Order dismissing Eolian's request for rehearing and clarification of the June 18, 2026 NYISO show-cause order
FERC dismisses Eolian's request for rehearing or clarification of the June 18 NYISO show cause order, because that order made only preliminary findings and is not a final order, and declines to clarify while the proceeding is in abeyance.
Treats the E-12 NYISO order as non-final and dismisses a rehearing request aimed at its proximate-generation directive, leaving clarification until after the abeyance ends November 16, 2026.
E-12 NYISO: Show cause or propose tariff changes in 60 days (p. 5) E-12 NYISO: Proximate-generation service (P 121, p. 72)
Key points
- Eolian sought a ruling that proximate generation can get permanent load-limited generator interconnection service.
electrically proximate generation may access permanent load-limited generator interconnection service where it is equally capable of enabling the large load to limit its withdrawals from the transmission system Source text
- FERC says the show cause order was not final, so rehearing is unavailable.
The Commission determined only that the Tariff appears to be unjust, unreasonable, and unduly discriminatory or preferential and instituted an FPA section 206 show cause proceeding to reach a final determination on this issue. Source text
- FERC dismisses the clarification request and will not issue guidance during abeyance.
We do not intend to provide clarification or guidance with respect to the Show Cause Order while the show cause proceeding is held in abeyance. Source text
- FERC encourages NYISO, the transmission owners and stakeholders to continue developing section 205 proposals.
We encourage NYISO, the Transmission Owners, and stakeholders to continue with the development of one or more FPA section 205 proposals. Source text
Topics in the text: Filing procedure · Connecting load and generation · Cost allocation
What the document says
Unpaginated filing
FERC dismisses the rehearing requests because a show-cause order is not a final order.
The Commission determined only that the Tariff appears to be unjust, unreasonable, and unduly discriminatory or preferential and instituted an FPA section 206 show cause proceeding to reach a final determination on this issue. Source text
Unpaginated filing
FERC will not clarify the show-cause orders while the cases sit in abeyance.
We do not intend to provide clarification or guidance with respect to the Show Cause Order while the show cause proceeding is held in abeyance. Source text
Unpaginated filing
Eolian sought permanent load-limited interconnection for front-of-meter generation in five of six proceedings.
Eolian requests clarification or, in the alternative, rehearing to provide that electrically proximate generation may access permanent load-limited generator interconnection service Source text
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
Show Cause Order In the Show Cause Order, the Commission found that NYISO’s existing Tariff appears to be unjust, unreasonable, or unduly discriminatory or preferential because it lacks certain provisions related to large loads and co-located loads and instituted a show cause proceeding pursuant to…Read this passage
Discussion
printed heading · Topic match: Filing procedure
Discussion Rule 713(b) of the Commission’s Rules of Practice and Procedure permits requests for rehearing “of any final decision or other final order in a proceeding.”[fn:19] A final order imposes an obligation, denies a right, or fixes some legal relationship as a consummation of the…Read this passage
Footnotes
Word notes · Topic match: Filing procedure
Operator, Inc., 196 FERC ¶ 61,130, at PP 9-10 (2026) (Abeyance Order). [fn:13] Id.Read this passage