EL25-49-000 · 2026-01-20 · Constellation Energy Generation, LLC
Answer of Constellation Energy Generation, LLC in Opposition to the Indicated PJM Transmission Owners' Motion for Extension of Time
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
Docket No. EL25-49-000
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
ANSWER OF CONSTELLATION ENERGY GENERATION, LLC
IN OPPOSITION TO THE INDICATED PJM TRANSMISSION OWNERS’
MOTION FOR EXTENSION OF TIME
Constellation respectfully opposes1 the Indicated Transmission Owners’ motion to delay
compliance2 with the Commission’s order establishing rules to promptly interconnect large loads in the PJM region.3 The TOs seek a thirty (30) day extension of time for submission of
(i) compliance filings due 60 days from the date of the order; and (ii) initial and reply briefs in the paper hearing that the Commission established in the December Order.4 The Commission should deny the TO’s Motion for three reasons.
1 Constellation Energy Generation, LLC (“Constellation”) files this answer pursuant to Rule 213 of the Commission’s Rules of Practice and Procedure. See 18 C.F.R. § 385.213.2 Motion for Extension of Time, Shortened Answer Period, and Request for Expedited Action of the Indicated PJM Transmission Owners in the above-captioned proceedings (filed January 14, 2026) (the “TO’s Motion”).3 Per PJM Interconnection. L.L.C., 193 FERC ¶ 61,217, at Ordering Clause (C) (2025) (“December Order”) the applicable tariff revisions are due 60 days from the December Order, or February 16, 2026.4 TO’s Motion at n. 12: “currently initial briefs are due on or before February 16, 2026 with responses to initial briefs due March 18, 2026, and the replies to those responses due April 17, 2026. Under the 30-day extension, initial briefs would be due on March 18, 2026, responses to initial briefs would be due on April 17, 2026, and the replies to those responses would be due May 18, 2026.”
PDF page 2
2
First, the Commission’s 60-day deadline was appropriate in the circumstances given the national imperative to facilitate the prompt interconnection of large loads and the long delays in doing so in PJM. The Commission’s timeline is consistent with the Secretary of Energy’s proposed ANOPR and the Secretary’s statement that the interconnection of large loads to the transmission system—the subject of both the ANOPR and this show cause proceeding—“is an urgent issue that requires prompt attention.”5 The Commission’s compliance deadlines require timely action to break the logjam on serving these critical large loads.
Second, the TO’s interest in delaying compliance is troubling in light of positions
Commonwealth Edison Company (“ComEd”)6 has taken in Illinois where ComEd asserts that its rates need not reflect the new Commission-mandated transmission services because these are not yet final and unappealable.7 ComEd’s approach would simply ignore the current circumstance, which is that the Commission has found the existing rate structure where there is only a single, gross wholesale transmission rate to be unjust and unreasonable and directed replacement rates. Among other things, the replacement rates include a new class of interruptible or non-firm wholesale transmission service which, in turn, could reduce collateral and deposit requirements to take service from ComEd. The TOs’ attempts to delay compliance in the Commission’s docket
5 On October 23, 2025, the Secretary of Energy proposed an ANOPR under section 403 of the Department of Energy Organization Act, 42 U.S.C. § 7173(a). U.S. Department of Energy, Secretary of Energy, Letter to FERC re: “Ensuring the Timely and Orderly Interconnection of Large Loads,” Advance Notice of Proposed Rulemaking (Oct. 23, 2025) (issued pursuant to Department of Energy Organization Act § 403, 42 U.S.C. § 7173) (cover letter, “Secretary’s Letter,” and Advanced Notice of Proposed Rulemaking, “ANOPR”); see Secretary’s Letter at 1.6 ComEd’s parent, Exelon, joined the TO’s Motion.7 ComEd Response to the Constellation’s Motion To Reopen The Evidentiary Record in IL ICC Docket Nos. 25-0677 and 25-0679, p. 6 (Jan. 8, 2026) (“[t]he proposed retail tariff ensures that large load customers contribute revenue in accordance with their load requests … regardless of any changes FERC might or might not make to the design of transmission rates applicable to any particular transmission customer.”) (“ComEd January 8 Response”).
PDF page 3
3
thus are consistent with their efforts to avoid updating their rate structures until there is a final Commission order. Such delays are contrary to the December Order8 and the Federal Power Act.9 Finally, prompt compliance in this proceeding in PJM is also critical because the record reflects that Transmission Owners have long benefited by delaying existing large load co-location requests unless customers agree in advance to take both transmission and distribution service from them.10 The TO’s Motion now seeks further delay.
For all the above reasons, Constellation opposes the TO’s Motion. The Commission should
deny the motion and continue with the deadlines as established in the December Order.
8 See News Release, FERC Directs Nation’s Largest Grid Operator to Create New Rules to Embrace Innovation and Protect Consumers, (Dec. 18, 2025) available at https://www.ferc.gov/news-events/news/ferc-directs-nations- largest-grid-operator-create-new-rules-embrace-innovation-and (“As technology leaps forward, clear and fair regulations must keep pace to support advancement, help prevent price volatility, and promote competition, ultimately benefiting consumers by keeping electricity costs manageable.”); see also December Order, Commissioner Rosner Concurring (“a business-as-usual approach to load growth—planning for generation and load separately—will not suffice to timely meet growing demand while also keeping prices reasonable. Today’s order helps break the logjam.”).9 See 16 U.S.C. § 825l(c) (providing that the filing of an application for rehearing shall not, unless specifically ordered by the Commission, operate as a stay of the Commission’s order). In ComEd’s January 8 Response, ComEd alleges that until the Commission issues an order on compliance, “no actionable framework is in effect.” ComEd January 8 Response at p.6. ComEd is incorrect. Unless and until the December Order is set aside, it is a final order that binds PJM, the TOs, and other market participants unless and until the Commission or a court of appeals determines otherwise.10 See Constellation Complaint at 6-9 (citing Protest of Constellation Energy Generation, LLC, Docket No. EL24- 149-000, Exh. 2 (correspondence with Exelon) (filed Oct. 30, 2024); Motion to Lodge of Constellation Energy Generation, LLC, Docket No. EL24-149-000, Exh. 1 (November 12, 2024 Exelon Letter) (filed Nov. 18, 2024)); see also Constellation Complaint, Exh. 5, Declaration of James R. McCoskey (detailing interaction with Exelon to study co-location projects); see also Atl. City Elec. Co., 190 FERC ¶ 61,109 (2025) (rejecting Exelon Transmission Owners’ attempt to force all co-located load to take full transmission service).
PDF page 4
4
Respectfully submitted,
/s/ Paul F. Wight
January 20, 2026
Carrie Hill Allen
Sr. Vice President & Deputy General Counsel Seth Lucia
Assistant General Counsel
Constellation Energy Generation, LLC 250 Massachusetts Ave. NW, Suite 760 Washington, D.C. 20001
carrie.allen@constellation.com
seth.lucia@constellation.com
Christopher A. Wilson
Managing Director, Federal Regulatory Affairs Constellation Energy Generation, LLC 250 Massachusetts Ave. NW, Suite 760 Washington, D.C. 20001
202-347-7500
FERCe-filings1@constellation.com
Paul F. Wight
Carolyn E. Clarkin
DLA Piper LLP (US)
500 Eighth Street NW
Washington, D.C. 20004
703-773-4058
paul.wight@us.dlapiper.com
carolyn.clarkin@us.dlapiper.com
Sophia Browning
DLA Piper LLP (US)
4365 Executive Drive
San Diego, CA 92121
858-677-1455
sophia.browning@us.dlapiper.com
Counsel for Constellation Energy
Generation, LLC
PDF page 5
5
CERTIFICATE OF SERVICE
I hereby certify that I have on this 20th day of January 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010.
/s/ Sophia Browning
Sophia Browning
DLA Piper LLP (US)
4365 Executive Drive
San Diego, CA 92121
858-677-1455
sophia.browning@us.dlapiper.com