EL25-49-000 · 2025-05-15 · Exus Renewables North America

Comments of Exus Renewables North America in support of Option 6 proposed in PJM Interconnection, L.L.C.’s 03/24/2025 response to FERC's February Order to…

PDF page 1

ORIGINAL
FILED
SECRETARY OF THE
"ISSION
1015 rAY I S P 1: 5L.

PDF page 2

exus
Renewables
NORTI4 AMERICA
Edith Webster-Freed
Senior Vice President & General Counsel
EWF(&exus.us
929-715-3876
New York
www.exus.us
April 23, 2025
Debbie-Anne A. Reese
Secretary, Office of the Secretary
Federal Energy Regulatory Commission
888 First Street, NE
Washington, DC 20426
RE:
Large Loads Co-Located at Generating Facilities and Show Cause Proceeding in PJM Interconnection, L.L.C.; Docket Nos. EL25-49-000 and AD24-11-000

Dear Secretary Reese:
On behalf of Exus Renewables North America ("Exus"), a leading independent owner, developer, and operator of utility-scale renewable energy projects throughout the United States, I am writing in support of Option 6 proposed by PJM Interconnection, L.L.C. ("PJM") in PJM's March 24, 2025 answer ("Answer") to the Federal Energy Regulatory Commission's ("Commission" or "FERC") February "Order to Show Cause" in the above-referenced dockets.' PJM, in furtherance of its fundamental responsibility to maintain grid reliability, proposes to maintain Existing Option 1 and Existing Option 2 because those options should achieve the highest levels of reliability while utilizing existing Network Integration Transmission Service ("NITS") rules.2

In its Answer, PJM emphasizes the obligation to serve new large loads and advances several new options to serve large loads. Option 6, which incentivizes a new large load to become a networked load and bring its own generation that would serve as a PJM Capacity Resource, presents several compelling features to a project developer like Exus while also addressing reliability, operational, and fairness concerns raised in the Commission's Show Cause Order. Option 6 balances the interests of new large loads with existing consumers. Exus understands that Option 6 ensures fair treatment to existing customers because the new networked load would remain responsible for the appropriate NITS charges based on the load's actual use of the transmission system. The co-located, front-of-the-meter generation resource would be responsible for reasonable costs associated with the generator interconnection. As a result, the Exus is not requesting to intervene in the above-referenced proceedings out of time or to otherwise become a party of record. Exus is instead submitting these brief comments from the perspective of an active project developer for consideration by the Commission in rendering a decision in response to PJM's Answer.

2  See "Answer of PJM Interconnection, L.L.C." PJM Interconnection, L.L.C. et al. Docket Nos. EL25-49-000, AD24-11-000, and EL25-20-000 at Exhibit A (filed Mar. 24, 2025).

PDF page 3

existing grid and customer base would not be adversely impacted by the large load addition because the large load would not be causing improper cost shifts or facilitating the removal of any existing generation capacity from participating in the PJM-administered markets. Unlike other new proposed options, Option 6 addresses resource adequacy in an accelerated fashion by incentivizing the new large load to bring networked generation in exchange for a faster interconnection with accelerated interconnection studies of any new (or replacement) generation. Critically, Option 6 would be open to both existing generation and new generation that has arrangements in place with generation that is scheduled to deactivate, thereby advancing several state and federal policies around economic redevelopment and repurposing existing infrastructure.

Option 6 would allow bilateral transactions (transparently reflected in the market) between the networked co-located generation and the new large load for financial and contractual purposes. The co-located generation would be able to retain its Capacity Resource status through a grid connection, thereby allowing PJM to call on the resource during capacity emergencies. Option 6 also accommodates different state policies, allowing an interested state to pursue its policy goals on a case-by-case basis through the State Agreement Approach that would allow accelerated investment in the new large load infrastructure connection via the State's assumption of cost responsibility for applicable transmission upgrades in PJM's Regional Transmission Expansion Plan.

Further, PJM explains that, while some Tariff revisions may be required, most of the existing framework is in place and the new large load would be studied pursuant to the existing transmission owner/electric distribution company application and study processes for new customers and new load connections.

Thank you for the Commission's consideration of these comments.
Sincerely,
Edith Webster-Freed
Senior Vice President & General Counsel