ER27-484-000 · 2026-11-13 · ISO New England Inc., NEPOOL Participants Committee and the Participating Transmission Owners

ISO-NE, NEPOOL and the transmission owners file large-load tariff revisions under section 205

ISO New England (ISO-NE) files large load tariff revisions on November 13, 2026, joined by the New England Power Pool (NEPOOL) Participants Committee, the Participating Transmission Owners Administrative Committee and thirteen listed transmission owners. NEPOOL does not join on the cost recovery agreement. Services would start June 1, 2028.

Asks FERC to: Accept the tariff revisions without modification or condition effective November 14, 2026, waive the 60-day notice, allow a comment period to December 7, 2026, and terminate the show cause proceeding.

Filed under section 205 to answer the E-11 show cause order for ISO-NE. It cites the order throughout and says the revisions address all of its concerns in five reform categories.

E-11 ISO-NE: Show cause or propose tariff changes in 60 days (p. 5) E-11 ISO-NE: Application / study process (P 5, p. 25) E-11 ISO-NE: Cost-recovery agreement (P 6, p. 6) E-11 ISO-NE: BTMG netting (P 60, p. 60) E-11 ISO-NE: Proximate-generation service (P 7, p. 7) E-11 ISO-NE: 30-day report on serving large loads with adequate generation (p. 7) E-11 ISO-NE: Alternative transmission technologies (P 75, p. 75)

Key points

  1. ISO-NE sets the Large Load threshold at 50 MW and says that size is reasonable for the New England transmission system.
    The definition includes a 50 MW load size which is reasonable for the New England transmission system. PDF p. 17
  2. A load becomes a Large Load when its gross peak demand rises 50 MW or more above its exempt demand.
    when its gross peak demand increases by 50 MW or more relative to its exempt demand PDF p. 24
  3. Interim Contract Demand Service would last up to seven years, or until the required network upgrades are in service if that takes longer.
    Interim Contract Demand Service shall be available for a term of no more than seven years, or the length of time required to place the required Large Load Network Upgrades in-service, whichever is longer PDF p. 27
  4. Interim and non-firm service would be re-dispatched when the large load's price exceeds $250/MWh.
    all or a portion of a Large Load’s Interim Contract Demand Service and Non-Firm Contract Demand Service will be re-dispatched when the Large Load’s applicable LMP exceeds a Large Load Re-Dispatch Price of $250/MWh. PDF p. 31
  5. Where combined impacts need detailed study, ISO-NE would use reasonable efforts to publish the final system impact study report within 120 days of the preliminary report.
    If the Cluster Study and other coordination screening determines that there are combined impacts that need to be studied in detail, then the ISO shall use reasonable efforts consistent with Good Utility Practice to complete the additional coordination analysis (i.e., with the Cluster and other studies) and publish a final Large Load System Impact Study report within 120 days of publishing the preliminary Large Load System Impact Study report. PDF p. 39
  6. ISO-NE proposes a netting threshold of zero MW, which applies only to Large Loads.
    the ISO proposes a netting threshold of zero MW (which applies only to Large Loads). PDF p. 18
  7. ISO-NE says injection from a generator one or more substations away from the load would likely not fully flow to that load, which is why it limits proximity.
    an injection into the transmission system from a Large Load Electrically Proximate Generator that is one or more substations away from a corresponding Electrically Proximate Large Load would likely not fully flow to the Electrically Proximate Large Load PDF p. 19
  8. The transmission owners say a cost recovery agreement among ISO-NE, the utility and the eligible customer is insufficient to prevent the cost shifting the order raised.
    the PTOs believe that a cost recovery agreement among ISO-NE, the relevant transmission owner, and the Eligible Customer taking transmission service on behalf of large loads is an insufficient guarantor of preventing the cost-shifting concerns raised by the Commission in the Show Cause Order. PDF p. 54
  9. Co-located and proximate generators on the expedited path would not count toward regional capacity or take part in the capacity market.
    will not be counted towards the region’s capacity for resource adequacy purposes, will not participate in the capacity market, and will not be accredited using the same method as other ISO-NE generating facilities. PDF p. 92
  10. ISO-NE would post a list of the network upgrades identified for each large load, with a cost estimate for each, on its website.
    post on its website, in an easily accessible, searchable and fillable format: (1) a cumulative list reflecting the Large Load Network Upgrades identified for each Large Load, categorized by upgrade type PDF p. 13
Contents · 70 sections
  1. I. DESCRIPTION OF THE FILING PARTIES AND COMMUNICATIONS p. 2
  2. II. STANDARD OF REVIEW p. 8
  3. III. BACKGROUND AND EXECUTIVE SUMMARY p. 9
  4. A. Background p. 9
  5. B. Executive Summary p. 11
  6. 1. The Tariff Revisions Address the Five Categories of Reform in the Show Cause Order p. 11
  7. a. Efficient Study Processes p. 11
  8. b. Co-location Rules p. 12
  9. c. Flexible Load Service p. 12
  10. d. Generation Studies p. 13
  11. e. Cost Transparency p. 13
  12. 2. The Tariff Revisions Address Resource Adequacy Concerns p. 13
  13. IV. DESCRIPTION OF THE PROPOSED TARIFF REVISIONS TO ADDRESS THE COMMISSION’S CONCERNS IN THE SHOW CAUSE ORDER p. 14
  14. A. Tariff Revisions in Section I.2.2 of the Tariff (Definitions) p. 16
  15. 1. Definition of Large Load p. 16
  16. 2. Definition of Behind-the-Meter Generation p. 17
  17. 3. Definition of Electrically Proximate Large Load p. 18
  18. 4. Other Definitions p. 19
  19. B. Tariff Revisions in Response to the Show Cause Order Proposed by the ISO Under the ISO’s Section 205 Rights p. 23
  20. 1. Preamble in New Part II.J of the OATT – Transition to New Large Load Transmission Services to Accommodate Existing Commercial Arrangements p. 23
  21. 2. New Section II.56 of the OATT – Establishment of New Large Load Transmission Services p. 26
  22. 3. New Section II.57 of the OATT and New Section III.1.10.5A of the Tariff – Nature and Flexibility of New Large Load Transmission Services p. 27
  23. a. DARD Model p. 28
  24. b. Price-Based Re-Dispatch Mechanism p. 31
  25. 4. New Section II.58 of the OATT – Application Process to Evaluate the Provision of Large Load Transmission Services p. 33
  26. 5. New Section II.60 of the OATT – Study Procedures to Evaluate the Provision of Large Load Transmission Services p. 35
  27. a. Study Timelines p. 36
  28. b. Large Load Material Modification p. 37
  29. c. Large Load System Impact Study Scope p. 38
  30. d. Large Load System Impact Study Report p. 39
  31. e. Evaluation of Alternative Transmission Technologies p. 39
  32. f. Large Load Facilities Study Procedures p. 40
  33. g. Coordination of Studies to Support a Non-Firm Large Load Generator Arrangement p. 41
  34. 6. New Section II.61 of the OATT – Remote Disconnection of a Large Load and Load Shedding p. 41
  35. 7. New Section II.63 of the OATT – Operational Requirements for Large Load Transmission Customers p. 42
  36. 8. New Attachments S, T, and U to the OATT – Large Load Transmission Service Agreement, Large Load System Impact Study Agreement, and Large Load Facilities Study Agreement p. 44
  37. 9. Revisions in Schedules 2, 16, and 17 of the OATT p. 46
  38. 10. Conforming Revisions to Sections II.20.2 and II.20.3 of the OATT p. 47
  39. 11. Revisions in Sections III.1, III.2, and III.15 of the Tariff p. 48
  40. C. Tariff Revisions in Response to the Show Cause Order Proposed by the ISO and the PTOs Under Joint ISO/PTOs Section 205 Rights p. 48
  41. D. PTOs’ Tariff Revisions in Response to the Show Cause Order p. 53
  42. 1. New Section II.62 of the OATT p. 53
  43. 2. New Attachment V of the OATT (Large Load Cost Recovery Agreement) p. 54
  44. a. Operation and Provisions of the LLCRA p. 56
  45. b. Cost Allocation Mechanisms of the LLCRA p. 59
  46. i. Direct Assignment Facilities p. 59
  47. ii. Cost Recovery Charge p. 60
  48. iii. Exit Fee p. 60
  49. iv. Credit Support p. 60
  50. c. The LLCRA Meets the FPA Section 205 Standard p. 60
  51. d. The LLCRA is subject to the Commission’s jurisdiction p. 64
  52. iii. The LLCRA avoids the jurisdictional defects identified in the PJM IRAS Order p. 72
  53. iv. The LLCRA addresses the concerns identified in the Show Cause Order p. 74
  54. 3. Revisions to Schedule 1 of the OATT p. 74
  55. 4. New Schedule 9A of the OATT p. 75
  56. 5. Revisions to Schedule 21-Common p. 75
  57. 6. Revisions to Local Service Schedules in Schedule 21 of the OATT p. 76
  58. 7. Conforming Revisions in Section II.21.2 of the OATT p. 81
  59. E. Tariff Revisions in Response to the Commission’s Resource Adequacy p. 81
  60. V. ANSWERS TO BRIEFING QUESTIONS p. 85
  61. A. How should ISO-NE and the PTOs protect existing commercial arrangements, p. 85
  62. B. What, if any, potential impacts on regional and local transmission planning would p. 86
  63. C. Include information regarding potential structures for agreements between the p. 87
  64. D. Further briefing regarding specific characteristics of providing transmission p. 88
  65. E. To what extent would ISO-NE allow an interconnection customer's generating p. 89
  66. F. To the extent that ISO-NE plans for the electrically proximate large load or large p. 91
  67. VI. STAKEHOLDER PROCESS p. 92
  68. VII. EFFECTIVE DATE; REQUESTS FOR WAIVER AND EXTENDED COMMENT PERIOD p. 93
  69. VIII. ADDITIONAL SUPPORTING INFORMATION p. 94
  70. IX. CONCLUSION p. 96

Topics in the text: Cost allocation · Reliability and curtailment · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

ISO-NE discussed these resource adequacy concerns and its anticipated response in its informational report on resource adequacy submitted to the Commission on July 20, 2026.6 The Filing Parties respectfully request that the Commission waive the 60-day notice requirement and accept the Tariff…
Read this passage

I. DESCRIPTION OF THE FILING PARTIES AND COMMUNICATIONS

PDF bookmark · Topic match: Cost allocation

In its capacity as an RTO, ISO-NE has the responsibility to protect the short-term reliability of the New England 5 VEC is a non-jurisdictional utility pursuant to section 201(f) of the FPA, 16 U.S.C. § 824(f), and is expressly excluded from the PTOs that must respond to the Show Cause Order.
Read this passage

II. STANDARD OF REVIEW

PDF bookmark

The Honorable Debbie Anne Reese, Secretary November 13, 2026 Page 9 of 99 methodology, or even the most accurate.”15 As a result, even if an intervenor or the Commission develops an alternate proposal, the Commission must accept this section 205 filing if it is just and reasonable.16
Read this passage

III. BACKGROUND AND EXECUTIVE SUMMARY

PDF bookmark

III.
Read this passage

A. Background

PDF bookmark · Topic match: Cost allocation

The Honorable Debbie Anne Reese, Secretary November 13, 2026 Page 10 of 99 loads that are willing and able to limit their use of the transmission system under certain conditions; and (e) the rates, terms, and conditions of service applicable to interconnection customers serving electrically…
Read this passage

B. Executive Summary

PDF bookmark

B.
Read this passage

1. The Tariff Revisions Address the Five Categories of Reform in the Show Cause Order

PDF bookmark

The Tariff Revisions Address the Five Categories of Reform in the Show Cause Order The Filing Parties submit that the Tariff Revisions address all of the Commission’s concerns in each of the five categories of reform of the Show Cause Order (i.e., efficient study processes, co-location rules,…
Read this passage

a. Efficient Study Processes

PDF bookmark

The Honorable Debbie Anne Reese, Secretary November 13, 2026 Page 12 of 99 requests for transmission service.
Read this passage

b. Co-location Rules

PDF bookmark

Co-location Rules To address this category of reform, the ISO is proposing a definition of Behind-the-Meter Generation along with a netting threshold of zero MW for Large Loads.
Read this passage

c. Flexible Load Service

PDF bookmark

Flexible Load Service The Tariff Revisions include three new transmission services: firm transmission service for Large Loads that bring their own new capacity and have completed network upgrades; interim transmission service (i.e.,, non-firm transmission service for Large Loads that are in the…
Read this passage

d. Generation Studies

PDF bookmark

Generation Studies To address this category of reform, the Tariff Revisions include a definition of Electrically Proximate Large Load, which is appropriately tailored to New England’s tightly networked transmission system (i.e., an injection into the New England transmission system from a Large…
Read this passage

e. Cost Transparency

PDF bookmark

Cost Transparency To address this category of reform, the Tariff Revisions require the ISO to provide, develop, maintain, and post on its website, in an easily accessible, searchable and fillable format: (1) a cumulative list reflecting the Large Load Network Upgrades identified for each Large…
Read this passage

2. The Tariff Revisions Address Resource Adequacy Concerns

PDF bookmark · Topic match: Reliability and curtailment

The ISO appreciates that, in addition to its continuing work to ensure resource adequacy, it must explicitly consider the potential impact of large loads on the markets.
Read this passage

IV. DESCRIPTION OF THE PROPOSED TARIFF REVISIONS TO ADDRESS THE COMMISSION’S CONCERNS IN THE SHOW CAUSE ORDER

PDF bookmark · Topic match: Reliability and curtailment

In addition, ISO-NE is proposing Tariff Revisions to address the Commission’s resource adequacy concerns.
Read this passage

A. Tariff Revisions in Section I.2.2 of the Tariff (Definitions)

PDF bookmark

Tariff Revisions in Section I.2.2 of the Tariff (Definitions) In response to the Show Cause Order, several definitions are being added in Section I.2.2 of the Tariff.32
Read this passage

1. Definition of Large Load

PDF bookmark

In response, ISO-NE proposes to add the following definition of Large Load in Section I.2.2 of the Tariff: Large Load is a commercial or industrial customer, located at a single site behind one or more points of delivery, and that has a gross peak demand of 50 MW or greater, relative to its exempt…
Read this passage

2. Definition of Behind-the-Meter Generation

PDF bookmark

Definition of Behind-the-Meter Generation In the Show Cause Order, the Commission points out that the Tariff does not define the term “Behind the Meter Generation.”36 Accordingly, ISO-NE proposes to add the following definition of Behind-the-Meter Generation in Section I.2.2 of the Tariff:…
Read this passage

3. Definition of Electrically Proximate Large Load

PDF bookmark

Definition of Electrically Proximate Large Load In the Show Cause Order, the Commission stated that, for purposes of the order, “electrically proximate large load” means a large load, as defined in the order, that is sufficiently electrically close to the interconnection customer’s requested point…
Read this passage

4. Other Definitions

PDF bookmark · Topic match: Connecting load and generation

Large Load Interconnection Facilities are sole use facilities and shall not include Distribution Upgrades, Stand Alone Network Upgrades or Large Load Network Upgrades.
Read this passage

B. Tariff Revisions in Response to the Show Cause Order Proposed by the ISO Under the ISO’s Section 205 Rights

PDF bookmark

Tariff Revisions in Response to the Show Cause Order Proposed by the ISO Under the ISO’s Section 205 Rights
Read this passage

1. Preamble in New Part II.J of the OATT – Transition to New Large Load Transmission Services to Accommodate Existing Commercial Arrangements

PDF bookmark

Specifically, under ISO-NE’s proposal, the MW value of exempt demand for a load in operation or determined by the ISO to be a Large Load Sufficiently Under Construction prior to June 18, 2026, shall be determined as the greater of: (i) its measured maximum observed hourly gross peak in the 10 years…
Read this passage

2. New Section II.56 of the OATT – Establishment of New Large Load Transmission Services

PDF bookmark

New Section II.56.2 of the OATT establishes that upon completion of the application, study, and service agreement requirements set forth in new Section IV.58 of the OATT, each of the three types of transmission services must be taken and paid for by each Large Load Transmission Customer that…
Read this passage

3. New Section II.57 of the OATT and New Section III.1.10.5A of the Tariff – Nature and Flexibility of New Large Load Transmission Services

PDF bookmark

All identified Large Load Network Upgrades shall be in service before a Large Load Transmission Customer can be provided Firm Contract Demand Service for a Large Load.
Read this passage

a. DARD Model

PDF bookmark

DARD Model In order for a Large Load Transmission Customer to be able to receive Firm Contract Demand Service, Interim Contract Demand Service, or Non-Firm Contract Demand Service for a Large Load, under new Section III.1.10.5A(a)(i) of the Tariff, the Large Load Transmission Customer shall (or…
Read this passage

b. Price-Based Re-Dispatch Mechanism

PDF bookmark · Topic match: Cost allocation

If the Large Load Transmission Customer elects to submit Demand Bids pursuant to new Section III.1.10.5A(b)(i) of the Tariff, then the ISO must schedule the Large Load to withdraw energy based on the lesser of the Large Load’s Demand Bid MW and the sum of the Large Load’s transmission services MW…
Read this passage

4. New Section II.58 of the OATT – Application Process to Evaluate the Provision of Large Load Transmission Services

PDF bookmark · Topic match: Connecting load and generation

If a deficiency is identified, the Large Load Eligible Customer must cure within 15 days of receipt of the notice.
Read this passage

5. New Section II.60 of the OATT – Study Procedures to Evaluate the Provision of Large Load Transmission Services

PDF bookmark · Topic match: Connecting load and generation

The ISO is also required to post Large Load System Impact Study reports. 63 Show Cause Order at P 64. 64 Similar requirements apply to Regional Network Service under Section II.16.3 of the OATT. 65 Similar requirements apply to Regional Network Service under Section II.16.4 of the OATT. 66 Show…
Read this passage

a. Study Timelines

PDF bookmark

Study Timelines Under new Section II.60.1 of the OATT, within 15 days of the ISO’s notice to the Large Load Eligible Customer that its Large Load Transmission Service Application is complete, the ISO must hold a Large Load Scoping Meeting that includes the ISO, the Large Load Eligible Customer, the…
Read this passage

b. Large Load Material Modification

PDF bookmark

b.
Read this passage

c. Large Load System Impact Study Scope

PDF bookmark · Topic match: Connecting load and generation

Large Load System Impact Study Scope New Section II.60.2 of the OATT provides that the Large Load System Impact Study must evaluate the impact of the proposed Large Load on the reliability and operation of the New England Transmission System.
Read this passage

d. Large Load System Impact Study Report

PDF bookmark

Large Load System Impact Study Report New Section II.60.2 of the OATT provides that the Large Load System Impact Study report must state the assumptions upon which it is based and the results of the analysis, as well as provide the requirements or potential impediments to providing the requested…
Read this passage

e. Evaluation of Alternative Transmission Technologies

PDF bookmark

The ISO must evaluate each identified alternative transmission technology and determine, in the manner described in the ISO New England Planning Procedures, whether the technologies should be used, consistent with Good Utility Practice, Applicable Reliability Standards, and Applicable Laws and…
Read this passage

f. Large Load Facilities Study Procedures

PDF bookmark

Large Load Facilities Study Procedures Under new Section II.60.6 of the OATT, if a Large Load System Impact Study indicates that Large Load Network Upgrades are needed to supply the Large Load Eligible Customer’s service or to mitigate indirect impacts on Merchant Transmission Facilities (MTF) or…
Read this passage

g. Coordination of Studies to Support a Non-Firm Large Load Generator Arrangement

PDF bookmark

These studies must meet the requirements of Schedules 22 and 23 of the OATT for a Large Load Co-Located Generator or Large Load Electrically Proximate Generator.
Read this passage

6. New Section II.61 of the OATT – Remote Disconnection of a Large Load and Load Shedding

PDF bookmark

New Section II.61.1 of the OATT provides that the parties shall implement such programs during any period when the ISO determines that a system contingency exists and such procedures are necessary to alleviate the contingency, up to and including the capability to coordinate the remote…
Read this passage

7. New Section II.63 of the OATT – Operational Requirements for Large Load Transmission Customers

PDF bookmark

New Section II.63 of the OATT – Operational Requirements for Large Load Transmission Customers In the Show Cause Order, the Commission preliminarily found that the Tariff appears to be unjust and unreasonable because it lacks provisions addressing ongoing operational requirements for transmission…
Read this passage

8. New Attachments S, T, and U to the OATT – Large Load Transmission Service Agreement, Large Load System Impact Study Agreement, and Large Load Facilities Study Agreement

PDF bookmark

In addition, to implement the study procedures in new Section II.60 of the OATT, the ISO proposes to add Attachment T to the OATT – Large Load System Impact Study Agreement, which is an agreement between the ISO, the Large Load Eligible Customer, the Large Load Interconnecting Transmission Owner…
Read this passage

9. Revisions in Schedules 2, 16, and 17 of the OATT

PDF bookmark · Topic match: Cost allocation

Large Load Transmission Customers receiving Firm Contract Demand Service, Interim Contract Demand Service, and/or Non-Firm Contract Demand Service will benefit from 91 The Large Load Facilities Study Agreement also includes the following general terms: no interconnection or wheeling rights/no…
Read this passage

10. Conforming Revisions to Sections II.20.2 and II.20.3 of the OATT

PDF bookmark

Conforming Revisions to Sections II.20.2 and II.20.3 of the OATT Section II.20.2 of the OATT is being revised to include “any Large Load Transmission Customer’s use of the PTF on behalf of its Large Loads” in the types of use of the PTF that cannot be unduly discriminated in redispatch under that…
Read this passage

11. Revisions in Sections III.1, III.2, and III.15 of the Tariff

PDF bookmark · Topic match: Cost allocation

The revisions state that “[f]or a [DARD] associated with a Large Load, all components of the Real-Time Reserve Designation shall be zero.” Similarly, the revisions in Section III.1.8.1 establish that a Large Load is ineligible to provide Day-Ahead Ancillary Services (i.e., day-ahead reserves).
Read this passage

C. Tariff Revisions in Response to the Show Cause Order Proposed by the ISO and the PTOs Under Joint ISO/PTOs Section 205 Rights

PDF bookmark · Topic match: Connecting load and generation

Furthermore, to address the Show Cause Order’s considerations on cost shifting,98 new Section III.1.10.5A(d)(ii) of the Tariff provides that the Assigned Meter Reader for the Large Load must submit Revenue Quality Metering for hourly and monthly settlement that represents gross supply quantities…
Read this passage

D. PTOs’ Tariff Revisions in Response to the Show Cause Order

PDF bookmark

PTOs’ Tariff Revisions in Response to the Show Cause Order
Read this passage

1. New Section II.62 of the OATT

PDF bookmark

The RTO or [Independent System Operator] shall therefore have greater flexibility to customize its interconnection procedures and agreements to fit regional needs.”), order on reh’g, Order No. 2003-A, 106 FERC ¶ 61,220, at P 759 (“[T]here is a rational basis for giving RTOs and [Independent System…
Read this passage

2. New Attachment V of the OATT (Large Load Cost Recovery Agreement)

PDF bookmark · Topic match: Cost allocation

Such agreements will be outside of the pro forma LLCRA and shall be filed with the Commission pursuant to FPA section 205 for approval or acceptance.
Read this passage

a. Operation and Provisions of the LLCRA

PDF bookmark · Topic match: Cost allocation

Operation and Provisions of the LLCRA The LLCRA is a cost recovery agreement between the LLITO, the Large Load Eligible Customer, and the Large Load Entity that provides for the construction of LLITO’s Network Upgrades and the sole-use facilities necessary to effect the reliable interconnection of…
Read this passage

b. Cost Allocation Mechanisms of the LLCRA

PDF bookmark · Topic match: Cost allocation

If the Large Load Eligible Customer and the Large Load Entity are the same entity, that entity is responsible under the LLCRA for these payments and the Credit Support.
Read this passage

i. Direct Assignment Facilities

PDF bookmark

Direct Assignment Facilities The Direct Assignment Facilities, analogous to Interconnecting Transmission Owner’s Interconnection Facilities in a generator context, are sole-use facilities which will be constructed by the LLITO and paid for on a reimbursable basis by the Large Load Entity,…
Read this passage

ii. Cost Recovery Charge

PDF bookmark

Cost Recovery Charge The Cost Recovery Charge is the primary mechanism under which the PTOs will prevent cost shifts to other transmission customers caused by the interconnection of the Large Load Facility.
Read this passage

iii. Exit Fee

PDF bookmark · Topic match: Cost allocation

The Exit Fee is equal to the Net Book Value of LLITO’s Network Upgrades along with Decommissioning Costs, and will, like the Cost Recovery Charge, be credited against the applicable transmission revenue requirement to avoid cost shifting to transmission customers.
Read this passage

iv. Credit Support

PDF bookmark

Credit Support The LLCRA also requires the Large Load Entity to post sufficient financial assurance (“Credit Support”) both prior to commercial operation to cover the costs of the Direct Assignment Facilities and LLITO’s Network Upgrades111 as well as subsequent to commercial operation to cover the…
Read this passage

c. The LLCRA Meets the FPA Section 205 Standard

PDF bookmark · Topic match: Cost allocation

The LLCRA Meets the FPA Section 205 Standard In the Show Cause Order, and in acting on the Secretary of Energy’s Advance Notice of Proposed Rulemaking on large loads, the Commission recognized the extraordinary growth in requests 111 See id.
Read this passage

d. The LLCRA is subject to the Commission’s jurisdiction

PDF bookmark · Topic match: Retail and wholesale authority

The LLCRA’s construction provisions are modeled on Article 5 of the Large Generator Interconnection Agreement in Schedule 22 of the OATT, and the Tariff already allocates the costs of network upgrades needed to accommodate Regional Network Service requests in the same manner as generator upgrades…
Read this passage

iii. The LLCRA avoids the jurisdictional defects identified in the PJM IRAS Order

PDF bookmark · Topic match: Retail and wholesale authority

The PJM IRAS Order also reaffirmed that “the rapid emergence of large loads presents a shared regulatory challenge that implicates both federal and state authority,” and that states have “a crucial role to play” in designating which retail customers must be curtailed when the system is stressed.188…
Read this passage

iv. The LLCRA addresses the concerns identified in the Show Cause Order

PDF bookmark

The Commission will therefore review the LLCRA under the ordinary just-and-reasonable standard, and any non-conforming LLCRA must be filed pursuant to Article 3.
Read this passage

3. Revisions to Schedule 1 of the OATT

PDF bookmark · Topic match: Cost allocation

Large Load Transmission Customers shall be required to pay the scheduling and dispatch surcharge in an amount equal to that customer’s demand for FCDS, NFCDS, and ICDS as determined by Section II.62 of the OATT multiplied by the Monthly Scheduling and Dispatch Surcharge Rate as determined by…
Read this passage

4. New Schedule 9A of the OATT

PDF bookmark

New Schedule 9A of the OATT The proposed new Schedule 9A to the OATT establishes the rates to be charged for Large Load Transmission Customers taking FCDS, NFCDS, and/or ICDS.
Read this passage

5. Revisions to Schedule 21-Common

PDF bookmark

Revisions to Schedule 21-Common The proposed revisions to Schedule 21-Common of the OATT create transmission services over Local Facilities that parallel the transmission services proposed in Part II.J of the OATT.194 Specifically, the revisions create three new transmission services to be offered…
Read this passage

6. Revisions to Local Service Schedules in Schedule 21 of the OATT

PDF bookmark · Topic match: Reliability and curtailment

Revisions to Schedule 21-CTMEEC CTMEEC proposes limited revisions to Schedule 21-CTMEEC to account for the addition to the OATT and Schedule 21-Common of new transmission service types available to Large Load.
Read this passage

7. Conforming Revisions in Section II.21.2 of the OATT

PDF bookmark

Conforming Revisions in Section II.21.2 of the OATT The term “Large Load Transmission Customers” is being added in Section II.21.2 of the OATT as a conforming revision in the language that currently applies to Regional Network Service.
Read this passage

E. Tariff Revisions in Response to the Commission’s Resource Adequacy

printed heading · Topic match: Reliability and curtailment

Tailored changes currently underway, including CAR, are appropriate to sustain the markets’ strength as the system evolves.206 The ISO appreciates that, in addition to its continuing work to ensure resource adequacy, it must explicitly consider the potential impact of Large Loads on the markets.
Read this passage

V. ANSWERS TO BRIEFING QUESTIONS

PDF bookmark

ANSWERS TO BRIEFING QUESTIONS In the Show Cause Order, the Commission directed further briefing on six questions.
Read this passage

A. How should ISO-NE and the PTOs protect existing commercial arrangements,

printed heading

How should ISO-NE and the PTOs protect existing commercial arrangements, including: (1) what would be a reasonable implementation period to ensure minimal disruption to such existing commercial arrangements, and (2) how to allow a reasonable amount of time to finalize ongoing agreements that are…
Read this passage

B. What, if any, potential impacts on regional and local transmission planning would

printed heading · Topic match: Cost allocation

The inclusion of the Large Load’s required upgrades, as identified in the Large Load System Impact Study, will ensure that any reliability impacts directly attributable to the Large Load are mitigated, and not designated as regional reliability needs to be addressed through ratepayer-funded…
Read this passage

C. Include information regarding potential structures for agreements between the

printed heading · Topic match: Cost allocation

Further, please include information on what an appropriate minimum level of cost recovery and financial security from an Eligible Customer would be under any such agreements.210 As explained in Section IV.D.2 above, the PTOs believe that the only sure way to prevent unjust and unreasonable cost…
Read this passage

D. Further briefing regarding specific characteristics of providing transmission

printed heading · Topic match: Reliability and curtailment

To address resource adequacy concerns associated with the rapid addition of large loads, ISO-NE proposes a BYONC requirement as a condition of Firm Contract Demand Service.
Read this passage

E. To what extent would ISO-NE allow an interconnection customer's generating

printed heading · Topic match: Cost allocation

To align with the Show Cause Order’s considerations on cost shifting, the ISO proposes to meter Large Loads and any associated Large Load Co-Located Generator or Large Load Electrically Proximate Generator separately based on gross demand and gross supply, such that the two are not netted.
Read this passage

F. To the extent that ISO-NE plans for the electrically proximate large load or large

printed heading · Topic match: Connecting load and generation

To the extent that ISO-NE plans for the electrically proximate large load or large co-located load associated with an interconnection customer's generating facility for resource adequacy purposes, would ISO-NE account for the generating facilities serving electrically proximate large load or large…
Read this passage

VI. STAKEHOLDER PROCESS

PDF bookmark

STAKEHOLDER PROCESS The Tariff Revisions were considered and supported in the NEPOOL stakeholder process.
Read this passage

VII. EFFECTIVE DATE; REQUESTS FOR WAIVER AND EXTENDED COMMENT PERIOD

PDF bookmark

EFFECTIVE DATE; REQUESTS FOR WAIVER AND EXTENDED COMMENT PERIOD The Filing Parties respectfully request that the Commission accept the Tariff Revisions to become effective on November 14, 2026, one day after filing.
Read this passage

VIII. ADDITIONAL SUPPORTING INFORMATION

PDF bookmark

ADDITIONAL SUPPORTING INFORMATION Section 35.13 of the Commission’s regulations generally requires public utilities to file certain cost and other information related to an examination of traditional cost-of-service rates.225 However, the Tariff Revisions filed herein are not traditional “rates.”…
Read this passage

IX. CONCLUSION

PDF bookmark

CONCLUSION For the foregoing reasons, the Filing Parties respectfully request that the Commission accept the Tariff Revisions as proposed herein, without modifications or conditions, so that they can become effective on November 14, 2026, and terminate the show cause proceeding in full.
Read this passage