Order dismissing Eolian's request for rehearing and clarification of the June 18, 2026 CAISO show-cause order
FERC dismisses Eolian's request for rehearing or clarification of the CAISO show cause order. It finds the show cause order is not a final order, and declines to give guidance while the proceeding is in abeyance until November 16, 2026.
Disposes of a rehearing request against the E-10 CAISO show cause order and confirms the August 14 abeyance, leaving responses due November 16, 2026.
E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5)
Key points
- Eolian asked that electrically proximate generation be allowed permanent load-limited generator interconnection service.
electrically proximate generation may access permanent load-limited generator interconnection service where it is equally capable of enabling the large load to limit its withdrawals Source text
- Eolian also asked that CAISO be required to show its reforms open a pathway for significant generating capacity to take load-limited interconnection.
must be paired with an obligation for CAISO to show that the reforms will enable a pathway for significant generating capacity to provide load-limited interconnection. Source text
- FERC says the show cause order made no final determination, only a preliminary finding that the tariffs appear unjust and unreasonable.
The Commission determined only that the tariffs appear to be unjust, unreasonable, and unduly discriminatory or preferential and instituted an FPA section 206 show cause proceeding Source text
- FERC dismisses the clarification request and gives no guidance during the abeyance.
We do not intend to provide clarification or guidance with respect to the Show Cause Order while the show cause proceeding is held in abeyance. Source text
- FERC restates that responses are due November 16 and answers December 16, 2026.
responses to the Show Cause Order will be due on November 16, 2026, and answers to responses will be due on December 16, 2026. Source text
Topics in the text: Filing procedure · Connecting load and generation · Cost allocation
What the document says
Unpaginated filing
FERC dismisses the rehearing requests because a show-cause order is not a final order.
The Commission determined only that the tariffs appear to be unjust, unreasonable, and unduly discriminatory or preferential and instituted an FPA section 206 show cause proceeding to reach a final determination on this issue. Source text
Unpaginated filing
FERC will not clarify the show-cause orders while the cases sit in abeyance.
We do not intend to provide clarification or guidance with respect to the Show Cause Order while the show cause proceeding is held in abeyance. Source text
Unpaginated filing
Eolian sought permanent load-limited interconnection for front-of-meter generation in five of six proceedings.
Eolian requests clarification or, in the alternative, rehearing to provide that electrically proximate generation may access permanent load-limited generator interconnection service Source text
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
Show Cause Order In the Show Cause Order, the Commission found that CAISO’s existing Tariff and/or the TO Tariffs appear to be unjust, unreasonable, or unduly discriminatory or preferential because they lack certain provisions related to large loads and co-located loads and instituted a show cause…Read this passage
Discussion
printed heading · Topic match: Filing procedure
Discussion Rule 713(b) of the Commission’s Rules of Practice and Procedure permits requests for rehearing “of any final decision or other final order in a proceeding.”[fn:18] A final order imposes an obligation, denies a right, or fixes some legal relationship as a consummation of the…Read this passage
Footnotes
Word notes · Topic match: Filing procedure
Operator Corp., 195 FERC ¶ 61,214, at PP 3, 31 (2026) (Show Cause Order); order granting rescission and abeyance requests, Cal.Read this passage