CAISO files large-load tariff revisions under section 205 in response to the show cause order
CAISO files tariff revisions under section 205 on November 16, 2026, in a new docket, ER27-506-000, as its response to the show cause order. It defines a large load as 50 MW or more, makes generators disclose plans to serve co-located load, and adds a Flexible Interim Load Interconnection (FILI) service. Deposits, security and cost recovery sit in the transmission owners' own tariffs, filed separately the same day.
Asks FERC to: Accept the revisions effective February 16, 2027, with scheduling coordinator changes on November 1, 2027 and settlement changes on April 30, 2028, and set a 30-day comment period.
Filed under section 205 to answer the E-10 show cause order for CAISO. The California transmission owners filed their own tariff revisions in separate dockets the same day.
E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25) E-10 CAISO: Cost-recovery agreement (§ III.B.3, p. 25) E-10 CAISO: Service for flexible loads (§ III.D, p. 62) E-10 CAISO: BTMG netting (pp. 60-61, p. 60)
Key points
- A large load is a single site of 50 MW or more.
and that has a peak load of 50 MW or greater. PDF p. 11
- Deposits, security and cost recovery are left to each transmission owner's tariff.
the PTOs will implement just and reasonable deposit, security, reimbursement, and cost-recovery provisions in their own tariffs PDF p. 3
- Generator interconnection customers must disclose plans to serve co-located load.
requires generator interconnection customers to disclose plans to serve co- located load PDF p. 3
- FILI would let flexible loads energize before network upgrades are finished.
The CAISO’s Flexible Interim Load Interconnection (FILI) can permit earlier energization while network upgrades are pending PDF p. 3
- A permanent flexible service is left for later work.
with additional work planned on permanent flexibility and other emerging configurations PDF p. 3
- CAISO does not require large loads to bring their own generation, and says it will not copy generation-linked mechanisms used in other regions.
This distinction also explains why the CAISO does not propose to replicate generation-linked mechanisms developed or proposed in other ISO/RTO regions. PDF p. 7
- CAISO says a load sitting near generation does not by itself reduce transmission needs or resource adequacy obligations.
physical proximity between load and generation does not guarantee reduced transmission requirements or resource adequacy obligations PDF p. 28
- Large loads with backup or non-exporting behind-the-meter generation would be handled under local retail interconnection rules, not CAISO's resource process.
These will include large loads with back-up generation only to be used during outages or islanding, and large loads with non-exporting behind-the-meter generation. PDF p. 28
- CAISO says it will set out the alternatives, including alternative transmission technologies, considered for each preferred transmission solution.
The CAISO will continue to set out the alternatives that were considered in the selection of all preferred transmission solutions, whether ATTs or other more conventional solutions PDF p. 19
- CAISO agrees to post cost data for large-load network upgrades on its website in a searchable format.
The CAISO agrees that cost data should be transparent and can be provided on the CAISO website in a searchable format. PDF p. 25
Contents · 37 sections
- I. Executive Summary
- II. Background
- A. Large Loads
- B. Key CAISO Differences
- 1. Capacity Requirements
- 2. Eligible Customers and Order No. 888
- 3. Allocation of Responsibilities
- 4. Non-jurisdictional Transmission Owners
- III. Tariff Revisions and Order to Show Cause
- A. Transmission Service to Eligible Customers on Behalf of Large Loads
- 1. Definition and Applicability
- 2. Large Load Interconnection Study Procedures
- 3. Large Load Application Process
- 4. Operational Requirements
- 5. Large Load Service Agreements
- B. Cost Shifting Risk among Transmission Customers
- 1. Cost Allocation Rules and Agreements
- 2. Data Transparency
- C. Co-Location Arrangements and Load with Behind the Meter Generation
- 1. Co-located Interconnection Studies
- 2. Cost Allocation for Co-located Loads
- 3. Transmission Access Charges
- D. Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads
- E. Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load
- F. Future Issues
- IV. Briefing Questions
- V. Order to Show Cause
- VI. Effective Date, Comment Period, Request for Waiver
- VII. Communications
- VIII. Service
- IX. Contents of Filing
- Attachment A
- Attachment B
- Attachment C
- Attachment D
- Attachment E
- X. Conclusion
Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
www.caiso.com │ 250 Outcropping Way, Folsom, CA 95630 │ 916.351.4400 California Independent System Operator Corporation November 16, 2026 The Honorable Debbie-Anne A.Read this passage
I. Executive Summary
PDF bookmark · Topic match: Connecting load and generation
The Commission’s Order asks whether the CAISO tariff remains just and reasonable as unprecedented large load growth tests utility tariffs nationwide.Read this passage
II. Background
PDF bookmark
II.Read this passage
A. Large Loads
PDF bookmark · Topic match: Cost allocation
The CAISO’s Issue Paper, posted in January 2026, described current roles, considerations, and processes for large loads, including transmission and resource planning, transmission service offerings, cost allocation and responsibility, technical requirements and standards, operational requirements,…Read this passage
B. Key CAISO Differences
PDF bookmark
B.Read this passage
1. Capacity Requirements
PDF bookmark · Topic match: Reliability and curtailment
Large loads must still complete applicable interconnection studies, satisfy technical and operating requirements, and fund or await required facilities and network upgrades.Read this passage
2. Eligible Customers and Order No. 888
PDF bookmark
Eligible Customers and Order No. 888 Similarly, the CAISO’s framework for providing transmission access differs from the traditional Order No. 888 model.Read this passage
3. Allocation of Responsibilities
PDF bookmark · Topic match: Cost allocation
Stakeholders’ preference was for the existing framework to remain in place, with the PTOs administering load interconnection requests and performing the associated studies under their tariffs, coordinated with the CAISO’s transmission planning, generator interconnection, and system reliability…Read this passage
4. Non-jurisdictional Transmission Owners
PDF bookmark
In such a case, the Commission “expected CAISO to respond to this order regarding the non-public utility’s CAISO tariff provisions on file with the Commission.”15 Based on this direction, the CAISO’s non-public utilities requested the Commission rescind the Order, which the Commission granted.16…Read this passage
III. Tariff Revisions and Order to Show Cause
PDF bookmark
Tariff Revisions and Order to Show Cause Although the CAISO believes the tariff revisions in this filing do not substantially affect Order Nos. 888, 1000, 2003, 792, 845, 2023, or 1920 policies, the CAISO’s proposed tariff revisions meet both the just and reasonable standard and the independent…Read this passage
A. Transmission Service to Eligible Customers on Behalf of Large Loads
PDF bookmark
Transmission Service to Eligible Customers on Behalf of Large LoadsRead this passage
1. Definition and Applicability
PDF bookmark · Topic match: Retail and wholesale authority
The CAISO also notes that its proposed definition is similar to the proposed definition the Commission recently approved in the PJM Interconnection.20 The CAISO proposes not to include a description of the types of load (i.e., commercial or industrial customer) in its definition of Large Load.Read this passage
2. Large Load Interconnection Study Procedures
PDF bookmark · Topic match: Connecting load and generation
The CAISO also expects the PTOs to address network upgrade considerations and deterring speculative requests.Read this passage
3. Large Load Application Process
PDF bookmark
For this reason, the CAISO proposes enhanced and ongoing coordination with the PTOs on the load and resource interconnection processes and expects the PTOs to align their load application processes with the CAISO’s resource interconnection process to ensure the level of visibility necessary for the…Read this passage
4. Operational Requirements
PDF bookmark · Topic match: Reliability and curtailment
Prior to the interconnection of any large load to the CAISO controlled grid, the CAISO proposes to require the PTO to provide the CAISO with the following information for the large load: Load type, variable or flat load designation, expected hourly operating profile, points of interconnection and…Read this passage
5. Large Load Service Agreements
PDF bookmark
Large Load Service Agreements The Commission preliminarily found in the Order that the CAISO and PTO tariffs lack pro forma provisions in a transmission service agreement, or other applicable agreement, to memorialize the technical and operational terms the Order describes.74 The PTOs will propose…Read this passage
B. Cost Shifting Risk among Transmission Customers
PDF bookmark · Topic match: Cost allocation
Cost Shifting Risk among Transmission CustomersRead this passage
1. Cost Allocation Rules and Agreements
PDF bookmark · Topic match: Cost allocation
The CAISO believes that the PTOs may develop their own proposals to address any cost shifting, and that the current transmission revenue requirement and credit mechanisms in the transmission access charges can accommodate those proposals.78 The CAISO proposes some metering and settlement changes in…Read this passage
2. Data Transparency
PDF bookmark · Topic match: Cost allocation
For State regulators and stakeholders, per the Commission’s direction,81 the CAISO also proposes to clarify in the transmission planning process where network upgrades were needed to accommodate both general load growth and large load interconnection specifically.Read this passage
C. Co-Location Arrangements and Load with Behind the Meter Generation
PDF bookmark
Co-Location Arrangements and Load with Behind the Meter GenerationRead this passage
1. Co-located Interconnection Studies
PDF bookmark · Topic match: Connecting load and generation
Co-located Interconnection Studies The Commission stated in the Order that the CAISO’s tariff does not contain provisions addressing with sufficient clarity and consistency the rates, terms, and conditions of service that apply to interconnection customers serving co-located load.86 The Commission…Read this passage
2. Cost Allocation for Co-located Loads
PDF bookmark · Topic match: Cost allocation
The CAISO proposes to address this issue by requiring the PTOs to sub-meter each co-located large load 108 See CAISO Master File at https://www.caiso.com/systems-applications/portals- applications/master-file. 109 Section 40 of the CAISO tariff establishes rules about eligible capacity and uses…Read this passage
3. Transmission Access Charges
PDF bookmark · Topic match: Reliability and curtailment
Excess Behind the Meter Production shall not be netted against End-Use Customer Load in determining Gross Load.” The definition also provides a list of certain loads excluded, including “Load of an individual retail customer served by its own onsite Generating Unit or energy storage device, or as…Read this passage
D. Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads
PDF bookmark · Topic match: Connecting load and generation
Reese November 16, 2026 Page 36 in the PJM Co-Location Order.”122 The Commission then explained that the customer “must have necessary control technologies and/or protection systems, which may include a special protection scheme, to limit its energy withdrawals to its approved level,” which are…Read this passage
E. Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load
PDF bookmark · Topic match: Connecting load and generation
Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load The Commission preliminarily found in the Order that the CAISO tariff appears to be unjust and unreasonable because it does not contain provisions allowing an interconnection customer to seek the generator…Read this passage
F. Future Issues
PDF bookmark · Topic match: Reliability and curtailment
All parties must work to ensure compliance maintains reliability without being unduly burdensome.Read this passage
IV. Briefing Questions
PDF bookmark · Topic match: Reliability and curtailment
We find that there may be a variety of possible approaches to protect customers from significant cost shifts associated with network upgrades triggered by large loads.” Order to Show Cause at P 125.Read this passage
V. Order to Show Cause
PDF bookmark
Order to Show Cause The Commission should conclude the Order to Show Cause proceeding.Read this passage
VI. Effective Date, Comment Period, Request for Waiver
PDF bookmark
Effective Date, Comment Period, Request for Waiver With the exception of the two sections described below, the CAISO requests that the Commission accept the tariff revisions contained in this filing effective February 16, 2027 (i.e., 92 days after the date of this filing).142 Although the CAISO is…Read this passage
VII. Communications
PDF bookmark
Communications Pursuant to Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure,144 the CAISO requests that all correspondence, pleadings, and other communications regarding this filing should be directed to the following: William H.Read this passage
VIII. Service
PDF bookmark
Service The CAISO has served copies of this filing on the CPUC, the CEC, and all parties with scheduling coordinator agreements under the CAISO tariff.Read this passage
IX. Contents of Filing
PDF bookmark
Contents of Filing In addition to this transmittal letter, this filing includes the following attachments:Read this passage
Attachment A
printed heading
Attachment A Clean CAISO tariff sheets incorporating this tariff amendmentRead this passage
Attachment B
printed heading
Attachment B Red-lined document showing the revisions in this tariff amendmentRead this passage
Attachment C
printed heading
Attachment C Final ProposalRead this passage
Attachment D
printed heading
Attachment D Technical Working Group ProposalRead this passage
Attachment E
printed heading
Attachment E Board Memorandum 144 18 C.F.R. § 385.203(b)(3).Read this passage
X. Conclusion
PDF bookmark
Conclusion For the reasons set forth above, the CAISO respectfully requests that the Commission accept the CAISO’s proposed tariff revisions and conclude the Order to Show Cause proceeding.Read this passage