ER27-520-000 · 2026-11-16 · PJM Transmission Owners (filed by PECO Energy Company and PJM)

PJM Transmission Owners file tariff revisions for service to co-located and large loads under section 205

The PJM Transmission Owners file tariff revisions under section 205 on November 16, 2026, in a new docket, ER27-520-000. The filing sets rates for the new co-located and large-load services, a pro forma cost recovery agreement with a minimum revenue commitment and credit support, and a 15-year zonal allocation of upgrade costs from PJM’s Fast Energization Process.

Asks FERC to: Accept the tariff revisions without hearing, modification or condition, with the new service rates effective March 16, 2027 and the agreement and cost allocation on an indeterminate date.

Filed under section 205 to answer the E-7 show cause order for PJM. The owners also say it meets their compliance obligation under the E-2 co-location order and will tell the EL25-49 parties so by letter.

E-7 PJM: Show cause or propose tariff changes in 60 days (p. 7) E-7 PJM: Cost-recovery agreement (P 77, p. 28) E-7 PJM: Cost transparency (P 71, p. 51) E-2 PJM: Paper hearing sets the rates (Disposition, p. 5) E-2 PJM: One of three new co-location services (P 2, p. 3)

Key points

  1. The owners say the revisions answer the E-7 show cause order and comply with the E-2 co-location order.
    These revisions are both responsive to and consistent with the preliminary findings made by the Commission in its June 18, 2026 Order Instituting Proceeding PDF p. 1
  2. Large Load customers would make a minimum contribution to transmission revenue requirements, backed by shortfall payments and financial security.
    to make a minimum contribution towards transmission owners’ revenue requirements, along with a shortfall payment and crediting mechanism and financial security obligations PDF p. 2
  3. The committed contribution is 80% to 100% of a full firm transmission service benchmark.
    which percentage shall be no less than 80% and no greater than 100% PDF p. 77
  4. Initial credit support equals the projected charges on the full initial load commitment over the agreement’s term.
    equals the aggregate projected charges associated with 100 percent of the Initial Load Commitment over the CRA term PDF p. 18
  5. The cost recovery agreement runs at least ten years after the first service date.
    the date that is at least ten (10) years after the first Service Date as specified in Exhibit A PDF p. 80
  6. Owners may keep using existing or new customer protections instead of the pro forma agreement if FERC accepts them.
    as alternatives to the pro forma CRA, so long as those arrangements result in comparable protections and are accepted for filing by the Commission PDF p. 2
  7. Upgrade costs from Fast Energization go to the zones with large loads for 15 years, then to regional allocation.
    this allocation methodology will apply to each portfolio of IRRs identified through PJM’s Fast Energization Process for 15 years PDF p. 3
  8. Rates for the three new transmission services largely repeat those FERC approved in the co-location order.
    The rates for these services are largely identical to those proposed by the PJM Transmission Owners and approved by the Commission in the Co-Located Load Paper Hearing Order PDF p. 3
  9. The owners commit to change their formula rate templates to show state regulators the costs of transmission built for large loads.
    provide transparency to state regulators and other interested parties regarding the costs of transmission facilities being constructed by each Transmission Owner to provide transmission service to Large Loads PDF p. 4
Contents · 89 sections
  1. I. EXECUTIVE SUMMARY p. 5
  2. II. BACKGROUND p. 7
  3. A. PJM Transmission Owner Filing Rights p. 7
  4. B. Procedural Background p. 7
  5. III. DISCUSSION p. 10
  6. A. Pro Forma Cost Recovery Agreement and Related Tariff Provisions p. 10
  7. B. Transmission Service Rates and Related Charges for Co-Located Load and p. 27
  8. C. Extension of Transmission Services and Financial Penalties for Unreserved p. 28
  9. D. Cost Allocation and Recovery for Interconnection Reliability Reinforcements p. 34
  10. IV. EFFECTIVE DATE AND IMPLEMENTATION p. 45
  11. Attachment F-3A, Attachment F-4, and certain parts of Part VIII to the Tariff. For the remaining p. 45
  12. V. ADDITIONAL FILING INFORMATION p. 46
  13. A. Request for Waiver. p. 46
  14. B. Documents Submitted With This Filing. p. 46
  15. C. Communications. p. 47
  16. D. Service. p. 47
  17. VI. CONCLUSION p. 48
  18. Attachment A p. 49
  19. Attachment K-Appendix, section 6.6(c) or the defaults below: p. 60
  20. Attachment H-11 and p. 126
  21. Attachment H-34 p. 126
  22. Attachment H-11 and p. 126
  23. Attachment H-34 p. 126
  24. Attachment H-14 and p. 126
  25. Attachment H-20 p. 126
  26. Attachment H-14 and p. 126
  27. Attachment H-20 p. 126
  28. Attachment H-14 and p. 126
  29. Attachment H-20 p. 126
  30. Attachment H-15 p. 126
  31. Attachment H-15 p. 126
  32. Attachment H-15 p. 126
  33. Attachment H-21 p. 126
  34. Attachment H-21 p. 126
  35. Attachment H-21 p. 126
  36. Attachment H-21 p. 126
  37. Attachment H-21 p. 126
  38. Attachment H-22 p. 126
  39. Attachment H-22 p. 126
  40. Attachment H-22 p. 126
  41. Attachment H-22 p. 126
  42. Attachment H-22 p. 126
  43. Attachment H-24 p. 126
  44. Attachment H-24 p. 126
  45. Attachment H-24 p. 126
  46. Attachment H-24 p. 126
  47. Attachment H-24 p. 126
  48. Attachment B p. 166
  49. Attachment K-Appendix, section 6.6(c) or the defaults below: p. 177
  50. Attachment H-11 and p. 243
  51. Attachment H-34 p. 243
  52. Attachment H-11 and p. 243
  53. Attachment H-34 p. 243
  54. Attachment H-14 and p. 243
  55. Attachment H-20 p. 243
  56. Attachment H-14 and p. 243
  57. Attachment H-20 p. 243
  58. Attachment H-14 and p. 243
  59. Attachment H-20 p. 243
  60. Attachment H-15 p. 243
  61. Attachment H-15 p. 243
  62. Attachment H-15 p. 243
  63. Attachment H-21 p. 243
  64. Attachment H-21 p. 243
  65. Attachment H-21 p. 243
  66. Attachment H-21 p. 243
  67. Attachment H-21 p. 243
  68. Attachment H-22 p. 243
  69. Attachment H-22 p. 243
  70. Attachment H-22 p. 243
  71. Attachment H-22 p. 243
  72. Attachment H-22 p. 243
  73. Attachment H-24 p. 243
  74. Attachment H-24 p. 243
  75. Attachment H-24 p. 243
  76. Attachment H-24 p. 243
  77. Attachment H-24 p. 243
  78. I. INTRODUCTION p. 283
  79. II. BACKGROUND p. 284
  80. III. PURPOSE OF TESTIMONY p. 289
  81. IV. EXTENSION OF APPROVED RATE DESIGN ELEMENTS TO LARGE LOAD- p. 289
  82. V. PROPOSED RATE FOR NON-FIRM CONTRACT DEMAND TRANSMISSION p. 291
  83. VI. ALLOCATION AND RECOVERY OF COSTS ASSOCIATED WITH UPGRADES p. 293
  84. A. Summary of Cost Allocation and Recovery p. 293
  85. B. Proportional Impact Methodology p. 296
  86. C. Generator Reliability Reinforcement Fee p. 305
  87. D. Interconnection Reliability Reinforcement Charge and Cost Allocation p. 307
  88. E. Ratepayer Protection Mechanisms p. 311
  89. VIII. COST RECOVERY AGREEMENT p. 314

Topics in the text: Cost allocation · Connecting load and generation · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

EL25-49, et al. (“Co-Located Load Paper Hearing Order”).9 Additionally, the proposed tariff revisions have been designed to be consistent with PJM’s responsive section 205 filings establishing provisions for: (1) a new Fast Energization Process for generation interconnection and Large Load-related…
Read this passage

I. EXECUTIVE SUMMARY

printed heading · Topic match: Cost allocation

The PJM Transmission Owners are also proposing that all IRRs be allocated to Zones containing Large Load-related transmission requests for 15 years, after which point the remaining costs will be allocated using the then-current general regional cost allocation methodology.
Read this passage

II. BACKGROUND

printed heading

II.
Read this passage

A. PJM Transmission Owner Filing Rights

printed heading · Topic match: Cost allocation

PJM Transmission Owner Filing Rights As the Commission has noted, the PJM Transmission Owners have exclusive and unilateral rights regarding the cost allocation provisions of Schedule 12 of the Tariff.16 The PJM Transmission Owners relied on those same authorities in their February 23, 2026 paper…
Read this passage

B. Procedural Background

printed heading · Topic match: Connecting load and generation

Reese November 16, 2026 Page 8 On December 18, 2025, the Commission found the Tariff to be unjust and unreasonable and established a framework under which an Eligible Customer taking transmission service on behalf of Co-Located Load must take: (1) NITS, including interim non-firm service pending…
Read this passage

III. DISCUSSION

printed heading

III.
Read this passage

A. Pro Forma Cost Recovery Agreement and Related Tariff Provisions

printed heading · Topic match: Cost allocation

The Large Load Customer must identify and reflect in the CRA its: (i) anticipated load demand, (ii) proposed schedule for ramping up such demand, if any, and (iii) anticipated dates for each stage of service.
Read this passage

B. Transmission Service Rates and Related Charges for Co-Located Load and

printed heading · Topic match: Connecting load and generation

Accordingly, the PJM Transmission Owners’ filing implements the rate treatments already found just and reasonable for FCDS and Interim NITS through compliance tariff records,108 and proposes a revised NFCDS discounted rate methodology and related tariff provisions in compliance with the…
Read this passage

C. Extension of Transmission Services and Financial Penalties for Unreserved

printed heading · Topic match: Connecting load and generation

PTO-0006 at 1-2. 146 Id. at 1. 147 Co-Located Load Paper Hearing Order at P 248. 148 Id. at P 248. 149 Co-Located Load Paper Hearing Order at PP 572-573. 150 See Co-Located Load Paper Hearing Order at P 573; see also PJM Interconnection, L.L.C., Co-Located Load Order Workshop Meeting Materials,…
Read this passage

D. Cost Allocation and Recovery for Interconnection Reliability Reinforcements

printed heading · Topic match: Cost allocation

In balancing the need for a cost allocation methodology that assigns costs in a manner roughly commensurate with benefits while also being efficient, practically implementable, and protecting other transmission customers, the PJM Transmission Owners’ proposed cost allocation approach is intended…
Read this passage

IV. EFFECTIVE DATE AND IMPLEMENTATION

printed heading

EFFECTIVE DATE AND IMPLEMENTATION The PJM Transmission Owners understand that PJM intends to request an effective date of March 16, 2027 for the proposed revisions to Parts I, III, VI, VII, IX, XI, Attachment F-3,
Read this passage

Attachment F-3A, Attachment F-4, and certain parts of Part VIII to the Tariff. For the remaining

printed heading · Topic match: Connecting load and generation

Accordingly, given the interrelated nature of the filings, the PJM Transmission Owners request an effective date of March 16, 2027 for their proposed revisions to Tariff, Part XI and Schedules 20, 21, and 22, and an effective date of 12/31/9998 for the proposed pro forma CRA (Part IX, Subpart P);…
Read this passage

V. ADDITIONAL FILING INFORMATION

printed heading

V.
Read this passage

A. Request for Waiver.

printed heading

To the extent necessary, the PJM Transmission Owners request waiver of the requirement to submit the cost of service data required by 18 C.F.R. § 35.13.
Read this passage

B. Documents Submitted With This Filing.

printed heading

The PJM Transmission Owners submit the following materials: 1.
Read this passage

C. Communications.

printed heading

Communications regarding this filing should be addressed to the following individuals, whose names should be entered on the official service list maintained by the Secretary for this proceeding: Pulin Shah Vice President, Transmission Development EXELON CORPORATION 2301 Market Street Philadelphia,…
Read this passage

D. Service.

printed heading

PJM has served a copy of this filing on all PJM Members and on all state utility regulatory commissions in the PJM Region by posting this filing electronically.
Read this passage

VI. CONCLUSION

printed heading

CONCLUSION For the reasons stated herein, the PJM Transmission Owners respectfully request that the Commission accept the Tariff revisions without hearing, modification or condition.
Read this passage

Attachment A

printed heading · Topic match: Connecting load and generation

Reasonable Efforts: Page 2 “Reasonable Efforts” shall mean, with respect to any action required to be made, attempted, or taken by an Interconnection Party or by a Construction Party under Tariff, Part IV or Part VI, an Interconnection Service Agreement, or a Construction Service Agreement, such…
Read this passage

Attachment K-Appendix, section 6.6(c) or the defaults below:

printed heading · Topic match: Registry access

Information shall constitute Confidential Information only if: (i) it is identified as confidential when disclosed; or (ii) its nature or the circumstances of disclosure would reasonably indicate that it is confidential. 14.2 Exclusions Confidential Information does not include information that the…
Read this passage

Attachment H-11 and

printed heading

Attachment H-11 and
Read this passage

Attachment H-34

printed heading

Attachment H-34 Rate Pursuant to Attachment H-11 and Attachment H-34 Rate Pursuant to Attachment H-11 and Attachment H-34 Rate Pursuant to
Read this passage

Attachment H-11 and

printed heading

Attachment H-11 and
Read this passage

Attachment H-34

printed heading

Attachment H-34 Rockland Zone 53.766 4.481 1.0340 0.2068 0.1477 ComEd Zone4/ 5/ AEP East Zone6/ Rate Pursuant to
Read this passage

Attachment H-14 and

printed heading

Attachment H-14 and
Read this passage

Attachment H-20

printed heading

Attachment H-20 Rate Pursuant to
Read this passage

Attachment H-14 and

printed heading

Attachment H-14 and
Read this passage

Attachment H-20

printed heading

Attachment H-20 Rate Pursuant to Attachment H-14 and Attachment H-20 Rate Pursuant to Attachment H-14 and Attachment H-20 Rate Pursuant to
Read this passage

Attachment H-14 and

printed heading

Attachment H-14 and
Read this passage

Attachment H-20

printed heading

Attachment H-20 Dayton Zone Rate Pursuant to
Read this passage

Attachment H-15

printed heading

Attachment H-15 Rate Pursuant to
Read this passage

Attachment H-15

printed heading

Attachment H-15 Rate Pursuant to Attachment H-15 Rate Pursuant to Attachment H-15 Rate Pursuant to
Read this passage

Attachment H-15

printed heading

Attachment H-15 Duquesne Zone 14.17 1.18 0.27 0.0540 0.0386 Dominion Zone7/ ATSI Zone Rate Pursuant to
Read this passage

Attachment H-21

printed heading

Attachment H-21 Rate Pursuant to
Read this passage

Attachment H-21

printed heading

Attachment H-21 Rate Pursuant to
Read this passage

Attachment H-21

printed heading

Attachment H-21 Rate Pursuant to
Read this passage

Attachment H-21

printed heading

Attachment H-21 Rate Pursuant to
Read this passage

Attachment H-21

printed heading

Attachment H-21 DEOK Zone Rate Pursuant to
Read this passage

Attachment H-22

printed heading

Attachment H-22 Rate Pursuant to
Read this passage

Attachment H-22

printed heading

Attachment H-22 Rate Pursuant to
Read this passage

Attachment H-22

printed heading

Attachment H-22 Rate Pursuant to
Read this passage

Attachment H-22

printed heading

Attachment H-22 Rate Pursuant to
Read this passage

Attachment H-22

printed heading

Attachment H-22 EKPC Zone Rate Pursuant to
Read this passage

Attachment H-24

printed heading

Attachment H-24 Rate Pursuant to
Read this passage

Attachment H-24

printed heading

Attachment H-24 Rate Pursuant to
Read this passage

Attachment H-24

printed heading

Attachment H-24 Rate Pursuant to
Read this passage

Attachment H-24

printed heading

Attachment H-24 Rate Pursuant to
Read this passage

Attachment H-24

printed heading · Topic match: Connecting load and generation

Transmission Enhancement Charges allocated to a Merchant Transmission Facility for which collection is deferred in accordance with this section (b)(x)(B)(1) shall be recorded in appropriate Transmission Provider accounts for deferred charges and collected in accordance with section (b)(x)(B)(3)…
Read this passage

Attachment B

printed heading · Topic match: Connecting load and generation

Reasonable Efforts: Page 2 “Reasonable Efforts” shall mean, with respect to any action required to be made, attempted, or taken by an Interconnection Party or by a Construction Party under Tariff, Part IV or Part VI, an Interconnection Service Agreement, or a Construction Service Agreement, such…
Read this passage

Attachment K-Appendix, section 6.6(c) or the defaults below:

printed heading · Topic match: Registry access

Information shall constitute Confidential Information only if: (i) it is identified as confidential when disclosed; or (ii) its nature or the circumstances of disclosure would reasonably indicate that it is confidential. 14.2 Exclusions Confidential Information does not include information that the…
Read this passage

Attachment H-11 and

printed heading

Attachment H-11 and
Read this passage

Attachment H-34

printed heading

Attachment H-34 Rate Pursuant to Attachment H-11 and Attachment H-34 Rate Pursuant to Attachment H-11 and Attachment H-34 Rate Pursuant to
Read this passage

Attachment H-11 and

printed heading

Attachment H-11 and
Read this passage

Attachment H-34

printed heading

Attachment H-34 Rockland Zone 53.766 4.481 1.0340 0.2068 0.1477 ComEd Zone4/ 5/ AEP East Zone6/ Rate Pursuant to
Read this passage

Attachment H-14 and

printed heading

Attachment H-14 and
Read this passage

Attachment H-20

printed heading

Attachment H-20 Rate Pursuant to
Read this passage

Attachment H-14 and

printed heading

Attachment H-14 and
Read this passage

Attachment H-20

printed heading

Attachment H-20 Rate Pursuant to Attachment H-14 and Attachment H-20 Rate Pursuant to Attachment H-14 and Attachment H-20 Rate Pursuant to
Read this passage

Attachment H-14 and

printed heading

Attachment H-14 and
Read this passage

Attachment H-20

printed heading

Attachment H-20 Dayton Zone Rate Pursuant to
Read this passage

Attachment H-15

printed heading

Attachment H-15 Rate Pursuant to
Read this passage

Attachment H-15

printed heading

Attachment H-15 Rate Pursuant to Attachment H-15 Rate Pursuant to Attachment H-15 Rate Pursuant to
Read this passage

Attachment H-15

printed heading

Attachment H-15 Duquesne Zone 14.17 1.18 0.27 0.0540 0.0386 Dominion Zone7/ ATSI Zone Rate Pursuant to
Read this passage

Attachment H-21

printed heading

Attachment H-21 Rate Pursuant to
Read this passage

Attachment H-21

printed heading

Attachment H-21 Rate Pursuant to
Read this passage

Attachment H-21

printed heading

Attachment H-21 Rate Pursuant to
Read this passage

Attachment H-21

printed heading

Attachment H-21 Rate Pursuant to
Read this passage

Attachment H-21

printed heading

Attachment H-21 DEOK Zone Rate Pursuant to
Read this passage

Attachment H-22

printed heading

Attachment H-22 Rate Pursuant to
Read this passage

Attachment H-22

printed heading

Attachment H-22 Rate Pursuant to
Read this passage

Attachment H-22

printed heading

Attachment H-22 Rate Pursuant to
Read this passage

Attachment H-22

printed heading

Attachment H-22 Rate Pursuant to
Read this passage

Attachment H-22

printed heading

Attachment H-22 EKPC Zone Rate Pursuant to
Read this passage

Attachment H-24

printed heading

Attachment H-24 Rate Pursuant to
Read this passage

Attachment H-24

printed heading

Attachment H-24 Rate Pursuant to
Read this passage

Attachment H-24

printed heading

Attachment H-24 Rate Pursuant to
Read this passage

Attachment H-24

printed heading

Attachment H-24 Rate Pursuant to
Read this passage

Attachment H-24

printed heading · Topic match: Connecting load and generation

Transmission Enhancement Charges allocated to a Merchant Transmission Facility for which collection is deferred in accordance with this section (b)(x)(B)(1) shall be recorded in appropriate Transmission Provider accounts for deferred charges and collected in accordance with section (b)(x)(B)(3)…
Read this passage

I. INTRODUCTION

printed heading · Topic match: Cost allocation

In my current role, I advise regulators, utilities, grid operators, and project 1 developers on complex regulatory and market matters, with a particular focus on 2 transmission planning, cost allocation and cost recovery, and large load tariffs.
Read this passage

II. BACKGROUND

printed heading · Topic match: Cost allocation

The Large Load must execute the CRA and post credit support before it can 4 proceed through PJM’s Fast Energization Process.
Read this passage

III. PURPOSE OF TESTIMONY

printed heading · Topic match: Connecting load and generation

What is the purpose of your testimony? 8 A. [Blazunas and Hammer] The purpose of this testimony is to describe and support certain 9 PJM Transmission Owners’ Tariff revisions submitted in response to the Show Cause 10 Order and Co-Located Load Paper Hearing Order.
Read this passage

IV. EXTENSION OF APPROVED RATE DESIGN ELEMENTS TO LARGE LOAD-

printed heading · Topic match: Connecting load and generation

PTO-0001 Page 8 of 43 basis.”10 In its filing in response to the Show Cause Order, PJM is proposing to extend the 1 new transmission services (FCDS, NFCDS, and Interim NITS) to Eligible Customers 2 taking service on behalf of Large Load customers, in addition to Co-Located Load. 3 Consequently, the…
Read this passage

V. PROPOSED RATE FOR NON-FIRM CONTRACT DEMAND TRANSMISSION

printed heading · Topic match: Connecting load and generation

In short, the discounted 17 NFCDS rate for a given Zone is calculated as the zonal FCDS rate multiplied by the 18 transmission system load factor for the Zone.16 The transmission system load factor is 19 13 Co-Located Load Paper Hearing Order at PP 402, 404, 412. 14 Id. at P 412. 15 Id. 16 Proposed…
Read this passage

VI. ALLOCATION AND RECOVERY OF COSTS ASSOCIATED WITH UPGRADES

printed heading

ALLOCATION AND RECOVERY OF COSTS ASSOCIATED WITH UPGRADES 1 IDENTIFIED IN PJM’S FAST ENERGIZATION PROCESS 2
Read this passage

A. Summary of Cost Allocation and Recovery

printed heading · Topic match: Cost allocation

Why are the PJM Transmission Owners proposing a new cost allocation methodology 4 as part of the response to the Commission’s Show Cause Order? 5 A. [Hammer] The Transmission Owners are proposing a new cost allocation framework 6 because PJM’s proposed Fast Energization Process will study Large…
Read this passage

B. Proportional Impact Methodology

printed heading · Topic match: Cost allocation

Unlike an allocation based on project size or requested 6 MWs of service, the proportional impact methodology measures the extent to which the 7 generation interconnection and Large Load transmission service requests impact the 8 underlying reliability needs and the resulting portfolio of…
Read this passage

C. Generator Reliability Reinforcement Fee

printed heading

This 15- 17 32 For purposes of calculating such weighted average, each applicable Transmission Owner’s Weighted Average Cost of Capital shall be weighted based on the ratio of the final estimated costs of the Interconnection Reliability Reinforcements that it has been designated to construct and…
Read this passage

D. Interconnection Reliability Reinforcement Charge and Cost Allocation

printed heading · Topic match: Cost allocation

After 15 years, the remaining costs of Interconnection 8 Reliability Reinforcements shall be allocated and recovered pursuant to the existing 9 regional cost allocation methodology set forth in Schedule 12.
Read this passage

E. Ratepayer Protection Mechanisms

printed heading · Topic match: Cost allocation

Does the PJM Transmission Owners’ proposal address potential cost shifts among 7 retail customers within the same utility? 8 A. [Hammer] Consistent with the Commission’s findings in the Show Cause Order, the PJM 9 Transmission Owners’ proposal focuses on cost allocation and potential cost shifts at…
Read this passage

VIII. COST RECOVERY AGREEMENT

printed heading · Topic match: Cost allocation

If actual revenues fall below the committed amount, the Large Load 1 Customer must pay the difference as a Shortfall Amount.
Read this passage