ISO-NE requests more time to answer the June 18 show cause order
ISO-NE and the Participating Transmission Owners Administrative Committee jointly ask FERC to hold the E-11 show cause proceeding in abeyance for 90 days from August 17, 2026 and commit to a single section 205 filing by November 16, 2026.
Asks FERC to: Hold the proceeding in abeyance for 90 days starting August 17, 2026, with a five-day comment period and a ruling by August 13, 2026.
Uses the abeyance option in the E-11 order to postpone the 60-day deadline and maps ISO-NE's planned section 205 filing onto the order's five reform categories.
E-11 ISO-NE: Show cause or propose tariff changes in 60 days (p. 5) E-11 ISO-NE: Application / study process (P 5, p. 25) E-11 ISO-NE: Alternative transmission technologies (P 75, p. 75) E-11 ISO-NE: Cost-recovery agreement (P 6, p. 6)
Key points
- The movants commit to file by November 16, 2026.
ISO-NE and the PTOs will submit the FPA Section 205 filing to the Commission on or before November 16, 2026. PDF p. 2
- They ask for a shortened comment period and expedited ruling because the response is due August 17.
respectfully request that the Commission shorten the comment period for this motion to five days and grant expedited treatment PDF p. 2
- They say more time is needed to develop proposals and present them for stakeholder review.
additional time is needed to develop those proposals and present them for stakeholder review. PDF p. 4
- The filing will cover all five reform categories: study processes, cost transparency, co-location rules, flexible load service and generation studies.
efficient study processes, cost transparency, co-location rules, flexible load service, and generation studies PDF p. 5
- Study reform will include a large load definition with a size and interconnection voltage threshold, and evaluation of alternative transmission technologies.
This definition will be based on the characteristics of ISO-NE’s transmission system and will include load size and an interconnection voltage threshold. PDF p. 5
Contents · 6 sections
Topics in the text: Filing procedure · Connecting load and generation · Cost allocation
Elsewhere in the record
Other parties on the same questions, in their own documents.
- New England states back time for regional deliberation New England States Committee on Electricity
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
The abeyance will allow ISO-NE and the PTOs to work through the stakeholder process to develop and refine a FPA Section 205 filing that will address the issues raised in the Show Cause Order.Read this passage
I. BACKGROUND
printed heading · Topic match: Filing procedure
In the Show Cause Order, the Commission directed ISO-NE and the PTOs, within 60 days of the order, to either: (1) show cause as to why the Tariff remains just and reasonable and not unduly discriminatory or preferential without provisions addressing: (a) the application process, study procedures,…Read this passage
II. REQUEST FOR ABEYANCE OF ALL ASPECTS OF THE SHOW CAUSE
printed heading · Topic match: Filing procedure
REQUEST FOR ABEYANCE OF ALL ASPECTS OF THE SHOW CAUSE ORDER PROCEEDINGRead this passage
A. Content of Future FPA Section 205 Filing
printed heading · Topic match: Connecting load and generation
Additional Content of FPA Section 205 Filing Related to Resource Adequacy In order to address the Commission’s concerns related to resource adequacy, as explained in ISO-NE’s Informational Filing submitted in this docket on July 20, 2026,12 ISO-NE anticipates including statements in the FPA Section…Read this passage
B. Timing for Filing of FPA Section 205 Filing
printed heading · Topic match: Filing procedure
Timing for Filing of FPA Section 205 Filing If granted, the 90-day abeyance period would end on November 15, 2026, which is a Sunday.Read this passage
III. REQUEST FOR SHORTENED COMMENT PERIOD AND EXPEDITED
printed heading · Topic match: Filing procedure
Without expedited Commission action, ISO-NE and the PTOs will be required to spend critical time and resources preparing a response to the Show Cause Order that may be unnecessary, as opposed to further advancing the FPA Section 205 proposal discussed herein. 14 The Commission directed that…Read this passage
IV. CONCLUSION
printed heading · Topic match: Filing procedure
CONCLUSION For the foregoing reasons, ISO-NE and the PTO-AC respectfully request that the Commission grant their motion to hold the instant Section 206 proceeding in abeyance for 90 days.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Holyoke, Massachusetts this 3rd day of August 2026. /s/ Julie Horgan Julie Horgan eTariff Coordinator ISO New England Inc.Read this passage