EL26-67-000 · 2026-10-26 · National Congress of American Indians
Comments of the National Congress of American Indians urging FERC for a Moratorium on Hyperscale Data Center Approvals Pending Comprehensive Grid Reliability and Ratepayer Impact Assessments
PDF page 1
National Congress of American Indians | 1516 P St NW, Washington, DC 20005 | (202) 466-7767 | www.ncai.org October 5, 2026
The Honorable Laura V. Swett, Chairman
Federal Energy Regulatory Commission
888 First Street NE
Washington, DC 20426
RE: Transmittal of NCAI Resolution #MEM-26-016 – Urgent Request for a FERC Moratorium on Hyperscale Data Center Approvals Pending Comprehensive Grid Reliability and Ratepayer Impact Assessments
Dear Chairman Swett:
On behalf of the National Congress of American Indians (NCAI), the oldest and largest national organization composed of American Indian and Alaska Native Tribal governments, I am writing to formally transmit NCAI Resolution #MEM-26-016, "Calling for a Moratorium on Hyperscale Data Center Permits Pending Comprehensive Environmental and Tribal Impact Assessment."
This resolution was enacted at the 2026 NCAI Mid Year Convention in Memphis, Tennessee. It represents the unified stance of Tribal Nations regarding the rapid proliferation of hyperscale data centers and their unprecedented impact on the bulk power system and transmission infrastructure overseen by the Federal Energy Regulatory Commission (FERC).
While Tribal Nations support responsible economic and digital development, we are deeply concerned about the immense grid demands associated with hyperscale data centers requiring 100 megawatts or greater of power continuously. The rapid interconnection of these massive load centers places extreme pressure on regional electrical grids, accelerates the need for costly interstate transmission upgrades, and threatens bulk power system reliability. Furthermore, without proper regulatory safeguards, the substantial costs of these infrastructure upgrades are frequently shifted onto existing residential and Tribal ratepayers.
The implementation of Executive Order 14318, "Accelerating Federal Permitting of Data Center Infrastructure" (2025) exacerbates these risks. By directing federal agencies to fast-track infrastructure approvals through new National Environmental Policy Act (NEPA) categorical exclusions and streamlined FAST-41 processes, the directive bypasses mandatory, government-to-government Tribal consultation and undermines thorough evaluation of the cumulative impacts on energy transmission networks.
1
PDF page 2
To uphold the federal trust responsibility and protect the integrity of the power grid, NCAI formally calls upon the FERC to impose an immediate moratorium on the issuance of any related certificates, transmission approvals, or regulatory authorizations supporting hyperscale data centers until a comprehensive, independent impact assessment is completed.
Consistent with the FERC’s statutory authority over interstate electricity transmission, reliability, and wholesale rates, we urge the Commission to ensure the following:
●
Cost allocation and ratepayer protection: Before any transmission planning approvals or cost-allocation agreements are finalized for data center loads, binding conditions must guarantee that all grid and infrastructure upgrade costs attributable to data center demand are borne entirely by the facility operators, not passed on to existing Tribal or residential ratepayers. ●
Grid reliability and impact assessment: The FERC must require rigorous, independent, and conflict-free assessments of how these facilities impact regional resource adequacy and transmission congestion, ensuring transparent economic analysis of the true costs required to support their operations.
●
Mandatory Tribal consultation: The FERC must engage Tribal Nations as sovereign partners at the outset of any transmission planning or interconnection process related to these developments, ensuring that routing and infrastructure decisions do not negatively impact treaty rights, cultural resources, or sacred sites.
The Commission has a legal and moral obligation to conduct genuine consultation before making regulatory decisions that affect the economic and energy security of Tribal Nations. Proper respect for these sovereign interests will result in a more reliable, just, and resilient energy grid for all Americans. We welcome the opportunity to meet with you and the Commission to discuss the implementation of this moratorium.
A full copy of Resolution #MEM-26-016 can be accessed and reviewed in its entirety at: qrco.de/MEM-26-016.
Sincerely,
Larry Wright, Jr.
Executive Director
National Congress of American Indians
cc:
The Honorable Chris Wright, Secretary, U.S. Department of Energy
The Honorable Doug Burgum, Secretary, U.S. Department of the Interior
Nicole Sitaraman, Director, Office of Public Participation, Federal Energy Regulatory Commission 2