ER26-3515-000 · 2026-09-03 · Data Center Coalition

Motion to Intervene and Protest of the Data Center Coalition to PJM Interconnection, L.L.C.’s proposal to establish Interim Resource Adequacy Service and a Large Load Registry

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, L.L.C.
 )
 Docket No. ER26-3515-000
)

MOTION TO INTERVENE
AND PROTEST OF THE DATA CENTER COALITION

Pursuant to Rules 211, 212, and 214 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or the “Commission”)1 and the Commission’s August 13, 2026 Combined Notice of Filings #2,2 the Data Center Coalition (“DCC”) hereby moves to intervene and submits this protest of PJM Interconnection, L.L.C.’s (“PJM”) proposal to establish Interim Resource Adequacy Service (“IRAS”) and a Large Load Registry.3

I. INTRODUCTION
DCC is the membership organization for the U.S. data center industry, representing leading data center owners and operators that develop, operate, and maintain data center infrastructure and teams across the country.  DCC members operate data centers that constitute significant loads within the PJM region and DCC has been an active stakeholder in regional efforts to ensure reliability, enable new generation, and discipline load forecasts.

DCC and its members have been at the forefront of efforts to advance reforms in PJM and at the state level to accommodate the growth of data centers and other large load customers within the PJM region while maintaining reliability and protecting existing retail customers.  DCC agrees

1 18 C.F.R. §§ 385.211, 385.212, and 385.214. 2 PJM Interconnection, L.L.C., et al., Docket No. ER26-3515-000, et al., Combined Notice of Filings #2 (Aug. 13, 2026).
3 PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability (Aug. 13, 2026) (“Filing”).

PDF page 2

- 2 -
with PJM that steps must be taken to maintain reliability, protect existing customers from inappropriate cost shifts, and ensure that data centers and other large load customers take appropriate responsibility for supporting the development of new generation and infrastructure necessary to serve their demand.

Indeed, DCC was a leading voice in the PJM Critical Issue Fast Path (“CIFP”) processes that led to PJM’s Filing in this docket.  From the outset of these processes, DCC championed reforms to enable data centers to bring their own generation capacity to insulate existing customers from the costs of serving demand from large load customers, as well as legally-durable pathways to enable states to implement interruptible retail tariffs to support grid-wide reliability and resilience.  Looking beyond the positions DCC took in PJM’s stakeholder process, DCC members have proudly joined over 200 governors, utilities, electric cooperatives, and data center developers in support of the White House’s “Ratepayer Protection Pledge,”4 which, through historic levels of industry investment in long-needed new capacity, is already helping to resolve many of the fundamental issues PJM aims to address through this proceeding.

DCC also strongly supports state efforts to establish interruptible service tariffs that facilitate the integration of new large loads while maintaining reliability and protecting existing customers.  In fact, DCC has, alongside the Virginia State Corporation Commission (“VA SCC”), called for other state regulators to develop model retail interruptible tariffs and emergency load- reduction programs that would allow large loads to take interruptible service, establish standardized curtailment obligations and operating rules, and allow state-jurisdictional utilities to curtail participating large commercial and industrial customers during system emergencies to

4 Ratepayer Protection Pledge, THE WHITE HOUSE, Proclamation No. 11014, 91 Fed. Reg. 11439 (Mar. 4, 2026), https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/.

PDF page 3

- 3 -
protect existing customers.5

Notwithstanding DCC’s support for bring-your-own-generation-capacity solutions and the other initiatives described above, DCC believes that the IRAS proposal is legally defective and must be rejected.  The Federal Power Act (“FPA”) grants states—not PJM or FERC—exclusive authority over the rates, terms, and conditions of retail service.  Yet, PJM asks the Commission to grant it authorization to impose a new curtailment program that aims to interrupt retail service to large load customers that PJM determines have failed to comply with new bring your own new capacity (“BYONC”) requirements prescribed in the PJM tariff (“Eligible New Large Loads”). Rather than accommodating state efforts to modify retail curtailment policies to account for the growth of large loads, IRAS instead seeks to compel states within the PJM footprint to conform their retail curtailment frameworks to PJM tariff requirements.  DCC believes that this top-down approach to addressing the curtailment of retail customers is inconsistent with principles of cooperative federalism and disregards the carefully calibrated division of authority between FERC and the states.

DCC acknowledges that successfully addressing the challenges of large load integration in the region will require collaboration and cooperation among PJM, state regulators, large loads, electric distribution companies, and other stakeholders.  But Congress’s decision to reserve to the states authority over retail service means that it is the states that must take the lead in developing the retail service frameworks through which new large loads are integrated into the electric system, including the rules governing the priority of customer classes, the terms for interrupting service to retail customers, and the requirements that customers must meet to obtain firm service.  While

5 See Exh. A; Letter to Ms. Paula Conboy and Mr. David Mills from VA SCC Chair, Kelsey Bagot and DCC President & CEO, Josh Levi (June 30, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/2026/20260630/20260630-written-comments---va-scc-and-data-center-coalition.pdf.

PDF page 4

- 4 -
PJM has a critical role to play in ensuring that large loads are integrated into the system reliably, it should not seek to displace the role of the states by imposing a uniform retail curtailment policy across the PJM region.

This does not mean that PJM and the Commission are powerless to take actions to protect customers from service interruptions when grid conditions are tight.  During the CIFP process, DCC outlined a framework for a state “opt-in framework” that would couple state-led implementation of interruptible service with changes to PJM’s operational practices to ensure that retail curtailments are implemented in a manner that recognizes the respective roles of wholesale and retail regulators.6  Under that proposal, states would be responsible for establishing interruptible customer classes for large load customers while PJM would continue to monitor system conditions and, when conditions warrant, would issue a signal to utilities in participating states that would trigger curtailments in accordance with state-established tariffs and service priorities.  To provide immediate relief to customers while states work to update their retail tariffs, DCC also proposed that PJM update its manual load-shed procedures to establish a framework under which data centers and other large loads would be contacted during emergencies and provided an opportunity to voluntarily curtail prior to PJM’s implementation of broader load dump procedures.

DCC’s proposal illustrates that there are approaches that can achieve the same reliability outcomes as IRAS while respecting the traditional division of responsibility between FERC and the states.  But the benefits of a state-led approach are not limited to merely avoiding the significant

6 See Exh. B; DCC Connect & Manage Alternative: State-Led Implementation with Immediate Residential Customer Protection (June 30, 2026), available at: https://www.pjm.com/-/media/DotCom/committees- groups/committees/mc/2026/20260630-special/item-01c---data-center-coalition---cm---executive-summary.pdf.  See also Exh. C; DCC, A Path to Reliable Large-Load Integration: Creating Certainty for Investment, Customers, and the Grid (June 10, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/2026/20260611/20260611-item-03a---data-center-coalition-presentation.pdf.

PDF page 5

- 5 -
legal issues presented by IRAS.  Allowing states to take the lead in establishing retail curtailment priorities avoids one of the other major shortcomings of IRAS: there is no assurance that a PJM- led framework will be effective or achieve the objectives that PJM seeks.  If states are truly free to establish different curtailment priorities as PJM claims, PJM cannot ensure that the customers it seeks to target through IRAS will be curtailed, that retail customers that comply with PJM’s BYONC requirements will avoid service interruptions, or that the proposal will deliver the reliability benefits PJM claims.

IRAS is also unjust, unreasonable, and unduly discriminatory on its own terms.  IRAS would create a sub-class of Network Integration Transmission Service (“NITS”) customers that would be defined by the characteristics of the retail customers that they serve.  NITS customers serving Eligible New Large Loads would be required to pay the same transmission and capacity charges as other NITS customers, but would be curtailed ahead of other NITS customers and firm point-to-point customers.  In fact, while NITS customers serving Eligible New Large Loads still would be required to pay charges reflecting the cost of capacity committed through PJM’s capacity market, PJM proposes to curtail these customers prior to deploying Demand Resources that have been committed to provide capacity to maintain reliability and avoid interruptions to firm customers.  The result would be to force these NITS customers to bear the costs of capacity that would not be available to meet their needs.

Compounding these problems is the fact that the Filing offers no transition mechanism and effectively provides New Large Loads a window of less than ten months to procure new capacity or face curtailment—an interval that PJM’s own documented difficulties in bringing resources online demonstrates is not realistic.  The result is that large loads that have spent billions of dollars

PDF page 6

- 6 -
and entered complex commercial arrangements in reliance on PJM’s longstanding rules will suddenly face the prospect of being unable to obtain the reliable service their projects depend on.

Rather than implementing measures to degrade the quality of service provided to Eligible New Large Loads, PJM should be pursuing reforms that eliminate barriers to the development of the new generation capacity needed to maintain reliability and avoid the curtailment of retail customers.  Yet, PJM proposes to undermine the ability of the capacity market to send price signals for the development of new capacity by excluding Eligible New Large Loads from the calculation of the Variable Resource Requirement curve (“VRR Curve”) beginning with the 2029/2030 Delivery Year.  Ultimately, the result will be a capacity market that produces prices and results that are untethered to actual supply and demand conditions within the PJM footprint.  A capacity market that is modeled as if a large and growing increment of demand does not exist cannot send the price signals needed to attract the supply that PJM says the region lacks. DCC recognizes that the PJM region must adapt to this high load growth environment in which new resource entry remains frustrated and is committed to advancing durable solutions that preserve states’ role in integrating large loads, protect existing customers from inappropriate cost shifts, and provide data centers and other large loads with timely pathways to power that ultimately improves reliability throughout the region.  Establishing a framework that can accomplish these objectives is essential to ensuring that America’s industries of the future—data centers, semiconductors, battery manufacturing, and the automotive, steel, metal, chemical, petrochemical, and refining industries—remain competitive in the global economy.  But PJM’s proposal to impose a retail curtailment scheme on states that eviscerates the jurisdictional lines drawn by Congress, requires customers to pay for capacity that they will not benefit from, undermines the settled

PDF page 7

- 7 -
expectations of New Large Loads, and may ultimately prove unworkable is not a viable path forward.

For the foregoing reasons, DCC asks the Commission to issue an order rejecting the Filing and encouraging PJM to work with stakeholders to develop changes to PJM’s emergency procedures that accommodate—rather than dictate—the retail curtailment priorities of individual states.  Alternatively, if the Commission finds that the growth of large loads has rendered PJM’s existing emergency procedures unjust and unreasonable, the Commission should initiate a Section 206 proceeding to develop proposed revisions to these procedures that respect the jurisdictional boundaries established by the FPA while protecting existing retail customers from service disruptions and inappropriate cost shifts.

If the Commission does not reject IRAS outright, then it should direct PJM to establish a meaningful transition mechanism that avoids disrupting existing contractual arrangements and provides both large load customers and the states a reasonable timeline to take the steps necessary to adapt to the IRAS framework.  Among other things, any transition mechanism should limit the application of IRAS in a manner that respects existing contracts and investment decisions, including exempting large load customers that have already entered into contracts for retail service that pre-date implementation of IRAS.  Additionally, the Commission should direct PJM to delay implementation of IRAS until June 1, 2028 to provide new large loads a reasonable amount of time to comply with PJM’s BYONC requirements and to provide state authorities with the time necessary to update their retail policies to account for the IRAS framework.

PDF page 8

- 8 -
II. PROTEST
A. IRAS Unlawfully Intrudes On State Authority Over Retail Sales
In drafting the FPA, “Congress meant to draw a bright line easily ascertained, between state and federal jurisdiction[.]”7  Congress granted FERC jurisdiction over wholesale sales of electricity and transmission service in interstate commerce.8  At the same time, the FPA “limits FERC’s regulatory reach, and . . . maintains a zone of exclusive state jurisdiction”9 by reserving to the states jurisdiction over “any other sale of electric energy” and “over facilities used for the generation of electric energy” and “facilities used in local distribution[.]”10

Although the “wholesale and retail markets in electricity are inextricably linked,” the mere fact that the rates, terms, and conditions of retail service may affect wholesale markets is not a sufficient basis for FERC to assert jurisdiction.11  FERC cannot take an action transgressing the limits prescribed by Congress “no matter how direct, or dramatic, its impact on wholesale rates.”12 FERC may not approve tariff provisions that directly regulate retail customers, dictate retail service terms, or prescribe the curtailment priority of retail customers.13  Nor may FERC approve tariff provisions that “target” those matters left for the states to regulate.14 PJM portrays IRAS as a narrow reliability measure that merely supplements existing emergency procedures.  But the proposal cannot be evaluated based on labels alone.  The

7 Federal Power Comm’n v. Southern California Edison Co., 376 U.S. 205 (1964).
8 16 U.S.C. § 824(b)(1).
9 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 266 (2015). 10 16 U.S.C. § 824(b)(1).
11 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 264 (2015).
12 Id. at 280.
13 Northern States Power Co. v. FERC, 176 F.3d 1090 (8th Cir. 1999) (finding that FERC’s “attempt to regulate the curtailment of electrical transmission on native/retail consumers is unlawful, as it falls outside of the FPA’s specific grant of authority to FERC.”); Tri-State Generation and Transmission Association, Inc., 193 FERC ¶ 61,070, at P 49 (2025) (rejecting large load tariff that “appear[s] to dictate certain terms and conditions for retail sales[.]”).
14 Oneok, Inc. v. Learjet, Inc., 575 U.S. 373, 385 (2015).

PDF page 9

- 9 -
Commission must examine what IRAS actually does in practice.  When PJM’s Filing and proposed tariff language are considered as a whole, the target of the Filing becomes clear: IRAS is an unprecedented program that aims to interrupt service to specific retail customers that do not comply with federally-approved resource procurement requirements prescribed by the PJM tariff and directs state-regulated distribution utilities to implement PJM’s retail curtailment priorities. PJM casts IRAS as a new wholesale service that retail customers can provide.  But IRAS is not a novel form of demand response; it is a framework for singling out retail customers for forced service interruptions during tight grid conditions based on criteria established in a FERC- jurisdictional tariff.  Under IRAS, “end-use customer load” with a peak load of 50 MW or greater that goes into service15 after PJM prescribed deadlines (i.e., New Large Loads) will be required to bring capacity meeting PJM’s BYONC criteria or be deemed to be subject to interruption during emergency conditions.  In effect, IRAS:

• seeks to create a new interruptible retail customer class consisting of large load
customers that do not meet PJM’s BYONC requirements;16
• authorizes PJM to issue curtailment instructions during prescribed conditions to
compel Electric Distributors17 to reduce the load of these customers;18
• directs Electric Distributors to provide compensation to Eligible New Large Loads
whose load is curtailed pursuant to these directives equal to 50% of the Non-
Performance Charge Rate set out in the PJM tariff (unless the Eligible New Large
Load agrees to “accept in its retail rates” a lower sum);19 and

15 Filing, Transmittal Letter at 1, n.2 (defining “New Large Load” to include end-use customer load that is either “a Large Load that goes into service after” the deadline prescribed by the tariff or “incremental load in-service after [such deadline], that increases the existing end-use customer load at a single electrical site that, prior to such incremental load, did not previously meet the definition of Large Load.”).
16 Id. at 69.
17 Electric Distributor is defined as a PJM member that owns or leases electric distribution facilities that are used to provide electric distribution service to load within the PJM region or a cooperative or joint municipal agency that has a member that owns electric distribution facilities used to provide electric distribution service to load within the PJM region.  PJM, Reliability Assurance Agreement Among Load Serving Entities in the PJM Region, Art. 1 (defining Electric Distributor).
18 Filing, Transmittal Letter at 74-75, 83-84.
19 Id. at 102.

PDF page 10

- 10 -
• directs Electric Distributors to impose charges on other customers to fund these
compensation payments.20
PJM has failed to provide a sufficient basis for the Commission to find that IRAS does not regulate the terms and conditions of retail service in ways that go beyond the Commission’s authority.  FERC does not have any authority to exercise jurisdiction over the quality of service that retail customers receive, the terms and conditions that retail customers must meet to avoid interruption during emergency conditions, or the compensation paid to retail customers whose service is curtailed.  Each of these areas are matters that states have historically regulated pursuant to their exclusive authority over the rates, terms, and conditions of retail service.

The extent to which IRAS targets matters within the jurisdiction of the states is readily discernable by even a cursory review of the subject matters addressed by state laws and tariffs governing retail service.  For instance, state laws and tariffs within the PJM region recognize the authority of state public utility commissions to establish the relative priority of retail customers for service,21 require state electric utilities to implement curtailments in a manner that complies with state law and regulation, establish interruptible service classes,22 determine eligibility for participation in interruptible rate schedules,23 and establish credits and compensation for customers

20 Id., Att. A, Proposed Att. DD-4(X).
21 See, e.g., Va. Code § 56-250 (authorizing Virginia state corporation commission to establish plan governing curtailment of retail customers during grid emergencies and shortages); 20 VAC5-300-20 (establishing procedures for Virginia utilities to take during emergencies and establishing relative priority of residential, commercial, and industrial customers);  Ohio Administrative Code 4901:5-19 (recognizing right of Public Utility Commission of Ohio to implement measures that fulfill “electric requirements for priority use by its consumers” and reallocate or curtail supplies “among its consumers”).
22 See, e.g., PPL Electric Utilities Corp., General Tariff: Rules and Rate Schedules for Electric Service, Rate Schedule LP-6 (Large Load Interconnections) (providing large load customers the option to voluntarily elect “interruptible service . . . instead of firm service”).
23 See, e.g., Pub. Util. Comm’n of Ohio, In the Matter of the Application of Ohio Power Company for Authority to Establish a Standard Service Offer Pursuant to R.C. 4928.143, In The Form Of An Electric Security Plan, Opinion and Order, Case No. 23-23-EL-SSO at ¶¶ 105-109, 140-144 (Apr. 3, 2024) (approving interruptible power tariff for customers that meet notice requirements and establishing demand credits).

PDF page 11

- 11 -
that interrupt their service.24  The service classification of retail customers, the curtailment priority of different classes, and the consideration paid for these service interruptions are all familiar components of state-regulated retail service and beyond the bounds of permissible FERC regulation.

PJM attempts to justify its proposal by stating that it will not curtail specific end-use customers directly, but will direct Electric Distributors25 to curtail these customers’ demand.26  But the fact that PJM does not have authority to directly curtail retail customers merely reinforces that PJM is attempting to exercise control over matters that are outside of its purview and beyond the boundaries of the Commission’s jurisdiction.  And the fact that PJM is attempting to do indirectly what it cannot do directly is of no legal significance.27  The FPA leaves no room either for FERC to directly regulate retail sales or approve regulations that would indirectly achieve this result. PJM argues that IRAS is consistent with the Supreme Court’s determination in EPSA that Order No. 745’s directive to regional transmission organizations (“RTO”) and independent system operators (“ISO”) to pay demand response resources participating in the energy market the locational price for energy did not intrude on the jurisdiction of the states.28  But the reasoning that the Court employed in sustaining Order No. 745 in EPSA has no application to IRAS. Importantly, EPSA upheld Order No. 745 based on the Court’s determination that Order No. 745 merely established a rate for wholesale transactions and was confined solely to the rules

24 See, e.g., id.
25 DCC notes that it is unclear how PJM’s proposal would work in retail choice jurisdictions where competitive retail suppliers—rather than the Electric Distributor—may be responsible for providing service to retail customers.
26 Filing, Transmittal Letter at 86.
27 Hughes v. Talen Energy Marketing, LLC, 578 U.S. 150, 163 (2016) (“FPA leaves no room either for direct state regulation of the prices of interstate wholesales or for regulation that would indirectly achieve the same result.”).
28 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 266 (2015).

PDF page 12

- 12 -
governing the wholesale markets.29  The same cannot be said of IRAS.  To the contrary, PJM’s tariff revisions seek to prescribe the amount paid to retail customers through their retail rates for service interruptions implemented at PJM’s direction.30  And, in contrast to Order No. 745, the effectiveness of PJM’s proposed framework depends on electric distributors issuing directives to their retail customers to reduce demand31 and state regulatory authorities adopting retail tariffs that align with the curtailment priorities set forth in the PJM tariff.32

The Court also noted that Order No. 745 was carefully crafted to preserve the jurisdiction of the states by providing state regulators with the option of prohibiting retail customers from offering demand response into the wholesale markets33 and FERC’s “justifications for regulating demand response are all about, and only about, improving the wholesale market.”34  IRAS does not provide state regulators with any such opt out.  Regardless of the decisions made by individual state regulators, PJM will continue to issue directives to electric distributors to curtail New Large Load customers that do not comply with PJM’s BYONC requirements.  And while the

justifications for Order No. 745 were all about the wholesale market, PJM acknowledges that IRAS is intended to “establish load reduction priorities for retail customers”35 and encourage “states to

29 Id. at 282 (stating that “every aspect of the regulatory plan happens exclusively on the wholesale market and governs exclusively that market’s rules”).
30 Filing, Att. A, Proposed Att. DD-4(X)(a) (stating that the rate for the provision of IRAS “shall be 50% of the Non-Performance Charge Rate . . . unless any Eligible New Large Load elects to (i) accept in its retail rates a sum less than 50% of the Non-Performance Charge Rate . . . or (ii) waive receipt in its retail rates any compensation for the provision of” IRAS”) (emphasis added).
31 Id., Transmittal Letter at 26 (“Electric Distributors must execute PJM’s load reduction directives when PJM issues an Interim Resource Adequacy Alert.”).
32 Id. at 3 (“PJM anticipates participating in efforts to develop standardized regulatory tools and model retail tariff structures that individual state commissions may consider as they address the integration of new loads and otherwise decide whether and how to act in response to the evolving federal wholesale landscape, inclusive of the IRAS filing.”).
33 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 287 (“[T]he Rule allows any State regulator to prohibit its consumers from making demand response bids in the wholesale market.”).
34 Id. at 282.
35 Filing, Transmittal Letter at 31.

PDF page 13

- 13 -
re-evaluate load reduction plans.”36  The objective of IRAS is clear: to compel state regulators to modify their regulation of the retail market to conform to PJM policy.

Additionally, Order No. 745 established the rate that demand response providers would be paid if they voluntarily elected to participate in the wholesale markets.  The wholesale demand response programs at issue in Order No. 745 did not compel retail customers to curtail their loads involuntarily or state regulators to re-evaluate their retail curtailment programs.  IRAS, in contrast, targets individual retail customers that fail to comply with PJM’s BYONC requirements for involuntary curtailment and seeks to ensure that states conform their curtailment policies to align with the priorities established by the PJM tariff.

PJM attempts to avoid these jurisdictional issues by claiming that states retain discretion37 over how to shape their retail policies in response to IRAS and that it will be Electric Distributors and state regulators that determine which retail customers actually are curtailed.  PJM’s reasoning misses the point.  It is the role of the states—not PJM—to establish load reduction priorities for retail service.  Neither PJM nor FERC should be dictating retail curtailment rules, whether directly or by establishing market rules intended to compel compliance.

Ultimately, IRAS does not offer states a genuine choice.  For a state to ignore PJM’s dictates would be to run the risk that reliability events could result in broader service disruptions affecting other customers within its jurisdiction rather than a more targeted curtailment of individual large load customers.  Offering states the choice between compliance and indiscriminate curtailment of retail customers is well past the point at which “pressure turns into compulsion” and

36 Id. at 3.
37 Notwithstanding PJM’s claims about the flexibility afforded to state authorities, a decision by FERC to assert jurisdiction over, and approve, IRAS would raise serious legal questions about what discretion states have to deviate from the terms of the filed rate approved by the Commission.  See Nantahala Power & Light Co. v. Thornburg, 476 U.S. 953, 966 (1986) (once FERC “sets a rate, a state may not conclude in setting retail rates that the FERC- approved wholesale rates are unreasonable”).

PDF page 14

- 14 -
undermines the cooperative federalism embodied in the FPA.38
Even if states were given a meaningful choice, PJM’s repeated references to the discretion of the states as to whether to comply with IRAS highlights a fundamental flaw in PJM’s proposal. PJM cannot simultaneously maintain that states retain meaningful discretion over the implementation of retail curtailments and assume that IRAS will operate exactly as PJM describes. If states are genuinely free to establish different curtailment priorities, PJM cannot guarantee that the customers it seeks to target through IRAS will actually be curtailed or that the proposal will achieve its objectives.

Nor can PJM ensure that new large load customers that comply with PJM’s BYONC
requirements will avoid service interruption.  For instance, an Eligible New Large Load customer that procures new capacity to meet its load may still experience service disruptions during emergency conditions if the relevant state authorities and Electric Distributors do not adopt curtailment priorities that align with the IRAS framework.  The lack of certainty that a customer that complies with PJM’s BYONC requirements will avoid service interruptions will undermine one of the primary justifications for the IRAS framework: to provide an incentive for new large load customers to support the development of new capacity required to meet their needs. PJM states that IRAS is merely an example of the “federal regime helping to effectuate state decisions associated with the rates, terms, and conditions of retail service.”39  But it is quite the opposite.  Rather than accommodating state decisions—as the proposal DCC advanced in the PJM stakeholder process would have—PJM asks the Commission to approve a tariff framework designed to ensure that retail customers are curtailed in a manner that aligns with PJM’s

38 Nat’l Fed’n of Indep. Bus. v. Sebelius, 567 U.S. 519, 580 (2012) (internal citations and quotations omitted).
39 Filing, Transmittal Letter at 3.

PDF page 15

- 15 -
preferences, priorities, and requirements.  If Congress had intended to give FERC the authority to determine the retail load priorities within 13 states and the District of Columbia then it would have explicitly provided FERC with this authority in the FPA.40  But it did not.  Instead, it explicitly denied FERC any authority to exercise jurisdiction over the rates, terms, and conditions of retail service, reserving these matters to the states.

PJM minimizes jurisdictional concerns by noting that the FPA’s drafters could not have foreseen the resource adequacy impacts of data centers and technological advancements in artificial intelligence.41  That may be true.  But the drafters of the FPA did foresee a different risk: that federal regulation of the electric industry could encroach upon the authority long enjoyed by the states.  Congress therefore drew a clear jurisdictional boundary, granting FERC authority over wholesale sales and interstate transmission while reserving regulation of retail service to the states. Implicit in this structure is the recognition that not all problems require a federal solution.  The novelty of today’s reliability challenges does not permit the Commission to disregard the boundaries established by Congress.

40 West Virginia v. EPA, 597 U.S. 697, 716 (2022) (explaining that under the major questions doctrine, “courts ‘expect Congress to speak clearly if it wishes to assign to an agency decisions of vast economic and political significance.’”) (quoting Utility Air Regulatory Group v. EPA, 571 U.S. 302 (2014)).
41 Filing, Transmittal Letter at 91.

PDF page 16

- 16 -
B. IRAS Is Unjust, Unreasonable, Unduly Discriminatory, And Inconsistent
With Cost Causation Requirements

1. Curtailing New Large Loads Before Requiring Demand Resources To
Perform Is Unjust And Unreasonable
The purpose of committing capacity through the PJM Reliability Pricing Model (“RPM”) is to ensure that PJM has sufficient resources available to avoid the risk of supply interruptions.42 In the last two PJM Base Residual Auctions (“BRA”), Demand Resources were paid over a combined $1.5 billion to reduce their demand when called upon by PJM to maintain reliability.43 Demand Resources are compensated at this level based on “the expectation that such resources will be available to provide energy and reserves when called upon” just like other Capacity Resources.44

If IRAS is approved, however, Demand Resources committed through the capacity market will no longer be available to serve the needs of Eligible New Large Load customers.  Specifically, PJM’s proposed curtailment order following the adoption of IRAS would be as follows:

• PJM dispatches available generation and economic demand response;45

• PJM curtails non-firm export transactions associated with Capacity Resources;46

• PJM curtails new Non-Firm Contract Demand Service and Interim Network
Integrated Transmission Service;47

42 PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment To Support Durable Reliability at 14 (May 6, 2026), https://www.pjm.com/- /media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market- design.pdf.  See also PJM Interconnection, L.L.C., 195 FERC ¶ 61,209, at P 520 (2026) (“Capacity resources are purchased to meet the needs of transmission customers taking existing firm service, such as NITS.”).
43 See PJM 2028/2029 Base Residual Auction Report at 2-3, 5, 12 (July 14, 2026), available at: https://www.pjm.com/markets-and-operations/rpm.aspx (showing 7,641 MW of Demand Response clearing at $333.44 MW-day for 2027/2028 Delivery Year and 7,364 MW of Demand Response clearing at $325.00 MW-day for 2028/2029 Delivery Year).
44 PJM Interconnection, L.L.C., 151 FERC ¶ 61,208, at P 99 (2015).
45 Filing, Att. C – Aff. of Christopher Pilong on behalf of PJM Interconnection, L.L.C. at ¶ 8.  See also Filing, Transmittal Letter at 78.
46 Id. at ¶ 9.  See also Filing, Transmittal Letter at 78.
47 Id. at ¶ 12.  See also Filing, Transmittal Letter at 78.

PDF page 17

- 17 -

• PJM curtails Eligible New Large Loads under IRAS;48 and, finally,

• PJM initiates Pre-Emergency Load Management Reduction Actions, including
mandatory reductions for Demand Response.49
In short, under PJM’s proposal New Large Loads that have not satisfied the BYONC requirements will be curtailed before PJM calls on Demand Resources that have been paid to reduce their load.50 PJM has not demonstrated that it is just and reasonable to direct the curtailment of retail customers prior to deploying Demand Resources that have been committed precisely to avoid such service disruptions.  The point of Capacity Resources and Demand Resources is that they will provide capacity when called upon “to avoid periods of involuntarily firm load shed or blackouts.”51  And the Commission has consistently found that paying resources, including Demand Resources, for capacity but not expecting them to perform “threaten[s] reliable operation of the system and forc[es] consumers to pay for capacity without receiving commensurate reliability benefits” ultimately resulting in unjust and unreasonable rates.52  PJM’s IRAS proposal reverses that relationship: PJM proposes to involuntarily curtail customers that continue paying

48 Id. at ¶ 13. See also Filing, Transmittal Letter at 78.
49 Id. at ¶ 14; PJM Manual 13: Emergency Operations § 2 (Revision 98; effective June 24, 2026) (“Applicability: Any site registered in the PJM Demand Response program as a demand resource (a.k.a. DR) type that needs 30, 60 or 120 minute lead time to make its reductions.  These reductions are mandatory when dispatched during the product availability window.”).
50 The relative curtailment priority of Eligible New Large Loads and Demand Resources also raises questions about the efficacy of the IRAS framework.  Under PJM’s proposal, a New Eligible Large Load would have a strong incentive to become a Demand Resource, receive capacity revenues, and then be dispatched under PJM’s demand response rules—after IRAS otherwise would have required it to curtail.  In effect, a New Large Load customer could move from paying for capacity and being curtailed prior to the deployment of demand response to receiving capacity revenues and receiving a later curtailment priority simply by changing its wholesale market status.
51 PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment To Support Durable Reliability at 14 (May 6, 2026), https://www.pjm.com/- /media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market- design.pdf.
52 ISO New England, Inc., 147 FERC ¶ 61,172, at P 23 (2014).

PDF page 18

- 18 -
capacity charges while leaving Demand Resources that have been committed to provide capacity undeployed.

The only explanation PJM has provided to justify its proposal is that Demand Resources are curtailed as part of the Pre-Emergency Load Management Reductions when a North American Electric Reliability Corporation Energy Emergency Alert Level 1 (“EEA1”) is established.53  And because Pre-Emergency Load Management Reductions indicate that the “region is approaching a capacity event,” PJM says that it is “[t]hus, … appropriate for PJM to direct Electric Distributors to reduce those New Large Loads that have failed to cover their capacity obligations before relying on Demand Resources, through Pre-Emergency Load Management Reductions Actions, to maintain reliability.”54

While it is obvious that requiring Eligible New Large Loads to curtail would be helpful to avoid Pre-Emergency Load Management Reductions Actions, it does not follow that curtailing retail customers through IRAS is an appropriate mechanism to prevent Demand Response from being called upon to avoid Pre-Emergency Load Management Reductions Actions.  If PJM is concerned that calling upon Demand Resources will trigger a Pre-Emergency Load Management Reduction or EEA1 earlier than it believes is warranted, it should revise its curtailment procedures to allow it to require Demand Response to perform without triggering a Pre-Emergency Load Management Reduction or EEA1.  Indeed, PJM has previously recognized that it needed to revise its definition of “Emergency Action” to avoid triggering a Performance Assessment Interval (“PAI”) when it called upon Demand Resources:

[I]nclusion of load management resources, which are generally committed Demand Resources in the capacity market, in the definition of Emergency Action is not representative of a capacity emergency.  That is because Pre-Emergency Load

53 Filing, Transmittal Letter at 79.
54 Id. (emphasis in original).

PDF page 19

- 19 -
Response Program, like all other committed Capacity Resources, should be able to support the reliability needs of the PJM Region regardless of whether there is a capacity emergency.  Consequently, deployment of pre-emergency load

management reduction should not, in and of itself, trigger a PAI.55

If PJM is similarly concerned that it cannot call upon Demand Resources before triggering a Pre- Emergency Load Management Reduction or EEA1, then it should revise its curtailment procedures so that Demand Resources can be relied upon to perform the capacity function they are paid for. But PJM should not be permitted to only rely on Demand Resources after it has issued directives calling for the curtailment of retail load.

2. Curtailing Load That Pays For Demand Response Before Calling Upon
Demand Response Is Inconsistent With Cost Causation Requirements

The Commission and the courts have recognized that the FPA’s “just and reasonable” standard incorporates a cost causation principle.56  The cost causation principle requires that “all approved rates reflect to some degree the costs actually caused by the customer who must pay them” and prohibits the Commission from approving a rate scheme that will result in one group of customers being required to subsidize the provision of service to a different group of customers.57 The cost causation principle can be considered “a matter of making sure that burden is matched with benefit.”58

DCC and its members are committed to paying for the costs associated with integrating data centers into the grid, including the incremental capacity costs associated with providing them firm, reliable service.  DCC is also a strong proponent of BYONC mechanisms that facilitate

55 PJM Interconnection, L.L.C., Docket No. ER23-1996-000, Proposed Revisions to Prospectively Refine the Definition of Emergency Action, Request for Shortened Comment Period and Expedited Commission Action at 8 (May 30, 2023).
56  See, e.g., City of Lincoln v. FERC, 89 F.4th 926, 930 (D.C. Cir. 2024).
57 Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1050 (D.C. Cir. 2022) (quoting Black Oak Energy, LLC v. FERC, 725 F.3d 230 (D.C. Cir. 2013)).
58 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014).

PDF page 20

- 20 -
pathways to power for data centers and other large loads while adding capacity to the grid for the benefit of all customers.  But it is nevertheless important that costs imposed on large loads be consistent with the cost causation principle.

PJM’s IRAS proposal will result in Eligible New Large Load customers incurring the burden of paying Demand Resources for capacity for which these large loads will not receive a corresponding benefit.  Under PJM’s proposal, NITS customers serving Eligible New Large Loads will continue to be responsible for paying Locational Reliability Charges reflecting the costs of capacity procured through the BRA, including Demand Resources—costs that ultimately will be passed through to Eligible New Large Load customers.59  Yet, these NITS customers and the Eligible New Large Loads that they serve will no longer benefit from the Demand Resources committed through the capacity market, as these resources will only be called upon to perform after PJM issues a directive to these customers to curtail.  Requiring NITS customers and their retail customers to pay the costs of capacity that only will be deployed after their service has been curtailed is inconsistent with cost causation requirements.

PJM appeared to recognize as much in its stakeholder process.  Specifically, in its June 10, 2026 presentation to stakeholders PJM stated that “[l]oads that are subject to Connect and Manage [now known as IRAS] are not assessed capacity charges” and that it “will adjust EDC RPM Load Obligations to reflect UCAP associated with new Large Loads assigned Connect & Manage.”60 Yet, PJM’s Filing in this proceeding is devoid of any tariff revisions that would result in Eligible New Large Loads subject to IRAS being exempt from capacity charges.  PJM has not proposed to

59 See PJM Manual 18: PJM Capacity Market § 9.2.1 (Revision 62; effective Dec. 17, 2025) (“Each LSE that serves load in a PJM Zone or load outside PJM using PJM resources (Non-Zone Network Load) during the Delivery Year is responsible for paying a Locational Reliability Charge equal to their Daily Unforced Capacity Obligation in a Zone times the applicable Final Zonal Capacity Price for that Delivery Year.”).
60 PJM CIFP–RBP / Connect and Manage - Stage 3 (June 10, 2026 – Meeting Materials), Connect & Manage Package Updates at 40 (June 10, 2026), available at: https://www.pjm.com/committees-and-groups/cifp-rbp.

PDF page 21

- 21 -
revise provisions of its tariff addressing the Locational Reliability Charge61 or the determination of Unforced Capacity Obligations.62  Moreover, PJM’s Filing does not include any mention of exempting Eligible New Large Loads from a capacity charge other than its cursory statement that “[t]he net result” of the compensation that may be paid to Eligible New Large Loads subject to curtailment “is a reduced capacity charge for Eligible New Large Loads.”63  But even if this compensation was intended to offset the capacity costs Eligible New Large Loads will pay for, it is only a partial offset.  And, as PJM concedes, there is no guarantee that such compensation will even be awarded to Eligible New Large Loads.”64

The cost causation principle “generally calls for giving the same treatment to new and continuing customers, [w]here ‘all customers cause the incurrence of the costs . . . , whether by adding or merely continuing their usage[.]”65  But this principle is founded upon the understanding that all customers contributing to the costs will be given an equal opportunity to enjoy the corresponding benefits.  It is inconsistent with cost causation to force Eligible New Large Loads to bear the cost of Demand Resources that will not be used to provide them with service.  And if Eligible New Large Loads are to bear the costs of these capacity resources, then Demand Resources committed to provide capacity should be deployed prior to interrupting service to Eligible New Large Loads.

61 PJM, Reliability Assurance Agreement Among Load Serving Entities in the PJM Region § 7.2 (“[E]ach Party shall pay, as to the loads it serves in each Zone during a Delivery Year, a Locational Reliability Charge for each such Zone during such Delivery Year.  The Locational Reliability Charge shall equal such Party’s Daily Unforced Capacity Obligation in a Zone, as determined pursuant to RAA, Schedule 8, times the Final Zonal Capacity Price for such Zone, as determined pursuant to Tariff, Attachment DD.”).
62 PJM, Reliability Assurance Agreement Among Load Serving Entities in the PJM Region, Schedule 8.
63 Filing, Transmittal Letter at 104.
64 Id. at 106 (stating that “how this wholesale rate is used to compensate for IRAS and how it is used to collect monies for such compensation will be left to the Electric Distributors that directed the specific load reductions to implement IRAS, consistent with their state-approved program…”). 65 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (2014) (citations omitted).

PDF page 22

- 22 -
To be clear, data centers are committed to paying their fair share of the costs associated with procuring sufficient capacity to maintain reliability in PJM.  Indeed, the DCC and the data center industry generally have been vocal proponents of proposals that allow data centers to bring their own capacity to mitigate the potential resource adequacy impact of large load integration. But where data centers in fact pay for capacity and that capacity is available to be called upon to preserve reliability, it is unjust and unreasonable for PJM to instead curtail data centers and other large loads rather than requiring paid-for capacity to perform.

3. PJM’s Proposal Will Require Customers In Zones With Large Load
Customers To Subsidize The Costs Of Capacity For The PJM Region
PJM’s IRAS proposal also presents a separate and distinct cost causation issue: customers located in electric distribution service areas where large loads are interconnecting will be required to subsidize the cost of capacity for the broader PJM region.  Under PJM’s proposal, Eligible New Large Loads will contribute to paying a share of Locational Reliability Charges and, thus, reduce the capacity costs borne by other customers across the PJM region.  PJM then proposes to offset these capacity costs by requiring Electric Distributors to compensate Eligible New Large Load customers that are curtailed under IRAS.  However, the costs of funding these payments to Eligible New Large Loads will not be allocated across the region.  Instead, PJM’s proposal contemplates that Electric Distributors will be required to fund these payments by imposing additional charges on the customers within their service territory.  The net result of this framework is that customers in service territories with large load growth effectively will be required to subsidize rate reductions for customers in other portions of the PJM footprint.66

PJM’s proposed payment scheme for funding payments to Eligible New Large Loads

66 Filing, Transmittal Letter at 101.  Indeed, PJM says that the rate paid to large loads for curtailment under IRAS by electric distributors is “intended to be conjoined with retail rates.” Filing, Transmittal Letter at 104.

PDF page 23

- 23 -
violates cost causation requirements.  As the courts have recognized, the cost causation principle prohibits the Commission from approving a rate scheme that requires one set of customers to subsidize the provision of service to others.67  In this case, the capacity-related benefits produced by Eligible New Large Loads would be shared across the PJM region through lower Locational Reliability Charges, but the costs of compensating those loads for IRAS curtailments would be imposed on customers in the host Electric Distributor’s service territory.  The result is a mismatch between costs and benefits: customers in areas experiencing large load growth are required to fund a regional benefit enjoyed by customers throughout PJM.  Cost causation principles do not permit such cross subsidization.

4. Providing Inferior Service At The Same Price Is Unjust, Unreasonable,
and Contrary To Cost Causation Principles
PJM also has not demonstrated that charging NITS customers serving Eligible New Large Loads the same transmission rates as other NITS customers is just, reasonable, and not unduly discriminatory or preferential.  The Commission repeatedly has recognized that the transmission rates imposed on customers must reflect the firmness of the service provided.68  In Order No. 888, the Commission recognized that “non-firm transmission prices should reflect the interruptibility of the service and should promote efficient use of the transmission system[.]”69  More recently, the Commission rejected the PJM Transmission Owner’s proposal to set the rate for Non-Firm Contract Demand transmission service equal to the rate for Firm Point-to-Point Service because it

67 El Paso Elec. Co. v. FERC, 76 F.4th 352, 363 (5th Cir. 2023).
68 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209, at P 406 (2026) (stating that “rates should vary based on the quality of the transmission service”). 69 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. & Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996), clarified, 76 FERC ¶ 61,009 (1996), order on reh’g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048, at 30272 (1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in part and remanded in part sub nom. Transmission Access Policy Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).

PDF page 24

- 24 -
found “the rates should vary based on the quality of the transmission service.”70  Under the IRAS proposal, NITS customers subject to interruption under IRAS would be required to pay the same transmission rates as other NITS customers despite receiving inferior service. PJM cannot have it both ways.  If NITS customers serving Eligible New Large Loads pay the same rates as other NITS customers, then they should receive a comparable level of service and be curtailed at the same time as other NITS customers.  Alternatively, if PJM is going to subject NITS customers serving Eligible New Large Loads to interruption ahead of other NITS customers, then the rates for these customers must reflect the lower quality of service being provided.  PJM’s proposal to offer less service at the same price is unjust, unreasonable, and contrary to cost causation requirements.

5. Excluding New Large Loads From The VRR Curve Will Undermine
Efforts To Maintain Reliability

At a time when PJM needs additional capacity to meet resource adequacy needs within the region, PJM’s proposal to exclude New Large Loads that do not meet BYONC requirements from the VRR Curve beginning with the 2029/2030 Delivery Year is counterproductive and misguided.71  The VRR Curve is intended to “produce accurate market signals that will encourage appropriate capacity investment and achieve an adequate level of reliability.”72  But the VRR Curve and the market as a whole can only send the price signals necessary to attract new investment if they accurately reflect supply-demand conditions within the PJM region.  By excluding Eligible New Large Loads from consideration in the capacity market, PJM’s proposal will result in a capacity market construct that will produce market prices and results that are

70 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209, at P 406 (2026).
71 Filing, Transmittal Letter at 23.
72 PJM Interconnection, L.L.C., 167 FERC ¶ 61,029, at P 19 (2019).

PDF page 25

- 25 -
untethered from market fundamentals within the PJM region.
The fact that excluding Eligible New Large Loads from the VRR curve will mute investment signals and undermine reliability has been acknowledged by PJM.  In the stakeholder process, PJM explained that it was important to model loads subject to IRAS in the RPM because “[i]ncluding Connect and Manage [now known as IRAS] in the RPM Auction continues to provide price signals for new investment while providing an incentive for New Large Load to BYONC through new supply or DR/DER.”73  Indeed, there would be no way for the market to send a price signal that additional supply is needed in the region if the market treats new demand as if it did not exist.  The PJM Board, however, modified the IRAS proposal to remove Eligible New Large Loads from the VRR Curve on the basis that “[i]ncremental new Large Loads relative to the forecast utilized for the 2028/2029 BRA will be excluded from the forecast used in future RPM auctions for the 2029/2030 Delivery Year and beyond unless and until there are new supply resources offered into an RPM auction in sufficient quantity to cover the new Large Load.”74  The PJM Board cannot expect new supply resources to appear if the price signals sent by the market do not reflect—as will be the case under PJM’s IRAS proposal—the actual load that must be served in the region.

While PJM’s proposal may temporarily suppress capacity prices, it will do so based on an utterly inaccurate view of the actual demand for capacity in PJM.  And if the RPM does not accurately reflect demand, it is hard to understand how PJM expects the RPM to send price signals that will ensure the entry of new resources capable of meeting the region’s needs.  As the

73 PJM CIFP – RBP / Connect and Manage - Stage 3 (May 27, 2026 – Meeting Materials), Connect and Manage PJM Package at 29 (May 27, 2026), available at: https://www.pjm.com/committees-and-groups/cifp-rbp.
74 PJM Post CIFP Workshop - Technical Overview, PJM Board - CIFP Framework for Service During Periods of Insufficient Resource Adequacy - Executive Summary (July 30, 2026), available at: https://www.pjm.com/committees-and-groups/cifp-rbp.

PDF page 26

- 26 -
Commission observed, a capacity market should “provide price signals that guide the orderly entry and exit of capacity resources, result in the selection of the least-cost set of resources that possess the attributes sought by the markets, provide price transparency, shift risk as appropriate from customers to private capital, and mitigate market power.”75  But a capacity market that does not send price signals that accurately reflect market fundamentals cannot achieve these objectives.

6. PJM’s Proposal To Provide Inferior Service To NITS Customers
Serving Eligible New Large Loads Is Unduly Discriminatory
IRAS is not merely a change to PJM’s emergency operating procedures.  IRAS degrades one of the defining characteristics of NITS—its curtailment priority—for a subset of customers. NITS customers historically have been entitled to receive “firm transmission service over the Transmission System for the delivery of capacity and energy from its designated Network Resources to service its Network Loads on a basis that is comparable to each Transmission Owner’s use of the Transmission System to reliably service its Native Load Customers.”76  When curtailments are required to maintain reliability, the transmission provider is required to curtail NITS customers on a non-discriminatory and pro rata basis consistent with the treatment of native load and firm point-to-point customers.77

This will no longer be the case if IRAS is accepted.  In practical terms, IRAS creates a form of second-class NITS customers.  NITS customers serving Eligible New Large Loads will continue purchasing NITS and paying the same transmission and capacity charges as other firm customers.  Yet, these NITS customers and the Eligible New Large Loads that they serve will be deprived of one of the principal benefits of NITS: protection from service interruptions and

75 ISO New England Inc., 162 FERC ¶ 61,205, at P 21 (2018).
76 PJM Tariff, Part III § 28.1.
77 PJM Tariff, Part II § 13.6; id., Part III § 33.5.

PDF page 27

- 27 -
curtailment on a basis comparable to other firm uses of the system.78  PJM cannot charge customers for firm service while reserving the right to treat them as interruptible customers when reliability conditions deteriorate.

The FPA prohibits public utilities from engaging in any undue discrimination or granting any undue preference or advantage in providing transmission service.79  Undue discrimination or preference occurs, as both the courts and the Commission have held, when similarly situated customers are treated differently “for no good reason.”80  To justify treating customers differently, the prohibition on undue discrimination requires that the utility proposing disparate treatment demonstrate that there are “specific factual differences” between the customers that justify the specific rates, terms, and conditions imposed by the utility.81

PJM does not deny that its proposal is discriminatory.  Instead, it attempts to justify the differences in treatment by pointing to the Commission’s decision to require PJM to revise its tariff to create a definition for large loads and cites to general statements by the Commission that large loads are unique and pose specific challenges to the transmission system.82  But PJM cannot justify the disparate treatment proposed in this case by making general references to the unique challenges posed by large load integration.  The issue is not merely whether there are some differences between the classes at issue; but whether there are differences that are “material to the inquiry at hand” that justify the specific differences in treatment that are being proposed.83

78 Filing, Transmittal Letter at 94 (stating that NITS customers serving Eligible New Large Load customers will “be asked to reduce load prior to other NITS customers in accordance with the Interim Resource Adequacy Service they may be asked to provide”).
79 16 U.S.C. § 824d(b).
80 Consol. Edison Co. of N.Y., Inc., 45 F.4th 265, 282 (D.C. Cir. 2022); State Corp. Comm’n of Kan. v. FERC, 876 F.3d 322, 335 (D.C. Cir. 2017).
81 See, e.g., Pub. Serv. Co. of Ind. v. FERC, 575 F.2d 1204, 1212 (7th Cir. 1978).
82 Filing, Transmittal Letter at 96.
83 N.Y. Indep. Sys. Operator, Inc., 162 FERC ¶ 61,124, at P 10 (2018).  See Basin Elec. Power Cooperative, 188 FERC ¶ 61,132, at PP 95-96 (2024).

PDF page 28

- 28 -
PJM has failed to meet its burden in this case.  As an initial matter, PJM’s suggestion that FERC has granted transmission providers carte blanche to discriminate against large load customers because of the characteristics of these customers is simply incorrect.  It is true that the Commission has required PJM to revise its tariff to include a definition of large load.  But the Commission also has sought to create new pathways for large loads to come online while protecting customers and maintaining reliability, including encouraging PJM and other transmission providers to revise their tariffs to create new transmission service products that better align with the characteristics of large load customers, create new interim pathways for the integration of large load customers and new generation capacity, and provide these customers with greater flexibility to calibrate their use of the transmission system to meet their needs.84  The notion that the Commission has found that large load customers inherently are less deserving of firm, predictable service is incorrect and unsupported by Commission precedent.

Additionally, PJM’s justification fails to account for the fact that IRAS will result in Electric Distributors serving large load receiving very different treatment based on the timing of when the load is placed into service.  Under IRAS, two Electric Distributors purchasing NITS to serve loads of comparable size and paying the same rate will receive fundamentally different services based on when their retail customers were placed into service.  For instance, an Electric Distributor that takes NITS to serve a 100 MW large load customer that is placed into service on May 31, 2027 will not be interrupted during an emergency until PJM initiates a manual load dump action after all capacity resources have been exhausted.  An Electric Distributor who takes NITS to serve a 100 MW large load customer that is placed into service one day later, on June 1, 2027,

84 See, e.g., PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 2 (2025) (directing changes to the PJM tariff to better account for the characteristics of large load customers).

PDF page 29

- 29 -
will not be guaranteed this same level of service unless they demonstrate that the retail customer’s load is supported by new capacity complying with PJM’s BYONC requirements.

The arbitrary nature of IRAS becomes especially apparent when applied to facilities with a load ramp.  Two otherwise identical MW of the same facility could be subject to different curtailment priorities solely because one increment of load came online before PJM’s cutoff date and the other came online after.85  Such vintage-based discrimination does not reflect any difference material to reliability or resource adequacy and cannot justify the disparate treatment at issue here.

Nor has PJM demonstrated that the timing of when load has come online is a legitimate basis for discrimination.  Existing resources, like new resources, contribute to the need for capacity86 and PJM has not explained why existing customers should receive preferential treatment.  IRAS appears premised on the assumption that New Large Load customers solely are responsible for recent supply shortfalls in the BRA.  But there are multiple factors that have contributed to the supply-demand balance within the PJM region, including the retirement of existing generation resources, the slow pace of new entry, and load growth within the region.87 PJM offers no evidence that a MW of demand imposes different resource adequacy impacts based solely on when the demand first takes service.  Nor does PJM explain why new customers should

85 As noted above, PJM proposes to define New Large Load as end-use customer load that is either a Large Load that goes into service after June 1, 2027 or incremental load in-service after this deadline that increases the existing end-use customer load at a site that did not previously meet the definition of Large Load.  Filing, Transmittal Letter at 1, n.2.  Although PJM’s proposed definition of New Large Load is ambiguous, DCC understands that PJM intends to subject any increment of load placed in service by a large load customer after the deadline to IRAS unless the increment is supported by capacity meeting PJM’s BYONC requirements.  However, DCC believes that the Commission should require PJM to clarify the scope of its proposal and its application to customers with load ramp periods that extend beyond the deadlines prescribed in the PJM tariff.
86 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014).
87 See PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment To Support Durable Reliability at 4 (May 6, 2026), https://www.pjm.com/- /media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market- design.pdf.

PDF page 30

- 30 -
bear the reliability impact of generation retirements or a broken interconnection process.  PJM’s proposal to afford less favorable treatment to customers merely because they are “new” is unduly discriminatory and should be rejected.

In short, PJM’s proposal to afford less favorable treatment to NITS customers serving Eligible New Large Loads is unduly discriminatory and preferential.  NITS customers serving Eligible New Large Loads are similarly situated to other NITS customers: they have reserved firm transmission to allow them to meet their supply obligations, pay the same transmission rates as other NITS customers, and will pay the costs of capacity that has been committed through the RPM to maintain reliability.  Yet, IRAS will result in NITS customers serving Eligible New Large Loads being afforded less favorable treatment than other NITS customers.  And PJM’s vague references to the unique characteristics of large customers are insufficient to justify the arbitrary differences in treatment under the IRAS proposal.

C. IRAS Fails To Account For Existing Contractual Arrangements And Reliance
Interests
Although PJM is permitted to make filings under FPA Section 205 to change its market rules, in evaluating these changes FERC must be cognizant that existing market rules “may have ‘engendered serious reliance interests that must be taken into account’”88 and “‘assess whether there were reliance interests’ in the prior rule, determine whether those interests ‘[are] significant,’ and weigh them ‘against competing policy concerns.’”89

PJM’s proposal to curtail a subset of retail customers that do not bring their own capacity represents a fundamental shift in how PJM’s markets have functioned for the duration of its existence.  For decades new loads in the PJM region were permitted to interconnect and obtain

88 Encino Motorcars, LLC v. Navarro, 579 U.S. 211, 212 (2016).
89 Solar Energy Indus. Ass’n. v. FERC, 80 F.4th 956, 980 (D.C. Cir. 2023) (quoting DHS v. Regents of Univ. of Cal., 140 S. Ct. 1891, 1914 (2020)); Capital Power Corp. v. FERC, 156 F.4th 644, 653 (D.C. Cir. 2025).

PDF page 31

- 31 -
service based on the same rates, terms, and conditions that were afforded to all other customers. Service to load in PJM was not conditioned on such load bringing its own new capacity.  PJM’s IRAS proposal drastically alters the ability of certain loads to obtain reliable service in PJM by limiting New Large Loads to receiving an inferior service until they procure their own new capacity.  PJM proposes these significant structural changes without any transition mechanism or even acknowledging the potential impact on customers’ investment decisions.

PJM’s proposal will undermine the settled expectations of New Large Loads that have made investment decisions and entered into contracts based on their ability to receive firm service consistent with long-standing market rules and retail requirements.  As the Commission has acknowledged, Large Loads have entered into binding contractual obligations and made significant investments in reliance on the ability to obtain reliable service within the PJM region based on its longstanding rules.90  These arrangements include entering into energy supply and transmission service agreements, executing leases with data center tenants, obtaining real property interests, posting security for the construction of line extensions and other physical infrastructure, and entering into financing agreements necessary for the construction of their facilities.  PJM’s proposal will undermine the economic assumptions underpinning these arrangements by forcing New Large Loads to accept less reliable service—which may not align with the contractual commitments made to their tenants—or incurring significant new costs to ensure that they receive the same level of firm service that historically has been available.

90 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, at P 5 (2026) (“We recognize that large loads, including data centers, are actively working with transmission owners and other relevant entities to interconnect to, and to take service from, the transmission system. We appreciate that different large loads are currently at different stages of that process. We also understand that large loads and Eligible Customers taking transmission service on behalf of large loads are negotiating, entering into, and/or have executed various agreements related to interconnecting to the transmission system and/or the provision of transmission service.”).

PDF page 32

- 32 -
The disruption from IRAS will not be limited only to New Large Loads that first place their facilities into service after June 1, 2027 (or subsequent deadlines established by PJM).  IRAS also appears to extend to incremental load placed in service by an existing customer after this date.  In practice, this means that IRAS will extend to data center customers that have placed their existing facilities into operation but that have load ramp schedules that extend beyond June 1, 2027.  If IRAS is approved, these customers will now face the prospect that a portion of their loads will be deemed interruptible unless they comply with PJM’s BYONC requirements.

In some cases, it simply will be too late for large load customers to revisit their investment decisions or rewrite contracts that were entered into years prior.  Even if a data center has some flexibility to renegotiate existing leases with their tenants, it would have to attempt to renegotiate these arrangements without certainty regarding how IRAS will be implemented, how relevant state authorities plan to address IRAS, or when the data center will be able to guarantee firm service for its tenants.  The significant uncertainty that would be created by approval of IRAS has the potential to create new obstacles to the completion of data center projects that have been under development for years.

Moreover, IRAS establishes what is effectively a less than 10-month window for New Large Loads to obtain their own new capacity to avoid curtailment.  As the Commission is well aware91 and as PJM’s own documented struggles with bringing new resources online

91 See, e.g., PJM Interconnection, L.L.C., 190 FERC ¶ 61,084 (2025) (Comm’r Rosner and Phillips, concurring at P 2) (“PJM’s legacy interconnection process is overwhelmed by the volume of requests to connect new generation and storage, causing the typical wait time in PJM’s queue to exceed five years.   While long overdue, PJM’s transition away from a legacy serial process includes the unfortunate feature of pausing study of all new interconnection requests while PJM implements its new, faster process.”).

PDF page 33

- 33 -
demonstrate,92 this timeline does not provide a realistic opportunity for New Large Loads to meet the BYONC requirements and avoid curtailment.  The result will be a significant disruption to nearly all large load projects with a post-June 1, 2027 in-service date that is likely to threaten the viability of many projects that are essential for maintaining the nation’s competitive edge in the global economy.

PJM’s implementation timeline for IRAS and failure to include a transition mechanism is
even more alarming given that many of the regulatory structures PJM acknowledges that states must adopt to give effect to IRAS have yet to even be proposed.93  While certain state commissions like the VA SCC may have commenced efforts to establish a regulatory scheme that is consistent with IRAS,94 such efforts have not been mirrored by most of the PJM state commissions.  As a result, New Large Loads will be forced to scramble to comply with an entirely new service paradigm in PJM while the rules necessary for implementing IRAS in their relevant states are still being developed.  Undermining the settled expectations of large load customers will alone present a significant challenge to the ability of large load customers to move forward with their projects,

92 PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment To Support Durable Reliability at 4 (May 6, 2026), https://www.pjm.com/- /media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market- design.pdf.  (“Construction timelines have doubled. A decade ago, the market’s three-year forward procurement horizon was calibrated to the development timeline of the market’s reference technology.  Today, a new natural gas turbine plant – the reference technology for the capacity market – requires at least four years under optimistic assumptions from financial investment decision to commercial operation, due to supply chain constraints on major equipment (gas turbines, step-up transformers), extended permitting and interconnection timelines, and larger project scale.”).
93 Filing, Transmittal Letter at 86-87 (“PJM will not direct specific LSEs and/or specific customers of LSEs— including specific Large Loads—to reduce their load and/or switch to on-site backup resources.  Those decisions would be worked out through revised state retail tariffs.”) (emphasis in original).
94 Id. at 88 (citing Letter of Chair of Virginia State Corporation Commission, Kelsey Bagot and President and CEO of Data Center Coalition, Josh Levi to Ms. Paula Conboy, Chair of PJM Board of Managers, and Mr. David Mills, President and CEO of PJM Interconnection, L.L.C. at 2 (June 30, 2026), https://www.pjm.com/- /media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-written-comments---va-scc-and-data-center- coalition.pdf).

PDF page 34

- 34 -
but disrupting their settled expectations and making them plan for a service paradigm in which the rules are still being developed presents a challenge of a different magnitude.

PJM’s proposal to subject a subset of retail load to mandatory curtailments represents a stark departure from the historic paradigm in which customers were able to obtain reliable service on the same rates, terms, and conditions as all other customers.  While DCC supports BYONC requirements, such requirements must be implemented on a timeframe that provides large loads a reasonable opportunity to comply.  The fact that PJM has proposed this departure from its prior rules without including a transition mechanism as part of its proposal or even considering the reasonable reliance interests of large loads further warrants rejection of the Filing by the Commission.

D. The Commission Should Reject IRAS Or Impose A Meaningful Transition
Mechanism
DCC urges the Commission to issue an order rejecting IRAS while encouraging PJM to pursue alternative pathways that better align with the jurisdictional divide established by the FPA. As noted above, DCC believes that the objectives underlying IRAS can be achieved by allowing states to take the lead in establishing interruptible retail service schedules while PJM modifies its operational practices to accommodate the choices of states within its footprint.  For that reason, DCC believes that any order in this proceeding rejecting IRAS should encourage PJM to work with states to pursue a framework that respects the authority reserved to the states under the FPA while protecting residential customers from service disruptions during emergency conditions. Alternatively, if the Commission determines based on the record in this proceeding that PJM’s emergency procedures must be reformed immediately, then it should initiate a Section 206 proceeding to determine how PJM’s emergency procedures can be modified to mitigate reliability risks without encroaching on state jurisdiction over the rates, terms, and conditions of retail

PDF page 35

- 35 -
service.  While DCC believes that any effort to modify the curtailment priority of retail customers must be led by the states, a Section 206 proceeding would provide the Commission and other parties opportunities to further explore what changes can be made to the wholesale market to further mitigate reliability risks.

Finally, even if the Commission is inclined to approve IRAS, it should direct PJM to modify its proposal to establish a meaningful transition mechanism that avoids disrupting existing contractual arrangements and investment decisions, and provides large load customers and the states a reasonable implementation timeline.  Among other things, any transition mechanism should limit the application of IRAS in a manner that respects existing contracts and investment decisions (e.g., exempting large load customers that already have entered into contracts for retail service prior to the implementation date of IRAS).  The Commission also should direct PJM to delay implementation of IRAS until June 1, 2028 to provide new large loads a reasonable amount of time to procure new capacity before they are subject to IRAS and to provide state authorities sufficient time to modify their retail policies as necessary to account for the IRAS framework.

III. MOTION TO INTERVENE
DCC respectfully moves to intervene in this proceeding. DCC is the membership
organization for the U.S. data center industry, representing leading data center owners and operators that develop, operate, and maintain data center infrastructure and teams across the country.95  DCC members operate data centers that constitute significant loads within the PJM

95 The DCC is a membership organization of leading data center owners and operators.  Public testimony and written comments submitted by DCC do not necessarily reflect the views of each individual DCC member.  A list of current DCC members is accessible at https://www.datacentercoalition.org/members.

PDF page 36

- 36 -
region and DCC has been an active stakeholder in regional efforts to ensure reliability, enable new generation, and discipline load forecasts.

DCC’s member companies provide the essential digital infrastructure that underpins the modern economy and supports critical public services, including cloud computing, artificial intelligence, emergency response systems, and public safety operations.  From 2017 to 2023, the data center industry contributed $3.5 trillion to U.S. GDP.  As the industry unlocks unprecedented economic opportunities across the country and in the PJM region, supporting affordability is a foundational priority for DCC members and the communities they serve.  DCC advocates for grid reforms that minimize unnecessary cost burdens, align with cost causation principles, facilitate responsible load growth, support the development of new generation, and enhance grid resilience system-wide without imposing undue costs on existing ratepayers.

For the above reasons, DCC has a substantial interest in the outcome of this proceeding that cannot be represented adequately by any other participant to this proceeding.  DCC’s intervention is in the public interest and its motion for leave to intervene in this proceeding should be granted.

PDF page 37

- 37 -
IV. CORRESPONDENCE AND COMMUNICATIONS
DCC requests that the following names be placed on the official service list for this proceeding by the Commission and that all correspondence and communications with respect to this proceeding be addressed to the following:96

Morgan A. Sipple
Director, Energy Policy – FERC and RTOs
DATA CENTER COALITION
1250 H Street, NW
Washington, DC  20005
morgan@datacentercoalition.org

Stephen J. Hug
Ben N. Reiter
AKIN GUMP STRAUSS HAUER & FELD LLP
2001 K Street, N.W.
Washington, D.C.  20006
Tel: (202) 887-4000
shug@akingump.com
breiter@akingump.com

V. CONCLUSION
For the reasons set out above, DCC respectfully requests that the Commission issue an order consistent with this protest.

Respectfully submitted,

/s/ Stephen J. Hug
Morgan A. Sipple
Director, Energy Policy – FERC and RTOs
DATA CENTER COALITION
1250 H Street, NW
Washington, DC  20005
morgan@datacentercoalition.org

Data Center Coalition
Stephen J. Hug
Ben N. Reiter
AKIN GUMP STRAUSS HAUER & FELD LLP
2001 K Street, N.W.
Washington, D.C.  20006
Tel: (202) 887-4000
shug@akingump.com
breiter@akingump.com

Dated: September 3, 2026

Counsel for the Data Center Coalition

96 DCC respectfully requests waiver of Rule 203(b)(3) of the Commission’s regulations, 18 C.F.R. § 385.203(b)(3), in order to permit designation of more than two persons for service in this proceeding.

PDF page 38

Exhibit A
Letter to Ms. Paula Conboy and Mr. David Mills from VA SCC Chair, Kelsey Bagot and DCC President & CEO, Josh Levi

PDF page 39

Confidential
June 30, 2026

Ms. Paula Conboy, Chair, PJM Board of Managers
Mr. David Mills, PJM President and CEO
PJM Interconnection, L.L.C.
2750 Monroe Boulevard
Audubon, Pennsylvania 19403

Dear Ms. Conboy and Mr. Mills:
The Virginia State Corporation Commission (VA SCC), along with its fellow PJM state utility commissions, is mandated to ensure reliable electric service, just and reasonable retail rates, and to protect residential and traditional industrial customers from undue cost shifts as the electric system continues to evolve. The growth of large electric loads presents both significant opportunities for economic development and important challenges for maintaining affordability and reliability across the PJM region. The Data Center Coalition (DCC) is the national membership association for the data center industry, representing leading data center owners and operators who maintain data center infrastructure across the country and globe, as well as companies that lease large amounts of data center capacity.1  DCC represents many of the companies driving investment in the PJM region and seeks to ensure that its members have timely, efficient, and predictable pathways to secure the power necessary for their operations. DCC members are fully committed to bearing the costs associated with serving their load to ensure existing customers are protected from any undue cost shifts.

Together, the VA SCC and DCC recognize that the mandate of state utility commissions and serving emerging large loads are not mutually exclusive. Rather, achieving them will require proactive collaboration among states, industry, and PJM to develop standardized regulatory tools and model retail tariff structures that individual state commissions may consider as they address the integration of new large electric loads. By working collaboratively now, we believe it is possible to facilitate continued economic investment while preserving reliability and protecting existing customers from inappropriate cost shifts. Because many of the tools necessary to achieve these objectives fall within state jurisdiction, the VA SCC and DCC are launching a collaborative effort to develop model retail tariff structures and regulatory frameworks for consideration by interested state commissions.

State-Level Interruptible Tariffs and Load Reduction Priorities
The VA SCC and DCC will convene a joint working group with other interested states to develop model state regulatory frameworks that enable states to better integrate large loads while maintaining reliability

1 The Data Center Coalition is a membership organization of leading data center owners and operators. Public testimony, written comments and letters submitted by DCC do not necessarily reflect the views of each individual DCC member. A list of current DCC members is accessible at https://www.datacentercoalition.org/members.

PDF page 40

Confidential
and protecting existing customers. The initiative will focus on two complementary, but distinct, workstreams.

1. Model State Interruptible Tariffs
The parties will develop model retail interruptible tariff structures that state commissions may consider adopting to facilitate the integration of new large electric loads while maintaining reliability and protecting existing customers. These model tariffs would:

● Establish standardized retail tariff provisions under which large customers may receive interruptible service, whether through voluntary election or pursuant to state regulatory requirements;

● Define the operational expectations, customer obligations, and utility responsibilities associated with interruptible service;

● Establish the retail mechanisms through which interruptible customers would respond to requests for curtailment consistent with applicable state tariffs and regional reliability procedures; and

● Provide model tariff language for consideration by interested state commissions while fully preserving each state's independent regulatory authority.

The intended completion date for this work is no later than February 1, 2027.
2. Emergency Load Reduction
The VA SCC, DCC, and other interested states will jointly develop model state tariffs establishing emergency load reduction programs designed to protect residential customers during the most severe reliability emergencies while preserving reliable system operations. These model tariffs would:

● Establish retail mechanisms authorizing utilities to curtail designated large commercial and industrial customers, or require the use of available on-site backup generation, once PJM has exhausted all other available reliability resources, including demand response, but before implementation of broad manual load shed;

● Define the operational expectations, customer obligations, and utility implementation procedures associated with those programs; and

● Provide model tariff language for consideration by state utility commissions while preserving each state's independent regulatory authority.

By targeting reductions from large commercial and industrial customers before implementing widespread feeder-level outages, this approach can significantly reduce the likelihood that residential customers are interrupted during the most severe reliability emergencies. It is particularly beneficial for jurisdictions with little or no large-load development, where residential customers could otherwise be subject to manual load shed even though targeted reductions of large loads—or deployment of available on-site backup generation—in other parts of the PJM region would have been sufficient to address the reliability need.

The intended completion date for this work is no later than February 1, 2027.

PDF page 41

Confidential
Reliability Backstop Cost Allocation
The VA SCC, DCC, and other interested states will also collaborate to develop model state tariff provisions addressing the retail allocation of costs associated with PJM's Reliability Backstop Procurement.

The objective is to develop transparent retail mechanisms that appropriately assign reliability backstop costs to the large load customers whose demand contributes to the need for those procurements, while protecting existing residential and traditional industrial customers from inappropriate cost shifts. The intended completion date for this work is no later than January 1, 2028.

Moving Forward
This collaborative effort reflects our shared commitment to finding practical, durable solutions that balance reliability, affordability, economic development, and regulatory certainty. Together, the VA SCC and DCC recognize that these objectives are complementary. Achieving them will require proactive collaboration among states, industry, utilities, and PJM to develop standardized regulatory tools and model retail tariff structures that state utility commissions may consider as they address the integration of new large electric loads. We also recognize that meeting the region's growing electricity demand will require significant investment in new generation and other energy resources. DCC members are committed to pursuing those investments, and both the VA SCC and DCC recognize that clear, predictable regulatory frameworks are essential to supporting the investment in new generation and energy resources needed to reliably serve the region's growing demand while protecting existing customers.

We appreciate PJM's continued leadership on these matters and look forward to working collaboratively with PJM, the states, and all stakeholders as these efforts move forward.

Sincerely,
Kelsey Bagot
Chair, Virginia State Corporation Commission

Josh Levi
President & CEO
Data Center Coalition

PDF page 42

Exhibit B
DCC Connect & Manage Alternative: State-Led Implementation with Immediate Residential Customer Protection

PDF page 43

DCC Connect & Manage Alternative:
State-Led Implementation with Immediate Residential
Customer Protection
The Data Center Coalition supports PJM’s objective of ensuring that new large loads contribute to maintaining system reliability and that sufficient capacity is developed to support continued economic growth. We agree that reliability must be maintained and that new capacity should accompany significant new load additions. At the same time, implementation frameworks must provide clear customer treatment, align obligations with benefits, and protect existing customers.

DCC’s proposal is founded on the principle that large-load integration requires coordination among PJM, states, electric distribution companies (EDCs), and customers. Durable solutions must recognize the respective roles of wholesale and retail regulators while providing certainty regarding reliability obligations, customer protections, and curtailment treatment.

State Opt-In Framework
DCC proposes a State Opt-In model that allows states and EDCs to establish interruptible service classifications and customer treatment rules while PJM continues to administer wholesale reliability requirements. Under this approach:

• States establish interruptible customer classes and associated tariff provisions for large- load customers.

• PJM monitors system conditions and, when reliability conditions warrant, issues a wholesale reliability signal for interruption of interruptible load.

• The PJM signal activates the applicable state interruptible tariff.
• The EDC implements curtailments in accordance with state-established customer classifications, priorities, and protections.

• PJM maintains responsibility for bulk-system reliability, while states retain authority over retail customer classifications and curtailment treatment.

• This approach achieves the desired reliability outcome while preserving the traditional division of state and federal responsibilities and avoiding the jurisdictional concerns associated with PJM directly imposing mandatory curtailment obligations on retail customers.

PDF page 44

• The framework also preserves incentives for customers to support the development of new capacity resources.

The proposal acknowledges a practical reality: regardless of the wholesale framework adopted, states and EDCs ultimately determine how customers are treated during emergency conditions. By explicitly incorporating state implementation into the framework, the proposal creates a more transparent and durable path for integrating large- load growth while maintaining reliability.

The state-led approach is also necessary to avoid significant jurisdictional concerns. Any framework that requires PJM to impose mandatory curtailment obligations based on the characteristics of specific retail customers risks blurring the longstanding division between wholesale and retail regulation. By relying on states and EDCs to establish customer classifications, interruptible service arrangements, and curtailment priorities, the proposal preserves the traditional regulatory compact while allowing PJM to maintain reliability through wholesale market signals.

Immediate Reliability Action to Protect Residential Customers
While states develop long-term large-load tariffs and customer classifications, PJM, states, and EDCs should take immediate action to strengthen emergency load-shed procedures and better protect residential customers.

DCC proposes a phased manual load-shed approach under which large commercial and industrial customers are contacted and provided an opportunity to curtail load before residential customers are interrupted during emergency reliability events. States and zones without significant large-load customers available for curtailment would not be expected to participate in the initial phase. Instead, the first phase would focus on areas where large commercial and industrial load reductions can be achieved. Residential customers and critical services would remain a last-resort option after practical large-customer curtailment opportunities within the affected area have been exhausted.

This recommendation is significant because it can be implemented immediately and does not require states to first complete lengthy tariff, rulemaking, or customer-classification proceedings. It provides a practical bridge between today’s reliability challenges and the longer-term frameworks currently under development across the PJM region. The approach offers several benefits:

• Provides immediate protection for residential customers.
• Reduces the likelihood that residential and critical-service customers are interrupted.

PDF page 45

• Preserves state authority over retail customer classifications and curtailment priorities.
• Improves reliability outcomes during emergency conditions using existing operational tools and processes.

• Creates time for states, EDCs, customers, and PJM to develop durable long-term solutions without delaying meaningful residential customer protections.

Conclusion
DCC’s proposal advances PJM’s reliability objectives while providing a practical implementation pathway that aligns responsibilities among PJM, states, EDCs, and customers. The State Opt-In framework recognizes the realities of retail implementation, preserves incentives for new capacity development, and provides greater clarity regarding customer obligations and protections. Combined with immediate actions to better protect residential customers during reliability emergencies, the proposal offers both a near-term and long-term path for maintaining reliability while supporting continued economic growth throughout the PJM region.

PDF page 46

Exhibit C
DCC – A Path to Reliable Large-Load
Integration: Creating Certainty for Investment, Customers, and the Grid

PDF page 47

June 10, 2026
A Path to Reliable Large-Load Integration
Creating Certainty for Investment, Customers, and the Grid

PDF page 48

New Load Should Fund New Capacity
Industry practice has already shifted toward customer-funded capacity to protect existing ratepayers.

2

PDF page 49

Predictable Pathway to Firm Service
Large load needs regulatory certainty to confidently invest in new capacity. Key Takeaway:

Data Centers are
committed to invest in
new capacity once the
path to firm service
without paying twice is
assured.
3

PDF page 50

PJM Cannot Provide the Needed Answers
PJM lacks the authority to answer critical questions that customers need before investing billions to bring new supply to PJM.

Key Takeaway: PJM’s proposal depends on customer action
that PJM lacks authority to define, enforce, or guarantee. 4

PDF page 51

Large-load integration requires new
capacity and customer accountability.
Lasting solutions require states and PJM
to each perform their proper role.
5

PDF page 52

Connect & Manage:
Challenges

PDF page 53

Jurisdiction: Core Issue
C&M relies on retail customer characteristics to determine wholesale obligations creating a jurisdictional vulnerability. Curtailment obligations depend on retail customer characteristics.

Large-load size and interconnection date/ load ramp drives outcomes

Retail customer attributes become wholesale triggers Appears targeted at retail transactions

Raises Federal Power Act concerns
7

PDF page 54

C&M Is Not Really About Load Growth
Example
SCENARIO A
SCENARIO B
New Load
200 MW
100 MW
Customer Type
Many small loads
One large load
C&M Obligation
No
Yes

The outcome depends on customer type –

not the amount of load growth
8

PDF page 55

Undue Discrimination Risk
The proposal is not truly prospective – loads face different treatment based on ramp duration, not when they were put in service or contract terms. The difference is based on ramp timing. Proposed rules do not permit or contemplate evaluating contracts in place. Cost causation rationale is weak. 9

PDF page 56

Arbitrary Outcomes Created by Vintage
Cutoff dates create arbitrary results that are not based on load magnitude or system impact.

10

PDF page 57

Protection is Not Assured
The Claimed Benefit of BYONC Is Outside PJM’s Control Protection Must Be Real

• PJM cannot dictate retail curtailment decisions
• States and EDCs determine actual load-shed priorities
• Meeting PJM requirements may not guarantee protection
• Customers may still face curtailment despite meeting PJM’s BYONC requirements

• Benefits and obligations may not align
Customers need certainty regarding the benefit they receive for bringing new capacity.

11

PDF page 58

What Service Is Being Purchased?
• C&M load remains subject to interruption
• Customers continue paying for firm transmission (NITS)
• The proposal does not clearly establish what reliability rights accompany C&M treatment

• Undue discrimination relative to DR and disruption of DR contracts
• Benefits and obligations may not align
• Customers need certainty regarding the service they are purchasing Service Classification Mismatch

If customers are subject to interruption, the associated service rights and classifications should be clearly defined.

12

PDF page 59

• States may require locational or “in state” resources
• States may impose policy priorities on the resource type, e.g., threshold % for  clean resources

• States may impose additional conditions on workforce or other requirements

• Pennsylvania illustrates this trend
• BYONC to PJM ≠ BYONC to State
State Policy Preferences Will Differ
Retail implementation will remain state-specific 13

PDF page 60

Operational, Policy, and Litigation Risks
Defining new load, implementing across states and EDCs, and allocating costs create significant operational, policy and legal risks without assured customer benefit 14

PDF page 61

So Where Does This Leave Us?
We Agree on the Objective
• Reliability must be maintained
• New capacity should accompany new large load
The Missing Piece
• States, EDCs, and PJM lack a coordinated framework for customer curtailment and protection

The Path Forward
✓ Respect and coordinate with state jurisdiction
✓ Create clear customer treatment rules
✓ Align obligations with benefits
✓ Preserve incentives for new capacity
15

PDF page 62

A Better Path Forward: State Opt-In Model 16

PDF page 63

Immediate Reliability Action
Manual Load Dump: Curtail Large C&I Before Residential Load
While states develop interruptible-load tariffs and customer classifications, States, EDCs, and PJM should immediately improve emergency load-shed procedures.

17

PDF page 64

• Large-load integration requires action from PJM, states, EDCs, and customers

• Initial feedback on the opt-in framework focused on what happens if states do not act - that risk exists under any C&M framework

• PJM cannot establish retail curtailment rules through assumption
• State implementation is a dependency whether acknowledged or not
• PJM's proposal assumes states will take actions that the tariff itself cannot require

• Our proposal explicitly recognizes the respective roles of PJM and the states.

State Action is Necessary and Unavoidable
Restoring the Regulatory Compact
Ignoring the need for state action does not eliminate the dependency, it only obscures it.

18

PDF page 65

Reliability Backstop
Mechanism

PDF page 66

We Support a Limited, Targeted Backstop
• Bilateral procurement remains the preferred path for securing new capacity

• DCC supported PJM's proposal for an extended bilateral procurement window before any backstop procurement

• We recognize PJM's need to move forward on a September timeline We Will Not Oppose a September Backstop Auction

• The backstop should supplement – not replace – bilateral procurement

The Backstop Must Remain Limited
• Procurement should be limited to demonstrated capacity shortfall that will not be addressed through bilateral arrangements. Reliability Backstop: DCC Position

20

PDF page 67

Procure Only for Load That Will Not Bilateral
• Backstop MWs should be limited to demonstrated reliability shortfalls
• Capacity should not be procured for customers actively pursuing bilateral solutions – particularly for load on the 2030+ timeframe

• Avoid duplicative procurement for the same future load
• The objective is to fill remaining gaps, not substitute for private contracting

Procurement: Limited to Residual Needs
21

PDF page 68

Cost Responsibility Established Up Front
Transparency and Accountability Matter
• Cost responsibility should be determined before procurement commitments are made

• Customers expected to fund procurement should be identified whenever feasible

• States and EDCs should provide notice before acting on behalf of specific customers

• Broad socialization should not replace targeted cost responsibility

Capacity procurement and cost allocation should be determined together —not sequentially.

22

PDF page 69

Meaningful Market Power Mitigation
Mean + 2 Standard Deviations is Not a Market Power Screen
• The benchmark is calculated from market offers
• Market offers may already reflect concentrated supply conditions
• Excluding statistical outliers does not establish that remaining offers are competitive

• The benchmark may continue to embed market power
• Consumer protections should be grounded in resource economics
• Consider a cap based on Net CONE (require support for costs > Net CONE) Mitigation Should Not Depend on Potentially Exercised Market Power A statistical filter is not a substitute for economic mitigation 23

PDF page 70

Pamela Quinlan
Principal, GQS
PQuinlan@GQSenergy.com

PDF page 71

CERTIFICATE OF SERVICE
I hereby certify that I have this day served a copy of the foregoing document on the persons designated on the official service list compiled by the Secretary in this proceeding.

Dated at Washington, D.C., this 3rd day of September 2026.
/s/ Stephen J. Hug

Stephen Hug