EL25-49-000 · 2025-04-23 · Antora Energy LLC

Motion to Intervene Out of Time and Comments of Antora Energy LLC in Response to FERC’s Co-location Order

PDF page 1

UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company

Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC

Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative

PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company

Trans-Allegheny Interstate Line Company Transource West Virginia, LLC

UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company

AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc.

AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc. Appalachian Power Company

Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
Docket Nos. EL25-49-000

PDF page 2

City of Cleveland, Department of Public Utilities, Division
of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.

AD24-11-000

EL25-20-000
(Consolidated)

Motion to Intervene Out of Time and Comments of Antora Energy LLC In Response to the Commission’s Co-location Order

Pursuant to the Federal Energy Regulatory Commission’s (“FERC” or “Commission” order instituting a Federal Power Act (“FPA”) section 206 proceeding concerning PJM Interconnection, L.L.C.’s (“PJM”) rules regarding large loads co-located at generating facilities in the PJM footprint,1 as well as Rule 213 of the Commission’s Rules of Practice and Procedure,2 Antora Energy LLC (“Antora”) hereby provides comments on the order issued by the Commission in the above-captioned docket and PJM’s response thereto.3  Antora urges the Commission to find that the existing Tariff is not just and reasonable, and to require a replacement rate that allows for the flexible nature of Antora’s thermal storage load to be

3 Answer of PJM Interconnection (Mar. 24, 2025) (“PJM Answer”).
2 18 C.F.R. § 385.213.
1 PJM Interconnection, L.L.C., 190 FERC   61,115 (2025) (“Co-location Order”). 2

PDF page 3

appropriately and efficiently accounted for in its study processes, procedures, and transmission rates.4  The Commission should direct PJM to build from Options 4 and 7 set forth in the PJM Answer to create such a rate,5 while not precluding the development of additional rate designs and interconnection processes in the future or in other regions, as may be necessary to integrate flexible loads such as those of Antora’s thermal energy storage charging.

Antora is a U.S. manufacturer of thermal batteries, which are domestically built in San Jose, California, and developer of thermal storage projects for industrial facilities in the U.S. and abroad.  Antora is at the forefront of an industry that holds tremendous potential to lower the cost of industrial processes.  Antora can help support American energy dominance by providing a market for off-peak, low-cost power during periods of low demand.  But as explained herein, appropriate regulation that facilitates interconnection and transmission service capable of accounting for the unique low load factor, highly flexible nature of thermal energy storage charging loads is required for this industry to thrive and to maximize its benefits while minimizing costs for the grid and its customers.  Specifically, the flexible load profile of thermal energy storage facilities allows them to contribute to grid reliability while minimizing grid capacity costs and infrastructure costs and making greater use of existing generation and transmission infrastructure.  The Commission’s Order to Show Cause creates an important opportunity for PJM’s regulatory framework to evolve to meet the needs of Antora and other similar customers, remedying deficiencies that render the existing tariff unjust and unreasonable.

5 See PJM Answer at 13-14, 18-19 (outlining Options 4 and 7 to facilitate co-location arrangements).
4 See Co-location Order at P 87 (requesting comments addressing “(1) whether the existing tariff remains just and reasonable and not unduly discriminatory or preferential” and (2) “what changes to the Tariff should be implemented as replacement rates.”) 3

PDF page 4

I.​
Background
Antora’s thermal batteries will provide heat to industrial operations.  Initial deployments will focus on industrial process heat up to ~400C, and future deployments will include high-temperature processes such as mineral refining, cement, glass, aluminum, and steel.6  The technology uses low cost electricity to resistively super-heat carbon blocks that are capable of ultra-fast charging and absorption of heat.  The carbon blocks store the energy as heat, at temperatures over 2,000◦C, in a compact thermal battery.  The energy is discharged in the form of heat at the scale and temperature needed by large industrial operations.  Antora is also developing thermal storage products that allow the energy stored as heat to produce electricity, thereby serving as electric energy storage devices.

Like electro-chemical batteries, a significant portion of Antora’s thermal battery value comes from flexibility.  The battery is charged during periods of high energy production and low demand, thereby helping reduce curtailment of renewable resources and allowing the thermal battery to absorb low value/negatively priced electricity.  Because thermal storage can provide 24/7 heat over a multi-day period by charging only roughly 1/3 of the time, it can fully avoid periods of high demand, high-capacity utilization and high electricity pricing.  This allows Antora’s industrial and manufacturing clients to gain the benefits of low-cost periods of excess generation without requiring the factories themselves to curtail when low cost power is not available and during periods of coincident peak transmission system use and demand.  By co-locating an Antora thermal battery with a generation resource, Antora can provide factories

6 CNN has described Antora’s technology and electricity usage. Weir, B., These hot rocks can glow brighter than the sun. They could also help spell the end of fossil fuels (Dec. 18, 2023), available at https://www.cnn.com/2023/12/16/climate/solution-hot-rocks-renewable-energy-battery/index.ht ml 4

PDF page 5

with onsite power, heat for industrial processes, and energy storage if necessary.  Co-location of highly flexible, low load factor thermal energy storage can allow better utilization of variable renewable energy resources that might otherwise be curtailed, without causing additional co-incident peak demand and without impacting the ability  of that renewable energy project to support resource adequacy goals.  Co-location can also minimize or eliminate the already low impacts on the transmission system because thermal energy storage can be operated to use only energy from a co-located energy source (and only during hours when that resource is not needed for capacity).

Antora is committed to paying its fair share of grid costs.  The pathway a resource takes to interconnect to the system, whether via a supply study process that incorporates co-located load or through an Electric Distribution Company (“EDC”) or Transmission Owner (“TO”) process for interconnecting load alone, should not itself cause disparate rate treatment independent of the characteristics of the underlying load and generation facilities.  At the same time, however, study processes should account for load shape, flexibility, and dispatchability when determining the infrastructure necessary to serve that load.  Companies like Antora should not be required to fund infrastructure or secure network resources that they do not need.  Antora can follow curtailment instructions from grid operators (including Regional Transmission Organizations (RTOs) and EDCs) if doing so facilitates studying Antora’s load in a manner that appropriately accounts for its flexibility and low load-factor.

II.​
Communications
Noah Long​
​
​
​
Jason Evans​

Antora Energy LLC​ ​
​
Antora Energy
200 West De Vargas St​
​
1244 Reamwood Ave.
Santa Fe, NM 87501​ ​
​
Sunnyvale, CA 94089
noah.long@antora.energy ​
​
jason.evans@antora.energy

5

PDF page 6

III.​
Motion to Intervene Out of Time
As the developer of facilities with large and flexible thermal battery loads that may often be co-located with generation facilities, Antora’s interests cannot be represented by any other party and its intervention is in the public interest.  Antora respectfully requests that the Commission grant this request to intervene out-of-time.  Antora accepts the record as it stands, and this intervention will not place any additional burden on any other party, nor will it disrupt or delay Commission proceedings in this matter.

IV.​
Comments
PJM’s existing tariff is unjust, unreasonable, and unduly discriminatory because it does not offer any study process or form of transmission service that properly accounts for highly flexible and low load factor loads such as Antora’s thermal energy storage.  This yields higher costs or delays for the developers of flexible load facilities and for other customers, delays the interconnection of new loads, and fails to use the full capabilities of these loads to enhance system reliability.

The Commission should order PJM to remedy these deficiencies by developing a replacement rate that builds from Options 4 and 7 set forth in PJM’s Answer.  Specifically, the Commission should direct PJM to enable Option 4 by modifying its interconnection procedures to facilitate the study of co-located loads.7  In addition, the Commission should direct PJM to build out Option 7 by developing a new non-capacity backed service offering.  However, unlike Option 7 in PJM’s filing which suggests only a transitional service product, the Commission should direct PJM to provide such service on a permanent or transitional basis, subject to the

7 As described in Section IV.B.1 below, Antora supports potential modifications to Option 4 to limit reliability risk and resource adequacy and capacity price risks for other customers, to the extent the Commission deems such modifications necessary.

6

PDF page 7

election of the transmission customer.  These tariff revisions are not mutually exclusive with the development of additional options set forth in the PJM Answer that may be beneficial, such as Option 6 to provide a faster path to studying new generation co-located with new load or Option 8 to facilitate more effective participation of Network Load as demand response.8  The Commission could integrate the new flexible service interconnection pathways with any of the other options it may direct PJM to pursue, and should make clear that its order remedying PJM’s tariff does not preclude the development of additional pathways to interconnect and serve co-located load in PJM or elsewhere.

A.​
PJM’s tariff is unjust, unreasonable and unduly discriminatory in failing to appropriately study and incorporate flexible loads

PJM outlines two sets of potential pathways for co-located load to connect to the system, but neither of them appropriately incorporates highly flexible, low load factor flexible loads. The first set of potential pathways relies on the generator interconnection procedures, with loads connecting behind a generator’s Point of Interconnection using PJM’s necessary study

8 PJM explains that Option 6 “would also be open for existing generation that could serve the energy needs of the large loads so long as the generator would still be available to PJM as a Capacity Resource.”  PJM Answer at 16.  Antora facilities could co-locate with existing generation in this manner, drawing from the co-located generation only when it is not needed for capacity purposes.  To operationalize such a process, PJM could develop a mechanism through which it can provide automated curtailment instructions to the load so that the load can avoid drawing from the generation whenever the generation is needed for resource adequacy. Modifications may be required to PJM’s capacity accreditation to ensure that credit is based on the generation’s availability to PJM when needed, rather than on its total energy output to the PJM system.  Option 8 is beneficial insofar as it may facilitate more effective demand response participation, but it does nothing to remedy the problems in PJM’s study processes that fail to account for or leverage the flexibility of load to minimize transmission infrastructure costs and rely on fewer Network Resources to serve the same amount of load. 7

PDF page 8

process.9   These pathways offer a significant efficiency advantage over studying load separately from the colocated generation, as they assess the electrical impacts of proposed new generation and load in a single interconnection process.  As the record in Docket No. AD24-11 makes clear, co-location offers a host of potential benefits, including reduced infrastructure costs.10  A single study process will better ensure that these savings are accurately captured.  It also reduces project risk for the developer where the proposed new energy supply resource and co-located load are commercially reliant on one another, as being studied in a single process allows the different project components to receive study results on the same timeline, make decisions about milestone payments, and demonstrate commercial readiness in a single forum.  But this set of pathways fails to provide an adequate pathway for flexible loads because, as PJM explains, it “does not have a tariffed study process for load.”11  The Tariff’s study procedures lack the necessary detail to inform customers such as Antora how their charging loads will be studied and confirm that the loads’ flexibility will be accounted for.  The process has high transaction costs, as it requires the development of bespoke agreements.  In a recent proceeding, the Commission rejected a non-conforming interconnection agreement providing for a load to be studied under this process where the underlying agreement presented generalized co-location issues rather than unique concerns particular to the individual customer.12

12 PJM Interconnection, L.L.C., 189 FERC   61,078 (2024), order on reh’g, 191 FERC 61,025 (2025).
11 PJM Answer at 47.  The Commission suggests that PJM’s necessary study process is not adequate to study the reliability impacts of co-located loads.  See Co-location Order at P 79.
10 See, e.g., Pre-technical Conference Comments of the Clean Energy Buyers Association, Docket No. AD24-11, at 17-19 (Oct. 25, 2024).

9 See PJM Answer at 47-50 (outlining how and when PJM conducts its necessary study process for co-located load and explaining that load studied pursuant to this path way may or may not register as Network Load). 8

PDF page 9

The second set of pathways requires load to register as Network Load.  But as PJM states, its transmission planning, operating protocols, and procedures for providing service to Network Load do not account for load shape and flexibility.  Instead, PJM “assumes that it must serve the customer’s full load during peak conditions on the system.”13  This assumption is a poor match for loads such as Antora’s, which only draw from the system roughly 1/3 of the time and never during peak conditions, and are capable of responding immediately to curtailment instructions sent by PJM or the relevant EDC.14

While PJM’s necessary study process to some extent captures the flexibility of co-located load, PJM does not capture those benefits where the load is required to register as Network Load.15  Per PJM’s response, state law may require a customer to designate load as Network

15 The Commission directly asked PJM to “explain whether PJM’s necessary study process allows a co-location arrangement to demonstrate its capability to flexibly adjust its withdrawals from or injections to the transmission system” such as “by curtailing on-site load.” Co-location Order at P 88.d.ii.

14 While PJM offers demand response and price responsive demand programs that flexible loads may take advantage of in order to capture the value of avoiding electric energy consumption during peak demand, these programs do not reflect load flexibility in PJM’s transmission planning and operating procedures, which currently do not have a mechanism to allow load to respond to transmission system constraints in addition to generation constraints.
13 PJM Answer at 39 n. 64.  As PJM explains, in “any configuration where the co-located load is Network Load” the relevant EDC would conduct “load integration studies . . . in addition to necessary studies” performed in PJM’s generation interconnection process.  Id. at 8.  But the assumptions that PJM uses for Network Load in its own transmission planning and operations are highly relevant for those state-jurisdictional processes, as they define the scope of transmission service that will be studied in those processes for non Native Load Customers, and Network Service is designed to be comparable to the transmission service that Transmission Owners provide to Native Load Customers.  See id. at 39 n. 61 (highlighting the principle of comparable service). 9

PDF page 10

Load.16  Further, the necessary study process applies only in the limited circumstance where “the load is assumed to never take power from the grid.”17

Further, as discussed above, PJM’s tariff lacks general language as to how this necessary study process will be applied to loads.  PJM notes that “it is possible that the Generation Owner could propose a special protection scheme or Remedial Action Scheme (‘RAS’) to reduce the load under certain conditions (where, for example, the generating unit comes offline),” but PJM does not have any standard language to provide for any such arrangement and appears to contemplate load modulation as something that would occur only in an emergency rather than as a matter of course, as would occur with Antora’s thermal battery charging.  While PJM’s existing Behind the Meter (“BTM”) Generation rules provide one limited pathway to interconnection that partially accounts for load flexibility insofar as PJM allows load to be netted with generation when calculating Network Load,18 this structure is primarily concerned with rate treatment and does not provide for planning, forecasting, and operations procedures that fully leverage the flexibility of the underlying load to contribute to grid reliability and use less network infrastructure.

PJM’s failure to offer a service that matches the needs of flexible loads such as those of Antora facilities or other co-located facilities with flexible operations capabilities is unjust and unreasonable and unduly discriminatory19 because it may delay or prevent the interconnection of

19 See Calpine Corp. et al. v. PJM Interconnection, L.L.C., 163 FERC   61,236, at P 68 n. 112 (2018) (“Typically, undue discrimination cases involve a seller charging a different rate to similarly-situated customers; but undue discrimination can also occur when a seller charges the
18 Id. at 35.
17 PJM Answer at 51.  Under this study process, “the generator’s Capacity Interconnection Rights” are “reduced by the expected peak MW utilization of the co-located load.”  Id.
16 PJM Answer at 14.

10

PDF page 11

these loads,20 trigger the construction of infrastructure that is not needed to serve them, and fail to incentivize customers to provide operational flexibility that could benefit the system. To the extent PJM requires all loads to register as Network Load and assumes it must serve the customer’s full peak load during peak conditions even if the load is flexible and could be curtailed at PJM’s direction, this is likely to overcharge both the interconnecting load customer, and other customers on the system for transmission service or interconnecting facilities.  It overcharges the interconnecting loads because, as PJM explains, “[t]he costs of new facilities required to interconnect the new Network Load are charged to the Network Customer.”21  Where a customer could have instead taken curtailable transmission service that allows PJM and/or the EDC to curtail its load if that service were offered, the failure to provide a service option that incorporates load flexibility will directly lead to costs for the interconnecting customer that do not appropriately reflect its flexibility and resulting ability to avoid using high value energy or grid capacity.22  And it will lead to increased costs for other customers because PJM’s transmission and interconnection study processes and operating protocols will apply a lack of headroom in its system based on its assumed need to serve the entirety of the Network

22 Depending on how PJM interprets its Tariff, this requirement may also require a flexible load to secure more Network Resources than would be necessary to provide service to the load if its flexibility were properly accounted for.  In the context of developing a project in another RTO, the RTO has indicated that the LSE serving Antora must secure an amount of network resources to match the non-coincident peak load of the proposed Antora facility, a requirement that would substantially increase the project’s costs.
21 PJM Answer at 40.
20 While interconnection processes for retail customers are generally administered by EDCs pursuant to state jurisdictional processes, an EDC taking Network Integration Transmission Service from PJM must account for the terms of that service when designing retail rates, services, and interconnection processes.

same rate to differently-situated customers.”).

11

PDF page 12

Load at any given moment, despite the fact that the customer is capable of dispatching down pursuant to PJM and/or EDC instructions.23  This, in turn, will trigger identification of infrastructure upgrades that could have been avoided, with such costs either allocated pursuant to PJM’s applicable transmission planning process or else attributed to other Network Customers or interconnecting supply resources, depending on which study process identifies a need for infrastructure based on the assumption that the load may need to be served at any moment even though it is flexible and dispatchable.

By failing to offer a transmission service suited to flexible load, PJM also provides a disincentive to load flexibility that will yield higher capacity supply costs.  PJM explains that whether or not Network Load is flexible, “PJM will include the customer’s full load in the RPM for purposes of procuring adequate capacity to serve the load.”24  As PJM explains, “where conditions are tight, any additional load on the system requires either the addition of supply resources to serve that load reliably, or flexibility on the part of the load to curtail its consumption from the transmission system when necessary to maintain reliability.”25  To the extent that rates do not facilitate “supply and operational flexibility,” the system will require more resources to provide the same level of reliability in service to customers, rendering rates unjust and unreasonable.”26  If properly incorporated into PJM’s operations, fully flexible load such as that of Antora’s facilities need not impose any new resource adequacy burden.  Antora supports a rate mechanism and operations protocols that would allow PJM to direct Antora to

26 Co-location Order at P 85.
25 Id. at 8.
24 Id. at 39 n. 64.
23 PJM explains that it “will include the full load in the Load Forecast for purposes of PJM’s transmission planning with RTEP.”  PJM Answer at 39 n. 64. 12

PDF page 13

fully curtail its load whenever called upon to do so by PJM and ensure that the Antora load does not draw from the system when the grid is stressed either due to insufficient generation supply or due to a transmission system constraint.

The costs of this unnecessary infrastructure and capacity are substantial.  A recent study by researchers at the Nicholas Institute for Energy, Environment & Sustainability at Duke University suggests that nearly 100 GW of additional load could be served using existing infrastructure if the load were flexible.27

B.​
The Commission can order a just and reasonable and not unduly
discriminatory replacement rate that builds from Options 4 and 7 set forth
by PJM
To address the deficiencies that render PJM’s existing tariff unjust, unreasonable, and unduly discriminatory, the Commission should direct PJM to revise its tariff so as to enable Option 4, and to provide for a non-capacity backed transmission service like that described in Option 7 but available on a permanent basis.  These tariff revisions would facilitate the integration of highly flexible, low load factor loads co-located with supply resources.  These tariff revisions are not mutually exclusive with other tariff mechanisms to support co-location, so the Commission should make clear that they do not preclude the development and submission of other options set forth in PJM’s filing, or other potential tariff designs not included therein. 1.​ The Commission should require PJM to revise its tariff so as to facilitate interconnection pursuant to PJM’s Option 4

The Commission should require PJM to enable its proposed Option 4, as this is the only
27 Tyler Norris et al., Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible Loads in US Power Systems (2025), available at https://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-growth.pdf. While the study focused on headroom to serve peak demand and did not account for certain technical constraints of power plants or transmission constraints, it nevertheless suggests very significant potential system benefits of integrating flexible load.  Id. at 3, 23. 13

PDF page 14

pathway that allows for the fully coordinated study of co-located generation and load.  As PJM explains, tariff modifications are required to implement Option 4 in the wake of the Commission’s decision in Docket No. ER24-2172.28  Further, PJM indicates that were it to pursue this option, tariff changes would be appropriate to provide for the collection of ancillary services charges used by the co-located facilities.29

While PJM identifies certain aspects of Option 4 that cause PJM to not prefer this option, these risks would be mitigated for low-load factor loads such as Antora’s.  Antora would also support modifications to this option to ensure that its use does not compromise resource adequacy or increase capacity costs for other customers.

The principal risk cited by PJM with regard to Option 4 is the risk associated with system protection facilities needed to prevent delivery of the energy from the grid should the generator go offline.”30  This risk is inherently lower for Antora’s thermal battery facilities, as its low load

30 Id. at 14.  PJM also indicates that it prefers “Network Load” status because it allows for “[m]ore comprehensive and holistic system planning based on Network Load status” and provides for “[e]nhanced ability to manage load curtailment priority in emergency conditions.” Id. at 39.  But as discussed above, PJM’s system planning processes for Network Load do not appropriately capture flexible loads.  Antora supports integrating co-located facility loads into N-1 operating procedures, but including fully flexible loads in load forecasts and transmission plans will overbuild the system.  With regard to load shedding and curtailment, Antora would support implementing Option 4 in a manner that ensures the required system protection schemes curtail the co-located load in advance the curtailment of other system loads.  PJM also cites a potential drawback in not registering co-located load as Network Load of losing “access to potential Demand Response capabilities of large co-located loads.”  Id. at 39.  However, analogous system benefits could be captured through the design of the relevant protection scheme and rules regarding the capacity accreditation of the co-located generation resource. FERC should require PJM to design these mechanisms such that the load can be curtailed in response to PJM’s direction, thereby leaving the co-located generation available to fully contribute to resource adequacy.

29 Id. at 13.  The design of ancillary services charges should reflect the services the co-located facility needs.  Inverter-based resources, for example, will require a different mix of services than synchronous generating facilities.

28 PJM Answer at 14.

14

PDF page 15

factor facilities only charge at times when energy is abundant and low cost.  When the grid is stressed, the facilities will not draw from the grid or the co-located generation, allowing the co-located generation to support the grid’s needs.  Antora would support limits on the use of Option 4, restricting its use only to co-located loads that exhibit these characteristics and thereby limiting operational risk.  And while PJM argues that Option 4 “carries operational risk in that there is a dependence on the protection system to support reliability,”31 no equipment is immune from failure.  PJM can ensure that the use of these protection schemes does not increase overall reliability risk to the system by implementing operational standards for such protection schemes, and by incorporating them into its N-1 operating protocols.  With these measures in place, a failure of system protection equipment would be equivalent to an outage of a generation or transmission element on PJM’s system, which the system is designed to reliably overcome. Further, while the use of Option 4 potentially raises concerns insofar as it may provide a faster pathway to interconnecting new loads to existing generation facilities, thereby impacting resource adequacy and capacity costs, these concerns do not apply to Antora’s thermal battery loads given their load profile.  Specifically, Antora facilities are designed to draw electric energy from the system for charging only when it is abundant and low cost, allowing the co-located generation facility to continue to support resource adequacy for the PJM system.  So long as accreditation and co-location rules allow for these resources to continue to contribute to system resource adequacy, the addition of low-load factor, highly flexible loads such as Antora’s to existing facilities will not impact capacity prices or reduce resource adequacy.  Protection schemes could ensure not only that co-located loads never draw power from the grid, but also could ensure that the loads do not draw energy during times the PJM system requires it for 31 Id. at 14.

15

PDF page 16

resource adequacy, thereby preserving the capacity value of the co-located resource for the system.  Antora would support rules that require the use of such protection schemes, and urges the Commission to require modification to capacity accreditation rules as necessary to appropriately reflect their use.

2.​ The Commission should require PJM to implement tariff changes that enable customers to take non-capacity backed transmission service on a permanent

basis
The Commission should also require PJM to develop a new transmission service offering like that described in Option 7, but offered on a permanent basis.  PJM’s proposed Option 7 would provide for “a new non-capacity backed service that could be curtailed in advance of emergency procedures.”32  As PJM explains, this service “would allow a large load to integrate as Network Load at a potentially faster pace than under existing load integration frameworks.”33 “[T]he load would avoid capacity costs . . . in return for its willingness to curtail load . . . in those situations where, by way of example, PJM has identified conditions that may threaten the integrity or reliability of the PJM Region or the regional power system.”34

PJM suggests offering this service to customers “for a transitional period until any resource adequacy supply/demand imbalances associated with the large load addition could be addressed and the load could assume full Network Load status with all of its attendant benefits.”35  But it also explains that “[p]otential variations on this option could be explored with the ultimate goal being to enhance resource adequacy and provide opportunities for large loads to

35 Id. at 18-19.
34 Id. at 19.
33 Id. at 18.
32 Id. at 9. 16

PDF page 17

efficiently connect to the system by providing incentives for large loads to be more flexible.”36 Antora urges the Commission to require PJM to offer customers the option of taking this service on a permanent rather than transitional basis.  As Antora has explained, its thermal storage charging load is inherently flexible.  Unlike high load factor loads which may see flexible interconnection as a sub-optimal option that makes sense on a temporary basis in exchange for faster interconnection, Antora seeks flexible transmission service throughout the life of the facility.  Offering non-capacity backed transmission service on a permanent basis would allow PJM to capture the benefits discussed above, serving the same amount of total load at lower cost, with less transmission infrastructure and fewer capacity resources. ​

While PJM’s filing is a significant step forward in indicating a willingness to offer non-capacity backed transmission service, it leaves several questions unanswered.  To operationalize this proposal, PJM would need to propose detailed tariff provisions describing the new type of service and setting forth obligations for the transmission provider and transmission customer.  PJM would need to provide a mechanism for PJM and/or the relevant EDC to communicate curtailment instructions to the relevant load, providing for operational protocols consistent with NERC requirements, as well as a rate structure for the new service.  And it would need to provide for operations protocols, including revised N-1 procedures that leverage this capability.  PJM should explain how its operations protocols and transmission planning and interconnection study assumptions will be adjusted to account for load flexibility and dispatchability, as well as describe how it will revise its load forecasting used for determining the amount of capacity required to serve customers.  Given that EDCs would continue to administer state-jurisdictional processes for load, the Tariff should explain how these processes interact with

36 Id. at 19. 17

PDF page 18

PJM’s operations protocols and planning processes for the new transmission service.  By enabling load-flexible, non-capacity backed transmission service at the wholesale level, EDCs could take this service and secure commitments from their retail customers so as to take advantage of the benefits of this service and comply with the operational requirements it imposes.

Antora notes that in taking such service (either at the PJM level or passed through a relevant EDC, as appropriate given the facility configuration), it would be willing to respond to curtailment instructions from PJM or the relevant EDC.  Further, Antora facilities could provide for load flexibility not solely during emergency conditions.  Rather, they modulate charging load as a matter of routine operations.

By requiring PJM to build out Option 7 so as to offer permanent transmission service and operations protocols that more fully leverage flexible load, the Commission can facilitate the integration of more load, more quickly, at lower total cost to customers, while also reducing curtailment and thereby supporting the addition of new low-cost variable generation resources. V.​

Conclusion
While the Commission’s inquiry into co-location was initiated in response to a discrete challenge involving load locating behind-the-meter of large generating facilities, it has spotlighted a broader challenge in serving rapidly growing load with an aging grid and outdated interconnection processes for load and generation that too frequently result in unacceptable delays.  The Commission’s Co-Location Order takes an important step forward in finding that the PJM tariff may be unjust and unreasonable in several respects, and the Commission appropriately highlights the potential benefits of flexible facilities.

To its credit, PJM expresses a willingness to take significant steps forward in evolving its 18

PDF page 19

transmission service and study processes to meet the needs of load and generation in a timelier and more affordable way.  But to make rapid progress, the Commission must give PJM clear instructions in developing its replacement rate.  By implementing Option 4, PJM can provide for an efficient study process and more fully capture the benefits of co-located facilities.  And facilitating non-capacity backed transmission service by offering Option 7 on a permanent as well as temporary basis is a ‘no regrets’ measure that will help PJM and the nation address the building crisis in serving load without precluding the pursuit of other service or options, and without inappropriately shifting system costs.

Respectfully submitted,
Noah Long​
​

Director, State and Regulatory Affairs​
​

Antora Energy LLC​

19

PDF page 20

CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Santa Fe New Mexico, this 23rd day of April, 2025.

/s/ Noah Long
Noah Long​
​
​
​

Antora Energy LLC​ ​
​

200 West De Vargas St​
​

Santa Fe, NM 87501​

20