EL25-49-000 · 2025-05-07 · Exelon Corporation, American Electric Power Service Corporation and 15 others

Answer of the Indicated PJM Transmission Owners to the 04/22/2025 Joint Comments, Motion to Stay Proceedings and Request to Establish Settlement Judge…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.

)
Docket No. EL25-49-000

Large Loads Co-Located at Generating
Facilities
)
Docket No. AD24-11-000
Constellation Energy Generation, LLC

v.

PJM Interconnection, L.L.C.
)
Docket No. EL25-20-000
(consolidated)

ANSWER OF THE INDICATED PJM TRANSMISSION OWNERS
 TO THE MOTION TO STAY PROCEEDINGS

Pursuant to Rules 212 and 2131 of the Rules of Practice and Procedure of the Federal
Energy Regulatory Commission (“FERC” or “Commission”), the Indicated PJM Transmission
Owners (hereinafter, “Indicated TOs”)2 submit this Answer to the April 22, 2025 Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures (“Stay

1  18 C.F.R. §§ 385.212, 385.213 (2024).
2  The Indicated PJM Transmission Owners include: American Electric Power Service Corporation, on behalf of Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; AMP Transmission, LLC; City of Cleveland, Department of Public Utilities, Division of Cleveland Public Power; City of Hamilton, OH; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Corporation on behalf of its affiliates Duke Energy Ohio, Inc., Duke Energy Kentucky, Inc., and Duke Energy Business Services LLC; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation, on behalf of Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, as agent for its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission Company, The Potomac Edison Company, Monongahela Power Company and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Transmission Companies”); Old Dominion Electric Cooperative; PPL Electric Utilities Corporation; Rockland Electric Company; Southern Maryland Electric Cooperative, Inc.; UGI Utilities Inc; and Wabash Valley Power Association, Inc.

PDF page 2

2

Motion”) of the Electric Power Supply Association, the PJM Power Providers Group, Calpine Corporation, Cogentrix Energy Power Management, LLC, Constellation Energy Generation, LLC, and LS Power Development, LLC (“Joint Movants”).

I. ARGUMENT

The Stay Motion is unnecessary as the record in this proceeding is clear on two fundamental points.  First, all parties have expressed interest in the Commission providing regulatory guidance as soon as possible to bring clarity and assist with the current challenges and disputes.  Second, the existing PJM Open Access Transmission Tariff (“PJM Tariff”) is just and reasonable in regard to co-location arrangements and therefore the Commission has everything it needs to provide the expeditious regulatory guidance everyone seeks.

In order to take any action imposing changes to the PJM Tariff in a Federal Power Act (“FPA”) section 206 proceeding,3 the Commission must first find that the existing PJM Tariff is not just and reasonable.  No such showing has been made and thus there is no basis to pause the Commission’s effort to expeditiously provide guidance without first satisfying that threshold requirement.  Indeed, the record in this proceeding demonstrates that the existing PJM Tariff remains just and reasonable.  Unless and until the Commission finds to the contrary under FPA section 206, there are no grounds to amend the PJM Tariff.

Numerous commenters in this proceeding address the national security implications of service to these new large loads.  The truth is that the national interest will be best served by a quick dismissal of this proceeding, and a ruling that the existing PJM Tariff remains just and

3  16 U.S.C. § 824e.

PDF page 3

3

reasonable.  Rather than fighting about a wish list of new rules, the parties will then instead begin to focus on obtaining service under the rules in place today.

a. The PJM Tariff Has Not Been Shown to Be Unjust and Unreasonable.
In a proceeding under section 206 of the FPA, the Commission can only remedy a “rate [or] charge” or “any rule, regulation, practice, or contract affecting such rate [or] charge” after it is found to be “unjust [or] unreasonable.”4  “The burden of proving an unjust or unreasonable rate rests with the party that initiated the proceeding—the Commission [(as in this case)] or the third- party complainant.”5  Only after a successful showing that the prevailing rate is unjust and unreasonable may the Commission order a replacement rate.6  No such showing has been made here.

The Stay Motion succinctly summarizes the arguments for why the existing rate is purportedly unjust and unreasonable.7  The arguments boil down to the following: while the PJM Tariff provides that wholesale customers serving load in the PJM Interconnection L.L.C. (“PJM”) region should do so with Network Integration Transmission Service, a certain class of wholesale customer would rather take some new and different type of service that would cost them less. Of course, nearly everyone who buys nearly any service would rather pay less.  But in PJM, the transmission owners, as in virtually every other piece of the grid regulated by the Commission, assess on a postage-stamp basis, without consideration of the distance between load and generation, the embedded costs of their respective portions of the transmission grid from network

4  Id. § 824e(a).
5  Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021).
6  16 U.S.C. § 824e(a).
7  See Stay Motion at 3–4.

PDF page 4

4

customers.8  As the Commission has explained, “PJM recovers the full revenue requirements of existing facilities (embedded costs) through its firm transmission rates.”9  And the Commission has in recent years continued to reject requests that loads that claim reduced system impact merit some new third category of lower-cost transmission service.10

The Joint Movants seek to move past the need for a finding that the existing rate is unjust and unreasonable and thus ask for procedures that investigate the second step of an FPA section 206 proceeding (fixing a new rate) while bypassing the first step.  But the first step matters.  Unless and until the Commission makes a finding that the existing rate is unjust and unreasonable, any negotiation will be unproductive.11  Most importantly, the Commission has no authority to direct relief under FPA section 206 absent a finding that the existing tariff is unjust and unreasonable. b. Reliability Is at Stake.

The Indicated TOs, which include investor-owned utilities, municipalities, and
cooperatives, all believe that treating co-located load as anything other than Network Load would increase the risk of reliability failures and resource inadequacy in PJM.  Much of what is being

8  See, e.g., Pennsylvania-New Jersey-Maryland Interconnection, et al., 81 FERC ¶ 61,257 (1997) (adopting PJM pricing proposal to allow recovery of embedded transmission revenue requirement from network customers), corrected by, 82 FERC ¶ 61,103 (1998), and clarified in part by, 92 FERC ¶ 61,282 (2000), and review granted in part, vacated in part by, 295 F.3d 1 (D.C. Cir. 2002); PJM Tariff, Section 34.1 (providing for payment by network customers of load ratio share of embedded cost of their zone); PJM Tariff, Attachments H-1, H-1A, H-2, H-2A, H- 3, H-3D, H-7, H-7A, H-9, H-9A, H-13, and H-13A (establishing network revenue requirements for each of the Exelon Utilities based on the embedded costs of their respective transmission systems).
9  PJM Interconnection L.L.C., 139 FERC ¶ 61,243, at P 78 n.105 (2012).
10  See, e.g., Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp. et al., 171 FERC ¶ 61,237, order on reh’g, 173 FERC ¶ 61,043 (2020).
11  If the Commission were to determine that something about the existing PJM Tariff is unjust and unreasonable, the Commission would no doubt provide guidance on what aspect needs reform, allowing the parties to hone the discussion and focus on the parts that are really at issue.  Absent such guidance and direction, any settlement talks would be truly gargantuan in scope—and likely set the stage for further delay followed unfortunately by failure and then even more delay.

PDF page 5

5

proposed involves obscuring loads from the grid operator and hoping that the grid is not impacted. Questions raised by the North American Electric Reliability Corporation highlight the importance of these concerns.12  The record is clear—no matter how connected to the PJM Transmission System, large loads pose both a safety and a reliability concern.  It is unrealistic to ask the Indicated TOs to accede to these demands in the context of settlement procedures while those questions remain unresolved.

II. CONCLUSION
The national interest will not be well served if service requests under the existing rules are further delayed by the outcome of this proceeding in which a number of parties attempt to rewrite the PJM Tariff.  Instead, the best way to promote co-located load customers is to provide certainty, which the Commission can accomplish quickly by simply clarifying that co-located loads should seek service under the well-established, just and reasonable terms of the existing PJM Tariff. For the reasons stated above, the Indicated TOs respectfully request that the Commission reject the Stay Motion.

12  There are profound reliability issues associated with large data center loads that are being actively investigated right now.  See, e.g., Comments of the North American Electric Reliability Corporation (“NERC”) (Apr. 23, 2025); Item E-4 Presentation by NERC at April 17, 2025 Commission meeting.

PDF page 6

6

Respectfully submitted,

/s/ William Sauer
William Sauer
Vice President, Federal Regulatory Affairs Exelon Corporation

701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-868-7499
Email: william.sauer@exeloncorp.com
/s/ Max Minzner

Max Minzner
Vice President and Deputy General Counsel Exelon Corporation

701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-934-4740
Email: max.minzner@exeloncorp.com

On behalf of Exelon Corporation

/s/ Stacey Burbure
Stacey Burbure
Vice President FERC, RTO Strategy & Policy American Electric Power Service Corporation 1 Riverside Plaza

Columbus, OH 43215
Telephone: 614-716-2502
Email: slburbure@aep.com

/s/ Lisa G. McAlister
Lisa G. McAlister
AMP Transmission, LLC
1111 Schrock Road, Suite 100
Columbus, Ohio 43229
Telephone: 614-540-6400
Email: lmcalister@amppartners.org

On behalf of American Electric Power Service Corporation

On behalf of AMP Transmission, LLC

/s/ Martin J. Keane
Martin J. Keane
Director of Public Utilities
Cleveland Public Power
1300 Lakeside Ave.
Cleveland, OH 44114
Telephone: 216-664-2444 ext. 75604
Email: martin_keane@clevelandwater.com

/s/ Debra D. Roby
Debra D. Roby
Washington Energy Law LLP
900 17th Street N.W., Suite 500-A
Washington, D.C. 20006
Telephone: 703-785-9270
Email: droby@washingtonenergylaw.com

On behalf of City of Cleveland, Department of Public Utilities, Division of Cleveland Public Power

On behalf of the City of Hamilton, OH

PDF page 7

7

/s/ Wesley Walker
Wesley Walker
Senior Assistant General Counsel
Dominion Energy Services, Inc.
120 Tredegar Street
Richmond, VA 23219
Telephone: 804-819-2345
Email: wesley.walker@dominionenergy.com

/s/ Molly Suda
Molly Suda
Associate General Counsel
Annelise Rickert
Federal Government Affairs Director Duke Energy Corporation

1301 Pennsylvania Ave NW, Suite 200 Washington, DC 20004

Telephone: 202-824-8011
Email:  molly.suda@duke-energy.com Annelise.rickert@duke-energy.com

On behalf of Dominion Energy
On behalf of Duke Energy

/s/ Michael Brechlin
Michael Brechlin
PA Bar # 335424
Duquesne Light Company
411 7th Ave
Pittsburgh, PA 15219
Telephone: 412-393-6431
Email: mbrechlin@duqlight.com
/s/   Amanda P. Parker
Amanda P. Parker
Attorney
FirstEnergy Service Company
76 South Main Street
Akron, OH 44308
Telephone: (330) 384-4592
Email: aparker@firstenergycorp.com

On behalf of Duquesne Light Company On behalf of The FirstEnergy Transmission Companies

/s/ Denise R. Foster Cronin
Denise R. Foster Cronin
Vice President, Federal and RTO Regulatory Affairs

East Kentucky Power Cooperative, Inc. 4775 Lexington Road, P.O. Box 707

Winchester, KY 40392-0707
Telephone: 859-745-9615
Email: denise.cronin@ekpc.coop

/s/ Daniel E. Frank
Daniel E. Frank
Kelly Cuthbertson
Eversheds Sutherland (US) LLP
700 Sixth St., N.W., Suite 700
Washington, DC 20001-3980
Telephone: 202-383-0100
Email:
danielfrank@eversheds-sutherland.com kellycuthbertson@eversheds-sutherland.com

On Behalf of East Kentucky Power
Cooperative, Inc.

PDF page 8

8

/s/ Adrienne E. Clair
Adrienne E. Clair
Thompson Coburn LLP
1909 K Street, N.W., Suite 600
Washington, D.C.  20006-1167
Telephone: 202-585-6900
Email: aclair@thompsoncoburn.com

/s/ Steve Nadel
Steven M. Nadel
Senior Counsel
PPL Services Corp.
645 Hamilton Street, Suite 601
Allentown, PA 18101
Telephone: 610-774-4775
Email: SMNadel@pplweb.com

On behalf of Old Dominion Electric
Cooperative

On behalf of PPL Electric Utilities Corp.

/s/David Burns
David Burns
Senior Manager,
FERC Policy & Regulatory Affairs
Consolidated Edison Company of New York, Inc.

4 Irving Place
New York, NY 10003
Telephone: 571-678-9152
Email: burnsd@coned.com
/s/Joshua Kirstein
Joshua A. Kirstein
Senior Attorney
Law Department
Consolidated Edison Company of New York, Inc.

4 Irving Place, 18th Floor
New York, NY 10003
Telephone: 929-656-5971
Email: kirsteinj@coned.com

On behalf of Rockland Electric Company

/s/ Damon L. Krieger
Damon L. Krieger
Group Vice President, Legal, Strategy, and Sustainability, and Deputy General Counsel Southern Maryland Electric Cooperative, Inc. 15035 Burnt Store Road

P.O. Box 1937
Hughesville, Maryland 20637-1937
Telephone: 301-274-4323
Email: Damon.Krieger@SMECO.coop

/s/ Jeremy L. Fetty

Jeremy L. Fetty
Parr Richey
251 N. Illinois, Suite 1800
Indianapolis, Indiana 46204
Telephone: 317-269-2500
Email: j_fetty@wvpa.com

On behalf of Southern Maryland Electric Cooperative

On behalf of Wabash Valley Power
Association, Inc.

PDF page 9

9

/s/ Lindsay Berkstresser
Lindsay Berkstresser
Counsel – Energy & Regulatory
UGI Corporation
500 North Gulph Road
King of Prussia, PA 19406
Telephone: 717-504-9925
Email: berkstresserl@ugicorp.com

/s/ Richard P. Bonnifield
Richard P. Bonnifield
Husch Blackwell
1801 Pennsylvania Avenue, NW,
Suite 1000
Washington, DC 20006-3606
Telephone: 202-243-8844
Email:
richard.bonnifield@huschblackwell.com

On behalf of UGI Utilities Inc.

May 7, 2025

PDF page 10

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list in the above captioned dockets. Dated at Chicago, IL this 7th day of May, 2025.

/s/ Geneva Kennedy
Geneva Kennedy
Exelon Corporation