Advances in On-Premise Power Generation
Allow the Future of Data Centers in the
AI Era to Meet Capacity Constraints and
Achieve Their Sustainability Targets
Bring Your Own Power
(BYOP)
Co-authors
Susanna Kass
Energy Fellow, Stanford University
Data Center Advisor, UNSDG-EP
Operating Partner, Digital Gravity Infrastructure Partners Shannon Miller
Founder and CEO, Mainspring Energy
PDF page 2
Bring Your Own Power (BYOP)1
Introduction
In the data center world, action revolves around energy – power is critical to operation and key to efforts to improve the sector’s environmental footprint. As a sector, data centers are engaged in a just transition from fossil fuels to the clean energy economy. Meanwhile, rocketing growth from AI, cloud computing, and digitization is driving unprecedented demand for power. The IEA 2024 Electricity Forecast predicts that global electricity consumption from data centers will double, from 460 TWh in 2022, to 1,000 TWh in 2026 – roughly equivalent to the power consumption of Japan.1
Similarly, McKinsey’s forecast in the US shows more than 15 GW getting added over the next decade, a near doubling, just due to data centers.2
Compounding this challenge, electric grids have experienced relatively stagnant growth for nearly two decades. The 2024 Grid Strategies report forecasts a 38 gigawatt increase in peak electricity demand in the U.S.by 2028 and concludes that “The U.S. electric grid is not prepared for significant load growth.” Figure 1: Data center power consumption forecast from McKinsey where gray represents enterprise customers, light blue represents co-location providers, and dark blue represents hyperscalers.
In some regions, data center availability is low while demand for capacity is still high. Figure 2 shows that current available data center capacity in two of the largest U.S. data center markets, Silicon Valley/Bay Area and Northern Virginia, are just .5% and .2%, respectively. Power constraints add significant risk to growth in these regions.
Figure 2: Power constraints in growing data center markets contribute to single digit availability (Newmark Report 2023)4 There is keen awareness of a lack of power availability in key regions, pressure to meet timing of market requirements, and recognition of the need for access to a renewable energy supply to power data centers throughout the lifecycle and in the supply chain.
BYOP: What it means and how it works
Power capacity drives business growth. For data center developers, flexibility and control of power systems has become essential. Deploying highly flexible, onsite power, also known as “Bring Your Own Power” (BYOP), can significantly speed expansion, control costs, open new siting options, and provide the agility needed to adapt to energy system changes. It also can enable a faster and more predictable path to decarbonization and allow data centers to partner with utilities on solutions. Figure 3 shows a basic BYOP configuration where onsite power generation can fill in for both utility and backup generation and then remain onsite after the utility is connected to provide additional value discussed below.
2024 availability 0.2%
1.9%
3.8%
0.5%
1.6%
5000
4000
3000
2000
1000
0
Northern Virginia
Dallas/Fort Worth
Phoenix
Chicago
Silicon Valley/Bay Area
41%
increase
28%
increase
45%
increase
43%
increase
30%
increase
Projected market size in 2027 (MW)
Market size in 2024 (MW)
Data center power consumption, by providers / enterprises 1, gigawatts 2014
2020
2030
35—
25—
10—
30—
15—
20—
5—
0—
CAGR
+13.0%
+11.9%
+9.6%
+8.7%
PDF page 3
Time to Market: Accelerating time to commission
with faster deployment
A 2023 Lawrence Berkeley National Laboratory analysis states that the average utility interconnection timeline for new grid generation resources is 35 months in many parts of North America.5 New load interconnection also faces significant delays. Some data center customers report that they’re being given 3-5 year estimates for grid delivery of data center power. For a 100 MW data center, assuming US$150,000/MW of revenue per month (~US$150/month/kW), three years of delay translates to over US$500M in lost revenue.6 BYOP can accelerate data center commissioning to less than one year, which can be paired with the overall data center development and construction. This directly reduces time to customer delivery and accelerates revenue and growth.
Flexible onsite power also supports additional benefits such as incremental campus/site expansion, adaptivity to market fluctuations, backup needs and the ability to replace diesel generators, and partnering with local utilities by participating in wholesale markets during periods of high demand. Data center assets can sometimes grow in a modular way. BYOP can enable that growth, where power is added modularly with the expanding site, regardless of grid availability. This modular approach provides data center developers better use of capital. Besides scalability, modular power can also achieve high availability targets with redundancy and can even eliminate the need for generators solely used for backup power onsite, replacing diesel generators with cleaner options that pay for themselves by improving time to commission.
Lastly, BYOP with low-emissions power gives developers greater flexibility over where they site their data centers, not just at sites that have existing utility power. In many cases, the locations that need the capacity most are those where grid availability is already significantly constrained or delayed.7 Greater location flexibility opens up new possibilities for site selection – as long as the onsite power is low emissions (and thus easily permitted) and scalable in size to match data center needs.
Adaptivity: Flexible dispatch enables additional revenue in a changing environment
In a time of transformational change, the flexibility to be more “future-proof” to the evolving environment becomes critical. Key factors like grid pricing, server load profile, the cost of different fuels, rack power density, requirements in carbon management, and total build size all can change over the lifetime of a data center. BYOP gives developers and owners a tool to manage and respond to these changes.
Over the last three years, grid pricing has increased 5% in the U.S. after being flat for the prior two years.8 Given the extensive need for new capacity and new transmission and distribution, these growth rates are not expected to drop. These increased grid costs not only result in increases in the base cost of energy, but can also lead to higher demand charges or pricing based on usage during peak loads. Even if the grid is ultimately connected to the data center, flexible onsite power generation allows the operator to dispatch when needed, increasing power generation when rates are high and dropping power production when rates are low. Depending on the location, commercial grid power customers can save 10- 30% of their electric bill by just reducing their peak loads.9 This serves to reduce both costs for the data center operator and strain on the local power grid, supporting the local community and reducing the need for the grid operator to overbuild capacity.
Data centers will transition over time from being energy customers to being contributors to the local grid. When data center and utility grid operators both contribute to clean energy generation, a green grid is possible.
Bring Your Own Power (BYOP)
2
Figure 3: BYOP data center illustration single line diagram Inverter
Inverter
Optional
Optional
Utility
13.8kV
MV
Collector
Bus
Collector
Bus
Onsite power generation
LV
Collector
Bus
Server
Rack
Server
Rack
Server
Rack
Server
Rack
UPS
UPS
UPS
UPS
ATS
Optional
Backup
Generation
Solar
Step
Down
Step Down
ISO TX
PDF page 4
Bring Your Own Power (BYOP)3
Advanced power generation technologies, enabled by advances in power electronics and software, have made BYOP a viable alternative for data center developers. One such technology is the linear generator, recently featured in IEEE Spectrum.10
Distinct from an engine, microturbine, or fuel cell, a linear generator directly converts motion along a straight line into electricity using chemical energy. The outcome is high efficiency, near-zero NOx emissions, full dispatchability (0-100% load acceptance/rejection) for firming renewables, high availability via modular buildout, and switching between fuels – including zero carbon fuels like green hydrogen and ammonia.11
The unique combination of linear generator capabilities addresses data center power challenges by providing local, dispatchable, and fuel flexible prime power with low total cost of ownership, at any scale.
For developers, this can offer a fast track to bringing facilities online to address grid constraints. Later, when grid power eventually becomes available, the technology can transition to serve as clean, resilient backup power generation. Mainspring Project Showcase
The Linear Generator
by Shannon Miller
Decarbonization: Getting to zero carbon power and zero carbon backup
Building sustainably powered data centers requires a transition away from the use of fossil fuels. Data centers invest heavily in renewables, but achieving zero carbon 100% of the time cannot be done with renewables and batteries alone. Zero carbon fuels such as green ammonia and green hydrogen have a role to play. Onsite power that is fuel-flexible – meaning that it can switch between fuel types without retrofit – gives developers and operators greater optionality and control on the path to decarbonization. Fuel-flexible power enables them to build both prime and backup capacity today with solutions that are equivalent or cleaner than today’s grid, and transition to increasingly lower carbon fuel use over time.
The Mainspring Linear Generator core
PDF page 5
Bring Your Own Power (BYOP)
Deploy 50MW of prime power
linear generators running on
natural gas or directed biogas.
Modular design and high
reliability can support 99.99%
of uptime. Option to replace
diesel generators with linear
generators in the design.
Grid connection becomes
available. The dispatchable linear
generators provide peak-shaving,
wholesale market participation,
and continue to replace the need
for diesel backup. The linear
generator can also be combined
with the grid to increase the
data center’s capacity.
Customer installs onsite H2 or
NH3 storage tanks. In some
regions, an H2 or NH3 pipeline
could be accessible. Linear
generators provide zero carbon
backup for the data center and
a zero carbon peaking resource
that supports the data center and
can be exported to support the
local utility.
As zero carbon fuels reach parity
with traditional fuels, Mainspring
and the grid combine to provide
zero carbon power, 100% of the
time. Flexible dispatch enables
the best optimization of cost,
sustainability, and resilience.
Clean fuels and shared dispatch
with the utility eliminate the
need for diesel generators.
Step 1
Prime power
Step 2
Peak load shaving or
modular expansion
Step 3
Zero-carbon backup with
economic or sustainable dispatch
Step 4
100% zero-carbon power and
zero-carbon backup
Mainspring BYOP Scenario
A data center colocation provider needs access to 50MW power to fulfill market demand. The utility has shared that they could not meet this for four years. The data center provider has sustainability goals around reducing carbon and water usage. The site has access to natural gas.
The following is one potential pathway that the data center provider could pursue with linear generator assets
– recognizing that the flexibility of the product provides optionality for a number of other scenarios based on market conditions and what would generate the greatest value for the data center, utility, and local community.
Pre-Interconnection
Fast, flexible power
Post-Interconnection
Onsite capacity to support backup and economic or sustainable dispatch Islanded, black start capability
Fully dispatchable to shave
peaks or meet demand
underserved by utility power
Zero carbon backup
24/7/365 zero carbon
and/or
or
Add grid to increase total
capacity and expand facility
Zero carbon peaking resource
for utility
Natural gas
or biogas
Natural gas
or biogas
Electricity
Electricity
Electricity
Electricity
Electricity
Electricity
Electricity
Clean fuels
MSE
Grid
Zero carbon power
Results: Data center online 3 years early resulting in $270M revenue assuming $150k/MW/month. Over the first 10 years of operation, BYOP saved 350 Million lbs of CO2 and 670 million gallons of water vs local grid.12
PDF page 6
Bring Your Own Power (BYOP)5
Summary and recommendations
Many promising developments of data center new builds are facing the headwinds of grid power constraints across global energy markets. There is a new imperative for data center cloud and AI developers to consider onsite energy generation, to build more robust and resilient power systems, and to establish energy policy with regulatory policymakers to embrace the future of data center builds with clean energy digital infrastructure. Developers also must quantify the energy mix in a just clean energy transition and pivot their roles from solely energy consumers to energy contributors, collaborating with grid providers to green the grid. The authors recommend that developers capitalize on the advantages of BYOP on the path to a just, green energy transition such that:
• Data center colocation providers can accelerate the deployment of new power capacity and create competitive advantage.
• Energy procurement can move beyond conventional power purchase agreements, as data center developers take
control of their energy needs, participate in energy markets, and contribute to the green grid.
• Energy management systems can be optimized by shifting to a model that provides both primary power and backup power that are grid-interactive ready and sustainable. Developers no longer need to choose between adding power and meeting sustainability goals. It is time to think differently about how data centers design for and use power.
1 IEA 2024 Electricity Forecast
2 Investing in the rising data center economy, McKinsey, Jan 2023 3 The Era of Flat Demand is Over, Grid Strategies, Dec 2023 4,7 2023 U.S. Data Center Market Overview & Market Clusters 5 Characteristics of Power Plants Seeking Transmission Interconnection As of the End of 2022 6 CBRE North America Data Center Trends H1 2023
8 EIA Electricity Data Browser
9 Based on a sample of business case analyses performed for commercial customers in states with high demand charges
(e.g., California, Massachusetts, New York, etc). Demand charges can typically be reduced by 50% to 65%, depending on the load curve and
applicable tariff – resulting in a 10-30% savings to the overall customer utility bill. 10 This New Breed of Generator Can Run on Almost Any Fuel, Mainspring’s linear generator may speed the transition to a zero-carbon electrical grid 11 Mainspring product specifications
12 Assumes Mainspring’s linear generators running at 90% capacity factor for 3 years, then operating at 25% for peak shaving applications
for 7 years. CO2 and water savings compared with ERCOT subregion. Rendering with Mainspring Linear Generators
courtesy of Overwatch Capital
PDF page 7
The Future of Data Centers Absolute Zero Design
by Susanna Kass
Sustainability in The AI Data Center Era
Since the introduction of ChatGPT in November 2022, AI or/ and Generative AI have become part of our daily language. Some are enamored with the potential for artificial intelligence, while others are determining its implications for our present and future operations. For the Data Center ICT sector, AI has shown great potential.
Until the introduction of large language models (LLMs), training applications relied on analyzed data and made predictions based on learnings from data sets. They often required a large volume of data sets to be useful for applications, such as quality system control, chatbots, natural language processing risk analysis, security surveillance, or autonomous vehicle maneuvering navigation systems. LLMs are a new breed of AI Machine Learning with the ability to recognize, summarize, predict, and generate large volumes of datasets containing text, audio, images, video, and metaverse content beyond human and traditional cloud computing. Furthermore, the initial push for Generative AI is in content creation. In text form, this can be as an email or new articles, blog post, or poem; in audio format as a voice response, a series of sounds, or a complete song; in image format as a picture or a series of images; and in video format as a movie, game, or one or more metaverse scenes. These AI assets are stored in data centers and retrieved by the requests of IIoT devices for entertainment, education, and work purposes. The potential of AI content creation is endless. The consumerization of this new content will grow at a fast pace as AI digital assistants become more personalized with behavioral learning and the proliferation of AI devices coming to market. According to Nvidia, AI bucks the conventional belief that humans must become programmers who study computer science in order to compete in the information age. AI shows promise that human language is optimal for interacting with AI systems via text, audio, and touch. The interactions of the human interface are adapted by AI systems which generate programming language for AI systems to complete tasks for humans.
In 2024, we are seeing the advent of Generative AI applications adoption in the form of AI digital assistants. This deployment trend will have a significant societal impact by quickly driving the growth of AI to the edge; new edge data centers at urban communities will serve new content generation, providing contextual awareness of these digital assistants with location proximity. AI digital assistants will demonstrate productivity improvements in AI devices for entertainment, education, home, and work. The proliferation of autonomous vehicles aims to improve efficiency and human productivity.
Developers are using Generative AI in the creation of new code, therefore eliminating millions of programmer hours, ensuring consistency in code quality, and improving overall development performance, given that code is increasing in complexity and size beyond human comprehension. Moreover, generative AI can be versatile in different languages, unlike humans who are limited to several languages and in their accuracy.
Generative AI is making a definitive impact in research, and as the use of generative AI continues, we can expect future scientific breakthroughs.
Sustainability Impact with AI on Efficiency and
Performance have Unlimited Possibilities
As with any revolutionary technology, Generative AI models will be refined and optimized with regards to improving their impact on sustainability. The sustainability capabilities of resource usage effectiveness can be improved and measured by using multiple modalities of machine learning, so that multiple tasks are trained simultaneously to improve accuracy and efficiency. The total resources will be thus reduced. Additionally, the personalization of AI digital assistants in ever increasing and personalized versions of multimodal modes on various platforms will help to eliminate waste and redundancy. The use of AI in AIDC shows the promise of new realms of sustainability, with regards to 6
PDF page 8
The Future of Data Centers BYOP Absolute Zero Design by Susanna Kass (Continued)
7
resource usage effectiveness by efficiency and performance improvements using the foundations of AI scalarization of multi-tasks and multi-domains learning in machine learning and inference – in comparison to the traditional computation mode of using resources to process each model of LLM set.
The diffusion of AI models and the use of more advanced AI algorithms can further increase performance significantly, with specific designs that will reduce the latency of computing and networking resources over traditional cloud computing models in an AI accelerated Data Centers. Diffusion approach and AI quantization methods such as pruning and allotting zero resources to attention heads and in using advanced AI algorithms increase accuracy, therefore extending the reduction of idle resources and eliminating zombie requests for compute, network and data storage. Energy Efficiency Usage Effectiveness (EEUE) will be a key sustainability metric for the AI era in measuring the effectiveness of energy efficiency gains of resource usage consumption. In 2024, AI is experiencing intensive workload demands. The AI model starts at 1 Gigabyte and rapidly scales to hundreds of Gigabytes. Data Models are at the 300,000 range for Generative AI, and they are expected to drastically increase in size with the use of video and in metaverse settings.
New GPUs, NPU, and MPU using the next generation of AI chips are expected to come to market. The AI chips are expected to be more energy efficient with ultra-high density per rack and to be chip cooled ready.
It is an opportune time to explore linear generator technology as we embrace BYOP approach. AI at the Edge can operate reliably without connecting to the grid 24/7. It can commission without any delay in power constraints to energy markets, hence achieving high uptime performance and sustainability with resiliency. BYOP: Net Zero Availability Zone Future Proof
Resilience Grid Power System
Currently, it is a conventional design that each data center has a primary power system and a backup power system unit to maintain uninterrupted operation. Many power assets are designed for primary function, and the backup power assets take instantaneous action to provide power to the data center for a duration of time such as 4-8 hours or up to 24 hours – when the fault is being identified of the primary power systems until it can assume its normal operation. Otherwise, the backup systems are not used.
We need to examine if the concept of primary and backup systems is sustainable, in comparison to a resilient system that can operate as both to maintain uninterrupted operation for the data center. Net Zero Utility Availability Zones provide flexible, resilient systems at Grid scale, consequently eliminating the need for conventional backup systems for data centers.
BYOP: Empowerment as Energy Contributor
to promote Sustainability
The impact of a carbon free future is paramount for our generation. We must take action to pave the way for future generations. The planet itself is resilient; meanwhile, humans are depleting our natural ecosystems at a fast pace in a linear economy.
The design of the Future of Data Centers is to be connected with the grid; rather, it becomes grid interactive to ensure cloud and AI services are resilient, sustainable and affordable, and in so doing, futureproof their growth potential for primary and backup power. The result is a triple bottom line of much lower Capex for redundant assets, much higher utilization through multiple uses of common assets (e.g., energy infrastructure), maximized investment efficiency for renewable power investments, clean energy generation, and the elimination of need for backup assets. Data centers transition from an energy customer to a contributor to the local grid. When data centers and utility grid operators contribute to clean energy generation, a green grid is made possible. The design concept of availability zones, which originated in the data center sector, may be applied to the utility grid. The electric grid assets operate to maximize power availability for all stakeholders in order to reach the full potential of power availability and concurrently deliver cost efficiency at utility scale at Utility Net Zero Availability Zones by regions.
AI Data Centers are designed to be a sustainable contributor to the clean energy economy. We need to take a novel approach, utilizing net zero availability zones, linear generators with clean fuel for clean energy generation in place of on-premise prime power systems and a separate backup power system exemplifies the Sustainable Development Goals and impactful results.