NYISO requests more time to answer the June 18 show cause order
NYISO moves for the maximum 90-day abeyance of the EL26-69 show cause response, to November 16, 2026, so it can build a section 205 filing through its stakeholder governance process and coordinate with the New York transmission owners.
Asks FERC to: Issue an order by August 13, 2026 holding the proceeding in abeyance for 90 days until November 16, 2026, with a five-day answer period.
Invokes the E-12 order's 90-day abeyance option and describes the section 205 package NYISO plans on study process, flexible service, co-location and proximate generation.
E-12 NYISO: Show cause or propose tariff changes in 60 days (p. 5) E-12 NYISO: Timely study window (P 44, p. 31) E-12 NYISO: Proximate-generation service (P 121, p. 72)
Key points
- NYISO requests the full 90 days and action by August 13.
hold this proceeding in abeyance for the maximum period permitted by the Show Cause Order, i.e., for 90 days, until November 16, 2026. PDF p. 1
- NYISO plans a new large load study process replacing its existing load interconnection rules, with expedited joint studies.
the NYISO plans to create a new large load study process that would replace and improve upon its existing load interconnection rules. PDF p. 7
- NYISO would offer firm and non-firm variants of its financial reservation service, with non-firm withdrawal service for flexible large loads.
make large loads eligible to take non-firm withdrawal service to the extent their ability to be flexible mitigates their impact on the system. PDF p. 7
- For co-location, NYISO intends to sunset its BTM:NG program and treat load and generation as separate market entities.
the NYISO intends to propose sunsetting its BTM:NG program and replacing it with a new co-located resource participation model PDF p. 7
- NYISO ties the timing to New York's shared governance and the NYPSC's parallel large-load proceeding.
a 90-day abeyance is reasonable in the NYISO's case because it will facilitate the NYISO's ability to obtain approval from its stakeholder Management Committee before making a section 205 filing. PDF p. 9
- Schedule: committee votes October 14 and 15, Management Committee October 28, filing November 16, 2026.
Provided that Management Committee and Board approvals are secured, the NYISO will submit a section 205 proposal on November 16, 2026 PDF p. 11
Contents · 5 sections
Topics in the text: Filing procedure · Connecting load and generation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
The NYISO respectfully requests that the Commission hold this proceeding in abeyance for the maximum period permitted by the Show Cause Order, i.e., for 90 days, until November 16, 2026.Read this passage
I. Background
printed heading · Topic match: Filing procedure
Background The Commission has determined that there are “a host of urgent challenges associated with providing the transmission service needed to serve the ongoing influx of large loads while 5 The Show Cause Order states that it will “consider [abeyance] requests from NYISO and/or the Transmission…Read this passage
II. The NYISO Should Be Granted a 90-Day Abeyance to Pursue a Section 205 Filing
printed heading · Topic match: Filing procedure
The NYISO Should Be Granted a 90-Day Abeyance to Pursue a Section 205 Filing Through Its Shared Governance Process to Address the Show Cause Order in a Manner Tailored to the NYISO Region The NYISO recognizes that the concerns raised in the Show Cause Order are critically important and must be of…Read this passage
III. The NYISO’s Plans for Developing and Submitting its Section 205 Proposal
printed heading · Topic match: Filing procedure
It is apparent that stakeholders endorse an abeyance and are prepared to work collaboratively and quickly to help refine the NYISO’s proposal.Read this passage
IV. Request for Expedited Action by August 13 and for Shortened Comment Period
printed heading · Topic match: Filing procedure
Request for Expedited Action by August 13 and for Shortened Comment Period The NYISO respectfully requests that the Commission act on this motion by August 13, 2026.Read this passage
V. Conclusion
printed heading · Topic match: Filing procedure
Conclusion For the foregoing reasons, the NYISO respectfully requests that the Commission issue an order by August 13, 2026, holding this proceeding in abeyance for 90 days until November 16, 2026.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Rensselaer, NY this 3rd day of August 2026. /s/ Alexander Morse Alexander Morse New York Independent System Operator, Inc. 10 Krey Blvd.Read this passage