ER27-432-000 · 2026-11-06 · Southwest Power Pool, Inc.

SPP proposes conditional large-load service revenue credits for its western zones

PDF page 1

November 6, 2026

The Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, N.E.
Washington, D.C.  20426

Re:
Southwest Power Pool, Inc., Docket No. ER27-____-000
Submission of Tariff Revisions to Revise Schedule 15 and Attachment T for the SPP West Region

Dear Secretary Reese:

Pursuant to Section 205 of the Federal Power Act (“FPA”), 16 U.S.C. § 824d, and Section 35.13 of the Federal Energy Regulatory Commission’s (“Commission”) Regulations, 18 C.F.R. § 35.13, Southwest Power Pool, Inc. ("SPP") submits revisions to Schedule 15 and Attachment T of its Open Access Transmission Tariff (“Tariff”)1 to add provisions for Conditional High Impact Large Load Service (“CHILLS”) for pricing Zones in the SPP West Region, and to make other clarifying edits.

SPP respectfully requests that the Commission accept the proposed revisions, find the revisions just and reasonable, and set an effective date of February 1, 2027.

I. BACKGROUND
A. SPP’s Regional Transmission Organization Expansion

On April 1, 2026, SPP expanded its Regional Transmission Organization (“RTO”) into the Western Interconnection.2 Specifically, the following utilities now

1 Southwest Power Pool, Inc., Open Access Transmission Tariff, Sixth Revised Volume No. 1.  References in this filing to "Tariff" refer to the version of SPP’s Tariff currently in effect. "Proposed Tariff" refers to a version reflecting the revisions proposed in this filing. All capitalized terms not otherwise defined in this filing shall have the definitions assigned by the Tariff.
2 The revisions to effectuate the expansion were filed in Docket Nos. ER24-2184 and ER24-2185. Southwest Power Pool, Inc., Submission of Revisions to Tariff, Bylaws, and Membership Agreement to Expand the Regional Transmission Organization into the Western Interconnection (Part 1 of 2), Docket No. ER24-2184-000 and (Part 2 of 2), Docket No. ER24-2185-000 (June 4, 2024). All citations to the “SPP Expansion Filing” are to the Part 1 filing in Docket No. ER24-2184-000.The Commission accepted the revisions to SPP’s governing documents in a series of orders. Sw. Power Pool, Inc., 190

PDF page 2

The Honorable Debbie-Anne A. Reese
November 6, 2026
Page 2

include their transmission facilities in the Western Interconnection under SPP’s Tariff: Basin Electric Power Cooperative (“Basin Electric”); Colorado Springs Utilities (“CSU”); Deseret Generation and Transmission Cooperative; Platte River Power Authority (“Platte River”); Tri-State Generation and Transmission Association, Inc. (“Tri-State”); Western Area Power Administration – Colorado River Storage Project Management Center (“WAPA-CRSP”); Western Area Power Administration – Rocky Mountain Region (“WAPA-RMR”); and Western Area Power Administration – Upper Great Plains Region (“WAPA-UGP”) (collectively, the “Expansion Members”). Basin Electric, Tri-State, and WAPA-UGP were already Members of the SPP RTO and, with the expansion of the SPP RTO, expanded their SPP RTO participation with the inclusion of additional transmission facilities in the Western Interconnection.

SPP established five new transmission pricing Zones in Attachment H of the Tariff in order to effectuate the integration of the new transmission facilities: 100, 101, 102, 103, and 104.3 SPP also added the “Incremental Market Efficiency Use” provisions in the Tariff.4 In addition, SPP included a new Schedule 14 for the DC Tie Access Charge.5

B. Revisions to Add CHILLS

On February 10, 2026, SPP submitted revisions to the Tariff to add CHILLS to allow High Impact Large Loads (“HILL”) to be served with non-firm conditional transmission service.6 The Commission accepted the provisions in a series of orders.7

C. Purpose of Filing

At the time of the CHILLS Filing, the new pricing Zones for the SPP West Region had not yet been established in the Tariff. SPP submits this filing to include the pricing Zones in Schedule 15 of the Tariff, and to also add CHILLS provisions to

FERC ¶ 61,169 (2025); Sw. Power Pool, Inc., Letter Order, Docket No. ER24- 2184-002 (July 11, 2025).

3
SPP Expansion Filing at 91.
4 SPP Expansion Filing at 52-53.
5 SPP Expansion Filing at 48.
6 Submission of Tariff Revisions to Add Conditional High Impact Large Load Service of Southwest Power Pool, Inc., Docket No. ER26-1323-000 (Feb. 10, 2026) (“CHILLS Filing”).
7 Sw. Power Pool, Inc., 195 FERC ¶ 61,196 (2026); Sw. Power Pool, Inc., Letter Order, Docket No. ER26-1323-002 (Oct. 26, 2026).

PDF page 3

The Honorable Debbie-Anne A. Reese
November 6, 2026
Page 3

certain Rate Sheets for Point-To-Point Transmission Service under Attachment T of the Tariff. SPP also proposes other clarifying edits to Attachment T.

II. DESCRIPTION OF AND JUSTIFICATION FOR PROPOSED TARIFF
REVISIONS

A. Schedule 15

In the CHILLS Filing, SPP proposed a new Schedule 15, to establish charges for CHILLS.8 SPP proposes to add pricing Zones 100, 101, 102, 103, and 104 under Section 1 of Schedule 15:

Zone 100:
Colorado Springs Utilities

Zone 101:
Platte River Power Authority

Zone 102:
Tri-State G&T Association – West

Zone 103:
Colorado River Storage Project Zone

Zone 104:
Loveland Area Projects Zone

These revisions are just and reasonable because they effectuate the intent of the CHILLS Filing already accepted by the Commission and will allow those entities in the SPP West Region that take CHILLS to also pay for the use of the transmission facilities located in those newly formed Zones in the SPP West Region.

B. Attachment T

Attachment T includes the rate sheets for Point-To-Point Transmission Service for all applicable Transmission Owners under the Tariff. SPP proposes to revise the following rate sheets.

1. Rate Sheets for CSU, Platte River, and WAPA-CRSP

SPP proposes the following revisions to the rate sheets for CSU, Platte River, and WAPA-CRSP:

Point-To-Point Transmission Service and Conditional High Impact
Large Load Service Revenue Crediting for Point-To-Point Rates
Rates for Point-To-Point Transmission Service under this Attachment T shall reflect any adjustments for Schedule 7 and 8 revenues, and Schedule 15 revenues, and revenues distributed and allocated under Attachment AU, implemented in accordance with Section 34.1(2) of this Tariff.  The rates, including any applicable adjustments for Schedule 7 and 8 revenues, and Schedule 15 revenues, and revenues

8 CHILLS Filing at 29-30.

PDF page 4

The Honorable Debbie-Anne A. Reese
November 6, 2026
Page 4

distributed and allocated under Attachment AU, shall be set forth in the RRR File.9

First, SPP adds a reference to Schedule 15 to appropriately adjust the Point-To- Point Transmission Service Rates for any revenues received for Schedule 15 charges. These proposed changes to add a reference to Schedule 15 revenues are just and reasonable because they will appropriately adjust the Point-To-Point Transmission Service Rates for any revenues received for Schedule 15 charges. The changes are consistent with the revisions to other rate sheets accepted by the Commission in the CHILLS Filing.

Second, SPP removes the references to Attachment AU revenues. Due to an administrative error, SPP mistakenly included references to Attachment AU revenues in the rate sheets for CSU and Platte River in the SPP West Region. As explained in the SPP Expansion Filing, Attachment AU revenues are allocated only to Transmission Owners in the SPP East Region.10

2. Rate Sheets for Loveland Area Projects, SPP West Region
Average, and Tri-State G&T Association-West

SPP proposes the following revisions to the rate sheets for Loveland Area Projects, SPP West Region Average, and Tri-State G&T Association-West:

Point-To-Point Transmission Service Revenue Crediting for Point- To-Point Rates

Rates for Point-To-Point Transmission Service under this Attachment T shall reflect any adjustments for Schedules 7, and 8, 14, and 15 revenues, and Incremental Market Efficiency Use revenues, and

revenues distributed and allocated under Attachment AU, implemented in accordance with Section 34.1(2) of this Tariff.  The rates, including any applicable adjustments for Schedules 7, and 8, 14, and 15 revenues, and Incremental Market Efficiency Use revenues, and revenues

distributed and allocated under Attachment AU, shall be set forth in the RRR File.

9 SPP also includes a ministerial edit to the rate sheet for CSU to correctly reflect CSU’s Addendum number under Attachment H of the Tariff.

10 SPP Expansion Filing at 56. See also Tariff, Attachment AU, Section I (“Such revenues…shall be allocated to Transmission Owners in the SPP East Region based on the estimated flow impacts resulting from energy transfers between MISO north and south subregions, as described in this Attachment AU.”).

PDF page 5

The Honorable Debbie-Anne A. Reese
November 6, 2026
Page 5

First, SPP adds a reference to Schedule 14 for the DC Tie Access Charge. The DC Tie Access Charge is defined as “[a] charge on a transmission reservation utilizing a West DC Tie that sinks outside of the Zone where the West DC Tie is located.”11 The Transmission Customer is responsible for the DC Tie Access Charge determined in Schedule 14 of the Tariff. SPP adds this reference to the rate sheets where the DC Tie Access Charge is applicable.

Second, SPP adds a reference to Schedule 15 to appropriately adjust the Point- To-Point Transmission Service Rates for any revenues received for Schedule 15 charges. The proposed changes to add a reference to Schedule 15 revenues are just and reasonable because they will appropriately adjust the Point-To-Point Transmission Service Rates for any revenues received for Schedule 15 charges. The changes are consistent with the revisions to other rate sheets accepted by the Commission in the CHILLS Filing.

Third, SPP adds a reference to Incremental Market Efficiency Use revenues. The Incremental Market Efficiency Use Charge is “[a] market recovery mechanism to compensate West DC Tie Transmission Owners for the expected loss of life of certain West DC Tie facilities due to increased utilization of the West DC Ties by the Integrated Marketplace.”12 SPP adds this reference to the rate sheets where Incremental Market Efficiency Use revenues are applicable.

Fourth, SPP removes the reference to Attachment AU revenues. Due to an administrative error, SPP mistakenly included references to Attachment AU revenues rate sheets for Loveland Area Projects, SPP West Region Average, and Tri-State G&T Association-West in the SPP West Region. As explained in the SPP Expansion Filing, Attachment AU revenues are allocated only to Transmission Owners in the SPP East Region.13

III. EFFECTIVE DATE

For all the reasons discussed in this transmittal letter, SPP requests that the Commission accept the proposed revisions to the Tariff to become effective February

11 Tariff, Part I, Section 1 – Definitions D.
12 Tariff, Part I, Section 1 – Definitions I.
13 SPP Expansion Filing at 56. See also Tariff, Attachment AE, Section I (“Such revenues…shall be allocated to Transmission Owners in the SPP East Region based on the estimated flow impacts resulting from energy transfers between MISO north and south subregions, as described in this Attachment AU.”).

PDF page 6

The Honorable Debbie-Anne A. Reese
November 6, 2026
Page 6

1, 2027, which is not less than 60 days or more than 120 days prior to the submission of this filing as required by the Commission.14

IV. ADDITIONAL INFORMATION

A. Documents submitted with this filing:

In addition to this Transmittal Letter, SPP provides with this filing Clean and Redlined Tariff revisions under the Sixth Revised Volume No. 1.15

B. Service:

SPP has electronically served a copy of this filing on all its Members, Transmission Customers and Market Participants. A complete copy of this filing will be posted on the SPP web site, www.spp.org, and is also being served on all affected state commissions.

C. Requisite agreements:

There are none.

D. Communications
Correspondence and communications with respect to this filing should be sent to, and SPP requests the Secretary to include on the official service list, the following:

Justin A. Hinton
Senior Attorney
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223
Telephone: (501) 482-2468
jhinton@spp.org

Tessie Kentner
Director & Associate General Counsel
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223
Telephone: (501) 688-1782
tkentner@spp.org

14 18 C.F.R. § 35.3(a)(1). 15 Attachment T for the WAPA-CRSP Zone contains language in italics, which is pending before the Commission in Docket No. ER26-1136. SPP requests that the Commission accept the proposed revisions to this tariff sheet subject to the outcome of hearing and settlement judge procedures in Docket No. ER26-1136.

PDF page 7

The Honorable Debbie-Anne A. Reese
November 6, 2026
Page 7

V. CONCLUSION

For the foregoing reasons discussed in this transmittal letter, SPP respectfully requests that the Commission find the proposed revisions just and reasonable and not unduly discriminatory or preferential, and issue an order accepting the Tariff revisions with an effective date of February 1, 2027.

Respectfully submitted,

/s/ Justin A. Hinton
Justin A. Hinton
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR  72223-4936

Attorney for
Southwest Power Pool, Inc.