Answer of PJM Interconnection, L.L.C. to Motion for Expedited Action of Constellation Energy Generation, LLC
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
)
Large Loads Co-Located at
)
Generating Facilities
)
Docket No. AD24-11-000
)
Constellation Energy Generation, LLC
)
)
v.
)
Docket No. EL25-20-000
)
(Consolidated)
PJM Interconnection, L.L.C.
)
ANSWER OF PJM INTERCONNECTION, L.L.C. TO
MOTION FOR EXPEDITED ACTION OF CONSTELLATION
ENERGY GENERATION, LLC
Pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or “FERC”), 18 C.F.R. § 385.213, PJM Interconnection, L.L.C. (“PJM”) submits this answer to Constellation Energy Generation, LLC’s (“Constellation”) November 21, 2025, Motion for Expedited Action (“Motion”).1
The Motion recognizes that the subject matter of the captioned proceedings overlaps the issues in the recently-initiated, industry-wide ANOPR2 proceeding.3 The Motion nonetheless seeks a “full order on the merits” applicable solely in the PJM Region, “even while the Commission develops a comprehensive rule in response to the ANOPR”
1 PJM Interconnection, L.L.C., Motion for Expedited Action of Constellation Energy Generation, LLC, Docket Nos. EL25-49-000, et al. (Nov. 21, 2025). 2 Ensuring the Timely and Orderly Interconnection of Large Loads, Advance Notice of Proposed Rulemaking, Docket No. RM26-4-000 (Oct. 27, 2025) (“ANOPR”).3 Motion at 4 (noting that “the interconnection of large loads to the transmission system” is “the subject of both the ANOPR and this show cause proceeding”).
PDF page 2
2
applicable nationwide.4 The Motion seeks relief prior to any Commission determinations prompted by the ANOPR on foundational issues, including jurisdictional boundaries. The Motion invites the Commission to run afoul of the principle that agencies should defer taking action in specific adjudicatory matters where such action would supplant ongoing generic rulemakings.5 The Commission should not take the bait.
If that was not enough, PJM has been engaged with its stakeholders—including Constellation—in a Critical Issue Fast Path (“CIFP”) process to assist PJM’s Board of Managers in determining how to address this important, yet extremely complex, issue. The ANOPR clearly states that it was “not intended in any way to discourage public utilities from making filings to address these and similar issues under FPA section 205.”6
By seeking an expedited order on the merits in these proceedings, the Motion requests relief that not only pre-empts the ANOPR docket but also the CIFP process and any section 205 filings the ANOPR goes out of its way to avoid discouraging. The Motion attempts to lock in its movant’s desired outcome while foreclosing possible solutions under consideration by PJM’s Board of Mangers as developed in the expedited CIFP process. PJM encourages clear Commission guidance on these important issues, but not in the Motion’s requested fashion.
4 Motion at 4.5 See City of Anaheim v. FERC, 723 F.2d 656, 659 (9th Cir. 1984) (“[A]gencies may not use adjudication to circumvent the Administrative Procedure Act’s rulemaking procedures” and adjudication should not “supplant a pending rule-making proceeding.”); Duke Energy Moss Landing LLC, 86 FERC ¶ 61,227, at 61,815–16 (1999) (implying that an adjudication would circumvent the Administrative Procedure Act’s rulemaking provisions if it supplants a pending rulemaking). 6 ANOPR at P 32.
PDF page 3
3
Should the Commission feel inclined to address the issues raised by Constellation in its Motion through action on the Section 206 filing, the Commission should be cognizant that a set of rules or guidelines that are applicable only to the PJM market will not create a rational, durable, and predictable pathway for the national issues associated with large load interconnection. A “PJM-only” solution will only encourage data centers to shop for locations based not on the underlying values of a particular site but instead on exploiting regulatory arbitrage created by inconsistent regulatory treatment across regions. Such an approach is not consistent with the President’s Executive Order which focuses on the need for development of AI infrastructure as a national, not regional, imperative. ANSWER
PJM’s CIFP process concerning the integration of large loads has been ongoing since September, culminating in presentations before PJM’s Board of Managers on November 19, 2025. Various stakeholders or stakeholder groups presented a total of twelve proposal packages to the Board. Among those groups were the “Joint Stakeholders,” a group including Constellation (Constellation included the Joint Stakeholders’ package as an exhibit to its comments on the ANOPR).7 The Board is now considering the stakeholders’ various proposals and will soon determine and announce how it plans to proceed.
In addition, initial comments in the ANOPR process initiated by the Commission at the request of the Secretary of Energy were filed on November 21, 2025. As Constellation acknowledges, the ANOPR process involves issues identical to those at issue
7 PJM Interconnection, L.L.C., Supporting Comments of Constellation Energy Generation, LLC, Docket No. RM26-4-000, Exhibit 1 (Nov. 21, 2025) (“Constellation Comments”).
PDF page 4
4
in these dockets. The Secretary of Energy has directed the Commission to take “final action” on the ANOPR by April 30, 2026.
Rather than await the results of the ANOPR processes, without regard for City of Anaheim v. FERC, and indifferent to the ongoing deliberative CIFP process, the Motion asks the Commission to make a merits decision that would implement its movant’s preferred outcomes in these consolidated dockets immediately. The Motion’s requested relief includes a proposed finding that PJM’s Tariff is unjust and unreasonable and an accompanying order establishing a “full replacement rate.”8 While the components of the replacement rate are not specified in the Motion, the Constellation Comments in the ANOPR proceedings request the Commission to adopt certain options that PJM proposed in its Answer to the Commission’s order to show cause in these dockets.9 Specifically, the movant seeks adoption of PJM options 2,10 4,11 5,12 and 713 “as clarified and modified by
8 Motion at 1.9 PJM Interconnection, L.L.C., Answer of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al. (Mar. 24, 2025) (“PJM Show Cause Answer”). 10 Option 2, as conceived by PJM, already exists in its Tariff. It involves co-located load and generation at the same point of interconnection, but separately metered. The load would take Network Integration Transmission Service (“NITS”). PJM Show Cause Answer, Exhibit A. 11 Option 4 involves co-located load behind generation with protection systems to prevent delivery of energy from the grid to the load in the event the generation goes offline. This was essentially the fully-isolated co-located load configuration that motivated Constellation’s complaint. PJM Show Cause Answer, Exhibit A. 12 Option 5 is similar to Option 4, with an allowance for back-up service from the PJM system with permission. PJM Show Cause Answer, Exhibit A. 13 Option 7 involves co-located load and generation where the load is willing to curtail in advance of Emergency Procedures. PJM Show Cause Answer, Exhibit A.
PDF page 5
5
Constellation.”14 The movant also asks the Commission to reject PJM option 6,15 find that it lacks jurisdiction “over behind-the-meter sales between a co-located generator and load,” require Transmission Owners to “provide timely participation in relevant studies requested by PJM and in the interconnection agreement process,” and require Transmission Owners “to process load interconnection requests on the same timelines regardless of configuration.”16
If the Commission does not immediately prescribe this preferred “full replacement rate,” the Motion seeks alternative “targeted” relief including: (1) clarification of “jurisdictional boundaries consistent with the ANOPR,” (2) rejection of “a one-size-fits-all firm transmission regime based on gross rates,” and (3) requiring Transmission Owners to cooperate in processing large load co-location studies.17
As PJM previously explained in the captioned proceedings, it believes its Tariff remains just and reasonable.18 Based on Commission guidance, PJM is willing to implement improvements or clarifications to further facilitate large load interconnections. PJM also recognizes that the issues presented by integrating large data center loads into the interstate transmission system are complex and, thus far, have eluded Commission
14 Constellation Comments at 45. 15 Option 6 involves a large load connecting as a network customer and bringing its own generation. PJM Show Cause Answer, Exhibit A.16 Constellation Comments at 45-46.17 Motion at 2. Constellation embellishes these requests in the Constellation Comments at 47-51.18 Constellation Energy Generation, LLC v. PJM Interconnection, L.L.C., Answer and Motion to Dismiss of PJM Interconnection, L.L.C., Docket No. EL25-20-000, at 12-16 (Dec. 12, 2024); PJM Show Cause Answer at 4 (“The record will support a finding that PJM’s existing Tariff remains just and reasonable.”).
PDF page 6
6
guidance and stakeholder consensus and are now the subject of a nationwide rulemaking. PJM appreciates Constellation’s participation in the CIFP process and other proceedings at FERC. But participation alone should not translate into pre-emption of orderly regulatory processes and collaborative, industry-wide efforts to inform the PJM Board of Managers’ action. After all, the Secretary of Energy sought a national rulemaking from the Commission, not a solution only applicable to one particular region.
The Commission should complete its ANOPR process by the April 30, 2026, date the Secretary of Energy has directed, and allow PJM’s CIFP process to reach a conclusion without foreclosing any options available to PJM’s Board.
CONCLUSION
For the foregoing reasons, the Commission should deny the Motion.
Respectfully submitted,
/s/ Andrew T. Swers
Craig Glazer
Vice President–Federal Government Policy
PJM Interconnection, L.L.C.
1200 G Street, N.W., Suite 600
Washington, D.C. 20005
(202) 423-4743
craig.glazer@pjm.com
Mark J. Stanisz
Associate General Counsel
PJM Interconnection, L.L.C.
2750 Monroe Blvd.
Audubon, PA 19403
(610) 666-8800
mark.stanisz@pjm.com
Ryan J. Collins
Andrew T. Swers
Wright & Talisman, P.C.
1200 G Street, N.W., Suite 600
Washington, D.C. 20005
(202) 393-1200
collins@wrightlaw.com
swers@wrightlaw.com
Attorneys for
PJM Interconnection, L.L.C.
December 5, 2025
PDF page 7
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, D.C., this 5th day of December 2025.
/s/ Andrew T. Swers
Andrew T. Swers
Wright & Talisman, P.C.
1200 G Street, N.W., Suite 600
Washington, D.C. 20005
(202) 393-1200
swers@wrightlaw.com
Attorney for
PJM Interconnection, L.L.C.