EL25-49-000 · 2025-03-21 · Chair and Immediate Staff (FERC)

Chairman Mark C. Christie's response to the Commonwealth of Virginia Governor Glenn Youngkin's 10/31/2024 letter re the Commissioner-Led Technical…

PDF page 1

888 First Street | Washington, DC 20426
March 18, 2025
The Honorable Glenn Youngkin
Governor
Commonwealth of Virginia
Patrick Henry Building
1111 East Broad
Richmond, VA 23219

 Dear Governor Youngkin:

Thank you for your October 31, 2024, letter regarding the Federal Energy Regulatory Commission’s (Commission) technical conference on large loads co- located at generating facilities in Docket No. AD24-11-000.  Your insights are essential to the Commission’s consideration of this matter.

In your letter, you highlighted the importance of data center development to the economy of the Commonwealth of Virginia.  You also requested that the Commission continue to recognize the important role that co-located load arrangements could play in Virginia’s electric future, noting that the rapid load growth Virginia is experiencing requires innovative ways to maximize the attraction of new large load sources while minimizing bill impacts to traditional ratepayers, such as co- locating load with new generation behind the meter.

Because the issues referenced in your letter are relevant to contested pending proceedings, I cannot discuss the merits of these issues at this time.  I agree that co- located load arrangements will play an important role in the nation’s electric future. As I emphasized in my statement issued February 21, 2025, after the Commission unanimously voted to launch a review of issues associated with the co-location of large loads such as AI-enabled data centers at generating facilities in PJM, including whether the PJM tariff needs to establish rules to create clarity while ensuring grid reliability and fair costs to customers, we want to act quickly on this issue.  While I cannot announce a specific date for final action, it is our intent to conduct and complete this important proceeding expeditiously, so we can provide clarity and certainty to all, from consumers to investors to load-serving utilities and independent generators.

You have my commitment that we will continue to actively work on this issue. I take seriously our obligation to ensure that any action the Commission takes is in the

PDF page 2

888 First Street | Washington, DC 20426
public interest.  I assure you that Commission decisions are based upon a careful review of the record.

Your letter and this reply will be placed in the public file in Docket No. AD24- 11, ER24-2172, and EL25-49.  If I can be of further assistance in this or any other Commission matter, please do not hesitate to contact me.

Sincerely,

Mark C. Christie
Chairman