Order dismissing Eolian's request for rehearing and clarification of the June 18, 2026 ISO-NE show-cause order
FERC dismisses Eolian's request for clarification or rehearing of the E-11 ISO-NE show cause order because the order made only preliminary findings and is not final, and says it will not clarify the order while the proceeding is in abeyance.
Disposes of rehearing of the E-11 order by treating it as non-final and confirms the abeyance schedule; Eolian's request concerned the proximate-generation and flexible-load directives.
E-11 ISO-NE: Show cause or propose tariff changes in 60 days (p. 5)
Key points
- Eolian asked that electrically proximate generation be able to get permanent load-limited generator interconnection service.
electrically proximate generation may access permanent load-limited generator interconnection service where it is equally capable of enabling the large load to limit its withdrawals Source text
- FERC says the Show Cause Order made no final determination that the ISO-NE Tariff is unjust.
The Commission did not make any final decision or determination in the Show Cause Order on whether the ISO-NE Tariff is unjust, unreasonable, or unduly discriminatory or preferential. Source text
- FERC dismisses the rehearing request as directed at a non-final action.
We therefore dismiss the request for rehearing, which concerns a Commission action that is not final and that will be succeeded by further Commission action. Source text
- FERC will not provide guidance on the Show Cause Order during abeyance.
We do not intend to provide clarification or guidance with respect to the Show Cause Order while the show cause proceeding is held in abeyance. Source text
- The order restates the abeyance dates: responses November 16, 2026 and answers December 16, 2026.
responses to the Show Cause Order will be due on November 16, 2026, and answers to responses will be due on December 16, 2026. Source text
Topics in the text: Filing procedure · Connecting load and generation · Cost allocation
What the document says
Unpaginated filing
FERC dismisses the rehearing requests because a show-cause order is not a final order.
We therefore dismiss the request for rehearing, which concerns a Commission action that is not final and that will be succeeded by further Commission action. Source text
Unpaginated filing
FERC will not clarify the show-cause orders while the cases sit in abeyance.
We do not intend to provide clarification or guidance with respect to the Show Cause Order while the show cause proceeding is held in abeyance. Source text
Unpaginated filing
Eolian sought permanent load-limited interconnection for front-of-meter generation in five of six proceedings.
Eolian requests clarification or, in the alternative, rehearing to provide that electrically proximate generation may access permanent load-limited generator interconnection service Source text
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
Show Cause Order In the Show Cause Order, the Commission found that ISO-NE’s existing Tariff appears to be unjust, unreasonable, or unduly discriminatory or preferential because it lacks certain provisions related to large loads and co-located loads and instituted a show cause proceeding pursuant…Read this passage
Discussion
printed heading · Topic match: Filing procedure
Discussion Rule 713(b) of the Commission’s Rules of Practice and Procedure permits requests for rehearing “of any final decision or other final order in a proceeding.”[fn:18] A final order imposes an obligation, denies a right, or fixes some legal relationship as a consummation of the…Read this passage
Footnotes
Word notes · Topic match: Filing procedure
Inc., 196 FERC ¶ 61,132, at PP 7-8 (2026) (Abeyance Order). [fn:12] Id.Read this passage