Answer of Exelon Corporation to the Motion for Expedited Action of Constellation Energy Generation, LLC,
PDF page 1
PUBLIC VERSION
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Docket No. AD24-11-000
Docket No. EL25-20-000
(consolidated)
ANSWER OF EXELON CORPORATION TO THE MOTION FOR EXPEDITED
ACTION OF CONSTELLATION ENERGY GENERATION, LLC
(PUBLIC VERSION)
Pursuant to Rule 2131 of the Rules of Practice and Procedure of the Federal Energy
Regulatory Commission ("FERC" or "Commission"), Exelon Corporation on behalf of its
subsidiaries2 (collectively, "Exelon") submits this Answer to the Motion for Expedited Action that was filed by Constellation Energy Generation, LLC ("Constellation") on November 21, 2025 ("Constellation's Motion").3
For the reasons discussed in the Answer of the Indicated PJM Interconnection, L.L.C. ("PJM") Transmission Owners to Constellation's Motion, the Commission should reject
Constellation's Motion.4 Exelon also files this Answer to correct any misapprehension regarding 1
See 18 C.F.R. § 385.213(d)(1) ("Any answer to a motion or to an amendment to a motion must be made within 15 days after the motion or amendment is filed, except as described below or unless otherwise ordered.'"). Exelon's subsidiaries are as follows: Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company ("ComEd"), Commonwealth Edison Company of Indiana, Inc., Delmarva Power and Light Company, PECO Energy Company ("PECO"), and Potomac Electric Power Company.
3 Constellation attached its comments filed in Docket No. RM26-4-000 to its motion in this proceeding. Exelon is not addressing all of the issues with that RM26-4-000 filing here and will respond to those comments in Docket No. RM26-4-000.4 See Answer of the Indicated PJM Interconnection, L.L.C. Transmission Owners (Dec. 8, 2025).
PDF page 2
PUBLIC VERSION
the ability of large loads and their load serving entities to receive transmission services in the Exelon service territories.
I. REQUEST FOR CUU/PRIVIIIIC TREATMENT
In accordance with section 388.112 of the Commission's regulations,5 Exelon requests privileged treatment for a portion of this Answer containing confidential information concerning pending retail customer service applications. Exelon understands that the involved customers may view this information as competitively sensitive and ComEd (the relevant Exelon utility) also treats such information as non-public. Accordingly, good cause exists for the Commission to grant this request for privileged treatment of this information.
Exelon is filing both a public version of this Answer with necessary redactions and a non- public version of this Answer that contains the confidential information. The non-public version has been labelled "CUI//PRIV//HC" and should be made subject to privileged document protection by the Commission. In accordance with 18 C.F.R. § 388.112(b)(2)(i), a proposed form of protective agreement modeled on the Commission's Model Protective Order is enclosed as Attachment A. To respect the competitive concerns of its customer, the Protective Order has been modified to provide additional protections for material deemed "Highly Confidential Privileged Material." Similar provisions have been included in other approved protective orders in recent years.' Any questions regarding this request for privileged treatment should be directed to the undersigned.
5 18 C.F.R. § 388.112. 6 See, e.g., PJ.,11 Interconnection, L.L.C., Docket No. ER23-2214-000, Order of Chief Judge Adopting Protective Order, at P 1 (Dec. 4, 2023) (adopting proposed protective order that "deviates from the Commission's Model Protective Order by deleting inapplicable provisions related to oil pipeline proceedings" and also "includes provisions to bar disclosure of commercially sensitive information to `Competitive Duty Personnel.'" (citation omitted)); DCR Transmission, L.L('., Docket No. ER23-2309-000, Order of Chief Judge Adopting Protective Order, at P 16 (Jan. 18, 2024); see also Duke Energy Progress, LLC, Docket No. ER25-3483-000, Application, (cont'd) 2
PDF page 3
PUBLIC VERSION
II. ANSWER
In its motion, Constellation points to the Commission's statement that there are "allegations in the record that Exelon has delayed work on Constellation's requests to co-locate load with its generators at certain facilities due to Exelon's concerns that such requests are not allowed under the [PJM Open Access Transmission Tariff ("PJM Tariff')] without arranging for wholesale transmission or retail distribution service."' To be clear, these are merely allegations. Exelon has not "delayed" or refused service in response to any lawful request.
In Attachment 1 of Exhibit 5 to Constellation's November 22, 2024 Complaint filed in Docket No. EL25-20-000,8 Constellation produced a November 12, 2024 letter from ComEd to Constellation concerning interconnection requests at the LaSalle and Byron nuclear facilities. In that letter, ComEd details certain design issues with Constellation's proposal and then explains that the "end use load is retail load under both Illinois and federal law and cannot be interconnected solely through amendments to the LaSalle or Byron [interconnection service agreements]."9 ComEd went on to explain:
We continue to believe there is no lawful path to interconnect end
use load at LaSalle and Byron without that load taking service as a
retail customer of ComEd and we cannot continue to review
proposals for co-location of end use load at LaSalle and Byron on
some other basis.1°
at Attach. G (Sept. 22, 2025) (protective order in Federal Power Act section 205 filing with Highly Confidential Privileged Material provisions).
See Constellation's Motion at 2 (citation omitted).
8
See Constellation, Complaint, Docket No. EL25-20. at Ex. 5 Attach. 1 (Nov. 22, 2024).
9 Id., Ex. 5 Attach. 1, at 2. 10 Id. 3
PDF page 4
PUBLIC VERSION
ComEd appropriately suggested that Constellation move forward by making the requested design changes and submitting "an application for retail service."11
The decision was left with
Constellation. ComEd cannot unilaterally provide retail electric service to a customer that does not request it.
Rather than deciding to move forward by then submitting an application for retail service (or attempting to challenge ComEd's assessment that this was retail service), Constellation instead decided to file its complaint seeking to change the PJM Tariff. Notwithstanding Constellation's allegations, the documentation submitted in this proceeding unambiguously shows that ComEd explained to Constellation how to move forward and how to do so expeditiously. It is Constellation that chose delay by disregarding Illinois retail regulation and established tariff mechanisms for entities that serve retail customers to obtain and ensure adequate transmission service. Constellation has chosen this path of litigation.
The tariff changes that Constellation seeks in the pending motion are not necessary for large load interconnection requests to move forward, regardless of whether the load is proposed to be co-located with a generator or not. To the contrary, those requests are moving forward expeditiously, including in the Exelon footprint. Exelon agrees that "Nile United States' ability to remain at the forefront of technological innovation depends on a reliable supply of energy from all available electric generation sources and the integrity of our Nation's electric grid."12 Indeed, Exelon is furthering those efforts. As shown in the chart below, Exelon' s service territories have been and are projected to continue to be a focal point for data center interconnection.
11 Id.12 Strengthening the Reliability & Security of the U.S. Electric Grid, Exec. Order No. 14,262, at Section 1 (Apr. 8, 2025), https://www.whitehouse.gov/presidential-actions/2025/04/strengthening-the-reliability-and-security-of- the-united-states-electric-grid/. 4
PDF page 5
VIILIC VERSION
Projected Data Center Load Growth in Exelon's Footprint
3
al Phase 3
Phase 2
Phase 1
l Awaiting Cluster Studies 12026.1
F l Active Modatlantic Cluster Study
I Active ComEd Cluster Study
Awaiting Signed ISM
6
1
04 22
O4 23
11
16
18+
r
-6
03 24
O424
Q3'25
Four,
Powwow
Addbons
OM.
Studies expected
to start in 2026
Studies expected
to conclude in
2026
Expected late
2025 / early 2026
Source of Chart: Exelon, Earnings Conference Call Third Quarter 2025, at 13 (Nov. 4, 2025), https://investors.exeloncorp.com/static-files/3a3d9993-324a-456f-9ffl-db901e7dacde. As explained by Max Leichtman, the Director of Economic and Workforce Development at ComEd, "ComEd has experienced an unprecedented number of applications for service from new customers with relatively large forecasted demand,"" and at the time of his direct testimony, ComEd had 75 unique projects totaling over 28,000 megawatts ("MW") of maximum demand, i.e., approximately 4,000 MW higher than ComEd's all-time system peak demand in its 118-year hi story.14 Moreover, the Leichtman testimony notes that "the average size of a unique large 13
Direct Testimony on behalf of Commonwealth Edison Company, Ill. Commerce Commission, Docket No. 25- 0679,
Ex.
1.0.
Direct
Testimony
of
Max
Leichtman,
at
3:58-59 (filed
Aug.
21,
2025),
https://www.icc.illinois.gov/docket/P2025-0679/documents/369551 (choose -2. ComEd Ex. 1.0" from list).
14 Id. at 6:108-111. 5
PDF page 6
PUBLIC VERSION
demand project that began the process of obtaining electric service from ComEd in the [twelve months prior to the testimony] [was] approximately 700 MWs, roughly equivalent to the demand of 1,400 big box retail stores."15
In ComEd's service territory, data center demand has grown at an annual rate of 27 percent through June 2025, and ComEd's most recent large load adjustment request to PJM included a future expected demand increase of 11 gigawatts ("GW") by 2040, 6 GW higher than ComEd's submission relative to the prior year.16 Moreover, the 2025 actuals year to date, as of September 30, 2025, for historical on-peak hourly demand for data centers in the ComEd service territory in Northern Illinois was 600 MW.17 The foregoing underscores that Exelon is actively engaged in furthering the objectives of the Administration in the artificial intelligence race. In 2025, ComEd has received more than 25 customer service applications associated with requests for large load interconnections, representing new load in excess of 20 GW. These applications are moving forward, showing that Constellation is seeking a solution to a problem that does not exist. <BEGIN CUI//PRIV//HC>
<END CUI//PRIV//HC> Any argument that co-located load applications are stalled or that the requested relief is somehow necessary to ensure that interconnections proceed is patently false.
15 Id. at 6:113-115.16 Exelon, Docket No. RM26-4-000, Comments at 2 (Nov. 21, 2025).17 See Exelon, Earnings Conference Call Third Quarter 2025, at 13 (Nov. 4, 2025), https://inve sto rs.e xelo nc o rp. com/static-files/3a3d9993-324a-456f-9ff1-db901e7dacde. 6
PDF page 7
PUBLIC VERSION
Further, to leave no doubt that Exelon is working to help interconnect data centers, last month, in Docket No. ER25-3492-000, FERC issued an Order Accepting Transmission Security Agreement, an agreement by and between PECO and Amazon Data Services, Inc. ("Amazon"). Amazon is constructing a new data center campus in Falls Township, Pennsylvania, and PECO will provide retail electric delivery services for the data center campus, pursuant to its electric retail service tariff on file with the Pennsylvania Public Utility Commission. In addition, Network Integrated Transmission Service will be procured by the responsible Load Serving Entity, as such term is defined in the PJM Tariff. The Transmission Security Agreement "ensures that a contribution to the transmission revenue requirement is made by Amazon commensurate with its requested end-use load relating to the construction of and service to its Data Center."18 This is another example of Exelon, in compliance with the PJM Tariff, providing a feasible path forward for data centers.
Constellation's Motion and requested PJM Tariff changes are unwarranted and should be denied.
18 PECO, Docket No. ER25-3492-000, Tariff Filing, Transmittal Letter at 1 (Sept. 23, 2025). 7
PDF page 8
PUBLIC VERSION
Respectfully submitted,
,'s/ William Sauer
William Sauer
Vice President, Federal Regulatory
Affairs
Exelon Corporation
701 Ninth St., NW
Washington, DC 20001
Telephone: 202-868-7499
Email:
william.sauer@exeloncorp.com
/s,' Max Minzner
Max Minzner
Senior Vice President & Deputy General Counsel - Corporate
Exelon Corporation
701 Ninth St., NW
Washington, DC 20001
Telephone: 202-934-4740
Email: max.minzner@exeloncorp.com
On behalf of Exelon Corporation
PDF page 9
PUBLIC VERSION
ATTACHMENT A
PDF page 10
PUBLIC VERSION
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Docket No. AD24-11-000
Docket No. EL25-20-000
(consolidated)
PROTECTIVE AGREEMENT
This Protective Agreement ("Agreement"), entered into this
day of
, 20_ by
and between Exelon Corporation on behalf of its subsidiaries' ("Exelon") and ("Intervenor"), shall govern the use of all Privileged, Highly Confidential Privileged Material, and/or Critical Energy/Electric Infrastructure Information ("CEII") Material produced by Exelon to Intervenor, or vice versa, in connection with the captioned proceeding before the Federal Energy Regulatory Commission (the "Commission"). Exelon and Intervenor are sometimes referred to herein individually as a "Participant" or jointly as the "Participants."
1. Exelon filed in the above-referenced proceeding Privileged Material, Highly Confidential Privileged Material, and/or CEII, as those terms are defined herein.
Intervenor is a
Participant in such proceeding, as the term Participant is defined in 18 C.F.R. Section 385.102(b), or has filed a motion to intervene or a notice of intervention in such proceeding. Exelon and Intervenor enter into this Agreement to govern the use of Privileged Material, Highly Confidential Privileged Material, and/or CEII produced by, or on behalf of, Exelon and/or Intervenor in the above-referenced proceeding.
Notwithstanding any order
terminating such proceeding, this Agreement shall remain in effect unless and until specifically modified or terminated by the Commission or a court of competent jurisdiction. In the event this Agreement terminates, the obligations of Reviewing Representatives to maintain the confidentiality of Privileged Material, Highly Confidential Privileged Material, and/or CEII as provided hereunder shall remain in effect for 18 months following the date of termination.
Exelon's subsidiaries are as follows: Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power and Light Company. PECO Energy Company, and Potomac Electric Power Company.
PDF page 11
PUBLIC VERSION
2. The Commission's regulations' and its policy governing the labelling of controlled unclassified information ("CUI")3 establish and distinguish the respective designations of Privileged Material and CEII. As to these designations, this Protective Agreement provides that a Participant:
A. may designate as Privileged Material any material which customarily is treated
by that Participant as commercially sensitive or proprietary or material subject
to a legal privilege, which is not otherwise available to the public, and which if
disclosed, would subject that Participant or its customers to risk of competitive
disadvantage or other business injury; and
B. must designate as CEII, any material that meets the definition of that term as
provided by 18 C.F.R. §§ 388.113(a), (c).
3. For the purposes of this Protective Agreement, the listed terms are defined as follows:
A. Participant(s): As defined at 18 C.F.R. § 385.102(b).
B. Privileged Material:4
i. Material (including depositions) provided by a Participant in response
to discovery requests or filed with the Commission, and that is
designated as Privileged Material by such Participant;5
ii. Material that is privileged under federal, state, or foreign law, such as
work-product privilege, attorney-client privilege, or governmental
privilege, and that is designated as Privileged Material by such
Participant;6
Compare 18 C.F.R. § 388.112, with 18 C.F.R. § 388.113. This Protective Agreement does not alter the respective requirements imposed by these sections on Privileged Material or CEII.
3 Notice of Document Labelling Guidance for Documents Submitted to or Filed with the Commission or Commission Staff, 82 Fed. Reg. 18,632 (Apr. 20, 2017) (issued by Commission Apr. 14, 2017).4 The Commission's regulations state that "[f]or the purposes of the Commission's filing requirements, non-CEII subject to an outstanding claim of exemption from disclosure under FOIA will be referred to as privileged material." 18 C.F.R. § 388.112(a). The regulations further state that "[f]or material filed in proceedings set for trial-type hearing or settlement judge proceedings, a participant's access to material for which privileged treatment is claimed is governed by the presiding official's protective order." Id. § 388.112(b)(2)(v).5 See infra P 11 for the procedures governing the labeling of this designation.6 The Commission's regulations state that "[a] presiding officer may, by order . . . restrict public disclosure of discoverable matter in order to . . . [p]reserve a privilege of a participant" 18 C.F.R. § 385.410(c)(3). To adjudicate such privileges, the regulations further state that "[i]n the absence of controlling Commission precedent, privileges will be determined in accordance with decisions of the Federal courts with due consideration to the Commission's need to obtain information necessary to discharge its regulatory responsibilities." Id. § 385.410(d)(1)(i). 2
PDF page 12
PUBLIC VERSION
iii. Any information contained in or obtained from such designated material;
iv. Any other material which is made subject to this Protective Agreement by the Presiding Administrative Law Judge (Presiding Judge) or the Chief Administrative Law Judge (Chief Judge) in the absence of the Presiding Judge or where no presiding judge is designated, the
Commission, any court, or other body having appropriate authority, or by agreement of the Participants (subject to approval by the relevant authority);
v. Notes of Privileged Material (memoranda, handwritten notes, or any other form of information (including electronic form) which copies or discloses Privileged Material);' or
vi. Copies of Privileged Material.
vii. Privileged Material does not include:
1. Any information or document that has been filed with and accepted into the public files of the Commission, or contained in the public files of any other federal or state agency, or any federal or state court, unless the information or document has been determined to be privileged by such agency or court; or
2. Information that is public knowledge, or which becomes public knowledge, other than through disclosure in violation of this
Protective Agreement.
C. Highly Confidential Privileged Material: A Participant may use this designation for those materials that are of such a commercially sensitive nature among the Participants or of such a private, personal nature that the producing Participant is able to justify a heightened level of confidential protection with respect to those materials. Highly Confidential Privileged Material shall include Privileged Material that present a higher risk of competitive injury if disclosed to Competitive Duty Personnel as determined in good faith by the producing Participant and includes materials such as: (1) information regarding contract negotiations and contract buyouts and (2) strategic business or financial plans. Except for the more limited list of persons who qualify as Reviewing Representatives for the purposes of Reviewing Highly Confidential Privileged Material (i.e., Reviewing Representatives that are not Competitive Duty Personnel), such materials are subject to the same provisions in the Protective Agreement as other Privileged Material.
Notes of Privileged Material are subject to the same restrictions for Privileged Material except as specifically provided in this Protective Agreement.
3
PDF page 13
PUBLIC VERSION
D. Critical Energy/Electric Infrastructure Information ("CEII"): As defined at 18 C.F.R. §§ 388.113(a), (c).
E. Non-Disclosure Certificate: The certificate attached to this Protective Agreement, by which Participants granted access to Privileged Material, Highly Confidential Privileged Material, and or CEII must certify their understanding that such access to such material is provided pursuant to the terms and restrictions of this Protective Agreement, and that such Participants have read the Protective Agreement and agree to be bound by it. All executed Non-Disclosure Certificates must be served on all Participants on the official service list maintained by the Secretary of the Commission for this proceeding.
F. Reviewing Representative: A person who has signed a Non-Disclosure Certificate and who is:
i. Commission Trial Staff designated as such in this proceeding;
ii. An attorney who has made an appearance in this proceeding for a Participant;
iii. Attorneys, paralegals, and other employees associated for purposes of this case with an attorney who has made an appearance in this
proceeding on behalf of a Participant;
iv. An expert or an employee of an expert retained by a Participant for the purpose of advising, preparing for, submitting evidence or testifying in this proceeding;
v. A person designated as a Reviewing Representative by order of the Presiding Judge, the Chief Judge, or the Commission; or
vi. Employees or other representatives of Participants appearing in this proceeding with significant responsibility for this docket.
G. The term "Reviewing Representative" for purposes of reviewing Highly Confidential Privileged Material defined in Paragraph 3(C) shall mean a person who has signed a Non-Disclosure Certificate who is:
i. Listed in Paragraph 3(F), but is not Competitive Duty Personnel as defined in Paragraph 3(H); or
ii. Designated as a Reviewing Representative for purposes of reviewing Highly Confidential Privileged Material by agreement of the producing Participant or by order of the Presiding Judge.
H. The term "Competitive Duty Personnel" shall mean any individual(s) whose scope of employment or engagement includes the marketing, sale, or purchase of coal, natural gas, or electricity (collectively, "Energy"), the direct
PDF page 14
PUBLIC VERSION
supervision of any employee or employees whose duties include the marketing of Energy, or other Energy services in competition with the producing
Participant, all of which are considered "Competitive Duties," except that Competitive Duty Personnel shall not include employees of the Commission, any state utilities commission which is a Participant, in-house or outside counsel, and/or an outside consultant retained by a Participant for the purpose of advising, preparing for, submitting evidence, or testifying in this proceeding.
4. Privileged Material, Highly Confidential Privileged Material, and/or CEII shall be made available under the terms of this Protective Agreement only to Participants and only to their Reviewing Representatives as provided in Paragraphs 6-10 of this Protective Agreement. The contents of Privileged Material, Highly Confidential Privileged Material, CEII or any other form of information that copies or discloses such materials shall not be disclosed to anyone other than in accordance with this Protective Agreement and shall be used only in connection with this specific proceeding.
5. All Privileged Material, Highly Confidential Privileged Material, and or CEII must be maintained in a secure place. Access to those materials must be limited to Reviewing Representatives specifically authorized pursuant to Paragraphs 7-9 of this Protective Agreement.
6. Privileged Material, Highly Confidential Privileged Material, and/or CEII must be handled by each Participant and by each Reviewing Representative in accordance with the Non- Disclosure Certificate executed pursuant to Paragraph 9 of this Protective Agreement. Privileged Material, Highly Confidential Privileged Material, and/or CEII shall not be used except as necessary for the conduct of this proceeding, nor shall they (or the substance of their contents) be disclosed in any manner to any person except a Reviewing Representative who is engaged in this proceeding and who needs to know the information in order to carry out that person's responsibilities in this proceeding. A Reviewing Representative shall not disclose Highly Confidential Privileged Material to Competitive Duty Personnel, except as authorized pursuant to Paragraph 3(G).
Reviewing
Representatives may make copies of Privileged Material, Highly Confidential Privileged Material, and/or CEII, but such copies automatically become Privileged Material, Highly Confidential Privileged Material, and/or CEII. Reviewing Representatives may make notes of Privileged Material, which shall be treated as Notes of Privileged Material if they reflect the contents of Privileged Material.
7. If a Reviewing Representative's scope of employment includes any of the activities listed under this Paragraph 7, such Reviewing Representative may not use information contained in any Privileged Material, Highly Confidential Privileged Material, and/or CEII obtained in this proceeding for a commercial purpose (e.g., to give a Participant or competitor of any Participant a commercial advantage):
A. Energy marketing;
B. Direct supervision of any employee or employees whose duties include energy marketing; or
5
PDF page 15
PUBLIC VERSION
C. The provision of consulting services to any person whose duties include energy marketing.
8. If a Participant wishes to designate a person not described in Paragraph 3(F) above as a Reviewing Representative, the Participant must seek agreement from the Participant providing the Privileged Material, Highly Confidential Privileged Material, and/or CEII. If an agreement is reached, the designee shall be a Reviewing Representative pursuant to Paragraph 3(E) of this Protective Agreement with respect to those materials. If no agreement is reached, the matter must be submitted to the Presiding Judge or the Commission for resolution.
9. A Reviewing Representative shall not be permitted to inspect, participate in discussions regarding, or otherwise be permitted access to Privileged Material, Highly Confidential Privileged Material, and/or CEII pursuant to this Protective Agreement until three business days after that Reviewing Representative first has executed and served a Non-Disclosure Certificate.8 However, if an attorney qualified as a Reviewing Representative has executed a Non-Disclosure Certificate, any participating paralegal, secretarial and clerical personnel under the attorney's instruction, supervision or control need not do so.
Attorneys
designated Reviewing Representatives are responsible for ensuring that persons under their supervision or control comply with this Protective Agreement, and must take all reasonable precautions to ensure that Privileged Material, Highly Confidential Privileged Material, and/or CEII are not disclosed to unauthorized persons. Reviewing Representatives that are Competitive Duty Personnel as defined in Paragraph 3(H) must execute a Non-Disclosure Certificate for Competitive Duty Personnel in the form attached hereto. All executed Non- Disclosure Certificates must be served on all Participants on the official service list maintained by the Secretary of the Commission for the proceeding.
10. Any Reviewing Representative may, consistent with the requirements in Paragraph 3(G), disclose Privileged Material, Highly Confidential Privileged Material, and/or CEII to any other Reviewing Representative as long as both Reviewing Representatives have executed a Non-Disclosure Certificate. In the event any Reviewing Representative to whom Privileged Material, Highly Confidential Privileged Material, and/or CEII are disclosed ceases to participate in this proceeding, or becomes employed or retained for a position that renders him or her ineligible to be a Reviewing Representative under Paragraph 3(F) of this Protective Agreement, access to such materials by that person shall be terminated. Even if no longer engaged in this proceeding, every person who has executed a Non-Disclosure Certificate shall continue to be bound by the provisions of this Protective Agreement and the Non-Disclosure Certificate for as long as the Protective Agreement is in effect.'
11. All Privileged Material, Highly Confidential Privileged Material, and/or CHI in this proceeding filed with the Commission, submitted to the Presiding Judge, or submitted to any
8 During this three-day period, a Participant may file an objection with the Presiding Judge or the Commission contesting that an individual qualifies as a Reviewing Representative, and the individual shall not receive access to the Privileged Material, Highly Confidential Privileged Material, and/or CEII until resolution of the dispute. 9 See infra P 19. 6
PDF page 16
PUBLIC VERSION
Commission personnel, must comply with the Commission's Notice of Document Labelling Guidance for Documents Submitted to or Filed with the Commission or Commission Staff' Consistent with those requirements:
A. Documents that contain Privileged Material must include a top center header on each page of the document with the following text: CUI//PRIV or
CUU/PRIV//HC for Highly Confidential Privileged Material.
Any
corresponding electronic files must also include this text in the file name.
B. Documents that contain CEII must include a top center header on each page of the document with the following text: CUI//CEII.
Any corresponding
electronic files must also include this text in the file name.
C. Documents that contain both Privileged Material and CEII must include a top center header on each page of the document with the following text:
CUU/CEII/PRIV. Any corresponding electronic files must also include this text in the file name.
D. The specific content on each page of the document that constitutes Privileged Material and/or CEII must also be clearly identified. For example, lines or individual words or numbers that include both Privileged Material and CEII shall be prefaced and end with "BEGIN CUU/CEII/PRIV" and "END
CUI//CEII/PRIV".
12. If any Participant desires to include, utilize, or refer to Privileged Material (or Highly Confidential Privileged Material) or information derived from Privileged Material (or Highly Confidential Privileged Material) in testimony or other exhibits during the hearing in this proceeding in a manner that might require disclosure of such materials to persons other than Reviewing Representatives, that Participant first must notify both counsel for the disclosing Participant and the Presiding Judge (or the Commission), and identify all such Privileged Material (or Highly Confidential Privileged Material). Thereafter, use of such Privileged Material (or Highly Confidential Privileged Material) will be governed by procedures determined by the Presiding Judge (or the Commission).
13. Nothing in this Protective Agreement shall be construed as precluding any Participant from objecting to the production or use of Privileged Material, Highly Confidential Privileged Material, and/or CEII on any appropriate ground.
14. Nothing in this Protective Agreement shall preclude any Participant from requesting the Presiding Judge (or the Chief Judge in the Presiding Judge's absence or where no presiding judge is designated), the Commission, or any other body having appropriate authority, to find this Protective Agreement should not apply to all or any materials previously designated Privileged Material (or Highly Confidential Privileged Material) pursuant to this Protective Agreement. The Presiding Judge (or the Chief Judge in the Presiding Judge's absence or where no presiding judge is designated), the Commission, or any other body having appropriate 10
82 Fed. Reg. 18,632 (Apr. 20, 2017) (issued by Commission Apr. 14, 2017). 7
PDF page 17
PUBLIC VERSION
authority may alter or amend this Protective Agreement as circumstances \\ arrant at any time during the course of this proceeding.
15. Each Participant governed by this Protective Agreement has the right to seek changes in it as appropriate from the Presiding Judge (or the Chief Judge in the Presiding Judge's absence or where no presiding judge is designated), the Commission, or any other body having appropriate authority.
16. Subject to Paragraph 17, the Presiding Judge (or the Chief Judge in the Presiding Judge's absence or where no presiding judge is designated), or the Commission shall resolve any disputes arising under this Protective Agreement pertaining to Privileged Material (or Highly Confidential Privileged Material) according to the following procedures. Prior to presenting any such dispute to the Presiding Judge, the Chief Judge or the Commission, the Participants to the dispute shall employ good faith best efforts to resolve it.
A. Any Participant that contests the designation of material as Privileged Material (or Highly Confidential Privileged Material) shall notify the Participant that provided the Privileged Material (or Highly Confidential Privileged Material) by specifying in writing the material for which the designation is contested.
B. In any challenge to the designation of material as Privileged Material (or Highly Confidential Privileged Material), the burden of proof shall be on the Participant seeking protection. If the Presiding Judge, the Chief Judge, or the Commission finds that the material at issue is not entitled to the designation, the procedures of Paragraph 17 shall apply.
C. The procedures described above shall not apply to material designated by a Participant as CEII.
Material so designated shall remain subject to the
provisions of this Protective Agreement, unless a Participant requests and obtains a determination from the Commission's CEII Coordinator that such material need not retain that designation.
17. The designator will have five (5) days in which to respond to any pleading requesting disclosure of Privileged Material (or Highly Confidential Privileged Material). Should the Presiding Judge, the Chief Judge, or the Commission, as appropriate, determine that the information should be made public, the Presiding Judge, the Chief Judge, or the Commission will provide notice to the designator no less than five (5) days prior to the date on which the material will become public. This Protective Agreement shall automatically cease to apply to such material on the sixth (6th) calendar day after the notification is made unless the designator files a motion with the Presiding Judge, the Chief Judge, or the Commission, as appropriate, with supporting affidavits, demonstrating why the material should continue to be privileged. Should such a motion be filed, the material will remain confidential until such time as the interlocutory appeal or certified question has been addressed by the Motions Commissioner or the Commission, as provided in the Commission's regulations, 18 C.F.R. §§ 385.714 and 385.715. No Participant waives its rights to seek additional administrative or judicial remedies after a Presiding Judge or Chief Judge decision regarding Privileged Material (or Highly Confidential Privileged Material) 8
PDF page 18
PUBLIC VERSION
or the Commission's denial of any appeal thereof or determination in response to any certified question. The provisions of 18 C.F.R. §§ 388.112 and 388.113 shall apply to any requests under the Freedom of Information Act (5 U. S.C. § 552) for Privileged Material (or Highly Confidential Privileged Material) and/or CEII in the files of the Commission.
18. Privileged Material, Highly Confidential Privileged Material, and/or CEII shall remain available to Participants until the later of 1) the date an order terminating this proceeding no longer is subject to judicial review, or 2) the date any other Commission proceeding relating to the Privileged Material, Highly Confidential Privileged Material, and/or CEII is concluded and no longer subject to judicial review. After this time, the Participant that produced the Privileged Material, Highly Confidential Privileged Material, and/or CEII may request (in writing) that all other Participants return or destroy the Privileged Material, Highly Confidential Privileged Material, and/or CEII. This request must be satisfied with within fifteen (15) days of the date the request is made. However, copies of filings, official transcripts and exhibits in this proceeding containing Privileged Material, Highly Confidential Privileged Material, or Notes of Privileged Material, may be retained if they are maintained in accordance with Paragraph 5 of this Protective Agreement. If requested, each Participant also must submit to the Participant making the request an affidavit stating that to the best of its knowledge it has satisfied the request to return or destroy the Privileged Material, Highly Confidential Privileged Material, and/or CEII. To the extent Privileged Material, Highly Confidential Privileged Material, and/or CHI are not returned or destroyed, they shall remain subject to this Protective Agreement.
19. Regardless of any order terminating this proceeding, this Protective Agreement shall remain in effect until specifically modified or terminated by the Presiding Judge, the Chief Judge, or the Commission. All CEII designations shall be subject to the "[d]uration of the CEII designation" provisions of 18 C.F.R. § 388.113(e).
20. Any violation of this Protective Agreement and of any Non-Disclosure Certificate executed hereunder shall constitute a violation of an order of the Commission.
9
PDF page 19
PUBLIC VERSION
For Exelon:
Signed:
Printed Name:
Date:
For Inter enoi .
Signed:
Printed Name:
Date:
10
PDF page 20
PUBLIC VERSION
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
Docket No. EL25-49-000
Docket No. AD24-11-000
Docket No. EL25-20-000
(consolidated)
NON-DISCLOSURE CERTIFICATE FOR NON-COMPETITIVE DUTY PERSONNEL
I hereby certify my understanding that access to Privileged Material, Highly Confidential Privileged Material, and/or Critical Energy/Electric Infrastructure Information (CEII) i s provided to me pursuant to the terms and restrictions of the Protective Agreement in this proceeding, that I have been given a copy of and have read the Protective Agreement, and that I agree to be bound by it. I understand that the contents of Privileged Material, Highly Confidential Privileged Material, and/or CEII, any notes or other memoranda, or any other form of information that copies or discloses such materials, shall not be disclosed to anyone other than in accordance with the Protective Agreement. I acknowledge that a violation of this certificate constitutes a violation of an order of the Federal Energy Regulatory Commission.
By:
Printed Name:
Title:
Representing:
Date:
PDF page 21
PUBLIC VERSION
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v. PIM Interconnection, L.L.C.
Docket No. EL25-49-000
Docket No. AD24-11-000
Docket No. EL25-20-000
(consolidated)
NON-DISCLOSURE CERTIFICATE
FOR COMPETITIVE DUTY PERSONNEL
I hereby certify my understanding that access to Privileged Material in the above-captioned case is provided to me pursuant to the terms and restrictions of the Protective Agreement in this proceeding, that I have been given a copy of and have read the Protective Agreement, and that I agree to be bound by it. I understand that the contents of Privileged Material, any notes or other memoranda, or any other form of information that copies or discloses Privileged Material shall not be disclosed to anyone other than in accordance with the Protective Agreement and shall be used only in connection with this proceeding. I acknowledge that my duties and responsibilities include "Competitive Duties" as described in the Protective Agreement and, as such, I understand that I shall neither have access to, nor disclose, the contents of the Highly Confidential Privileged Material that are marked as "CUI//PRIVAIC," any notes or other memoranda, or any other form of information that copies or discloses Privileged Material that is marked as "CUI//PRIV//HC." I acknowledge that a violation of this certificate constitutes a violation of an order of the Federal Energy Regulatory Commission.
By:
Printed Name:
Title:
Representing:
Date:
PDF page 22
PUBLIC VERSION
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list in the above captioned dockets. Dated this 8th day of December, 2025.
s Alejandro Bautista
Alejandro Bautista
Assistant General Counsel
Exelon Corporation
2301 Market Street
Philadelphia, PA 19101
Telephone: 267-533-0120
Email: Alejandro.Bautista@exeloncorp.com