisions by January 1, 2028,6 may be good starting point, a solution that works for Virginia may not work for a retail access state like Illinois. For Illinois, it will take time to develop its own state tariff provisions.
We appreciate that the Commission acknowledged that it “has a duty to address the risk of cost shifting among transmission customers that may result in unjust and unreasonable
5 Backstop Filing at 104. 6 Id. at 12.
PDF page 6
6
transmission rates.”7 In the PJM Show Cause Order, the Commission said, “[w]e expect that the additional cost transparency measures proposed . . . will give state public utility commissions and other state regulators the information necessary to allow them to understand which transmission costs are caused by which transmission customers, so that they can sub-allocate these costs to the appropriate retail customers.”8 We continue to have concerns about this assumption. The ICC supports cooperative federalism. In the case of assessing cost causers and/or beneficiaries of transmission costs and/or in the case here of assessing cost causers of wholesale capacity procurement, however, expecting the states to make such determinations for PJM and the Commission may be unreasonable. PJM would seem to be in a better position and have access to the appropriate data to make an assessment of the cost causers and even beneficiaries of those transmission costs or wholesale capacity costs at issue here. Despite these concerns, however, given the need to rapidly bring on generation, the ICC is generally supportive of the filing. We recommend that the Commission requires sufficient mitigation efforts to protect against cost shifts to or any negative impacts on existing ratepayers, impose no new obligations upon the states, and require PJM to provide the clarifications requested herein as well as state access to any and all RBP related data.
B. PJM’s Proposal Requires Active Collaboration Between PJM and States
As PJM recognizes, under its proposal, states will play a central role in ensuring costs are paid by cost causers. It will be critical for PJM to support states in this critical endeavor. PJM’s territory covers vastly different market structures and PJM’s proposals must work for all of them. Put simply, flexibility is essential. The proposal must work for all fourteen jurisdictions across the region, and what works for Virginia will not be same solution that Illinois needs.
7 PJM Interconnection, L.L.C. et al, 195 FERC ¶ 61,211, P 68 (2026) (“PJM Show Cause Order”).8 Id. P 70.
PDF page 7
7
Also to enable the states, PJM needs to provide data support, analytic insight, and transparency to states when necessary to ensure costs are correctly allocated. The proposed Large Load Registry is an admirable first step that will track the size and location of new large loads, improving accuracy of load forecasts. The registry should collect all necessary data on load size, location, ramp rate, and other relevant features in an easy-to-use format that states can make use when assigning costs.
Further, it is important that PJM ensure the data collected in the registry is available to all states. States have different rules that can limit their access to confidential data. Due to state laws and limitations, the ICC, for instance, would not be in a position to sign the pro forma non- disclosure agreements to access confidential data from PJM as it reads at this time. There should be flexibility with the non-disclosure form language if such accommodations to particular states like Illinois become necessary. It is crucial that any large load registry be accessible to ICC staff in order to fulfill any state’s cost allocation obligations.
II. CONCLUSION
WHEREFORE, for the reasons set forth above, the Illinois Commerce Commission does hereby submit these comments for your consideration. The ICC further requests any and all other appropriate relief.
Respectfully submitted,
/s/ Christine F. Ericson
____________________________
Christine F. Ericson
Special Assistant Attorney General
Illinois Commerce Commission
Office of General Counsel
160 N. LaSalle St., Suite C-800
Chicago, IL 60601
(312) 814-3706
PDF page 8
8
Christine.Ericson@Illinois.gov
Counsel on behalf of the
ILLINOIS COMMERCE COMMISSION
Dated: August 19, 2026
PDF page 9
CERTIFICATE OF SERVICE
I hereby certify that I caused copies of the foregoing document of the Illinois Commerce Commission to be served this day upon each person designated on the official service list compiled by the Secretary in this proceeding in accordance with the requirements of Rule 2010 of the Commission's Rules of Practice and Procedure.
Dated at Chicago, Illinois, this 19th day of August, 2026.
/s/ Christine F. Ericson
_____________________________
Christine F. Ericson
Special Assistant Attorney General
Illinois Commerce Commission
Office of General Counsel
160 N. LaSalle St.
Suite 800-C
Chicago, IL 60601
(312) 814-3706