ER26-3552-000 · 2026-09-03 · Mississippi Public Service Commission, Louisiana Public Service Commission and 2 others
Answer of Mississippi Public Service Commission et al. in Support of Motion for Extension of Time filed by the Public Interest Organizations filed on 08/28/2026
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System Operator, Inc.
)
Docket No. ER26-3552-000
ANSWER OF SOUTHERN REGULATORS IN SUPPORT OF MOTION FOR
EXTENSION OF TIME
The Mississippi Public Service Commission, the Arkansas Public Service Commission, Louisiana Public Service Commission, and the Council of the City of New Orleans (the Southern Regulators) submit this answer1 in support of the Public Interest Organizations’ (PIOs)2 motion for an extension of time3 to submit comments on the Midcontinent Independent System Operator, Inc.’s (MISO) Zero-Injection Generator Interconnection Agreement (ZGIA) proposal in the above captioned docket. The PIOs request that the Federal Energy Regulatory Commission (Commission) extend the comment deadline in this proceeding by seven days from September 8, 2026, to September 15, 2026. Good cause exists for the Commission to grant the PIOs’ request.4 The ZGIA proposal is part of MISO’s response to a recent Show Cause Order,5 which required MISO to either (i) explain why its tariff remains just and reasonable and not unduly discriminatory or preferential without provisions addressing, among other things, transmission service and co-location arrangements for large load customers or (ii) file amendments to make its tariff just and reasonable as applied to large and co-located loads.6 The ZGIA framework is MISO’s novel proposal to study the interconnection of generating facilities that are co-located with
1 Southern Regulators submit this answer pursuant to Rule 213 of the Commission’s Rules of Practice and Procedure. 18 C.F.R. § 385.213.2 The PIOs are the Michigan Environmental Justice Coalition, Community Collaboration on Climate Change, Natural Resources Defense Council, and Sustainable FERC Project.3 Public Interest Organizations, Motion for Extension of Time (Aug. 28, 2026).4 18 C.F.R. § 385.2008(a) (allowing the Commission to extend filing deadlines for good cause).5 Midcontinent Independent System Operator, Inc., 195 FERC ¶ 61,212 (June 18, 2026).6 Id. at P 3.
PDF page 2
2
and exclusively serve large loads. As retail regulators of public utilities, the Southern Regulators have a substantial interest in understanding how the ZGIA proposal will impact reliability in MISO South and fit into MISO’s holistic Show Cause Order Response. Understanding these complex and novel issues requires the additional time requested by the PIOs.
Therefore, the Southern Regulators support the PIOs’ motion to extend the deadline to submit comments on MISO’s ZGIA proposal from September 8, 2026, to September 15, 2026.
Barton Norfleet
Special Counsel; Federal Energy Affairs
Mississippi Public Service Commission
501 N. West Street, Suite 201-A
P.O. Box 1174
Jackson, MS 39215-1174
Phone: (601) 961-5821
barton.norfleet@psc.ms.gov
Respectfully submitted,
/s/ William D. Booth
William D. Booth
Alex L. Peterson
Michael Best & Friedrich LLP
1000 Maine Avenue, S.W.
Suite 400
Washington, D.C. 20024
Phone: (202) 747-9560
wdbooth@michaelbest.com
alpeterson@michaelbest.com
Attorneys for the Mississippi Public
Service Commission
/s/ Noel J. Darce
Kathryn Bowman
Executive Counsel
Lauren Evans
Deputy General Counsel
Louisiana Public Service
Commission
602 North Fifth Street
Baton Rouge, Louisiana 70802
Phone: (225) 342-9888
Kathryn.bowman@la.gov
Lauren.evans@la.gov
Noel J. Darce
Dana M. Shelton
Justin A. Swaim
Fishman Haygood LLP
601 St. Charles Ave. Suite 4600
New Orleans LA 70170
Phone: (504) 586-5252
ndarce@fishmanhaygood.com
dshelton@fishmanhaygood.com
jswaim@fishmanhaygood.com
Attorneys for the Louisiana Public Service
Commission
PDF page 3
3
/s/ Bridgette Frazier
Bridgette Frazier
Luke Kinder
Commission Counsel
Arkansas
Public
Service
Commission
1000 Center Street
P.O. Box 400
Little Rock, AR 72201-4314
Telephone: (501) 682-5816
(501) 682-5766
bridgette.frazier@arkansas.gov
luke.kinder@arkansas.gov
Attorneys for the Arkansas Public
Service Commission
/s/ David Shaffer
Clinton A. Vince
Presley R. Reed, Jr.
David S. Shaffer
Dentons US LLP
1900 K Street, N.W.
Washington, DC 20006
Phone: (202) 408-9174
clinton.vince@dentons.com
presley.reedjr@dentons.com
david.shaffer@dentons.com
Attorneys for the Council of the City of
New Orleans
Dated: September 2, 2026
PDF page 4
CERTIFICATE OF SERVICE
I hereby certify that I have served the foregoing document upon each person listed on the official service list compiled by the Secretary in this proceeding.
Dated at Milwaukee, Wisconsin this 2nd day of September, 2026.
Respectfully submitted,
/s/ Zachary S. Schumacher
Zachary S. Schumacher
Michael Best & Friedrich LLP
790 N. Water St.
Suite 2500
Milwaukee, WI 53202
(414) 223.2513
zach.schumacher@michaelbest.com