ER27-522-000 · 2026-11-16 · PJM Interconnection, L.L.C.

PJM files ride-through and operating requirements for large computational loads under section 205

PDF page 1

PJM Interconnection, L.L.C.
2750 Monroe Blvd.
Audubon, PA 19403

Arleigh P. Helfer
Sr. Counsel
T:  (610) 666-4370
arleigh.helfer@pjm.com

November 16, 2026

The Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, N.E.
Washington, D.C. 20426-0001

Re:
PJM Interconnection L.L.C., Docket No. ER27-____-000,
Proposal to Address Operational Requirements for Large Computational Load and
Establish an Annual Transmission Service Reporting Requirement

Dear Secretary Reese:

Pursuant to Section 205 of the Federal Power Act1 and the August 14, 2026 letter order
issued in Docket No. EL26-67-000,2 PJM Interconnection, L.L.C. (“PJM”) hereby submits
revisions to the PJM Open Access Transmission Tariff (“Tariff”)3 to establish disturbance ride- through requirements applicable to Eligible Customers taking transmission service on behalf of Large Computational Loads, a targeted subset of Large Loads4 that may pose heightened

operational risks to the Bulk Electric System and PJM Transmission System during grid

1 16 U.S.C. § 824d. 2 PJM Interconnection, L.L.C., 196 FERC ¶ 61,129, at P 10 (2026) (noting that to extent PJM submits “an FPA section 205 filing addressing the Commission’s preliminary findings in the Show Cause Order on or before November 16, 2026, then the obligation of the respondent(s) who have made such an FPA section 205 filing to file a response to the Show Cause Order will be suspended[.]”).
3 For the purpose of this filing, capitalized terms not defined herein shall have the meaning as contained in the Open Access Transmission Tariff (“Tariff”), the Amended and Restated Operating Agreement of PJM (“Operating Agreement”), and the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region (“RAA”).
4 PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at PP 2, 16, 27–30 (2026) (accepting, effective October 12, 2026, PJM’s proposed definition of Large Load as “end-use customer(s) load that has a cumulative peak load of 50 [MW] or greater at a single electrical site behind one or more points of interconnection, where for configurations involving multiple affiliated load facilities or multiple points of interconnection with affiliated load facilities behind them, all affiliated load facilities within a one-mile radius will be considered a single electrical site as further described in the PJM Manuals.”).

PDF page 2

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 2

2

disturbances.  PJM is also proposing additional Tariff language to address ramp rates and other “ongoing operational requirements,” as described in the June 18, 2026 Show Cause Order.5   PJM is also proposing, on compliance, an annual transmission service reporting requirement.6

The Tariff language proposed herein is being filed in response to the Commission’s
preliminary finding, in the Show Cause Order,7 “that PJM’s Tariff appears to be unjust and
unreasonable because it lacks provisions addressing ongoing operational requirements for
transmission customers taking transmission service on behalf of large loads.”8  PJM submits this filing pursuant to its independent authority to modify its Tariff under FPA section 205 pursuant to Tariff, Part I, section 9.2(a) and the Consolidated Transmission Owners Agreement (“CTOA”), section 7.5.1(ii), following the requisite consultation specified under Tariff, Part I, section 9.2(b) and the CTOA, section 7.5.1(ii).

5 PJM Interconnection, L.L.C., et al., 195 FERC ¶ 61,211, at P 64 (2026) (“Show Cause Order”) (“[W]e preliminarily find that PJM’s Tariff appears to be unjust and unreasonable because it lacks provisions addressing ongoing operational requirements for transmission customers taking transmission service on behalf of large loads.”  Those ongoing operational requirements include: “ramp rates,” “ride-through requirements,” “PJM hourly forecasts, telemetry data, and other data to ensure sufficient visibility,” “equipment to enable PJM to monitor large load for impacts,” equipment “enabling PJM to remotely disconnect large loads when necessary,” and specification of “necessary control technologies or protection systems.”).
6 PJM will promptly submit a letter in Docket Nos. EL25-49 and EL26-27 informing participants of today’s tariff filings, some parts of which are submitted in compliance with Commission directives and others of which are submitted pursuant to Section 205 of the FPA.  In an abundance of caution, PJM requests waiver of any regulation or filing requirements relating to submissions in Docket Nos. EL25-49 and EL26-27 relating to today’s tariff filings.  Good cause exists to grant any necessary waivers because submission of these tariff filings in the structure presented efficiently addresses the complexity of the overlapping filing obligations and differing requested effective dates, PJM is providing prompt notice to participants in other relevant EL dockets of today’s filings, and PJM is requesting a sixty-day comment period and 120 day Commission action date that affords interested participants reasonable time to engage in the tariff filing dockets.
7 Id.
8 Id. at P 64.

PDF page 3

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 3

3

The proposed Tariff revisions mitigate threats to the reliability of the Transmission System and Bulk Electric System posed by Eligible Customers taking transmission service on behalf of Large Computational Loads by:

(1) defining Large Computational Loads, a subset of Large Loads that may pose heightened operational risks in the PJM Region, and thus trigger operational requirements on Eligible Customers serving them;

(2) setting the framework for minimum voltage ride-through and frequency ride-through requirements with which Eligible Customers taking transmission service on behalf of Large Computational Load must comply, which establishes the necessary groundwork for more detailed ride-through standards to be promulgated through revisions to PJM’s Manuals; and

(3) setting a framework for other operational requirements to be established in the Manuals, with which Eligible Customers taking transmission service on behalf of Large Computational Load must comply, relating to:  ramp rate requirements,

electromagnetic transient performance requirements, operation, coordination, and maintenance of necessary auxiliary equipment, control technologies and protection systems,

maintenance
outage
protocols,
remote
disconnection
capabilities
requirements, telemetry/data exchange requirements, and data and communication requirements.

The proposed Tariff provisions setting forth ride-through and other operational requirements state that these requirements on Eligible Customers taking transmission service on behalf of Large Computational Loads shall be set forth in PJM’s Manuals.9  At present, PJM is at an advanced stage of the process for developing Manual language for the ride-through requirement.  PJM plans to commence stakeholder engagement in early 2027 to develop Manual

9 PJM Large Computational Load Operational Review, PJM Interconnection, L.L.C., at slide 15 (Oct. 6, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/committees/pc/2026/20261006/20261006-item-07-a---1- lcl-ride-through-requirements-background---presentation.pdf; id. at slide 25, https://www.pjm.com/- /media/DotCom/committees-groups/committees/pc/2026/20261006/20261006-item-07-b---1-lcl-ride-through- requirements-solution---presentation.pdf; PJM’s Response Matrix to the Large Load Show Cause Order Opportunities, PJM Interconnection, L.L.C., Operational Requirements section (Oct. 29, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/committees/mc/2026/20261105-special/item-01---2- large-load-compliance-matrix.pdf.

PDF page 4

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 4

4

language and requirements applicable to other operational requirements set forth in the Show Cause Order.

PJM respectfully requests that the Commission accept the proposed Tariff revisions
addressing ride-through requirements and the Tariff language establishing the framework for other proposed operational requirements in the Manuals, effective January 16, 2027, which is 61 days after the date of this filing.10

For the reasons set forth below, the proposed revisions are just and reasonable.  However, if the Commission deems necessary, and to help facilitate the Commission’s acceptance of this filing without delay so that PJM can address the short-term needs for ride through requirements, PJM provides notice that it consents to the Commission’s exercise of authority to sever any element of the proposed Tariff language to the extent necessary and permitted under sections 205 and 206 of the FPA and NRG Power Marketing, LLC v. FERC.11  In particular, PJM consents to severance of the ride-through requirements from Tariff revisions proposed herein that pertain to other operational requirements because, as discussed further below, recent large load transfer events have made it abundantly clear that PJM already faces the serious reliability concerns that

10 In a separate FPA section 205 filing concurrently submitted today, PJM is proposing a later effective date of March 16, 2027, for other proposed revisions to PJM’s governing documents, including the addition of transmission products for Eligible Customers taking transmission on behalf of Large Loads.  Attachment D to that other filing includes a Chart Mapping Order Directives to Tariff Changes, some of which are the subject of the instant filing.
11 NRG Power Mktg., LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017).  As the Commission has often stated, “[t]he United States Court of Appeals for the District of Columbia Circuit has held that, in certain circumstances, the Commission has ‘authority to propose modifications to a utility’s [FPA section 205] proposal if the utility consents to the modifications.’”  N.Y. Indep. Sys. Operator, Inc., 188 FERC ¶ 61,051, at P 22 n.36 (2024) (alteration in original) (citing NRG Power Mktg., 862 F.3d at 114–15); see Midcontinent Indep. Sys. Operator, Inc., 180 FERC ¶ 61,141, at P 26 n.29 (2022) (same), order on reh’g, 182 FERC ¶ 61,096 (2023), aff’d sub nom., Entergy Ark., LLC v. FERC, 109 F.4th 583 (D.C. Cir. 2024); ISO New Eng. Inc., 175 FERC ¶ 61,172, at P 16 n.20 (2021) (same).

PDF page 5

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 5

5

are driving the need for the ride-through requirements in the short term.  Indeed, the Manual language for the ride-through requirements are in an advanced stage of development. Lastly, PJM is also addressing the Commission’s compliance directive in the June 2026 Co-Located Load Order requiring an annual report regarding the provision of new transmission services.12  PJM proposes to post on its website a report containing information about the demand for and use of:  Network Integration Transmission Service to the extent Interim Network Integration Transmission Service was also requested; Interim Network Integration Transmission Service; Firm Contract Demand Service; and Non-Firm Contract Demand Service, in a manner consistent with the method and substance of the Commission’s compliance directive.13  This proposed revision is just and reasonable because the annual report would give the Commission, states, PJM market participants, and stakeholders the benefit of additional transparency about the new transmission services being offered in PJM.  The Commission should accept this annual report proposal as just and reasonable or on compliance with the Co-Located Load Order.14

I. BACKGROUND
A. PJM Already Faces Risks Arising from Large Load-Transfer Events that
Necessitate Ride-Through Requirements
Unlike many of the other Regional Transmission Organizations and Independent System Operators (“RTOs/ISOs”) in the country, PJM already has approximately 10 GW of computational load in its footprint and, in recent years, has already experienced the reliability and operational impacts of large load transfer events.  For example: (1) on July 10, 2024, an approximately 1.5

12 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209, at PP 579–580 (2026) (“Co-Located Load Order”).
13 Proposed Tariff, Part III, section 28.2; Proposed Tariff, Part XI, section 718.2.
14 PJM’s filing does not further address this proposed revision.

PDF page 6

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 6

6

gigawatt (“GW”) large load transfer event caused frequency to increase to 60.047 Hz and voltage to increase to 1.07 per unit (“p.u.”), (2) on February 17, 2025, an approximately 1.8 GW large load transfer event caused frequency to increase to 60.047 Hz and voltage to increase to 1.07 per unit (“p.u.”),  and (3) on July 22, 2026, an approximately 3.9 GW large load event caused frequency in the Eastern Interconnection to reach 60.092 Hz and voltage to increase with a peak of ~1.138 p.u.15 As such, establishing minimum voltage ride-through and frequency ride-through requirements standards for Eligible Customers serving large loads is particularly critical to the reliability of the PJM Region.

According to the testimony of PJM Senior Manager, Generation Modeling and Dynamics Studies in the Planning Division Mr. David Egan, transfer events such as the one that occurred this past July “demonstrate[] how large amounts of load can disconnect in a very short period of time in response to transmission system conditions” which “can unnecessarily introduce additional dynamic impacts and exacerbate the underlying disturbance.”16

Critically, Mr. Egan explains, “[w]hen a large block of load disconnects unexpectedly, the actual system response may differ substantially from the conditions anticipated by planners and operators. Such disconnects can alter power flows, voltage profiles, frequency response, and system dynamics across a broad geographic area.”17  Mr. Egan further explains:

When several thousand megawatts of load disconnect within a short period of time, the resulting changes in voltage, frequency, and power flows can alter the response of generators throughout the interconnected system. These changes can affect the operation of excitation systems, voltage regulators, turbine-governor controls, and

15 PJM Large Computational Load Operational Review, PJM Interconnection, L.L.C., (Sept. 15, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/committees/pc/2026/20260915/20260915-item-02---lcl- ride-through-requirements-background-education---presentation.pdf

16 Egan Declaration ¶ 14.
17 Egan Declaration ¶ 15.

PDF page 7

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 7

7

other plant control systems that are responding to system conditions. As the magnitude and concentration of load transfers increase, so does the potential for these impacts to affect the broader interconnected system and complicate the restoration of stable system conditions following a disturbance.18

Such events pose serious threats to the reliability and safety of the Bulk Electric System in the PJM Region.  In this regard, the Commission’s Show Cause Order states that PJM’s Tariff appears to be unjust and unreasonable because it “does not specify ramp rate or ride-through requirements which the transmission customer taking transmission service on behalf of the large load must comply.”19 The Show Cause Order also recognizes the “unique nature of . . . large loads creates challenges for operation of the transmission system and necessitates greater visibility and operational control when providing transmission service to transmission customers on behalf of large loads, without which the reliability of the transmission system could be at risk.”20

The industry is facing unprecedented load growth, driven largely by data centers. PJM’s load forecast predicts peak load growth of 32 GW from 2024 to 2030, 30 GW of which is attributable to data centers.21 PJM is expected to host as much as 70% of future U.S. data center development, representing highly concentrated demand, especially in northern Virginia’s “data center alley.”  Thus, the proposed Tariff revisions are not only directly responsive to the Show Cause Order but are necessary to ensure the reliability and safety of PJM’s systems.

18 Egan Declaration ¶ 16.
19 Show Cause Order at P 64.
20 Id.
21 Id. at P 8.

PDF page 8

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 8

8

B. Consultation with Stakeholders in the Development of the Proposed Tariff
Language Regarding Large Computational Load and Ride Through
Requirements
The proposed Tariff language addresses concerns raised by the Commission.  First, the proposed Tariff revisions are directly responsive to the express, preliminary findings set forth in the Order to Show Cause.

Second, the proposed definition of Large Computational Load and the Tariff revisions associated with ride-through requirements were presented to stakeholders during the September 8, 2026 Planning Committee meeting.22  Concurrently, throughout the stakeholder process, PJM has presented stakeholders with proposed Manual language setting forth the proposed technical ride through performance requirements for Large Computational Loads.

Third, on September 15, 2026, PJM held a special session of the Planning Committee dedicated to educating stakeholders about the impetus for the proposed ride-through requirements, including reliability concerns.23

Fourth, PJM presented revised Tariff and Manual language defining Large Computational Load and addressing ride-through requirements during the October 6, 2026 Planning Committee meeting, including a comprehensive page-by-page review of the proposed provisions and

22 The agenda from PJM’s June 16, 2026 special Market Implementation Committee meeting is available at https://www.pjm.com/-/media/DotCom/committees-groups/committees/mic/2026/20260616-special/agenda.pdf.
23 PJM Large Computational Load Operational Review, PJM Interconnection, L.L.C., Item 02 (Sept. 15, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/committees/pc/2026/20260915/20260915-item-02---lcl- ride-through-requirements-background-education---presentation.pdf; id., Item 03 – 1 LCL Ride-Through Requirements Solution Education
–
Presentation,
https://www.pjm.com/-/media/DotCom/committees-
groups/committees/pc/2026/20260915/20260915-item-03---1-lcl-ride-through-requirements-solution-education--- presentation.pdf; id. Item 03 -2 LCL Ride-Through Requirements Proposed Language – Redline, https://www.pjm.com/-/media/DotCom/committees-groups/committees/pc/2026/20260915/20260915-item-03---2- lcl-ride-through-requirements-proposed-language---redline.pdf.

PDF page 9

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 9

9

implementation details.  PJM also considered and responded—both in writing24 and during and after the meeting—to submitted stakeholder questions and comments about the proposals, which subsequently gave rise to further refinements to various aspects of the proposed requirements. Fifth, as described further, below, and in the declaration of Mr. Egan, the proposal is informed by PJM’s ongoing participation in the North American Electric Reliability Corporation’s (“NERC”) development of operational standards and reliability criteria, including ride-through reliability standards, as well as PJM’s assessment and analysis of how other Regional Transmission Organizations and Independent System Operators (“RTOs/ISOs”) have addressed ride-through requirements for large loads.  At bottom, the proposed solution has benefited from several months of stakeholder input, coordinated efforts with NERC, and careful consideration of industry standards and initiatives.

C. Additional Tariff Provisions Setting the Groundwork for Future Development of
Other Operational Requirements Applicable to Eligible Customers Taking
Transmission Service on Behalf of Large Computational Loads
PJM’s submission also proposes Tariff language for other operational components to
address potential gaps in processes for evaluating reliability impacts and transmission needs of Large Loads.  PJM has not yet commenced stakeholder discussions to develop these requirements although they have been acknowledged in stakeholder consultations.25 PJM has indicated that

24 Q &  A on Large Computational Load Ride-Through Requirements, PJM Interconnection, L.L.C. (Oct. 6, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/committees/pc/2026/20261006/20261006-item-07-b---3- qa-on-lcl-rt-requirements.pdf
25 See, e.g., PJM’s Response Matrix to the Large Load Show Cause Order Opportunities, PJM Interconnection, L.L.C., at pages 3 through 6 (Oct. 29, 2026), https://www.pjm.com/-/media/DotCom/committees- groups/committees/mc/2026/20261105-special/item-01---2-large-load-compliance-matrix.pdf; Overview of June 18 Co-Located Load and Large Load Show Cause Orders, PJM Interconnection, L.L.C., at slides 14–15 (July 30, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/workshops/cllsco/2026/20260730/20260730-item-02--- co-located-load-and-large-load-show-cause-orders---presentation.pdf; PJM LCL Ride-through Requirements, PJM Interconnection, L.L.C., at slide 7 (Sept. 8, 2026), https://www.pjm.com/-/media/DotCom/committees- groups/committees/pc/2026/20260908/20260908-item-05---1-large-load-ride-through---presentation.pdf; PJM Large

PDF page 10

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 10

10

development of these other operational components will comprise significant ongoing work in 2027 to develop details in Manual language relating to ramp rate and other operational requirements.26

Under these additional proposed Tariff provisions, PJM is committing to develop requirements in the Manuals for Eligible Customer taking transmission service on behalf of Large Computational Loads to comply with in order to address other operational requirements for fast- ramping load that may impact the transmission system, as described in the Large Load Show Cause Order.27  The Manual language will be developed and specified in the PJM Manuals only after PJM has undergone the requisite additional study and stakeholder engagement in 2027.28

II. THE PROPOSED TARIFF REVISIONS ARE JUST AND REASONABLE
A. PJM Proposes to Define Large Computational Loads, the Relevant Subset of
Large Loads in PJM for Purposes of the Proposed Operational Requirements
As a preliminary matter, PJM proposes to apply the ride-through requirements for large loads to Eligible Customers taking transmission service on behalf of a subset of Large Loads, which PJM refers to as “Large Computational Load.”  PJM proposes to add a definition of Large Computational Load to the Tariff:

“Large Computational Load” shall mean Large Load containing 25 MW or greater

Computational Load Operational Review, PJM Interconnection, L.L.C., at slide 15 (Oct. 6, 2026); https://www.pjm.com/-/media/DotCom/committees-groups/committees/pc/2026/20261006/20261006-item-07-a---1- lcl-ride-through-requirements-background---presentation.pdf.

26 PJM has spoken of additional operational requirements, like ramp rates, as being the subject of additional study and stakeholder engagement before they could be implemented.  More precisely stated, the particulars of these additional operational requirements will be discussed and developed with stakeholders as Manual language is developed.
27 Paragraph 64 28 PJM Large Computational Load Ride-Through Requirements, PJM Interconnection, L.L.C., at slide 25 (noting ramp rate and design envelope work plan for 2027) (Oct. 6, 2026), https://www.pjm.com/- /media/DotCom/committees-groups/committees/pc/2026/20261006/20261006-item-07-b---1-lcl-ride-through- requirements-solution---presentation.pdf.

PDF page 11

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 11

11

of maximum load served through power electronic conversion equipment.  Large Computational Load shall include:

A) New Large Computational Load. Any Large Computational Load on whose behalf an Eligible Customer enters the Transmission Provider or Transmission Owner study processes on or after [61 days from filing].

B) Materially Modified Large Computational Load. Existing Large Load that otherwise meets the definition of Large Computational Load but does not meet the aggregate load 50 MW threshold that is subsequently modified in a manner resulting in the aggregate load becoming 50 MW or greater or otherwise constituting a material modification as determined by Transmission Provider and the applicable Transmission Owner on or after [61 days from filing].

C) Transitional Large Computational Load. Any Large Computational Load, including a Large Computational Load undergoing a Material Modification, on whose behalf, prior to [61 days from filing], an Eligible Customer serving such load has:

− formally initiated or completed an interconnection study with the Transmission Owner,

− executed an interconnection agreement, service agreement, or other agreement authorizing interconnection,

− commenced construction, or
− achieved commercial operation.
Large Computational Load is Large Load that “contain[s] 25 MW or greater of maximum load served through power electronic conversion equipment.”29  As Mr. Egan testifies, the 25 MW “evolved from PJM’s experience evaluating large co-located loads, stakeholder feedback on earlier draft language, and a review of approaches being developed by other regions, particularly MISO.”30  Furthermore, as Mr. Egan testifies, PJM tied the definition of Large Computational Load to a threshold quantity of “power electronic conversation equipment” because: PJM observed through its co-location and large load analyses that Large Computational Load facilities generally consist of two primary categories of load:

(1) cooling and support infrastructure loads used to remove heat and maintain facility operation, and (2) electronics-based loads supplied through power

29 Tariff, Part I, Definitions L–M–N (Large Computational Load).
30 Egan Declaration ¶ 20.

PDF page 12

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 12

12

electronic conversion equipment, including the AC-to-DC systems that serve
information technology equipment and similar technologies. The reliability
concern underlying PJM’s proposed requirements is primarily associated with the electronics-based portion of the load, as these systems can rapidly alter their demand or transfer off the Bulk Electric System during disturbance conditions. While the proportion of facility load attributable to cooling versus electronics varies across facility vintages and designs, PJM concluded that the defining reliability characteristic is the presence of substantial power electronic conversion equipment rather than the specific end use served by that equipment.31

The targeted application of ride-through requirements to Large Loads that meet the Large Computational Load definition is just and reasonable.  First, the proposed definition recognizes that ride-through and other operational requirements being developed are intended to apply only to Eligible Customers serving Large Loads with operating characteristics warranting additional reliability consideration.  Thus, for purposes of managing operational risk, defining Large Computational Load supports a more targeted approach than applying the same ride-through and other operational requirements to all Eligible Customers serving Large Loads without regard to facility type or operating behavior.

Second, the proposed definition of Large Computational Load is aligned with NERC’s proposed definition of computational load entities, which has likewise recognized that computational loads may warrant reliability requirements distinct from those applicable to traditional loads.32  Both PJM’s proposed definition of Large Computational Load and NERC’s developing definition recognize that power electronic conversion equipment that serves information technology, such as servers, storage, and networking hardware, similarly focus on the

31 Egan Declaration ¶ 22.
32 See Petition of the North American Electric Reliability Corporation for Approval of Revisions to the NERC Rules of Procedure Regarding Computational Load and Request for Expedited Action, Docket No. RD26-7 (“NERC Petition”), 4–5.

PDF page 13

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 13

13

underlying electronic equipment and characteristics of the Large Load rather than a particular industry or customer type.  As Mr. Egan explains, PJM’s definition of Large Computational Load is tailored to the specific needs of the PJM Region, while NERC’s developing definition of computational load, along with relevant registration criteria and Reliability Standards, is intended to determine which Large Loads will be subject to NERC’s mandatory reliability requirements. Specifically, “PJM concluded that the relevant reliability characteristic” of Large Loads in PJM “is not limited to servers or computational facilities, but rather the presence of large quantities of power electronic conversion equipment capable of exhibiting similar disturbance-response characteristics.”33 Defining Large Computational Loads as Large Loads meeting a threshold quantity of power electronic conversion equipment, “encompasses data centers” within the definition of Large Computational Load “while also remaining applicable to other emerging load types that rely heavily on power-electronic conversion technologies, such as certain hydrogen production facilities and other future industrial processes.”34

Third, the differences in PJM’s definition of Large Computational Load and NERC’s developing definition reflect the different purposes and responsibilities of PJM and NERC. Indeed, as described further, below, the proposed Tariff language establishing ride-through requirements for Large Computational Load allows an Eligible Customer or Transmission Owner to modify its ride-through requirements “to address changes in system conditions, reliability needs, applicable NERC Reliability Standards or Transmission Provider operating requirements, provided such requirements continue to meet or exceed the minimum requirements established by

33 Egan Declaration ¶ 21
34 Id.

PDF page 14

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 14

14

Transmission Provider in the PJM Manuals.”35
Fourth, PJM’s proposed approach to defining a specific subset of Large Load reflects PJM’s review and evaluation of emerging large-load and computational-load definitions under development by industry organizations and transmission providers.36 These industry efforts reflect a common recognition that certain computational loads present reliability considerations that differ from those associated with traditional commercial and industrial loads.  PJM’s proposed definition is generally consistent with the applicability thresholds being adopted or proposed elsewhere in the industry.  For example, MISO has similarly identified a subset of large load as computational load to which its proposed ride-through requirements will apply.  MISO has also similarly proposed to define computational load as “Large Load comprised of 25 MW or more of Demand from information technology equipment, such as servers, storage, and network hardware.”37 Although specific criteria vary across regions, these frameworks reflect a common recognition that large computational facilities can present unique reliability considerations requiring enhanced planning, modeling, and operational oversight.  Consistent with these industry developments, PJM’s proposed Large Computational Load definition identifies facilities containing substantial computational load that may create material reliability impacts if they respond to transmission disturbances in a coordinated manner. PJM’s proposed criteria are informed by these industry efforts but were ultimately developed based on PJM’s own reliability assessments, operational experience, planning studies, and analyses of Large Computation Load

35 Proposed Tariff, Part III, section 28.2.
36 See Egan Declaration ¶¶ 19–22, 25.
37 Midcontinent Indep. Sys. Op., Inc., Interconnection Reliability Requirements for Large Loads, Transmittal Letter, Docket No. ER26-3650-000, at 22 (Aug. 28, 2026).

PDF page 15

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 15

15

behavior on the PJM system. As such, PJM’s proposed definition is consistent with the broader industry trend toward recognizing computational loads as a distinct category of load for reliability purposes while tailoring the specific criteria to the reliability needs of the PJM region.38

B. PJM Is Proposing Ride-Through Requirements Applicable to Eligible Customers Taking Transmission Service on Behalf of Large Computational Loads

PJM is proposing to revise its Tariff to establish a framework for setting minimum voltage and frequency ride-through requirements, with which Eligible Customers taking transmission service on behalf of both existing and new Large Computational Loads must comply.39  Under the proposed language in Tariff, Part III, section 28.2, the Transmission Provider shall establish “minimum voltage ride-through and frequency ride-through requirements with which Eligible Customers taking transmission service on behalf of Large Computational Load must comply, which shall be set forth in the PJM Manuals.”  The proposed language sets a floor for disturbance ride-through requirements while also leaving room for Transmission Owners or Eligible Customers to establish ride-through requirements that are “no less stringent than the minimum requirements established by Transmission Provider in the PJM Manuals[]” where “the Transmission Owner determines that such requirements are necessary to maintain the reliability, security, or operational performance of its transmission facilities or the Transmission System.”40 Furthermore, any ride-through requirements established by an Eligible Customer or Transmission Owner must “be based upon reliability, planning, operational, stability, protection coordination, voltage performance, frequency performance, restoration, balancing, reserve management or other

38 Egan Declaration ¶ 25.
39 Proposed Tariff, Part III, section 28.2.
40 Proposed Tariff, Part III, section 28.2.

PDF page 16

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 16

16

reliability-related considerations and shall be applied in a not unduly discriminatory manner to similarly situated Large Computational Load.”41

Finally, it is worth noting that establishing minimum ride-through requirements applicable to Eligible Customers taking transmission service on behalf of Large Computational Loads has the necessary effect of also establishing consequences for failure to comply with such requirements, including, but not limited to, referrals to the Market Monitoring Unit and the North American Electric Reliability Corporation and its Regional Entities and action at or before the Commission.

1. The Proposed Ride-Through Requirements Apply Whether Large
Computational Loads Are Served Through Network Transmission Service
or One of the New Transmission Services Available to Large Loads
PJM’s proposed ride-through requirements apply whether Eligible Customers are serving Large Computational Loads by taking Network Service, under Part III of the Tariff,42 or by taking any one of the new transmission services for Large Loads, pursuant to Part XI of the Tariff.43  The application of the ride-through requirements to Eligible Customers taking any of these transmission services on behalf of Large Computational Loads adheres to the Show Cause Order, which provides:

[T]he provision of transmission service to Eligible Customers on behalf of large loads [is intended] to encompass the provision of new, modified, or additional

jurisdictional transmission service to Eligible Customers on behalf of large loads. We note that this phrase is not limited to instances where an Eligible Customer

submits an application to request new transmission service.  It also includes

41 Proposed Tariff, Part III, section 28.2.
42 Proposed Tariff, Part III, section 35.1 (“The Network Customer shall plan, construct, operate and maintain its facilities in accordance with Good Utility Practice and in conformance with the Network Operating Agreement. Eligible Customer taking transmission service to serve Large Computational Load shall ensure compliance with all the requirements established in accordance with Tariff, Part III, section 28.2, and set forth in the PJM Manuals.”).
43 Proposed Tariff, Part XI, section 718.2 (“Eligible Customer taking Transmission Service under Part XI to serve Large Computational Load shall ensure compliance with all the requirements established in accordance with Tariff, Part III, section 28.2, and set forth in in the PJM Manuals. Transmission Provider shall prepare the annual report consistent with Tariff, Part III, section 28.2.”).

PDF page 17

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 17

17

instances where an Eligible Customer requests a new or modified point of delivery
to serve a large load, where a large load seeks a new or modified delivery point as an unbundled retail transmission service customer, or where large loads are

otherwise included in an Eligible Customer’s reported load growth and that Eligible Customer is taking [Network Integrated Transmission Service (“NITS”)].”44

Indeed, the ride-through requirements are necessitated by the operational characteristics of the underlying Large Computational Load, not by the type of transmission service that an Eligible Customer is using to serve such load.  Thus, the ride-through requirements apply equally to NITS and non-NITS customers.

2. PJM’s Proposal Imposes Ride Through Requirements on Eligible
Customers Serving Large Computational Loads
As proposed, the ride-through requirements apply to Eligible Customers45 taking
transmission service on behalf of Large Computational Load.  Placing the onus on Eligible Customers to meet these requirements when procuring transmission service on behalf of Large Computational Loads ensures that the proposed Tariff language falls squarely within the Commission’s “exclusive jurisdiction over the rates, terms, and conditions of interstate transmission service to Eligible Customers on behalf of large loads connecting to the transmission system, and the practices directly affecting the provision of such interstate transmission of electricity.”46  This is just, reasonable, and not unduly discriminatory because it applies equally to all Eligible Customers taking service on behalf of LCLs in order to maintain the reliability and

44 Show Cause Order at P 42.
45 PJM’s Tariff defines an Eligible Customer as “(i) Any electric utility (including any Transmission Owner and any power marketer), Federal power marketing agency, or any person generating electric energy for sale for resale . . .  (ii) Any retail customer taking unbundled transmission service pursuant to a state requirement that the Transmission Provider or a Transmission Owner offer the transmission service, or pursuant to a voluntary offer of such service by a Transmission Owner, is an Eligible Customer under the Tariff.  As used in Tariff, Part VIII, Eligible Customer shall mean only those Eligible Customers that have submitted an Application and Study Agreement.”  Tariff, Part I, section 1, Definitions E – F.
46 Show Cause Order at P 47.

PDF page 18

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 18

18

safety of the Bulk Electric System.
Furthermore, the ride-through requirements apply to Eligible Customers, rather than
Transmission Customers.  PJM recognizes that the Show Cause Order notes that “ongoing
operation requirements should apply to transmission customers, rather than Eligible Customers, as these requirements apply after the Eligible Customer has an executed (or a filed unexecuted) service agreement for transmission service and have become transmission customers under the Tariff.”47  However, in PJM the term Transmission Customer is circumscribed to specific types of customers, which may unnecessarily constrain the scope of the application of these ride-through requirements.48  PJM proposes that Eligible Customers meet minimum ride-through requirements as a condition of interconnection.

3. PJM’s Proposes to Apply Ride-Through Requirements to Eligible
Customers Serving Existing and New Large Computational Load
As noted above, PJM already has approximately 10 GW of existing computational load in
its region and has, in recent years, already experienced the significant consequences of large load transfers.  Thus, PJM’s proposed definition does not exempt existing Large Computational Loads from the proposed ride-through requirements.  Nevertheless, PJM’s proposed ride-through

requirements are mindful of the Commission’s directive that any section 205 filing submitted in response to the Show Cause Order should “provide a reasoned explanation for how the proposal

47 Order to Show Cause at P 57 n.140.
48 The PJM Tariff defines Transmission Customers as “any Eligible Customer (or its Designated Agent) that (i) executes a Service Agreement, or (ii) requests in writing that the Transmission Provider file with the Commission a proposed unexecuted Service Agreement, to receive transmission service under Tariff, Part II.  This term is used in Tariff, Part I and Tariff, Part VI to include customers receiving transmission service under Tariff, Part II and Tariff, Part III. Where used in Tariff, Attachment K-Appendix and the parallel provisions of Operating Agreement, Schedule 1, Transmission Customer shall mean an entity using Point-to-Point Transmission Service.” Tariff, Part I, section 1, Definitions T – U – V.

PDF page 19

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 19

19

will avoid disrupting existing commercial arrangement and clearly identify a reasonable effective date that accommodates such existing commercial arrangements.”49  Specifically, PJM proposes to accommodate existing commercial arrangements by granting additional time for a category of Large Computational Loads, called “Transitional Large Computational Load Facilities” to achieve compliance with the proposed disturbance ride-through requirements.  As proposed, “where an Eligible Customer is taking transmission service on behalf of  Transitional Large Computational Load for purposes of these requirements, the Eligible Customers shall achieve compliance with respect to the Transitional Large Computational Load no later than [61 days from filing plus one year], or within one (1) year of its Commercial Operation Date, whichever is later.”50 Applying the ride-through requirements to existing Large Computational Load through a transitional mechanism is just and reasonable and, furthermore, recognizes that Eligible Customers taking transmission service on behalf of Large Computational Load poses operational risks to the PJM Region, regardless of whether the Large Computational Load is new or existing. Indeed, the PJM Tariff already requires that Network Customers “plan, construct, operate and maintain [their] facilities in accordance with Good Utility Practice[.]”  Good Utility Practice, in turn, is defined to “mean any of the practices, methods and acts engaged in or approved by a significant portion of the electric utility industry during the relevant time period, or any of the practices, methods and acts which, in the exercise of reasonable judgment in light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety and

49 Show Cause Order at P 38.
50 Proposed Tariff, Part III, section 28.2.

PDF page 20

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 20

20

expedition.  Good Utility Practice is not intended to be limited to the optimum practice, method, or act to the exclusion of all others, but rather is intended to include acceptable practices, methods, or acts generally accepted in the region; including those practices required by Federal Power Act, section 215(a)(4).”

Federal Power Act, section 215(a)(4) defines “reliable operation” as meaning “operating the elements of the bulk-power system within equipment and electric system thermal, voltage, and stability limits so that instability, uncontrolled separation, or cascading failures of such system will not occur as a result of a sudden disturbance, including a cybersecurity incident, or unanticipated failure of system elements.”

Thus, Network Customers must operate existing facilities consistent with Good Utility Practice to avoid significant grid reliability events caused by, among other things sudden system disturbances unique to new and existing Large Computational Loads.51 As Dr. Choi explains in his declaration, not doing so “would exempt a substantial portion of the current reliability risk from the proposed [ride-through] requirements.”52

As discussed above, PJM faces a unique risk unlike other regions where the existing installed Large Computational Load base is comparatively small, as demonstrated by the fact that PJM has already experienced several load-transfer events attributable to voltage ride-through performance issues, including the nearly 4 GW event on July 22, 2026.53 Unlike ERCOT and MISO, for example, PJM cannot exempt existing computational load and its demonstrated

51 Choi Declaration ¶ 8.
52 Id. 53 Id.

PDF page 21

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 21

21

operational effects: the requirements must apply to new and existing facilities, allowing reasonable time for Transitional Large Computational Load Facilities to achieve compliance.54 The additional compliance period applicable to Transitional Large Computational Load

provides
accommodations to Eligible Customers serving existing Large Computation Load, thus minimizing potential disruptions to existing commercial arrangements while upholding Network Customers’ obligations to operate consistent with Good Utility Practice and affirming PJM’s mandate to ensure the reliability of the transmission system in its region.

4. Specific ride-through requirements applicable to Eligible Customers
serving Large Computational Load shall be set forth in PJM’s Manuals
The proposed ride-through requirements require that any Eligible Customer taking transmission service on behalf of Large Computational Load adhere to minimum voltage and frequency ride-through requirements that “shall be set forth in the PJM Manuals.”55  PJM notes that this approach—establishing the core ride-through requirement in the Tariff and the technical criteria in the manual—is consistent with the approach recently proposed by the Southwest Power Pool, Inc. (“SPP”) and accepted by the Commission.  SPP’s ride-through requirements for transmission customers providing service to Large Loads requires transmission customers to comply with ride-through requirements set forth as guidelines in “a non-Tariff document that was separately approved by SPP stakeholder working groups.”56  Likewise, PJM is concurrently undergoing the process of developing and receiving feedback from its stakeholders on proposed

54 Id.
55 Proposed Tariff, Part III, section 28.2.
56 Sw. Power Pool, Inc., 194 FERC ¶ 61,031, at P 20 (2026).

PDF page 22

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 22

22

Manual language.57
C. PJM Is Proposing Tariff Language Authorizing the Development of Other
Operational
Requirements
Applicable
to
Eligible
Customers
Taking
Transmission Service on Behalf of Large Computational Loads
The Show Cause Order additionally found the PJM Tariff appeared to be unjust and
unreasonable because it lacks other “provisions addressing ongoing operational requirements for transmission customers taking transmission service on behalf of large loads.”58  PJM also proposes Tariff language to address the other operational requirements to be imposed on Eligible Customers taking transmission service to serve Large Computational Loads.   For the reasons cited above, as set forth at length for the ride through requirements specifically, and given the Commission’s acceptance of similar operational requirements provisions in other Regions and the Commission’s observations in the Large Load Show Cause Order, the Commission should accept these proposed revisions establishing the framework for other operational requirements to be developed in the Manuals as just and reasonable.59  PJM will work with stakeholders to develop the particular requirements necessary to implement each of these provisions through vetted Manual language, with due consideration for implementation dates, before these requirements can be of any force and effect.

57 See October 6, 2026 Planning Committee meeting agenda, available at https://www.pjm.com/- /media/DotCom/committees-groups/committees/pc/2026/20261006/20261006-agenda.pdf.
58 Show Cause Order at P 64.
59 See, e.g., Sw. Power Pool, Inc., 194 FERC ¶ 61,031 (2026) (accepting SPP Tariff language in SPP Tariff, Attachment AE, section 2.22, requiring SPP’s market participants registering High Impact Large Loads to, among other things, “Have remote capability to disconnect the load from the Transmission System made available to the transmission operator; . . . Have an effective up and down ramp rate not exceeding the specified limit outlined in the Market Protocols unless otherwise directed by the SPP Balancing Authority, Reliability Coordinator, or local transmission operator; . . . Provide registration information as specified in the Market Protocols; . . . Not have a negative withdrawal at the load delivery point without appropriate Transmission Service.”).

PDF page 23

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 23

23

D. Pro Forma Provisions in Transmission Service Agreements Exist or Will Exist to Memorialize Ongoing Operational Requirements

The Commission’s order also notes opportunities for pro forma provisions in a Transmission Service Agreement between PJM and the Eligible Customer taking transmission service on behalf of a Large Load in order to memorialize the ongoing operational requirements.60 PJM’s transmission service agreements (those existing today and those proposed) memorialize ongoing operational requirements for Eligible Customers taking transmission service.61  The pro forma Network Integration Transmission Service Agreement in the Tariff provides that the “Network Customer agrees to  take and pay for Network Transmission Service in accordance with the provisions of the Tariff, including the Network Operating Agreement (which is incorporated herein by reference), and this Service Agreement as they may be amended from time to time.”62 The Network Operating Agreement is the Restated and Amended Operating Agreement of PJM Interconnection, L.L.C.63  Pursuant to the Operating Agreement, entities must “[c]omply with the requirements of the PJM Manuals.”64  Similar constructs will exist for customers taking the newly proposed transmission services.65  Since the operational requirements addressed in this filing are being memorialized in the Tariff with details to be set forth in the Manuals, the desired pro forma provisions exist or will exist in the relevant service agreements to address the Commission’s concern.

60 Show Cause Order at P 65.
61 Show Cause Order at P 64.
62 Tariff, Attachment F-3, section 4.0. 63 Tariff, Part III, section 35.2; Tariff, Attachment G.
64 Operating Agreement, section 11.3.1(e).
65 Proposed Tariff, Part XI, Subpart C, section 720.2; Proposed Tariff, Attachment F-3A, section 4.0; Proposed Tariff, Attachment F-4, section 4.0.

PDF page 24

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 24

24

III. STAKEHOLDER ENGAGEMENT
The proposed Tariff revisions defining Large Computational Load and establishing ride- through requirements follow an expedited stakeholder engagement effort.  PJM presented its initial proposal to stakeholders at the September 8, 2026 Planning Committee meeting.66 PJM subsequently conducted a dedicated Planning Committee education session on September 15, 2026, during which Planning and Operations subject matter experts presented the July 22, 2026 load transfer event, the associated reliability concerns, and the technical basis supporting the proposed ride-through requirements.67  PJM then presented revised Tariff and Manual language at the October 6, 2026 Planning Committee meeting.68

With respect to other ongoing operational requirements applicable to Eligible Customers taking transmission on behalf of Large Computational Load, PJM is committed to developing Manual language through the stakeholder process starting in early 2027.  PJM has in other fora and in posted materials – particularly at and for the Co-Located Load Workshops, the Markets and Reliability Committee, and the Special Members Committee convened on November 5, 2026 preceding this Section 205 filing – noted the operational requirements described in the Show Cause Order.

66 See September 8, 2026 Planning Committee meeting agenda, available at https://www.pjm.com/- /media/DotCom/committees-groups/committees/pc/2026/20260908/20260908-agenda.pdf.
67 See September 15, 2026 Planning Committee–Special Session agenda, available at https://www.pjm.com/- /media/DotCom/committees-groups/committees/pc/2026/20260915/20260915-agenda.pdf.
68 See October 6, 2026 Planning Committee meeting agenda, available at https://www.pjm.com/- /media/DotCom/committees-groups/committees/pc/2026/20261006/20261006-agenda.pdf.

PDF page 25

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 25

25

IV. PROPOSED EFFECTIVE DATE
PJM proposes an effective date of January 16, 2027, for the proposed Tariff revisions referenced herein.  PJM requests that the Commission issue an order on this filing by January 15, 2027.

V. DESCRIPTION OF SUBMITTAL
This filing consists of the following:
1. This transmittal letter;
2. Attachment A – Revisions to the Tariff, in redline format;
3. Attachment B – Revisions to the Tariff, in clean format;
4. Attachment C – Declaration of David Egan;
5. Attachment D – Declaration of Byoungkon Choi.
VI. CORRESPONDENCE
The following individuals are designated for inclusion on the official service list in this proceeding and for receipt of any communications regarding this filing: Arleigh P. Helfer

Sr. Counsel
PJM Interconnection, L.L.C.
2750 Monroe Boulevard
Audubon, Pennsylvania 19403
(610) 666-4370
arleigh.helfer@pjm.com

Mark Stanisz
Associate General Counsel
PJM Interconnection, L.L.C.
2750 Monroe Boulevard
Audubon, PA 19403
(610) 666-2255
mark.stanisz@pjm.com

Craig Glazer
Vice President - Federal
Government Policy
PJM Interconnection, L.L.C.
1200 G Street, N.W, Suite 600
Washington, D.C. 20005
(202) 423-4743
craig.glazer@pjm.com

PDF page 26

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 26

26

VII. SERVICE
PJM has served a copy of this filing on all PJM Members and on all state utility regulatory commissions in the PJM Region by posting this filing electronically.  In accordance with the Commission’s regulations,69 PJM will post a copy of this filing to the FERC filings section of its internet site, located at the following link: https://www.pjm.com/library/filing-order with a specific link to the newly-filed document, and will send an e-mail on the same date as this filing to all PJM Members and all state utility regulatory commissions in the PJM Region70 alerting them that this filing has been made by PJM and is available by following such link.  If the document is not immediately available by using the referenced link, the document will be available through the referenced link within 24 hours of the filing.  Also, a copy of this filing will be available on the FERC’s eLibrary website located at the following link: http://www.ferc.gov/docsfiling/ elibrary.asp in accordance with the Commission’s regulations and Order No. 714.

69 See 18 C.F.R. §§ 35.2(e) and 385.2010(f)(3).
70 PJM already maintains, updates and regularly uses e-mail lists for all PJM Members and affected state commissions.

PDF page 27

Honorable Debbie-Anne A. Reese, Secretary
November 16, 2026
Page 27

27

VIII. CONCLUSION
Based on the foregoing, PJM respectfully requests that the Commission accept proposed revisions to PJM’s Tariff.

Respectfully submitted,
/s/ Arleigh P. Helfer

Craig Glazer
Vice President – Federal Government Policy
PJM Interconnection, L.L.C.
1200 G Street, N.W.
Suite 600
Washington, D.C. 20005
(202) 423-4743
craig.glazer@pjm.com
Arleigh P. Helfer
Sr. Counsel
PJM Interconnection, L.L.C.
2750 Monroe Boulevard
Audubon, PA 19403
(610) 666-4370
arleigh.helfer@pjm.com

Mark Stanisz
Associate General Counsel
PJM Interconnection, L.L.C.
2750 Monroe Boulevard
Audubon, PA 19403
(610) 666-2255
mark.stanisz@pjm.com

On behalf of
PJM Interconnection, L.L.C.