UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System Operator, Inc. ) Docket No. ER27-25-000
LIMITED PROTEST OF BLOOM ENERGY CORPORATION
Pursuant to Rule 211 of the Commission's Rules of Practice and Procedure, 18 C.F.R. § 385.211, Bloom Energy Corporation ("Bloom") submits this limited protest of the October 2, 2026 filing by the Midcontinent Independent System Operator, Inc. ("MISO") to establish the Large Load Addition Resource Study ("LARS").
Bloom supports LARS and urges the Commission to accept it by MISO's requested December 2, 2026 effective date. LARS solves a real problem: today, load and generation studies run on different timelines, so each must wait on the other. By studying a large load and its paired generation in parallel, LARS removes that delay. It does so in a technology-neutral way, tying generation to load through a 150% cap. And it protects the Definitive Planning Phase (“DPP”) queue from speculative entry through serial ten-pair cycles, deposits, milestone payment, and 15- year pairing requirement. Bloom protests one element only: the 200 MW minimum load size.
I. Limited Protest
MISO bears the burden under FPA section 205 to show that each element of its proposal is just and reasonable. Its only evidence of transmission system impact does not support a 200 MW threshold. MISO initially proposed 250 MW, relying on Expedited Project Review (“EPR”) results showing that loads of 250 MW and above created "meaningful grid impacts," with upgrades "increasingly likely between 300–500 MW."1 MISO then lowered the threshold to 200 MW, not on the basis of new analysis, but in response to stakeholder feedback that many projects
1 Transmittal Letter at 3.
PDF page 2
2
in the 200–250 MW range "can have significant system impacts."2 MISO presents no EPR results or other grid impact study for 200 MW, and none for loads below it. The 200 MW threshold therefore rests on stakeholder assertion, not on transmission system data. The point is not that MISO should have kept 250 MW; it is that MISO set aside the only impact data it offered without replacing it. Nothing in the record shows that a 75 MW or 150 MW load paired with new generation presents a materially different study problem than a 200 MW load. The 200 MW threshold departs from the Commission's framework and MISO's own
definition of Large Load. The Show Cause Order identified a reasonable large load definition as a single-site commercial or industrial customer with peak load of 50 MW or greater.3 MISO's pending Interconnection Reliability Requirement filing adopts this 50 MW threshold.4 MISO concedes the mismatch, noting that "not all 'Large Loads' will be eligible" for LARS,5 but offers no explanation for it. The Commission's concern with generation serving electrically proximate large loads is not limited to loads of 200 MW or more.62 Id. at 51; Prepared Direct Testimony of Christina Drake, Tab C, at 24:9-15 (“Drake Test.”).3 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 at P 58 (2026) (“Show Cause Order”).4 Midcontinent Indep. System Operator, Inc., Docket No. ER26-3650-000 at Att. A (filed Aug. 28, 2026) (Large Load is defined as: “Load with Demand of 50 MW or more associated with any facility or aggregation of facilities located at a single substation behind one or more Point(s) of Withdrawal from the Transmission System that is owned, operated, or controlled by: (a) a single entity, or (b) a group of entities that will coordinate with respect to the profile of the Load….”).5 Transmittal Letter at 1 n.4.6 Show Cause Order at PP 112–117 (“For purposes of this order, it appears to be reasonable to use the term ‘electrically proximate large load’ to mean a large load, as defined in this order [50 MW and connected at 69 kV and above], that is sufficiently electrically close to the interconnection customer’s requested point of interconnection, such that the impact on the transmission system of the combination of the generating facility and the load, with the exception of the transmission facilities between the two, will be effectively the same as if they were located at the same substation.” Id. at P 112 (noting that the Commission will consider revisions to this definition that ensure it is tailored to MISO’s transmission system)).
PDF page 3
3
Section 205 prohibits any public utility from maintaining “any unreasonable difference in rates, charges, service, facilities, or in any other respect” between classes of service.7 A paired load and generation that interconnect to the Transmission System are similarly situated whether the load is 75 MW or 200 MW. Each takes transmission service, each faces the study timing mismatch LARS cures, and each presents the same coordination problem. MISO must show that paired loads and generation below 200 MW affect the Transmission System differently. It has not done so.
MISO responds that the 200 MW minimum preserves LARS’s “focus on large, impactful load additions.”8 But MISO has already determined that loads of 50 MW or more are impactful enough to warrant its large load reliability requirements.9 MISO cannot treat those loads as large and impactful for reliability purposes yet not for the study process designed to integrate them. Nor does the load size bear on the problem LARS solves – the timing mismatch between MISO’s load study and its generator interconnection queue arises for any paired load awaiting a generator’s GIA. And the ten-pair cap, not a size threshold, already preserves the focus of each study cycle.10
MISO's supporting testimony also relies on stakeholder feedback that data center loads "come in 200 MW blocks,"11 but cites no data. Industry sources indicate that data center capacity is typically built and energized in smaller increments.12 Smaller loads also fall within the
7 16 U.S.C. § 824d(b).8 Transmittal Letter at 51.9 See supra note 4.10 See Transmittal Letter at 9.11 Drake Test. at 24:11-13.12 See, e.g., Elevate Energy Consulting & GridLab, Practical Guidance and Considerations for Large Load Interconnections at 20 and Fig. 2.3 (May 2025) (illustrating a 50 MW data center block within a 200 MW facility served through four points of connection), available at https://gridlab.org/portfolio- item/practical-guidance-and-considerations-for-large-load-interconnections/; JLL, 2026 Global Data
PDF page 4
4
industrial category that MISO expressly sought to reach by lowering the threshold.13 Additionally, other RTOs apply materially lower thresholds; Southwest Power Pool's High Impact Large Load Generation Assessment framework, for example, applies to loads of greater than 10 MW.14
The proper screen for LARS is interconnection of Large Load to the Transmission System, not load size. MISO’s own Large Load definition draws that exact line: it applies to loads of 50 MW or more that connect to the Transmission System. That definition implements the Commission’s direction to tailor the large load definition to MISO’s system.15 LARS itself requires that the paired load’s Point of Withdrawal connect to the Transmission System. The 200 MW minimum is the only thing separating the two, and MISO offers no transmission-based reason for departing from the Show Cause Order. LARS should therefore apply to loads of 50 MW or more that connect to the Transmission System. A 75 MW load connected to the 115-161 kV network that must await a paired generator's GIA faces the same delay as a 200 MW load. Nor is a 200 MW minimum needed to protect the process. MISO's other safeguards already screen out speculative and de minimis requests: the $250,000 non-refundable deposit, the milestone payment, full site control, and the bar on aggregating multiple loads.16 And the pairing agreement, the same LRZ requirement, and the 15-year commitment – not load size – are what keep LARS from becoming a bypass of the competitive DPP queue. A 200 MW minimum load size adds no protection beyond what these safeguards already provide.
Center Outlook (Jan. 2026) (reporting an average global build time of 18 months for a new 50 MW data center), available at https://www.jll.com/en-us/insights/market-outlook/data-center-outlook.
13 Transmittal Letter at 3, 51.14 See Sw. Power Pool, Inc., 194 FERC ¶ 61,031 (2026).15 Show Cause Order at P 58.16 Transmittal Letter at 9, 11, 25; Drake Test. at 24–25.
PDF page 5
5
Finally, if the Commission agrees that the minimum load size should be lowered, it should direct a conforming change to Section 3.12.2, which separately requires at least 200 MW of Network Resource Interconnection Service at each Point of Interconnection. That generation- side minimum derives from the load threshold and should scale with it, so that a qualifying load can be served by appropriately sized generation.
II. Conclusion
Bloom does not ask the Commission to delay LARS. Bloom respectfully requests that the Commission (1) accept LARS effective December 2, 2026; and (2) direct MISO, in a compliance filing within 60 days, either to (a) align LARS eligibility with MISO's Large Load definition, with a corresponding generation-side minimum, or (b) provide record evidence that loads below 200 MW connected to the Transmission System do not warrant coordinated study. Respectfully submitted,
/s/ Joel D. Newton
Joel D. Newton
VP, Regulatory Law
Bloom Energy Corporation
4353 North First Street
San Jose, CA 95134
joel.newton@bloomenergy.com
(202) 329-1119
October 23, 2026
Certificate of Service
I hereby certify that I have served the foregoing document on all persons listed on the Commission’s official service list compiled by the Secretary in this proceeding. Dated at Falls Church, VA this 23rd day of October, 2026.
/s/ Joel D. Newton