EL25-49-000 · 2026-01-20 · PJM Interconnection, L.L.C.

PJM Interconnection, L.L.C. submits Informational Report addressing several categories of requested information in response to FERC’s 12/18/2025 Order

PDF page 1

PJM Interconnection, L.L.C.
2750 Monroe Boulevard
Audubon, PA 19403
Mark. J. Stanisz
Associate General Counsel
T:  (610) 666-4707 ǀ F:  (610) 666-8211
mark.stanisz@pjm.com
January 20, 2026
Honorable Debbie-Anne A. Reese, Secretary
Federal Energy Regulatory Commission
888 First Street, N.E., Room 1A
Washington, D.C. 20426-0001
Re:
PJM Interconnection, L.L.C., Docket Nos. EL25-49-000 and -001
Informational Report
Dear Secretary Reese:
On December 18, 2025, the Federal Energy Regulatory Commission (“Commission”)
issued an order in part directing PJM Interconnection, L.L.C. (“PJM”) to submit an informational report addressing several categories of requested information.1 PJM submits this informational filing and encloses the PJM Board of Managers’ January 16, 2026 decisional letter2 outlining next steps resulting from the Critical Issue Fast Path (“CIFP”) – Large Load Additions stakeholder process.

I. INFORMATIONAL FILING
Among other things, the Order directs PJM to submit an informational filing to address several issues relating to the CIFP stakeholder process3 and associated efforts to maintain system

1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (the “Order”), at PP 237–39 (2025).
2 PJM Board Letter Regarding Results of the Critical Issue Past Path (CIFP) Process - Large Load Additions (Jan. 16, 2026) (the “Decisional Letter”, attached as Exhibit A), at: https://www.pjm.com/-/media/DotCom/about-pjm/who- we-are/public-disclosures/2026/20260116-pjm-board-letter-re-results-of-the-cifp-process-large-load-additions.pdf.
3 PJM, Critical Issue Fast Path – Large Load Additions, https://www.pjm.com/committees-and-groups/cifp-lla.

PDF page 2

The Honorable Debbie-Anne A. Reese, Secretary
January 20, 2026
Page 2

reliability while increasing the “pace of adding generating capacity in the PJM region.”4 PJM addresses each request as follows.

First, the Commission requested information about the “status of the proposals considered in the CIFP stakeholder process, including—but not limited to—the status of the expedited interconnection process to enable shovel-ready generation projects to serve PJM more quickly, modifications to PJM’s reliability backstop mechanism to improve PJM’s ability to respond to acute resource adequacy shortfalls, and the development of enhanced load forecasting and demand flexibility measures to assist PJM in determining the amount of new capacity that is needed to maintain system reliability.”5 In this regard, the Order refers to PJM’s October 20, 2025 letter to then-Chairman Rosner’s letter on load forecasting, and it instructs PJM to “expand on its response to then-Chairman Rosner . . . by explaining, in detail, any changes or updates to its load forecasting processes that it is considering.”6

PJM Response:  PJM directs the Commission to the PJM Board’s January 16, 2026 decisional letter enclosed as Exhibit A.  Among other things, this letter announces the following PJM actions that are specifically responsive to the informational filing directive:

• Load forecasting:  continued implementation of significant load forecasting improvements (many of which are already implemented) relating to state review, addressing duplicative load requests, load forecast benchmarking which may

include third party review, enhanced transparency expectations that will require sharing necessary information with PJM related to large loads, additional Load

4 Order at P 238.
5 Id.
6 Id. at n.487.

PDF page 3

The Honorable Debbie-Anne A. Reese, Secretary
January 20, 2026
Page 3

Analysis Subcommittee enhancements, and engagement with Electric Distribution Companies and Load Serving Entities to improve large load modeling assumptions around ramp rate and utilization (see Decisional Letter, pages 2-3 and Appendix B which sets forth applicable design components).

• Expedited interconnection process:  imminent filing with the Commission, following stakeholder review of proposed tariff language, to effectuate a voluntary Bring Your Own New Generation (“BYONG”) construct paired with an Expedited Interconnection Track (see Decisional Letter, pages 3-4 and Appendix C which sets forth applicable design components).

• Reliability backstop mechanism:  initiation of Reliability Backstop Procurement following stakeholder engagement to develop potential changes to the design of the procurement process (see Decisional Letter, pages 5-6).

• Demand flexibility measures:  following additional stakeholder process, implementation of a “Connect and Manage” construct for new large load additions that do not BYONG, whereby the incremental demand associated with such load growth would be subject to curtailment prior to the deployment of pre-emergency Demand Respond (see Decisional Letter, pages 4-5).

Further, the Order requests a “detailed schedule of key milestones, such as stakeholder or PJM Board votes, that includes the estimated date on which PJM expects to file any such proposals with the Commission.”7

7 Id. at P 238.

PDF page 4

The Honorable Debbie-Anne A. Reese, Secretary
January 20, 2026
Page 4

 PJM Response:  PJM directs the Commission to the PJM Board’s January 16, 2026 decisional letter enclosed as Exhibit A.  By way of further response, PJM provides the following response:

• Load forecasting:  PJM will continue to implement the PJM Board-directed load forecasting improvements.  These enhancements will be addressed using PJM’s existing authority through the Manuals, and PJM will review any specific language revisions with stakeholders in the February 2026 time period.  PJM does not anticipate needing to make a filing with the Commission to implement these enhancements.

• Expedited interconnection process:  PJM has already drafted the proposed Expedited Interconnection Track tariff language and intends to review the proposed tariff revisions with stakeholders on January 27, 2026 prior to filing with the Commission on or about January 30, 2026.  The Expedited Interconnection Track is anticipated to be in place by August 2026, subject to Commission acceptance.

• Reliability backstop mechanism:  The PJM Board is directing stakeholders to give immediate attention to discussing the design of the reliability backstop procurement mechanism in the tariff.  The process and deadlines for action will be discussed at the January 22, 2026 Members Committee meeting.  The PJM Board intends that the backstop be instituted as soon as practicable which may require changes to the current tariff.  Among other things, the stakeholder process will also be informed by the January 16, 2026-released “Statement of Principles Regarding PJM” endorsed by the White House National Energy Dominance Council and Governors of the PJM States, and consider the implementation of these Principles in enhancing

PDF page 5

The Honorable Debbie-Anne A. Reese, Secretary
January 20, 2026
Page 5

PJM’s reliability backstop procurement mechanism.8  By February 27, 2026, PJM will supplement this filing with additional detail regarding the timeline and process necessary to move forward expeditiously on revisions to the backstop procurement tariff construct and the timing of commencing the revised backstop procurement process following stakeholder review of the Decisional Letter and Principles, as well as stakeholder discussion on implementation.

• Demand flexibility measures:  Regarding the implementation of the “Connect and Manage” construct for new large load additions that do not BYONG, the PJM Board is directing that the requisite load shed prioritization and allocation should be completed as soon as practicable. The PJM Board is directing that this matter first be addressed via the Consensus Based Issue Resolution (“CBIR”) process, and the PJM Board is asking that the stakeholders proceed expeditiously such that changes are in place by the end of 2026.  The PJM Board will continue to monitor the progress of this stakeholder effort to determine whether to initiate an accelerated stakeholder process.

In addition, the Order directs “PJM to identify any problem statements, issue charges, or other ongoing stakeholder processes that aim to increase the pace of adding generating capacity in the PJM region.”9 It requests that PJM “provide as detailed a schedule as is feasible on the timing of such initiatives, including updates on the stakeholder process and approximate dates of any

8 Department of Energy, Statement of Principles Regarding PJM (Jan. 16, 2026), at: https://www.energy.gov/documents/statement-principles-regarding-pjm (the “Principles”).
9 Id.

PDF page 6

The Honorable Debbie-Anne A. Reese, Secretary
January 20, 2026
Page 6

anticipated filings with the Commission.”10  The Order also requires that this informational report “identify specifically which of these initiatives would support the addition, on an expedited basis, of new generation that is sufficient to serve large loads, like data centers, while meeting PJM’s near-term system resource adequacy needs.”11  Finally, the Order directs PJM to “explain the proposed effective date of any proposal that it intends to file so that the Commission can understand whether any of those proposals could be in place by the 2028/2029 Base Residual Auction (BRA) and subsequent BRAs to attract sufficient new generation to maintain regional resource adequacy.”12

PJM Response:  In response to these requests, the following proposals are or can be in place by the 2028/2029 Base Residual Auction (BRA) and subsequent BRAs:

• The Expedited Interconnection Track proposal will be imminently filed with the Commission.  If accepted, PJM will implement that mechanism with utmost haste by or before the summer of 2026.

•  PJM already has in place, and will continue to implement, load forecast enhancements that are having a demonstrable impact on load projections in the PJM Region.  On January 14, 2026, PJM posted its 2026 Load Forecast Report which confirms the trend of significant growth in demand over the next 20 years but reflects a decrease in the expected load growth for near-term years compared with PJM’s 2025 load forecast analysis.13

10 Id.
11 Id.
12 Id. at P 239.
13 2026 PJM Load Forecast Report (Jan. 14, 2026), at:  https://www.pjm.com/-/media/DotCom/library/reports- notices/load-forecast/2026-load-report.pdf.

PDF page 7

The Honorable Debbie-Anne A. Reese, Secretary
January 20, 2026
Page 7

• In response to disappointing performance from load management resources that were dispatched in the summer of 2025 and the expectation that PJM will likely need to dispatch load management more frequently due to the lower reserve

margins, PJM initiated a stakeholder process to explore opportunities to incentivize better performance from load management resources.14  PJM is aiming to

implement such enhancements effective with the 2028/2029 Delivery Year and will endeavor to submit a filing with the Commission for approval prior to conducting the Base Residual Auction associated with the 2028/2029 Delivery Year.

Further, PJM identifies the following additional problem statements, issue charges, or other ongoing stakeholder processes (and, to the extent now known, schedules associated therewith) that aim to increase the pace of adding generating capacity in the PJM region:

• In the fall of 2025, PJM initiated a stakeholder process to identify under what circumstances generation projects that advance to the Phase III of a Cycle may be permitted to safely and reliably begin generating prior to the completion of certain Cycle studies without impacting the timing or fundamentally altering PJM’s Generation Interconnection Procedures (“GIP”).  This stakeholder process is seeking to expand PJM’s existing provisional service process to include projects in Phase III that meet particular criteria to generate on an energy-only basis.15

14 See PJM Problem/Opportunity Statement, Load Management and PRD Event Performance, at: https://www.pjm.com/-/media/DotCom/committees-groups/committees/mic/2025/20251203/20251203-item-07-1--- load-management--prd-event-performance---problem-statement.pdf.
15 See PJM’s Issue Tracker, Expansion of Provisional Service, at https://www.pjm.com/committees-and-groups/issue- tracking/issue-tracking-details.aspx?Issue=23fc7fe8-f851-4a46-b2aa-33ea23b606b7 (setting forth the timeline for target completion by July 2026 and additional details); see also Interconnection Process Subcommittee meeting materials (November 11.24.2025) (presenting the Problem Statement, Issue Charge, and Work Plan); see also

PDF page 8

The Honorable Debbie-Anne A. Reese, Secretary
January 20, 2026
Page 8

• Since 2023, PJM has explored potential reforms to the reserve market to better incentivize the appropriate suite of ancillary service products coupled with the confidence that resources with reserve assignments will actually perform when called upon.16 After the years-long stakeholder discussions, PJM is aiming to seek a vote on the final package(s) that emerge through this process in September 2026, with a potential filing with the Commission before the end of the year.

By way of further response, the PJM Board has directed PJM to perform a holistic review of investment incentives in PJM’s Markets.  This review is to be completed in the first half of 2026.  Thereafter, PJM Staff will engage with stakeholders to formulate a workplan to implement recommendations made from the analysis.  The PJM Board is directing that the workplan be presented to the PJM Board with a recommendation for accelerated stakeholder processes to expeditiously implement the recommendations set forth in the analysis.

PJM will continue to update the Commission on the timing of initiatives outlined in this letter after additional near term consultations with stakeholders on the need for prioritization of these activities.

Interconnection Process Subcommittee meeting materials (December 18, 2025) (including the education regarding provisional service).  Please note that “provisional service” is also referred to as “interim deliverability.”

16 See PJM Problem/Opportunity Statement, Reserve Certainty, at: https://www.pjm.com/- /media/DotCom/committees-groups/task-forces/rcstf/postings/problem-statement.pdf.

PDF page 9

The Honorable Debbie-Anne A. Reese, Secretary
January 20, 2026
Page 9

II. CONCLUSION

PJM respectfully requests the Commission accept this informational filing.

Respectfully submitted,

By:   /s/ Mark J. Stanisz
Craig Glazer
Vice President–Federal Government Policy
PJM Interconnection, L.L.C.
1200 G Street, N.W, Suite 600
Washington, D.C. 20005
(202) 423-4743
craig.glazer@pjm.com

Mark J. Stanisz
Associate General Counsel
PJM Interconnection, L.L.C.
2750 Monroe Blvd.
Audubon, Pennsylvania 19403
(610) 666-4707
mark.stanisz@pjm.com

PDF page 10

EXHIBIT A

PDF page 11

610.666.8980 | www.pjm.com
David Mills
Interim President & CEO
PJM Interconnection
2750 Monroe Blvd.
Audubon, PA 19403
January 16, 2026

Dear Stakeholders,
Board Decisional Letter on Critical Issue Fast Path - Large Load Additions
At the outset, the PJM Board of Managers (Board) would like to thank you for your participation in the Critical Issue Fast Path (CIFP) accelerated stakeholder process for large load additions. Board members were able to listen in on each step of the CIFP, and the Board appreciated the opportunity to ask questions of presenters during the final stage. After significant deliberation, the Board is issuing this decisional letter that reflects components of the various presentations. Specific elements of presentations are credited in this letter, with the name of the presenter’s organization highlighted in bold print.1

Executive Summary
The Board’s decision consists of the following components, some of which will serve as transitional measures while the industry and government collectively work to bring more supply to the system to meet an unprecedented growth in demand. This is a dynamic period in the industry, and as such, the decisions made here can be revisited based on a series of factors, namely whether the region’s supply/demand balance and reserve margin are restored to a level that comfortably ensures resource adequacy for existing consumers and large load aditions. The primary components of the Board’s decision are as follows, with a deeper explanation of each found within the body of this letter.

•
Significant Load Forecasting Improvements
•
Voluntary Bring Your Own New Generation (BYONG) Paired With Expedited Interconnection Track
•
Connect and Manage for New Large Load Additions That Do Not BYONG and Curtailment Prior to
Emergency Demand Response in Circumstances Necessitating Load Shed
•
Immediate Initiation of Reliability Backstop Procurement
•
Holistic Review of Investment Incentives in PJM’s Markets in 2026
•
Feedback Request on Price Collar for 2028/2029 and 2029/2030 Capacity Auctions
Framing the Board’s Review
The Board analyzed the various proposals through a particular frame that we thought would be helpful to explain. That frame begins with the organization’s mandate to maintain grid reliability. As the results of the 2027/2028 Base Residual Auction (BRA) display, the RTO has cleared short of its reliability requirement for the first time in history. The 2027/2028 BRA cleared 5.6% short of our target reserve margin indicating that the system is at higher risk than

1 This correspondence satisfies the requirements of Manual 34 Section 8.6.4, and also represents the Board’s response to the many thoughtful letters it received during the pendency of the CIFP, a list of which is attached here as Appendix A.

PDF page 12

January 16, 2026
Page 2
610.666.8980 | www.pjm.com
previous years. The Board views this outcome as a clear signal that current trends are not acceptable and warrant corrective action.

Reliability is PJM’s primary responsibility, and our Operating Agreement is clear that advancing competitive markets is also part of our charge. PJM continues to believe in the benefits of well-functioning competitive markets as these markets have saved consumers billions of dollars pursuant to our value proposition calculations. We will continue to leverage markets to pursue cost-efficient outcomes for consumers.

The Board recognizes the expressed interests at both the federal and state levels in facilitating the timely interconnection of large loads to support continued economic and digital-sector growth. At this time, the Board is not taking action to restrict the interconnection of new load through the creation of a dedicated load interconnection queue or through other limiting measures.

Where PJM can support regional growth while maintaining system reliability and ensuring rates remain just and reasonable, the Board believes it is appropriate to pursue those outcomes. The Board also notes, consistent with the Federal Energy Regulatory Commission’s (FERC) recent colocation determination, the significant role of the states and their jurisdiction over the interconnection of retail load.

Further, as a mission-driven organization that fundamentally exists as part of a larger system serving consumers, PJM must be conscious of the affordability challenges facing the 67 million consumers in our footprint today. There is much that our states can be doing to contend with higher wholesale costs at the retail level.2 At the same time, as the market administrator, PJM should seek to balance the design of its markets to simultaneously set transparent prices that incent the desired behavior from market participants while not being punitive to consumers. It is with these critical elements in mind that the Board analyzed all proposals set forth during CIFP Stage 4 and hereby directs the staff to advance the following proposals or components of proposals along with other directives. Board Decision

1. Defining Large Load Additions
For purposes of the proposed Tariff and manual provisions being developed as a result of this CIFP process, the Board proposes to define large load additions as individual additions of load at or above 50 MW at a single Point of Interconnection.3 The Board notes that this level was supported in the CIFP process and is consistent with PJM’s definition of large load additions already being utilized in its large load adjustment process.

2. Load Forecasting Improvements
It became clear to the Board during the CIFP that additional improvements should be made to the load forecasting process, building on the progress made by PJM staff and stakeholders through the Load Analysis Subcommittee (LAS). Reforms vetted through the LAS should be implemented. Further, the improvements proposed in the PJM staff proposal in the CIFP should also be implemented. These improvements relate to state review of large load additions, addressing duplicative requests, the use of additional third-party review and increased transparency. These represent strong improvements that will continue to both refine the process and

2 Op-Ed from SVP Asim Z. Haque, State Frameworks Are Critical To Addressing PJM Affordability
3 EDC or LSE may request large loads under 50 MW for consideration on a case-by-case basis.

PDF page 13

January 16, 2026
Page 3
610.666.8980 | www.pjm.com
resulting load projections. The Board directs the PJM staff to implement the load forecasting improvements4 as set forth in Appendix B. PJM staff will review any specific language changes that are necessary or appropriate with stakeholders prior to their adoption. Load forecasting improvements that have not already been implemented for PJM’s 2026 Load Forecast should be in place for PJM’s 2027 Load Forecast.

3. Integrating Large Loads
Within the CIFP process, there was significant discussion concerning PJM’s obligation to procure capacity to serve large load additions, the curtailment priority for such large load additions and whether capacity obligations should differ where large loads are accompanied by incremental generation to offset their large load additions. The Board appreciates the breadth of stakeholder proposals submitted on these issues and has adopted elements of several proposals with the following goals in mind:

•
Provide the appropriate price signals to support the timely development of new capacity resources necessary to serve all load in PJM at the required level of reliability;

•
Align curtailment priority and implementation with frameworks established by the relevant states and/or Transmission Owners (TOs) – while PJM will determine the quantity of load requiring curtailment to preserve grid reliability, the states and/or TOs retain responsibility for determining which loads are curtailed when necessary;

•
Create incentives for Load Serving Entities (LSEs), large loads and/or states to bring new capacity resources to offset their load additions consistent with cost causation principles; and

•
Establish an expedited interconnection pathway for incremental generation advanced by LSEs, large loads and/or states.

For these elements to be successful, the Board expects the data center community and other large loads, along with the LSEs that serve them, to play a constructive role in addressing the reliability and affordability challenges associated with the scale and pace of the forecasted large load additions in the PJM region. The Board is therefore directing management to pursue the following components in accordance with the timelines set forth below.

a. Voluntary Bring Your Own New Generation (BYONG) Commensurate With Large Load
Additions and Expedited Interconnection Track
The Board is supportive of frameworks under which LSEs, large loads and states bring their own incremental generation to the system to offset, on an ELCC-measured basis, their load additions. The Board is mindful of the jurisdictional limits of PJM’s authority, which apply to PJM’s relationship with LSEs rather than individual retail customers. As a result, although the Board is proposing Tariff revisions that focus on aggregate new generation demonstrated by LSEs as available to offset their forecasted large load additions, the states within PJM’s footprint retain the authority to determine how such frameworks are applied to individual retail customers, including large loads.

4 The primary components of PJM’s load forecast proposal and changes made via the LAS affixed here as Appendix B

PDF page 14

January 16, 2026
Page 4
610.666.8980 | www.pjm.com
As has been referenced by many stakeholders, including the Independent Market Monitor (IMM), data centers in particular (which account for a substantial share of forecasted large load additions in the PJM footprint) present characteristics not previously experienced at scale, both in terms of magnitude and speed of deployment. According to McKinsey & Company, PJM is the largest data center market today and is expected to remain so at least until 2030. The Board does not support approaches that seek to limit or eliminate this growth. Rather, the Board views engagement by the data center community as an important component to addressing the reliability and downstream affordability challenges associated with rapid load growth.

Accordingly, the Board encourages voluntary “Bring Your Own New Generation” (BYONG) and directs the PJM staff to implement its proposal and associated matrix components related to the Expedited Interconnection Track5 that will serve as an alternate path for any entity seeking to mitigate curtailment risk by bringing their own new generation to the system on an accelerated basis. PJM staff will review any specific language changes necessary or appropriate with stakeholders prior to adoption or any requisite filing. The Expedited Interconnection Track should be in place by August 2026. Finally, the Board notes ongoing efforts by several states within the PJM footprint, including initiatives proposed by the Governors of Pennsylvania, Virginia, New Jersey and Maryland to facilitate BYONG as reflected in their joint proposal with the Data Center Coalition, Exelon and PPL. While these efforts fall outside the jurisdiction of FERC and are not actions that PJM can implement directly, state-led initiatives to advance new supply – including reforms to support permitting and siting of generation and the transmission necessary to integrate it – will be important to accelerating the addition of needed generation to the system.

b. Connect and Manage
Where an LSE identifies a shortfall between forecasted load additions and the availability of new incremental generation to offset that growth, the Board is directing development of a similar framework articulated by the PJM Legislators Collaborative/NRDC and the Joint Consumer Advocates. Under this framework, the incremental demand associated with such load growth would be subject to curtailment prior to the deployment of pre-emergency Demand Response. This will help to preserve Demand Response as a valuable reliability tool by not disrupting its business model through a dramatic increase in its use and will provide an incentive for new load to secure capacity or provide flexibility. Consistent with its operation of the system today, PJM will take all reasonable steps to maintain grid stability and avoid curtailment. However, should system conditions over a given period force PJM to invoke its emergency procedures, the Board finds it reasonable for certain large loads, including data centers, to move to their backup generators, or curtail their demand, for a limited number of hours during the year to prevent a larger scale outage for residential and other consumers. Such curtailment would be expected to occur infrequently, for limited durations, and only when necessary to prevent broader system impacts, consistent with PJM’s longstanding operational practice of avoiding curtailment whenever possible.

5 Details provided in Appendix C

PDF page 15

January 16, 2026
Page 5
610.666.8980 | www.pjm.com
Ultimately, the determination of which loads are curtailed during emergency conditions rests with TOs, and with LSEs that have direct relationships with their customers. PJM does not have authority to direct individual retail loads to curtail demand. However, PJM will establish an allocation framework whereby TOs and LSEs have advanced notification of the potential magnitude of load reductions that may be required under such conditions. PJM intends to explore how to design curtailment allocations based on the contributions of any shortfall to PJM’s required reserve margin.

The Board does not propose that “connect and manage” new large load be removed from the capacity market. Based on current load projections, the system is expected to tighten to a degree that excluding this demand would be unlikely to reduce capacity prices below point “A” on the Variable Resource Requirement (VRR) curve. Removing such load from the market would instead result in large new loads avoiding capacity costs altogether, with those costs shifted to existing consumers.6 The capacity market is designed to support system-wide resource adequacy, recognizing that PJM may be required to direct load curtailments to maintain system reliability, with TOs ultimately determining which customers to curtail. As further detailed below, the Board believes a more comprehensive review of the mechanisms through which PJM’s markets produce investment signals is warranted. However, the markets should retain structural integrity during the pendency of this review and beyond.

With respect to this issue and others addressed in this letter, the Board recognizes that a number of future developments will be relevant to the design of longer-term approaches to large load integration. These include, among other factors, the extent to which large loads contract for new generation to offset load additions, potential future actions by federal and state authorities, the resolution of supply chain constraints, success in siting and permitting, and other market and policy developments. In light of these uncertainties, the Board views the capacity market-related actions outlined in this letter as interim measures intended to address near-term reliability risks. These measures may be refined or revisited as additional data becomes available and their impacts can be assessed.

The load shed prioritization and allocation should be completed as soon as practicable. This matter should initially be addressed via the Consensus Based Issue Resolution (CBIR) process, but the Board asks that the stakeholders proceed expeditiously such that changes are in place by the end of 2026 and will monitor the progress to determine whether an accelerated stakeholder process should be initiated.

4. Immediate Initiation of Reliability Backstop Procurement
PJM’s primary responsibility is ensuring grid reliability, and an important component of this reliability mandate is resource adequacy. The results of the recent 2027/2028 capacity auction indicate that PJM will fall short of its FERC-required reliability requirement in that delivery year.

The PJM Tariff currently allows PJM to run a backstop capacity procurement if the system clears short of the reliability requirement for three consecutive capacity auctions. In light of the evolving risk profile, the Board

6 The Board reserves the right to look at this issue again as part of the design of the reliability backstop procurement described in this letter.

PDF page 16

January 16, 2026
Page 6
610.666.8980 | www.pjm.com
directs PJM staff to develop a proposal to both accelerate and execute this procurement. Accelerating a backstop capacity procurement is especially necessary in light of FERC’s recent decision on colocation and its request for more information on utilization of this backstop procurement framework.

During the CIFP process, the coalition comprised of Constellation, Talen, CPower, Google, Amazon and Microsoft proposed elements of a framework that the Board believes warrant further consideration by PJM staff and the stakeholders. Any backstop procurement should specify price, term and quantity as core award parameters and be consistent with the Board’s direction to procure for the full reliability requirement for the footprint.

The Board directs PJM staff to address cost allocation for any such procurement, including consideration of mechanisms that assign costs to those LSEs that are short as a result of incremental load growth within their service areas. Those LSEs may, in turn, determine how such costs are allocated to incremental loads, consistent with state law.

Over the longer term, the Board does not view it as desirable for PJM to serve as the procuring authority to long-term commitments resulting from backstop procurement. Accordingly, any such procurement should be viewed as a transitional measure intended to facilitate the timely integration of new supply, while options for a more durable mechanism are evaluated as part of the broader market review directed below. The Board recognizes that the existing backstop procurement rules are not sufficiently detailed, and that PJM and the stakeholders will need to discuss the design of the procurement. The Board is directing that immediate attention be provided to this matter with process and deadlines to be discussed at the upcoming January 22 Members Committee meeting.

5. Holistic Review of Investment Incentives in PJM’s Markets in 2026
PJM has concluded that the investment environment for new generation has evolved materially in recent years, and in ways that differ significantly from conditions that prevailed at the inception of the Reliability Pricing Model (RPM) capacity market. As it is designed, the three-year forward capacity market was intended to produce a transparent price signal reflecting the value of capacity in a given delivery year and, among other purposes, to inform bilateral contracting between willing buyers and sellers.

The resulting single-year commitment three years forward, however, provides a comparatively short-term signal relative to the long-lived nature of the generation resources that underpin resource adequacy. On its own, this structure may not provide the stable revenue streams needed to justify new investment in today’s volatile and uncertain investment environment, particularly when elevated costs are combined with external constraints or intervention.

In addition, a combination of recent factors including heightened price volatility, external headwinds and frequent rule changes has increased investment risk and reduced certainty around long-term procurement decisions. Recent examples of existing resources entering into longer-term bilateral arrangements provide evidence that such contracts are increasingly relied upon to support investment decisions within the independent power producer community.

To date, the current framework of a one-year capacity commitment procured three years forward has not produced a sufficient level of bilateral contracting or price certainty to support the scale of new resource

PDF page 17

January 16, 2026
Page 7
610.666.8980 | www.pjm.com
investment required to maintain resource adequacy. This is evidenced by the large quantity of prospective new resources with signed Generation Interconnection Agreements that are not rapidly moving to construction despite historically high-capacity prices. Accordingly, the Board believes it is appropriate to undertake a focused review of the capacity market to assess whether its design is appropriate for prevailing investment conditions and the incentives needed to attract timely new supply.

The Board also recognizes that PJM’s markets must operate in a coordinated manner to deliver clear and transparent price signals regarding the resources needed to maintain grid reliability. In this regard, the Board views the work underway in the Reserve Certainty Senior Task Force as an important foundation and expects that those efforts be advanced in addition to any material changes to the capacity market, so that investment and performance incentives across markets remain cohesive, understandable and actionable. Accordingly, the Board directs PJM to analyze how the energy, reserve and capacity markets can evolve in a coordinated manner to provide appropriate incentives for both investment and performance. Upon completion of this analysis, PJM should engage stakeholders to discuss a potential enhanced market framework. The Board’s objectives for this work are twofold: (1) to advance necessary changes to the energy and reserve markets that are already underway and that support system operators in managing an increasingly dynamic grid; and (2) to ensure that such changes are aligned with anticipated reforms to support resource adequacy, while continuing to provide a residual mechanism for states with vertically integrated structures. The Board directs PJM staff to perform this analysis in the first half of 2026. Thereafter, the PJM staff should discuss this analysis with the stakeholders and work with them to formulate a work plan that would serve to implement recommendations made from the analysis. That work plan should be presented to the Board with a recommendation for accelerated stakeholder processes so as to more expeditiously implement the recommendations set forth in the analysis.

6. Price Collar for 2028/2029 and 2029/2030 Capacity Auctions – Feedback Requested
Given the Board and PJM management’s acknowledgment of the challenges facing the current capacity market and need for further review, the Board seeks additional stakeholder input as to whether the price collar that was in place for the 2026/2027 and 2027/2028 auctions should be extended. The Board recognizes that there are both advantages and disadvantages associated with such an extension.

On the one hand, a price collar may obscure the market’s underlying clearing price and, as a result, could dampen signals needed to support the entry of new supply. On the other hand, as discussed above, there are legitimate questions regarding whether the current capacity market construct, on its own, is sufficient to incentivize new resource development in the absence of the longer-term bilateral arrangements contemplated at the time of the market’s design.

Accordingly, the Board seeks additional feedback from stakeholders on this issue and requests that responses address the questions set forth in Appendix D as soon as practicable, but before January 30, 2026. Please send responses to these questions via this link. All feedback will be posted publicly on the CIFP LLA webpage. After review of the feedback, the Board will issue an additional letter discussing its decision to make a Federal Power Act (FPA) Section 205 filing related to the price collar, or not, in time for the July auction (2028/2029 Delivery Year).

PDF page 18

January 16, 2026
Page 8
610.666.8980 | www.pjm.com
7. Summary of Actions, Associated Dates and Stakeholder Activity Action Taken

Associated Dates
Stakeholder Activity
Load Forecasting
Improvements
2027 Load Forecast (in place for)
Page Turn of Manuals
Expedited Interconnection
Track
August 2026 (in place by)
Page Turn Prior to Requisite Filing
Connect and Manage (Load
Shed Prioritization and
Allocation)
End of 2026 (in place by)
Consensus Based Issue Resolution
Stakeholder Process
Reliability Backstop
Procurement
Begin Discussion Immediately
Initial Discussion at Members Committee on
January 22, 2026
Market Investment
Incentives Review
Analysis Performed in First Half of
2026
Work Plan to Implement Recommendations
and Associated Stakeholder Processes
Presented to Board
Capacity Auction Price
Collar
Written Feedback by January 30,
2026.
Feedback to Board
Link here.

The Board thanks the stakeholders for their engagement, and we look forward to continuing to address both the tremendous challenges and opportunities with which we have been presented.

Sincerely and on behalf of my colleagues,

David E. Mills
Chair, PJM Board of Managers
Interim President & CEO, PJM Interconnection, LLC

PDF page 19

January 16, 2026
Page 9
610.666.8980 | www.pjm.com
Appendix A
List of Board Correspondences Regarding CIFP
1. PJM Board Letter Regarding Implementation of Critical Issue Fast Path Process for Large Load Additions (PDF)

2. Senator Fetterman Letter Regarding the Large Load Addition Critical Issues Fast Path (CIFP) Process (PDF)

3. IL Legislative Letter Regarding Critical Issue Fast Path – Large Load Additions (PDF)
4. Congressional Letter Regarding Critical Issue Fast Path – Large Load Additions (PDF)
5. GEO*ESG Solutions Regarding Objection to the Use of CIFP Authority and Request for Clarification on Standby Generation Policy for Data Centers (PDF)

6. Several Environment America Research & Policy Centers Regarding Inclusion of the Expedited Interconnection Track (EIT) in PJM’s Proposal in the CIFP Process for Large Load Additions (PDF)

7. NJBPU Staff Regarding Critical Issue Fast Path – Large Load Additions (PDF)
8. PJM Legislators’ Collaborative Letter Regarding Critical Issue Fast Path – Large Load Additions (PDF)
9. Illinois Governor Pritzker Letter Regarding Critical Issue Fast Path – Large Load Additions (PDF)
10. Apex Letter Regarding Critical Issue Fast Path – Large Load Additions (PDF)
11. Several Governors' Letter Regarding Critical Issue Fast Path – Large Load Additions (PDF)
12. Sierra Club Letter Regarding Critical Issue Fast Path – Large Load Additions (PDF)
13. PJM Ratepayer Comments on the Large Load CIFP (PDF)
14. CAPS Letter Regarding Consumer Advocate Voting on the SMECO Proposal in CIFP-Large Load Addition (PDF)

PDF page 20

January 16, 2026
Page 10
610.666.8980 | www.pjm.com
Appendix B
Load Forecasting: PJM Proposal and Load Analysis Subcommittee Work
PJM Staff CIFP Proposal Features:
State Review:
PJM will add a step to the large load adjustment annual submission process that will allow for state commissions to review and provide feedback on the large load adjustments submitted by TOs prior to finalizing and issuing the PJM Load Forecast. The state review would occur, from a timeline perspective, in parallel with the large load addition submission to PJM. Though informal and within the discretion of each state, Electric Distribution Company (EDC)/LSEs would be required to indicate the date the EDC/LSEs shared the large load additions with the Relevant Electric Retail Regulatory authority (RERRA) and provide any feedback received.

Duplicative Requests:
As part of the large load adjustment annual submissions to PJM, TOs shall inquire with their subject customers, and indicate to PJM accordingly, whether any load interconnection requests they’ve received (that do not have either an Electric Service Obligation [ESO] or Construction Commitment [CC]) are duplicative with other such requests made to interconnect large load either within or outside of the PJM region such that only a subset of such requests are expected to achieve actual commercial operation. If so, the submitters are required to provide the number of sites and amount of megawatts that are duplicative that are included in their submission. If the submitter does not provide the number of sites and megawatts, or further sufficient justification and explanation, then all such requests will be removed from the forecast. This will be added to the annual submission template.

Additional Review:
Provide additional industry-specific review of the PJM load forecast (i.e., cross-check with national-level forecast and equipment projections), which may include a third-party review. This third-party review, initiated by PJM, would weigh both the national level trends as well as the inter-PJM trends that would help inform PJM’s load forecast. This review would be presented to stakeholders for opportunity for feedback prior to finalizing for PJM consideration. Transparency:

To be included in the PJM load forecast, EDC/LSE/TO must ensure customer NDAs include the ability to share all information with PJM related to large loads and such information must be shared.

Load Analysis Subcommittee Enhancements:
•
Large load coming online during a delivery year covered by an RPM auction for that forecast cycle with CC or ESO contract of the load within the electric service provider’s territory will be considered for inclusion in the PJM forecast plus a meaningful/verifiable financial commitment (such as credit/collateral support, financially significant infrastructure investment, or long-term supply commitment with new or existing resources).

•
Large load coming online beyond a delivery year covered by an RMP auction but less than 8 years without construction commitments will be considered for inclusion in the PJM forecast if they have cleared demonstrable project milestones to be considered certain and may be de-rated to reflect its greater uncertainty.

PDF page 21

January 16, 2026
Page 11
610.666.8980 | www.pjm.com
•
Requestors should provide a ramp rate with supporting documentation. Absent an EDC/LSE-
provided ramp rate, PJM will initially use a default 3-year ramp rate subject to further adjustment based on a comparison of this default value with actual ramp rates of new large loads.

•
Utilization factor: PJM uses default historical factor (typically 70%) unless EDC/LSE provides supporting data.

PJM will convene a series of meetings with EDCs and LSEs to improve large load modeling assumptions around ramp rate and utilization. These invite-only meetings would need to maintain strict confidentiality in order to ensure a robust conversation. Any information made public coming out of these meetings would need to be aggregated and anonymized and would be used to help with the formulation of large load additions as well as in PJM’s evaluation of large load additions.

•
Financial commitment: Document and quantify the customer's financial responsibility. This may align with the rates and agreement provided or be reflected in the capital project plan of the requested EDC/LSE.

PDF page 22

January 16, 2026
Page 12
610.666.8980 | www.pjm.com
Appendix C
Expedited Interconnection Track
PJM Staff CIFP Proposal Features:
New Expedited Interconnection Track (EIT) for sponsored generation with a contractual commitment. This proposal would be standalone outside of the PJM interconnection cycle process and operate in parallel. Expedited timing allows shovel-ready resources to execute Generation Interconnection Agreements (GIAs) sooner and allows an earlier path toward construction and network upgrade certainly.

Contract/No Contract Requirements:
Generation with a contractual agreement: Available to new generation or uprates to existing generation supported by evidence of state commitment to expedite consideration of permitting and siting and a financial commitment with a load that has an executed electric service agreement to interconnect with the TO. The new generation or uprate to existing generation must have an accredited capacity value equal to or greater than the load with which it is contracted.

Generation without a contractual agreement: Available to new generation or uprates to existing generation supported by evidence of state commitment to expedite consideration of permitting and siting. Requires additional financial commitments in the form of higher readiness deposits.

Time Frame:
10 months from application
Generation Eligibility:
All of the following criteria must be met –
•
Capacity resource status must be requested with the application along with Capacity Interconnection Rights relevant to the fuel type being interconnected.

•
Commercial operations must be achieved within three years of the application submission. Output to the grid may still be limited based on completion of any network upgrades required.

•
Point of Interconnection (POI) – must be interconnecting to the transmission system in the relevant state supporting the project

•
Megawatt requirements – requests must be for large scale generation greater than 250 MW (UCAP).
•
Resource fuel type – all fuel types eligible, including storage
Generation Application:
•
Can be submitted to PJM at any time – there are no defined EIT application windows.
•
Are prioritized serially, in the order as each application is received by PJM
•
Large nonrefundable study deposit ($500,000) and readiness deposit
–
$10k/MW for generation paired with load

PDF page 23

January 16, 2026
Page 13
610.666.8980 | www.pjm.com
–
$20k/MW for generation not paired with load
•
Applications are capped annually at 10 projects.
•
Must provide 3 full years of site control for 100% of generating site and interconnection facilities at time of application.

Generation Post-Application, Costs and Agreement Requirements:
•
There are no site control changes or other project changes allowed such as fuel type, megawatt size, equipment type, etc. Changes post-GIA execution will follow the existing Necessary Study process.

•
Cost allocation – EIT resources are responsible for 100% of all identified required network upgrades. No cost sharing with other EIT projects or Cycle projects.

•
Cost estimates – for mitigations will be planning-level estimates only
•
Commercial operation no more than 3 years from the date of EIT application. Milestone dates are eligible for extensions according to existing procedures.

PDF page 24

January 16, 2026
Page 14
610.666.8980 | www.pjm.com
Appendix D
Board Questions Regarding Capacity Auction Price Collar
1. The existing price collar includes a price cap of $325 and a price floor of $175 adjusted for ELCC changes before each auction. Do you support any extension of the existing price collar? If so, at what level and for what period?

2. If you support an extension of the price collar, please provide the justification that you believe should be presented to FERC that supports your proposed level and time period being just and reasonable.

3. If you do not support any extension of the price collar, please provide the justification that you believe should be presented to FERC to support the argument that a short-term extension of the price collar is not just and reasonable.

4. To the extent you support an extension of the price collar, please explain how you believe such an extension would not adversely impact reliability or investment and when you believe the price collar could be lifted.

5. To the extent you oppose an extension of the price collar as inhibiting needed investment in the short term, please indicate the type of projects you believe could come into service during the delivery years covered by these auctions and the potential impact of a collar extension on those project types.

6. The Quadrennial Review, cosponsored by the Pennsylvania Public Utility Commission, was overwhelmingly approved by the stakeholders. Should the Board consider a transition mechanism to move from the existing collar to Point A on the demand curve? Please provide your views on whether such a transition would be appropriate and the length and stages of such a transition and its consistency with the stakeholder support of the Quadrennial Review.

PDF page 25

CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document on those parties on the official Service List compiled by the Secretary in these proceedings.

Dated at Audubon, Pennsylvania this 20th day of January, 2026.