CAISO requests more time to answer the June 18 show cause order
CAISO moves to hold the show cause proceeding in abeyance for 90 days. It lays out a stakeholder schedule leading to a November 16, 2026 FPA section 205 filing, made together with its Participating Transmission Owners.
Asks FERC to: Hold the EL26-71 section 206 proceeding in abeyance for 90 days, until November 16, 2026, while CAISO and the Participating Transmission Owners prepare section 205 filings.
Requests the up-to-90-day abeyance option in the E-10 CAISO show cause order, offering the description of a future section 205 filing and the timeline the order required. FERC granted it August 14, 2026.
E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25)
Key points
- CAISO wants 90 days from the response deadline to November 16, 2026, aligned with the Participating Transmission Owners' requests.
hold the instant proceeding in abeyance for 90 days from the deadline to respond PDF p. 1
- The filing is meant to address all preliminary findings and five reform categories in the order, with simultaneous PTO filings.
will address all the preliminary findings and five categories of reforms set forth in the Order to Show Cause, as appropriate for the CAISO region. PDF p. 5
- CAISO's Large Load stakeholder initiative is the vehicle; an issue paper came in January 2026 and a technical-requirements straw proposal in June 2026.
The CAISO’s ongoing Large Load stakeholder initiative will become the vehicle for CAISO reforms to address the Order to Show Cause. PDF p. 5
- Most tariff changes should take effect on approval; software-dependent items such as new settlement charges may take longer.
The CAISO expects that the vast majority of its tariff revisions will be able to become effective as soon as approved by the Commission. PDF p. 5
- The schedule runs a straw proposal in August, a draft final in September, governing body votes October 20 and 28, and a November 16 FERC filing.
two discrete proposals: a straw proposal in August and draft final proposal in September, before seeking Western Energy Market Governing Body and Board of Governors approval PDF p. 7
- CAISO and the PTOs keep the existing split of responsibilities and coordinate weekly.
including multiple weekly meetings among various teams of subject-matter experts for the categories of issues identified by the Commission. PDF p. 9
Contents · 3 sections
Topics in the text: Filing procedure · Cost allocation · Reliability and curtailment
Elsewhere in the record
Other parties on the same questions, in their own documents.
- Corporate buyers wanted time to test the California proposal Corporate Energy Buyers Association
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
EL26-71-000 MOTION FOR ABEYANCE Pursuant to Rule 212 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission, the California Independent System Operator Corporation (CAISO) respectfully submits this motion to hold the instant proceeding in abeyance for 90 days from the…Read this passage
I. Background
printed heading · Topic match: Filing procedure
The Commission emphasized that it would not grant such abeyances reflexively, that any abeyance will be limited to 90 days, and that 4 it would look with great disfavor toward requests to extend the abeyance period.4 The Commission anticipated that successful abeyance requests will include both (1)…Read this passage
II. Request for Abeyance
printed heading · Topic match: Filing procedure
The CAISO respectfully requests that the Commission hold the Section 206 proceeding initiated with the Order to Show Cause in abeyance for 90 days while the CAISO and its Participating Transmission Owners develop their respective Section 205 filings to address Commission’s preliminary findings.Read this passage
III. Conclusion
printed heading · Topic match: Filing procedure
Conclusion For the foregoing reasons, the CAISO respectfully requests that the Commission grant the CAISO’s motion for abeyance in this proceeding.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Folsom, CA this 3rd day of August, 2026. /s/ Jacqueline Meredith Jacqueline Meredith An employee of the California ISORead this passage