ER26-3650-000 · 2026-10-13 · Midcontinent Independent System Operator Inc.

Motion for Leave to Answer and Answer of Midcontinent Independent System Operator Inc. to the Comments and Protests re the proposal to establish Interconnection Reliability Requirements for Large Loads

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

Midcontinent Independent System

)
Operator, Inc.

)

Docket No. ER26-3650-000

)

MOTION FOR LEAVE TO ANSWER AND ANSWER OF THE MIDCONTINENT
INDEPENDENT SYSTEM OPERATOR, INC.

The Midcontinent Independent System Operator, Inc. (“MISO”) submits1 this Motion for Leave to Answer and Answer (“Answer”) to the comments and protests filed in the above- captioned docket by the Midwest TDUs,2 MISO Transmission Owners (“MISO TOs”), the North American Electric Reliability Corporation and Regional Entities (“NERC et al.”), the Organization of MISO States, Inc. (“OMS”), Entergy Services, LLC (“Entergy”), Google LLC (“Google”), the Large Energy Users,3 the Public Interest Organizations (“PIOs”),4 the Joint Consumer Advocates,5 the Data Center Coalition (“DCC”), Rowan Digital Infrastructure, LLC (“Rowan”), and Verrus, LLC (“Verrus”).

1 See Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”) (herein referred to the “Rules of Practice and Procedure”), 18 C.F.R. §§ 385.212 and 213 (2026). 2 The Midwest TDUs consist of Central Municipal Power Agency/Services (“CMPAS”), Indiana Municipal Power Agency (“IMPA”), Missouri Joint Municipal Electric Utility Commission (“MJMEUC”), and WPPI Energy (“WPPI”).
3 The Large Energy Users consist of the Coalition of MISO Transmission Customers, Illinois Industrial Energy Consumers, Association of Businesses Advocating Tariff Equity (“ABATE”), NIPSCO Large Customer Group, Louisiana Energy Users Group, and Texas Industrial Energy Consumers.
4 The PIOs consist of Sierra Club, Natural Resources Defense Council, Environmental Law & Policy Center, Clean Wisconsin, Union of Concerned Scientists, Sustainable FERC Project, and Fresh Energy.
5 The Joint Consumer Advocates consist of the Iowa Office of Consumer Advocate (“Iowa OCA”), Office of the Illinois Attorney General (“IL OAG”), Illinois Citizens Utility Board (“IL CUB”), Michigan Attorney General, Michigan Citizens Utility Board (“MI CUB”), Minnesota Department of Commerce (“Commerce”), Citizens Utility Board of Minnesota (“MN CUB”), Wisconsin Citizens Utility Board (“WI CUB”), Citizens Action Coalition of Indiana, Inc., and Alliance for Affordable Energy.

PDF page 2

2
The comments reflect support for MISO’s Interconnection Reliability Requirements Proposal (“IRR Proposal”) to establish reliability requirements for Large Loads, while several parties request modifications or clarification regarding specific aspects of the proposal.6  The pleadings reflect broad agreement on the central point underlying the IRR Proposal: the unprecedented scale, concentration, and operating characteristics of emerging Large Loads require additional visibility and operational reliability tools now.  Several parties expressly support the proposal or its core reliability framework, while other parties seek clarification or additional detail regarding implementation.7  Notably, only one protest requests the revisions to be rejected and MISO directed to file revised requirements by the end of 2027.8  And one comment requests that the revisions be rejected without prejudice to MISO filing a revised proposal.9  MISO believes the comments reinforce that MISO has put forth a balanced proposal that provides an opportunity to continue to move forward with the Commission’s desired outcome to support the appropriate integration of large loads onto the system in a reliable, efficient and transparent way. The comments and protests do not demonstrate that MISO’s IRR Proposal is unjust or unreasonable.  Several parties propose modifications to the definitions, transition provisions, or implementation of the proposed Large Load requirements, while others request that additional requirements or implementation details be included in the Tariff rather than MISO’s Business Practices Manuals (“BPMs”).10  These comments present alternative approaches to particular

6 MISO Transmission Owners Comments at 3, 6-7; Organization of MISO States Comments at 2-7; Verrus Comments at 2-4; Google Comments at 1-5; NERC et al. Comments at 6-9.
7 Id. 8 PIO Protest at 2.
9 DCC Protest at 25.
10  DCC Protest at 3-4; Google Comments at 2,7; Entergy Protest at 4-17; Southern Regulators Protest at 1-2; PIO Protest at 17-22.

PDF page 3

3
aspects of MISO’s proposal, but do not establish that the framework proposed by MISO fails to satisfy the requirements of Section 205 of the Federal Power Act.11  MISO’s proposal establishes requirements addressing the necessary visibility into Large Loads and their operation, including information, modeling, telemetry, and forecasting requirements, while also proposing specific requirements necessary to address the operational characteristics of Computational Loads.12 The Commission should therefore accept the IRR Proposal without delaying its

implementation or requiring MISO to expand this proceeding to resolve distinct large-load, transmission-service, or generator-interconnection issues.13  Accordingly, MISO respectfully requests that the IRR Proposal be accepted without modification and grant the requested effective date of December 4, 2026.

I. BACKGROUND
The IRR Proposal is an important near-term component of MISO’s broader response to rapidly accelerating Large Load development.  MISO’s 2026 Long-Term Load Forecast shows load growth at levels not experienced in decades, driven in substantial part by data centers, advanced manufacturing, and other large-load additions, some of which seek to develop on timelines materially shorter than traditional generation and transmission infrastructure.14  The North American Electric Reliability Corp (“NERC”) likewise has identified emerging computational loads as an increasing Bulk-Power System reliability consideration because conventional planning and operational assumptions may not capture the behavior of facilities that

11  16 U.S.C. § 824d.
12  IRR Proposal at 10-12, 19-26; Proposed Tariff §§ 37A.1-37A.8; Li Testimony at 12-14, 28-34.
13  IRR Proposal at 4.
14  IRR Proposal at 2, 7-8; Li Testimony at 5-10.

PDF page 4

4
are very large, capable of rapid demand changes, and increasingly dependent on power-electronic equipment.15

The Commission’s June 18, 2026 Show Cause Order preliminary found that MISO’s Tariff appears to be unjust and unreasonable because it lacks sufficiently clear and consistent Tariff provisions that address certain aspects of the process to provide transmission service to Eligible Customers on behalf of large loads, including: (1) a definition of large load sufficient to capture loads that present the unique challenges described in the Show Cause Order; and (2) ongoing operational requirements for transmission customers serving large loads necessary to ensure reliable operation of the transmission system.16  In response, MISO proposed Tariff revisions establishing ongoing operational requirements for transmission customers taking service on behalf of Large Loads, including hourly forecasts, telemetry and other visibility data, communications, monitoring equipment, ramp rates, and ride-through requirements.17  The IRR Proposal responds directly to those concerns through four complementary categories of requirements: (i) visibility requirements, including data, modeling, telemetry, and forecasting; (ii) PMU requirements for Computational Loads; (iii) ramp requirements for Computational Loads; and (iv) ride-through requirements for Computational Loads.18

This IRR Proposal has substantial support.  The MISO Transmission Owners support the IRR Proposal as a just and reasonable framework that complements MISO’s other Large Load

15  IRR Proposal at 2-3, 7-8; NERC, Essential Action to Industry - Computational Load Modeling, Studies, Instrumentation, Commissioning, Operations, Protection, and Control May 4, 2026.
16  Show Cause Order at P 57.
17  Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, at P 64 (2026) (“Show Cause Order”); IRR Proposal at 6.
18  IRR Proposal at 3-4, 9; Li Testimony at 10-11.

PDF page 5

5
initiatives.19  OMS generally supports the framework, including visibility, PMU, ramp, and ride- through requirements, and supports implementing requirements now while broader NERC standards continue to develop.20  Verrus supports MISO’s risk-scaled applicability and its use of the Tariff for core obligations with BPMs for implementation detail.21  NERC and the Regional Entities recognize that the IRR Proposal appears generally consistent with pending Reliability Standards efforts and describe MISO’s work as one contribution to advancing reliability while NERC and industry work in parallel.22

MISO recognizes that NERC and industry are working to mitigate the immediate reliability risks associated with computational load and does not intend the IRR Proposal to unnecessarily diverge from NERC’s developing framework.  At the same time, MISO recognizes that some NERC requirements, such as ride-through, will not begin development until 2027 and the urgency of immediate reliability risks necessitates NERC, MISO, and other stakeholders to act in parallel rather than sequentially; NERC recognizes this urgency as well.23  MISO has coordinated its proposal with emerging NERC guidance, and its stakeholder process expressly considered NERC’s Large Load and Computational Load work.24  NERC Project 2026-02 is itself moving rapidly: the initial posting was authorized August 19, 2026, and initial ballots on the first set of Computational Load standards concluded September 18, 2026.25  MISO will continue coordinating

19  MISO Transmission Owners Comments at 3, 6-7.
20  OMS Comments at 2-7.
21  Verrus Comments at 2-4.
22  NERC et al. Comments at 6-9.
23  NERC et. al. Comments at 7.
24  IRR Proposal at 28-30; Li Testimony at 36-39. 25  NERC, Project 2026-02 Computational Loads, Project Status (accessed Oct. 6, 2026).

PDF page 6

6
with NERC and will evaluate conforming changes as NERC’s registration criteria and Reliability Standards become final.

With the IRR Proposal, MISO is proposing to implement one part of a reliability-based framework to support the interconnection and ongoing operational challenges of Large Loads within the MISO region.  The objective is to establish scalable, technically justified, and risk- informed expectations that improve visibility into large load behavior, support planning and operational readiness, and preserve reliable operation of the Transmission System and Bulk Electric System.  The proposed framework is intended to complement existing and developing MISO planning, interconnection, and operational processes and align, to the extent practical, with emerging NERC guidance and industry practices.

II. MOTION FOR LEAVE TO FILE ANSWER

Under the Commission’s rules, answers to protests generally are not permitted.26 Nonetheless, the Commission waives this requirement where an otherwise prohibited answer would clarify the issues under consideration, ensure completeness of the record or assist the Commission in its decision-making.27

The comments and protests raise issues concerning the scope of MISO’s Large Load and Computational Load definitions, the transition framework, the division of requirements between the Tariff and Business Practices Manuals (“BPMs”), the responsibilities of Transmission Customers, and the operational forecasting requirements.  This Answer clarifies the record on

26  See Rule 213 of the Rules of Practice and Procedure, 18 C.F.R. § 385.213(a)(2) (2026).
27  See, e.g., Midcontinent Indep. Sys. Operator, Inc., 169 FERC ¶ 61,173, at P 24 (2019) (accepting MISO’s answer to protests because it assisted FERC in the decision-making process); Texas Eastern Transmission, LP, 122 FERC ¶ 61,205, at P 8 (2008) (accepting answer that completed the record); California Indep. Operator Corp., 105 FERC ¶ 61,284 at P 10 (2003) (accepting MISO’s answer that clarified the issues).

PDF page 7

7
those issues and explains why the IRR Proposal is just and reasonable as filed.  MISO therefore respectfully requests waiver of Rule 213(a)(2) and acceptance of this Answer.

III. ANSWER
A. MISO’S LARGE LOAD AND COMPUTATIONAL LOAD DEFINITIONS ARE JUST AND
REASONABLE.

1. The 50 MW Large Load threshold is reasonable, administratively
clear, and consistent with emerging industry practice.

The Commission should accept MISO’s Large Load definition as just and reasonable. As explained below, the 50 MW threshold — measured at Points of Withdrawal for facilities located at a single substation— (1) provides an objective, administrable screen for Large Loads; and (2) reflects specific characteristics of MISO’s transmission system; and (3) ensures necessary visibility through Section 37A; and (4) does so without a requiring a separate voltage criterion because applicability is already defined at the Transmission System boundary. First, MISO proposes to define a Large Load as Load with Demand of 50 MW or more associated with a facility or aggregation of facilities located at a single substation behind one or more Points of Withdrawal from the Transmission System and owned, operated, or controlled by a single entity or a coordinating group of entities; Load used exclusively for charging an Electric Storage Resource is excluded.28  MISO determined 50 MW was the appropriate threshold based on emerging industry practices, the reliability needs of the MISO region, and stakeholder feedback.29  For example, Southwest Power Pool’s (“SPP”) Commission-accepted HILL framework uses a 50 MW threshold to evaluate reliability impacts and operational requirements

28  IRR Proposal at 10-11; proposed Tariff Module A, § 1.L (Definition of “Large Load”); Li Testimony at 11-13.
29  IRR Proposal at 10-11; Li Testimony at 12-13.

PDF page 8

8
for load connected above 69 kV.30  NERC’s ongoing Computational Load initiative likewise has considered registration thresholds in this range, and the current process is expressly intended to align new computational-load functional entities with revisions to NERC Rules of Procedure Appendix 5B.31  Consistent with NERC’s recent developments, a 50 MW threshold is a reasonable and effective screening criterion, because it is sufficient to identify those loads whose individual operating characteristics warrants enhanced visibility to determine where specific requirements may be appropriate to address the identifiable aggregate risks to the transmission system.  Further, a 50 MW threshold is sufficiently material to warrant the Section 37A visibility requirements because it is consistent with NERC analysis that determined a 50 MW threshold captures the vast majority of computational load entities that pose aggregate risks to the Bulk Power System.32 Second, MISO’s footprint includes long transmission lines, constrained flowgates, and a diverse resource mix, all of which make large, fast-changing loads particularly consequential for real-time operations.  At this scale, a load’s behavior affects not only the local bus but also regional power flows and stability margins, making continuous visibility essential for reliable operations. Further, this threshold aligns with emerging NERC Technical Reasoning, which identifies that large, concentrated, and especially computational loads, exhibit fast-changing, electronics-driven characteristics that require elevated monitoring and disturbance-performance expectations.33  The

30  Sw. Power Pool, Inc., 194 FERC ¶ 61,031, at PP 13-21, 61, 64 (2026); SPP Tariff, pt. I, § 1, Definition of “HILL”.

31  NERC, Project 2026-02 Computational Loads, Project Details (2026); NERC Aug. 19, 2026 Technical Reasoning/Appendix 5B proposal reflecting current 50 MW threshold, available at: https://www.nerc.com/globalassets/who-we-are/rules-of-procedure/proposed/august-posting-technical- reasoning.pdf.

32  NERC, Proposed Computation Load Owner and Computational Load Operator, at 3. (https://prod.nerc.com/globalassets/who-we-are/rules-of-procedure/proposed/august-posting-technical- reasoning.pdf)
33  See NERC, Appendix 5B Technical Reasoning - Proposed Computational Load Entity (August 19,2026); available at: https://www.nerc.com/globalassets/who-we-are/rules-of-procedure/proposed/august-posting- technical-reasoning.pdf

PDF page 9

9
50 MW threshold represents the point at which load behavior becomes operationally significant enough that MISO system operators require additional data and performance assurance to maintain grid reliability.  The Commission need not require identical regional definitions, particularly where the Show Cause Order expressly recognized that an appropriate Large Load definition should reflect the characteristics of MISO’s transmission system.34  Under section 205, the Commission evaluates the proposal before it to determine whether it is just and reasonable and not unduly discriminatory or preferential.35  Multiple approaches may satisfy that standard, and MISO need not demonstrate that its proposed definition is the only reasonable approach or is superior to another potentially just and reasonable definition.36

Third, a 50 MW threshold also is technically appropriate because loads of this size create material system impacts—such as rapid demand swings, voltage and frequency disturbances, and dynamic interactions with power-electronic equipment, that cannot be reliably managed without enhanced modeling, telemetry, and forecasting.  Further, the threshold is sufficiently large to identify concentrated load additions that warrant enhanced visibility and reliability treatment while providing an objective and administratively clear rule.37  The IRR Proposal also provides clear and objective

aggregation
criteria—single‑substation
location,
common
or
coordinated
ownership/operation/control, and a 50 MW Demand threshold—which give customers advance notice of when aggregation applies and allow MISO to administer the rule consistently where

34  Show Cause Order at P 58 (explaining that an appropriate Large Load definition, including load size and interconnection voltage thresholds, should be based on the characteristics of MISO’s transmission system).
35  Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 662 (D.C. Cir. 2017) (explaining that, in reviewing a section 205 filing, the Commission restricts itself to evaluating the proposal before it); 16 U.S.C. § 824d(a)–(b).
36  Cities of Bethany v. FERC, 727 F.2d 1131, 1136 (D.C. Cir. 1984) (upholding the Commission’s evaluation of whether the proposed rate design was reasonable without requiring it to be superior to alternative designs); OXY USA, Inc. v. FERC, 64 F.3d 679, 692 (D.C. Cir. 1995) (explaining that a methodology need not be the only reasonable methodology or the most accurate).
37  Li Testimony at 12-13.

PDF page 10

10
common ownership, operation, control, or coordinated load profiles create the potential for aggregated transmission-system effects.38  Contrary to the Data Center Coalition’s concern that aggregation is insufficiently objective, the Tariff itself supplies the relevant limiting criteria: single-substation location, common or coordinated control, and a 50 MW Demand threshold.39 These criteria provide clear notice of aggregation applicability while preserving MISO’s ability to evaluate the system impacts and coordinated operations of coordinated facilities. These administrable criteria align with system behavior because the Transmission System is primarily impacted by the net electrical withdrawal at the point where the facilities connect, not the individual facilities behind that point.  Standard steady-state modeling treats such facilities as an equivalent aggregated load, and commonly owned or coordinated facilities typically behave as a unified electrical entity.  The single-substation boundary provides a clear, electrically meaningful point for aggregation while avoiding the inclusion of geographically dispersed and electrically unrelated facilities.  Even where multiple Points of Withdrawal exist, the facilities may affect shared substation equipment and upstream transmission facilities, resulting in a common or coordinated system impact.  Thus, the Tariff’s objective criteria both preserve notice and reflect the engineering reality of how aggregated demand interacts with upstream transmission equipment.

Fourth, no separate voltage threshold is necessary because Points of Withdrawal bound applicability across the Transmission System.  MISO’s Tariff definition of Transmission System includes both facilities over which functional control has been transferred to MISO and certain facilities over which MISO does not have functional control.40  Appendix H of MISO’s ISO

38  IRR Proposal at 10-11; Li Testimony at 12-13.
39  DCC Protest at 20-25; proposed Tariff Module A, § 1.L, Definition of “Large Load”.
40  Tariff Module A, supra note 29; see also Tariff Module A, § 1.T, Definition of “Transmission System”.

PDF page 11

11
agreement provides criteria governing the transfer of functional control of transmission facilities to MISO.41  Appendix H of the ISO Agreement provides the general criteria for these facilities as:

(1) all networked facilities above 100 kV; and (2) All transformers whose two highest voltages qualify under the above voltage criteria; and (3) all substation equipment that forms the endpoints of the transmission lines in item 1, terminate the transformers in item 2, or provide voltage/stability control.  The transferred facilities comprise the core of the MISO Transmission System.42  MISO’s Transmission System also includes certain Transmission Owner facilities where functional control has not been transferred.  Therefore, MISO appropriately defines an administrable scope in the IRR Proposal without duplicative and potentially confusing voltage criteria.

MISO’s proposed Large Load definition is just and reasonable. The 50 MW threshold is technically sound, regionally appropriate, operationally necessary, and administratively clear. Combined with measurement at Points of Withdrawal, it delivers the required visibility without imposing redundant voltage criteria. The Commission should approve the definition as a reasonable and well-supported approach to addressing the reliability concerns identified in the Show Cause Order.

2. The Computational Load definition appropriately targets additional
requirements to loads presenting distinct operational characteristics.

MISO separately defines “Computational Load” as a Large Load comprised of 25 MW or more of Demand from information technology equipment, such as servers, storage, and networking hardware.43  This definition serves an important risk-scaling function.  All Large Loads are  subject to the transition provisions, to basic facility data, modeling, telemetry, forecast-data, and audit

41  Tariff Rate Schedule 1.
42  Rate Schedule 01, Art. One, § I.T (Definition of "Transmission System").
43  IRR Proposal at 11; proposed Tariff Module A, § 1.C, Definition of “Computational Load”; Li Testimony at 11.

PDF page 12

12
requirements, while the incremental PMU, ride-through, and ramp requirements apply to Computational Loads.44

That distinction is supported by the record.  Computational Loads may exhibit rapid and coordinated changes in demand, significant power-electronic behavior, and distinct responses to transmission disturbances.45  The 25 MW computational component provides an objective measure of material computational content within an otherwise qualifying Large Load.  At the minimum 50 MW Large Load threshold, 25 MW represents half of the facility’s Demand, providing quantitative context for the emerging NERC concept of facilities that primarily contain information-technology infrastructure.

The unique and volatile power characteristics associated with Computational Load arise directly from the function of the underlying facility.  Although any individual Computational Load may, in isolation, appear unlikely to cause a material impact on Transmission System reliability, NERC has already determined through its Compliance Registry framework that entities which individually may not pose a material impact on reliability may nonetheless be required to register for applicable Reliability Standards and Requirements when the class has demonstrated to have such a such an impact in aggregate.46  MISO’s use of a 25 MW threshold for identifying Computational Load is directional aligned with NERC’s emerging Computational Load Site concept, which identifies computational facilities based on the presence of information-technology infrastructure such as servers, storage, and networking hardware.  Within MISO’s 50 MW Large Load applicability threshold, a 25 MW computational component provides an objective quantitative indicator that the facility contains material computational content and is therefore

44  Proposed Tariff § 37A.I; IRR Proposal at 11-12, 22-26.
45  IRR Proposal at 11-12; Li Testimony at 13-14.
46  NERC Registry Criteria Revision 5.2, Notes to Criteria, note 1 (footnote excluded).

PDF page 13

13
likely to exhibit the characteristic behaviors of computational loads—rapid and coordinated demand changes, software-driven control actions, and power-electronic responses to disturbances. This objective threshold enables MISO to proactively apply targeted PMU, ramp-rate, and ride-through requirements where the electrical behavior associated with computational activity is predictably present, rather than waiting for those behaviors to manifest in operations, which could expose the system to unmitigated reliability risks.

Google argues that reliability requirements should turn exclusively on electrical characteristics rather than end use, and DCC similarly seeks narrower and more predictable classification criteria.47  MISO agrees with the underlying principle that requirements should correspond to reliability risk; which is precisely why the IRR Proposal does not impose the incremental PMU, ramp, and ride-through requirements on every Large Load.48  The Computational Load definition is a reasonable proxy for the set of facilities currently known to present the rapid, coordinated, power-electronic behavior that motivated those requirements, and the Tariff authorizes MISO to determine whether Computational Load is associated with a Large Load based on information supplied by the Transmission Customer.49  MISO can refine implementation as operating experience and NERC standards develop without delaying protections that the record demonstrates are needed now.50

B. THE TRANSITION PROVISIONS REASONABLY PROTECTS EXISTING COMMERCIAL
ARRANGEMENTS  WITHOUT SACRIFICING RELIABILITY.

1. The transition framework directly responds to the Show Cause Order
and uses objective Tariff milestones.

47  Google Comments at 5-8; DCC Protest at 20-25.
48  IRR Proposal at 11-12; Li Testimony at 13-14.
49  Proposed Tariff § 37A.I.
50  IRR Proposal at 2-4, 7-9; NERC et al. Comments at 6-9.

PDF page 14

14
MISO’s transition framework responds to the Show Cause Order by using objective Tariff milestones to accommodate existing commercial arrangements and agreements nearing completion.  The Commission directed MISO to provide a reasonable implementation period that minimizes disruption to existing commercial arrangements, allows reasonable time to finalize ongoing agreements nearing completion when the Tariff provisions are filed, and establishes an effective date that accommodates those considerations.51  Paragraph 36 of the Show Cause Order further calls for a reasoned explanation of how the proposal will avoid disrupting existing commercial arrangements and an identification of a reasonable effective date that accommodates those arrangements.52  MISO’s framework addresses those objectives through differentiated treatment based on Service Commencement Date and the MTEP/EPR Condition, rather than requiring MISO to assess individual private contracts.53

First, a Large Load with a Service Commencement Date on or before December 4, 2026 is exempt from Section 37A with respect to the portion of the Large Load that has procured Transmission Service as of its Service Commencement Date.54  That exemption does not automatically extend to subsequent increases in Transmission Service. A modification or series of modifications resulting in a cumulative increase of 25 MW or more, with a Service Commencement Date after December 4, 2026, may subject the additional Load to Section 37A’s requirements, depending on whether the additional Load satisfies the applicable MTEP/EPR Condition and other transition criteria.55  The framework therefore distinguishes the previously

51  Show Cause Order at P 5; IRR Filing at 13.
52  Show Cause Order at P 36.
53  IRR Proposal at 13-15; Li Testimony at 23-27; proposed Tariff
54  Proposed Tariff § 37A.II.2(a); IRR Proposal at 14-15.
55  Id.

PDF page 15

15
exempt portion of the Large Load from additional Load commencing service after the effective date; the requirements applicable to that additional Load are determined under the Tariff’s transition provisions.56

Second, a Large Load, or portion thereof, that has not commenced service by the effective date but satisfies the MTEP/EPR Condition remains subject to visibility requirements while receiving an exemption from ramp and ride-through requirements.57  Third, a Large Load, or portion thereof, that does not qualify for those exemptions but is associated with a transmission project submitted for EPR after June 18, 2026 and on or before October 31, 2026 is generally subject to all applicable requirements, but MISO may, however, waive the ride-through requirements where an exemption would not adversely affect reliability and compliance would impose significant costs.58  Large Loads and additional load outside specified transition categories are subject to all applicable requirements.59

These provisions account for both commercial reliance and the costs of implementing new requirements.  The exemptions from ramp and ride-through requirements limit the potential need to revisit equipment selections and operating arrangements made in reliance on existing requirements, while the visibility requirements applicable to Load satisfying the MTEP/EPR Condition provide MISO with information needed to assess and manage reliability.  The limited ride-through waiver expressly addresses circumstances in which compliance would impose significant costs, but conditions relief on a determination that the exemption would not adversely

56  Id.
57  Proposed Tariff § 37A.II.2(b); IRR Proposal at 14-15.
58  IRR Proposal at 14-15; proposed Tariff § 37A.II.2(b)-(c).
59  IRR Proposal at 15.

PDF page 16

16
affect reliability.60  Significant costs alone therefore do not establish entitlement to a waiver.  This approach accommodates existing commercial arrangements while preserving a reliability assessment for the additional relief available under the waiver provision.

These milestones are preferable to a project-by-project inquiry into private commercial commitments.  DCC and Rowan propose transition protection based on executed agreements, equipment orders, investments, or other project-maturity evidence.61 Such an approach is unworkable for MISO.  Treating all agreements as a sufficient determination of project maturity would render the requirement largely meaningless, as such agreements may not indicate actual commitment.  Likewise, developing prescribed contractual terms and requirements would be unworkable for Large Loads whose commercial arrangements do not conform to predefined structures.  In the alternative, requiring MISO to make an individualized determination for each piece of evidence would require a degree of specialized legal knowledge and commercial expertise that MISO does not possess and could not reasonably acquire without significant staff augmentation.  Even with additional staff, applying individualized determinations across a geographical footprint that spans 15 states will almost inevitably involve discretionary judgements and lead to substantial disputes.  Those considerations may be relevant to a developer’s private economics, but they are not uniform milestones that can reasonably be administered by MISO under its Tariff.  Using private contracts would require MISO to evaluate agreements entered into and commercial commitments made outside of MISO’s Tariff framework to determine whether each project is sufficiently mature, introducing variability, disputes, and inconsistent treatment.62 By contrast, Service Commencement Date, MTEP approval, and EPR submission are objective

60  Proposed Tariff § 37A.II; IRR Filing at 14-15.
61  DCC Protest at 25-29; Rowan Protest at 3.
62  IRR Proposal at 13-14.

PDF page 17

17
milestones within MISO’s own processes and are readily verifiable and consistently administered.63

2. The transition provisions are narrowly tailored and preserve MISO’s
authority to address material adverse reliability impacts while
accommodating existing commercial arrangements.

MISO’s transition provisions operate within an existing framework of reliability assessments and local planning and interconnection requirements.  MISO’s Transmission Owners already evaluate load additions through their planning and interconnection processes; ATC, for example, maintains documented local planning and load-interconnection procedures.64  Section 37A’s ramp and ride-through requirements complement these existing practices by establishing consistent minimum performance expectations for Computational Loads across the MISO footprint.

MISO’s transition framework provides three forms of relief.  First, qualifying Large Loads with a Service Commencement Date on or before December 4, 2026, are exempt from Section 37A with respect to the portion of the Load that has procured Transmission Service as of that date. Second, qualifying Large Loads meeting the MTEP/EPR Condition remain subject to the applicable visibility and PMU requirements but are exempt from the ramp and ride-through requirements.  Third, eligible EPR submissions made between June 19 and October 31, 2026, remain subject to all applicable requirements, except that MISO may waive ride-through requirements upon determining that the exemption would not have an adverse reliability impact and compliance would result in significant costs.65  This framework thus balances the

63  IRR Proposal at 13-15; Li Testimony at 23-27.
64  Show Cause Order at P 28 & nn.74-75.
65  Proposed Tariff § 37A.II; IRR Proposal at 14; Li Testimony at 19022.

PDF page 18

18
Commission’s express concern of limiting impacts to existing and near-complete commercial arrangements with the need to preserve reliability.66

OMS, the PIOs, and the Joint Consumer Advocates raise concerns that the transition provisions could exempt a substantial quantity of existing or planned Large Load from some requirements.67  But the quantity of transitioned load does not establish that the transition framework is unjust and unreasonable.  The relevant question is how the differentiated transition provisions operate alongside existing reliability protections, retained information requirements, and MISO’s continuing authority to address reliability impacts.

The partial exemptions do not eliminate the information requirements that enable MISO to evaluate reliability risks.  Large Loads qualifying for partial exemptions remain subject to basic facility data, modeling, telemetry, forecasting, and audit requirements, as well as PMU requirements where applicable, under the prescribed compliance timelines.68  These baseline requirements provide the real-time and planning-stage information necessary to support contingency analysis, operational assessments, and the evaluation of disturbance performance, thereby maintaining system awareness even for partially exempt facilities.  In particular, the modeling provisions require verified models reflecting actual facility characteristics and continuing updates, while the forecasting provisions require current information supporting commitment and dispatch.69  The IRR framework complements MISO’s existing planning, interconnection, and operational processes, which continue to govern reliability evaluations and ensure that Large Loads are incorporated into model verification, forecasting, and operational

66  Show Cause Order at P 5; IRR Proposal at 13–14.
67  OMS Comments at 4-5; PIO Protest at 1-7; Joint Consumer Advocates Protest at 2-4.
68  Proposed Tariff § 37A.II.2(b); id. §§ 37A.1–37A.5, 37A.8.
69  Proposed Tariff §§ 37A.2, 37A.4; Li Testimony at 26:9-14.

PDF page 19

19
decision-making.  Although qualifying fully exempt loads receive broader relief, the transition framework does not categorically exempt developing Large Loads from the visibility requirements needed to assess their reliability impacts.

The transition provisions also do not create an absolute or perpetual reliability exemption. Section 37A expressly provides that, notwithstanding the transition provisions, MISO may require compliance with any or all Section 37A requirements if MISO determines that operation of a Large Load results in a material adverse effect on Transmission System reliability.70  Available models, planning assessments, operating data, and disturbance information can inform that determination and the identification of requirements needed to address the impact.  The process for making that determination and identifying which requirements must apply will be set forth in the Large Load BPM.71  This targeted reliability backstop preserves commercial certainty while allowing MISO to apply otherwise-exempt requirements where the Tariff’s reliability criterion is met.72 To the extent a party contends that the Tariff permits a Large Load to create reliability concerns while constraining MISO’s ability to act, MISO respectfully clarifies that the transition provisions do not limit, displace existing reliability obligations, or restrict MISO’s responsibilities as Reliability Coordinator.  IRO-001-4 requires MISO to address reliability within its Reliability Coordinator Area through direct action or Operating Instructions, and requires specified entities to comply with those instructions subject to the standard’s stated exceptions.73  Those obligations apply independently of a Large Load’s transition status.  Accordingly, the PIOs’ concern that MISO’s hands would be tied until a Large Load causes a reliability problem conflates the specific

70  Proposed Tariff § 37A.II.3.
71  Id.
72  IRR Proposal at 13–14; Li Testimony at 23:1–5; Proposed Tariff § 37A.II.3.
73  NERC Reliability Standard IRO-001-4, “Reliability Coordination—Responsibilities,” Requirements R1–R3.

PDF page 20

20
trigger for imposing otherwise-exempt Section 37A requirements with MISO’s continuing operational reliability responsibilities.  The transition provisions do not require MISO to await actual harm before exercising its existing reliability authority.

Finally, the IRR Proposal proceeds alongside NERC’s ongoing work to develop
Computational Load Reliability Standards and related registration criteria.74  That work provides a further opportunity for alignment as industry requirements evolve; it does not justify delaying the near-term protections proposed here.  Together, existing local requirements, retained visibility obligations for partially exempt loads, the targeted Section 37A backstop, and MISO’s continuing Reliability Coordinator responsibilities preserve reliability while accommodating the commercial arrangements identified by the Commission.

3. The cost-shifting arguments do not justify rejection or modification of
the IRR transition provisions.

The PIOs and Joint Consumer Advocates contend that exempting some Large Loads from facility-side requirements could lead to system mitigation costs that are borne by other customers.75  Those assertions do not establish a defect in this filing.  The IRR Proposal is directed to operational reliability requirements applicable to Large Load facilities and Transmission Customers; it does not purport to resolve the distinct questions of transmission-service design, study processes, or cost allocation identified in the Show Cause Order.76

MISO is separately developing proposals to address potential cost shifts associated with Large Load additions, along with additional transmission service products and enhanced Large Load application and study processes, for filing in connection with the Commission’s November

74  NERC, Project 2026-02—Computational Loads; IRR Proposal at 3.
75  PIO Protest at 3-7; Joint Consumer Advocates Protest at 3-4.
76  IRR Proposal at 1, 4, 9; Li Testimony at 9-11.

PDF page 21

21
16, 2026 deadline.77  The Commission should evaluate those cost-allocation issues on the record developed for those proposals rather than use speculative future cost outcomes to reject transition provisions that address a different and immediate reliability need.78

4. Rowan’s requested transition and review clarifications do not require
rejection of the filing.

Rowan requests additional specificity concerning project-maturity evidence, waiver documentation, review timelines, “material modifications,” and written decision criteria.79  Many of these requests concern implementation procedures that MISO is continuing to develop through the Large Load Working Group (“LLWG”) and the Large Load BPM.80  MISO notes it is continuing to work with collaboratively stakeholders through the LLWG and has posted draft BPM language for stakeholder review and feedback.81

C. THE IRR PROPOSAL PROPERLY PLACES CORE REQUIREMENTS IN THE TARIFF
AND IMPLEMENTATION DETAIL IN THE BPMS.

1. The Tariff contains the operative obligations and satisfies the
Commission’s Rule of Reason.

Entergy, the Southern Regulators, DCC, the PIOs, Google, and certain Large Energy Users argue in varying degrees that more technical detail should be placed in the Tariff rather than the BPMs.82  The Commission’s rule of reason requires tariff filing of provisions that significantly affect rates, terms, and conditions of service, are readily susceptible of specification, and are not

77  IRR Proposal at 4.
78  IRR Proposal at 1, 4.
79  Rowan Protest at 1-3.
80  IRR Proposal at 28-30; Li Testimony at 36-40.
81  LLWG BPM feedback response, tag Oct 8 meeting materials and feedback request. 82  Entergy Protest at 4-17; Southern Regulators Protest at 1-2; DCC Protest at 6-15; PIO Protest at 19-23; Google Comments at 7-8; Large Energy Users Protest at 7-9.

PDF page 22

22
generally understood in a contractual arrangement.83  It does not require every engineering parameter, data format, testing protocol, or implementation procedure to be frozen in a filed tariff.84  The Tariff appropriately balances the core details and principled requirements required for clarity within the tariff and the need for flexibility to address technical and administrative details that can mature in this particularly evolving area.

Section 37A contains the core obligations.  It identifies who is responsible for compliance; which requirements apply to all Large Loads and which apply only to Computational Loads; the categories of required facility information and modeling; the obligation to provide real-time telemetry; the requirement to provide forecast data; the location and ownership framework for PMU equipment; the obligation of Computational Loads to ride through specified disturbances; the measurement framework for ramp limits, including aggregate measurement at applicable Points of Withdrawal and eligibility for ramp smoothing; audit rights; transition categories; and consequences that may follow noncompliance.85  Those are the terms that establish the parties’ substantive rights and obligations.

The BPMs then provide the technical and administrative detail needed to implement those filed obligations consistently, including formats, timelines, technical performance curves, measurement intervals, validation protocols, communications specifications, and processes for determining remediation.86  That division is both practical and necessary in a rapidly evolving

83  Midcontinent Indep. Sys. Operator, Inc., 169 FERC ¶ 61,221, at P 67 2019, citing Energy Storage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296, at P 103 2018; City of Cleveland v. FERC, 773 F.2d 1368, 1376 D.C. Cir. 1985.
84  See Midcontinent Indep. Sys. Operator, Inc., 170 FERC ¶ 61,075, at P 38, 2020 (accepting use of BPM detail where tariff contained governing requirements and noting that tariff codification could curb needed operational flexibility.).
85  Proposed Tariff §§ 37A.I, 37A.1-37A.8, 37A.II; IRR Filing at 22-27.
86  IRR Proposal at 19-21, 23-27; Li Testimony at 28-35.

PDF page 23

23
technical area where MISO, NERC, equipment manufacturers, Transmission Owners, and Transmission Customers taking Transmission Service on behalf of Large Loads are continuing to gain operating experience.87

As industry gains experience with Large Loads, emerging usage patterns may provide insight into forecasting.  Ramp-rate limits are designed to ensure that changes in Large Load net demand do not pose unacceptable risk to the reliable operation of the transmission system. Technological advancements such as improved telemetry or enhanced forecasting may increase the maximum ramp-rate that the transmission system can reliably accommodate.  Because Large Loads rely on fast-acting controls, power-electronic interfaces, and increasingly sophisticated uninterruptible power supply systems, the detailed technical parameters that govern telemetry, PMU configuration, forecasting formats, ride-through curves, testing protocols, and ramp-rate measurement must remain adaptable as equipment capabilities evolve, NERC’s Computational Load Owner (CLO) standards finalize, and MISO gains operational experience with real-world Large Load behavior.  While the Tariff sets the binding reliability obligations, the technical implementation must evolve over time, and MISO expects continued refinement in areas such as telemetry resolution and data exchange methods, PMU placement and measurement settings, forecasting cadences, disturbance-performance envelopes, and ramp-measurement windows to ensure alignment with equipment capabilities, emerging NERC standards, and observed operating behavior.

2. The Commission’s acceptance of SPP’s HILL framework confirms
that a tariff may establish core Large Load obligations while leaving
implementation detail outside the tariff.

87  IRR Proposal at 2-4, 28-30; NERC et al. Comments at 6-9.

PDF page 24

24
The Commission recently accepted SPP’s HILL framework, which established enhanced study and ongoing operational requirements for high-impact loads, including nonconforming-load forecasting, real-time telemetry, remote-disconnect capability, a ramp-rate limit, installation of a PMU or similar equipment, and ride-through guidelines.88  The Commission did not require SPP’s tariff to reproduce every technical specification associated with each operational requirement; rather, the Commission accepted SPP’s ongoing operational requirements whose guidelines were set forth in a separate, non-tariff document.89  The relevant comparison therefore supports, rather than undermines, MISO’s approach: the Tariff must state the operative obligation and sufficiently constrain discretion, while technical implementation can be developed in manuals and guidelines. MISO’s proposed Tariff is clear on the fundamental categories of ongoing operational requirements identified by the Show Cause Order.  For example, Section 37A.7 states that Computational Load is subject to up- and down-ramp limits during stable-state transitions, measured in aggregate across applicable Points of Withdrawal, permits eligible generation or other resources to provide ramp smoothing, and provides for MISO to establish limits consistent with the BPM process.90  MISO has proposed initial up- and down-ramp limits of 30 MW/minute in its technical materials.91  Similarly, Section 37A.6 requires Computational Load to remain connected and continue operation during voltage and frequency disturbances within performance criteria established through the BPM, with compliance evaluated at the Points of Withdrawal.92

88  Sw. Power Pool, Inc., 194 FERC ¶ 61,031, at PP 13-21, 61, 63 (2026); Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212, at PP 22-23 & nn. 58-59 (2026).
89  Sw. Power Pool, Inc., 194 FERC ¶ 61,031, at PP 20-21, 63 (2026).
90  Proposed Tariff § 37A.7; IRR Proposal at 20, 26.
91  IRR Proposal at 20; Li Testimony at 30-32.
92  Proposed Tariff § 37A.6; IRR Proposal at 20-21, 25-26.

PDF page 25

25
MISO's initial ±30 MW/minute ramp limit establishes a reasonable, industry-informed baseline for managing rapid demand changes from Computational Loads.  The limit is intended to reduce sudden balancing needs and significant changes in transmission flows during stable-state transitions, while providing a consistent and predictable operating expectation.  This initial limit is informed by comparable industry practices and may be refined as MISO gains additional operating experience and develops more detailed technical criteria.  Because the Transmission System experiences the aggregate net demand at the applicable Points of Withdrawal (POWs), the ramp requirement is measured across those interfaces rather than individual computational equipment or load components.  This approach captures the actual impact on the Transmission System and provides flexibility for eligible associated generation, energy storage, uninterruptible power supply systems, and other load-management technologies to smooth demand changes, provided the resulting net ramp complies with applicable requirements.  The ride-through framework addresses a separate but complementary reliability concern by establishing minimum voltage and frequency performance expectations during system disturbances.  Applying these requirements with reference to the POWs supports predictable aggregate load response, reduces the risk of unnecessary simultaneous disconnections, and promotes stable post-disturbance recovery.

3. MISO’s transparent stakeholder process provides additional
protection against arbitrary implementation and supports continued BPM
development.

The premise that MISO will develop the BPM requirements without meaningful
stakeholder input is inconsistent with the record.  MISO began discussing Large Load reliability requirements with stakeholders early in 2026 and repeatedly revised both Tariff and

PDF page 26

26
implementation concepts in response to feedback.93  At the April 20 LLWG and April 22 Planning Advisory Committee (“PAC”) meetings, MISO presented revised definitions and transition concepts; at the May 14 LLWG it provided proposed Tariff language and further revisions; at the June 10 LLWG it revised applicability, transition provisions, roles and responsibilities, and requirement-specific language based on stakeholder feedback; and at the June 29, July 16, July 27, and August 12 LLWG meetings it continued refining the Tariff, Technical Compendium, and Large Load BPM framework.94

That process is continuing.  MISO has proposed a “hub-and-spoke” BPM architecture with a Large Load BPM serving as the central implementation manual and coordinated revisions to existing BPMs.95  MISO has separately solicited stakeholder feedback on operational forecasting, telemetry and PMU requirements, ride-through, ramping, and related BPM provisions.96  This transparent process allows technical requirements to be refined as systems and industry standards evolve without repeatedly reopening the Tariff for every implementation adjustment.

D. MISCELLANEOUS COMMENTS AND PROTESTS.

1. The IRR requirements apply to Transmission Customers taking
Transmission Service on behalf of Large Loads connected to the MISO
Transmission System.

The Midwest TDUs request confirmation that Section 37A does not independently extend to loads interconnected only to a distribution system and that compliance obligations will not

93  Li Testimony at 35-40; IRR Proposal at 28-30.
94  Li Testimony at 35-40 & Attachment A. 95  Li Testimony at 38-39.
96  Large Load Working Group: Large Load Operational Forecast Requirements; Stakeholder feedback, available at: https://www.misoenergy.org/engage/stakeholder-feedback/2026/llwg-large-load-operational-forecast- requirements-llwg-2026-4a-20260827/.

PDF page 27

27
unduly burden Transmission Customers.97  The Tariff already answers the first question.  In MISO, the Transmission System is used to provide Transmission Service, while the Wholesale Distribution System transmits energy over Distribution Facilities.98  Section 37A applies to a “Transmission Customer taking Transmission Service on behalf of a Large Load,” and the Large Load definition itself is framed by Points of Withdrawal “from the Transmission System.”99  Thus, the IRR Proposal does not create a free-standing MISO reliability regime for distribution- connected load that is not taking MISO Transmission Service.100

2. The Tariff reasonably assigns compliance responsibility to the
Transmission Customer while permitting contractual arrangements and
other documentation to demonstrate the ability to effectuate compliance.

The Midwest TDUs and Rowan emphasize that the Large Load customer or equipment owner may control information or equipment needed for compliance.101  MISO recognizes that practical reality, but MISO generally lacks contractual privity with the Large Load itself.  The Transmission Customer, by contrast, takes Transmission Service under a service agreement incorporating the Tariff and therefore provides the legally enforceable relationship through which Section 37A can operate.102  This approach is also consistent with the Show Cause Order’s focus on obligations of the Eligible Customer or transmission customer taking service on behalf of the Large Load.103

97  Midwest TDUs Comments at 1-2, 9-16.
98  Tariff Module A, § 1.T (Definition of “Transmission Service”); id. § 1.W (Definition of “Wholesale Distribution Service”).
99  Proposed Tariff § 37A.I; proposed Tariff Module A, §§ 1.L and 1.P (Definitions of “Large Load” and “Points of Withdrawal”).
100  IRR Proposal at 12; Li Testimony at 14-16.
101  Midwest TDUs Comments at 10-14; Rowan Protest at 1-2.
102  IRR Proposal at 12-13; Li Testimony at 14-16.
103  Show Cause Order at P 64.

PDF page 28

28
The proposed Tariff expressly accommodates contractual arrangements between the Transmission Customer and the Large Load.  A Transmission Customer must demonstrate its ability to effectuate compliance and provide documentation necessary for MISO to verify compliance; that documentation “may include applicable agreements, if any,” between the Transmission Customer and the entities that own, operate, or use the Large Load, or an officer attestation demonstrating access to the information needed for compliance.104  Thus, an agreement assigning relevant performance and information duties to the Large Load may be part of a sufficient compliance showing, although MISO must retain authority to evaluate whether the documentation actually enables the Transmission Customer to meet the Tariff obligation.105 In order to ensure reliability MISO must be able to perform the Reliability Assessment Commitment (“RAC”) and Security Constrained Economic Dispatch (“SCED”) studies, among others.  Because the RAC ensures power is available to the grid, it requires inputs of forecasted demand, and because the SCED balances power injections with withdrawals, it requires inputs of ramp-rates, load forecasts, and current state estimation (telemetry).

MISO will require load forecasts sufficient for RAC, SCED, and other reliability studies. In order to ensure system reliability and facilitate RAC and SCED, MISO needs telemetry, metering, and PMU data.  In order to study operating characteristics proactively MISO needs EMT model data and other equipment level model data, including protection settings, ride-through behavior, dynamic characteristics, staged development plans, and other operational attributes that are identified to materially affect reliability.  MISO would also require sufficient information to validate compliance with registration, modeling, and forecasting obligations, including the right

104  Proposed Tariff § 37A.I.
105  Id.

PDF page 29

29
to audit or verify any information submitted.  MISO must be able to obtain, through the Transmission Customer, all information and operational access necessary to evaluate, monitor, and verify Large Load behavior under Section 37A, including the facility data, electrical models, telemetry, PMU measurements, and forecasting inputs required to support planning studies, operational assessments, and disturbance-performance evaluations.  Because the Tariff designates the Transmission Customer as the responsible party, the Transmission Customer is required to “demonstrate its ability to effectuate compliance” and to provide the documentation MISO needs to verify adherence to Section 37A, with that documentation expressly permitted to include agreements or officer attestations establishing the Transmission Customer’s access to the information needed for compliance.  This structure ensures that MISO can obtain the visibility, modeling inputs, and operational coordination needed to implement the reliability requirements even when the end-use Large Load owns or controls specific equipment.

Section 37A also identifies the potential consequences of noncompliance: delayed Service Commencement Date, time for corrective action, operational limitations, or other remediation necessary to maintain Transmission System reliability, with the process for determining appropriate measures set forth in the BPM.106  These are reliability remedies, not an automatic penalty schedule.  MISO will continue working with Transmission Customers and Large Loads through implementation to facilitate efficient compliance and provide education regarding the new requirements.

3. The operational forecasting requirements are needed for reliability
and should apply to Large Loads.

106  Proposed Tariff § 37A.I.

PDF page 30

30
The Large Energy Users object in particular to a five-minute real-time forecasting requirement for non-computational Large Loads and argue that the requirement could impose costs on traditional industrial customers.107  Forecasting is a visibility requirement, not a computational- load-specific performance requirement.  The Commission itself identified the absence of hourly forecasts and other visibility data as a potential Tariff deficiency.108  MISO’s record likewise explains that accurate forecasting is necessary to anticipate Large Load Demand and operating changes, support commitment and dispatch, and manage variability in the operational horizon.109 Short-term operational forecasts are needed because Large Loads can change system conditions rapidly and cannot be forecast accurately using traditional, weather- and calendar-based models, making timely visibility into expected demand essential for reliable RAC, SCED, and other operational studies.  As Ms. Li explains, day-ahead and real-time forecasts provide MISO with the information needed to anticipate demand changes and maintain reliable commitment and dispatch, and that forecasts must be updated to reflect the most current expected conditions.110 Although MISO’s forecasting processes operate on hourly and five-minute horizons, the requirement concerns forecast visibility, not an obligation for the customer to follow a five-minute schedule; it ensures MISO has sufficiently granular insight into facilities whose deviations may be operationally material.  Section 37A establishes the obligation to provide this information while implementation details, such as cadence, formats, and processes, are appropriately refined through the BPM, allowing MISO to tailor burden and accommodate practical considerations while preserving the reliability objective of accurate short-term forecasting.

107  Large Energy Users Protest at 5-9.
108  Show Cause Order at P 64; IRR Proposal at 6.
109  IRR Proposal at 3, 8-9, 17-18; Li Testimony at 18-20.
110  Li Testimony at 26.

PDF page 31

31
MISO’s stakeholder materials have proposed short-term forecast submissions at the Commercial Pricing Node (“CPNode”) level on hourly and five-minute cadences aligned with commitment and dispatch.111  The purpose of the five-minute data is not to presume that every industrial load behaves like a data center; it is to provide MISO sufficient near-term visibility into a 50 MW-or-larger facility whose deviations can be operationally material and impact Transmission System reliability.112  MISO is continuing to work with stakeholders on forecast horizons, submission mechanics, validation, tolerance bands, and any incentive framework, which are precisely the kinds of implementation details appropriately addressed through the BPM process.113

MISO expects to use hourly forecasts as inputs to reliability commitment processes, including Multi-Day, Next-Day and Intraday RACs.  MISO expects to use five-minute forecasts as inputs to the Look-Ahead Commitment and UDS.  Both forecasts are required at the CPNode level to facilitate accurate integration of data submission into the network model for congestion and contingency analysis.  Large Loads can change system conditions rapidly in ways that cannot be reliably predicted from historical, weather-based, or calendar-based forecasting methods, which creates a reliability need for timely and accurate short-term operational forecasts.  Day-ahead and real-time forecast submissions give operators essential forward visibility into expected demand and enable informed commitment, dispatch, and other real-time reliability studies such as RAC and SCED.  Accurate short-term forecasts support situational awareness by allowing operators to anticipate material changes in consumption, assess the need for balancing actions, and identify

111  Li Testimony at 38; MISO, Large Load Operational Forecast Requirements, LLWG on Aug. 27, 2026.
112  Li Testimony at 8.
113  MISO Large Load Operational Forecast Requirements Stakeholder Feedback Sessions held from August through September, 2026.

PDF page 32

32
conditions that may produce contingency risks.  The value of granular, frequently updated information lies in improving MISO’s ability to understand and respond to changes in Large Load behavior, not in imposing a requirement that customers follow a five-minute dispatch schedule. Because the Tariff sets only the obligation to provide timely and updated forecasts, implementation details, including the cadence, format, and level of granularity, have been developed through the BPM.

E. CONCLUDING ARGUMENTS
The IRR Proposal should be accepted as filed.  It responds directly to the Commission’s identified operational-reliability concerns, establishes enforceable Tariff obligations for visibility, PMUs, ramping, and ride-through, scales incremental requirements to Computational Loads, and provides a reasonable transition framework for existing and in-flight projects.114  The comments identify implementation questions that MISO is actively addressing through the LLWG and BPM process, but they do not demonstrate that the filed framework is unjust or unreasonable. In addition, the Commission should not delay acceptance of this filing until every related Large Load issue is resolved.  MISO expressly identified that transmission-service products, enhanced study processes, and cost-shifting protections would be addressed through separate proposals, and MISO continues to develop those proposals in advance of the Commission’s November 16, 2026 deadline.115  The immediate operational needs addressed here—that is, visibility, forecasting, monitoring, ramping, and disturbance performance—exist regardless of the final design of those later proposals.116

114  IRR Proposal at 1-4, 9-27; Show Cause Order at P 64.
115  IRR Proposal at 1, 4.
116  IRR Proposal at 2-4, 7-9.

PDF page 33

33
Finally, continued use of BPMs for technical implementation is a feature of the framework, not a defect.  Large Load technologies, NERC standards, and MISO’s own operating experience are developing quickly.  The Tariff establishes the enforceable substantive obligations, while the BPMs allow MISO, Transmission Owners, customers, and stakeholders to refine technical implementation in a transparent process as experience grows.117  That structure provides the combination of certainty and flexibility necessary to integrate Large Loads reliably and efficiently. Retaining detailed technical implementation in the BPM and Technical Compendium is important because the Tariff establishes the core Section 37A obligations, while the underlying reliability needs continue to evolve with new NERC guidance, emerging Large Load technologies, and growing operating experience.  NERC’s work on emerging large loads highlights the need for ongoing refinement of modeling practices, real-time telemetry and PMU measurement capabilities,

short-term
forecasting
methods,
ramp-rate
characterization,
and
disturbance-performance expectations as equipment designs and dynamic behaviors change over time.  As a result, technical parameters such as the model detail required to represent power-electronic controls, the resolution and configuration of telemetry and PMU data, assumptions used in near-term forecasting, and active-power recovery behavior during disturbances are expected to require periodic updates.  Housing these specifics in the BPM and Technical Compendium allows MISO to incorporate new standards, device capabilities, and operating insights without altering the fundamental reliability requirements set forth in Section 37A.

117  IRR Proposal at 19-21, 23-30; Li Testimony at 28-40; NERC et al. Comments at 6-9.

PDF page 34

34
IV. NOTICE AND SERVICE
MISO has served a copy of this filing electronically, including attachments, upon each person designated on the official service list compiled by the Secretary as well as on all Tariff customers, MISO Members, Member representatives of transmission owners and non- transmission owners, as well as all state commissions within the MISO Region and the Organization of MISO States.  The filing has been posted electronically on MISO’s website at https://www.misoenergy.org/legal/ferc-filings/ for other interested parties in this matter.

V. CONCLUSION
MISO respectfully requests that the Commission (i) accept this Answer and (ii) accept the IRR Proposal without modification or condition.

Respectfully submitted,
/s/ Kalen Coleman
Michael Kessler
Managing Assistant General Counsel
Kalen Coleman
Corporate Counsel
Midcontinent Independent System
Operator Inc.
720 City Center Drive
Carmel, Indiana 46032
Telephone: 317 249-5400
mkessler@misoenergy.org
kcoleman@misoenergy.org

James C. Holsclaw
Calfee, Halter & Griswold LLP
3900 Salesforce Tower
111 Monument Circle
Indianapolis, Indiana 46204
Telephone: 317 308-4266
jholsclaw@calfee.com

Attorneys for the Midcontinent Independent
System Operator, Inc.
Dated: October 13, 2026

PDF page 35

35
CERTIFICATE OF SERVICE
I hereby certify that I have this day e-served a copy of this document upon all parties listed on the official service list compiled by the Secretary in the above-captioned proceeding, in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure 18 C.F.R. § 385.2010.

Dated this 13th day of October 2026, in Carmel, Indiana.
/s/ Julie Bunn
Julie Bunn
Midcontinent Independent
System Operator, Inc.
720 City Center Drive
Carmel, IN 46032
317-249-5400