EL25-49-002 · 2026-02-09 · Individual No Affiliation

Andrew D. Hinz submits Request for Rehearing of the 12/18/2025 Order

PDF page 1

Request for Rehearing
Federal Tariffs for Large Loads Co-Located at Generating Facilities 1
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
_____________________________________

 )
Federal Energy Regulatory Commission
 )
PJM Interconnection, L.L.C.

 )

EL25-49-000
Midcontinent Independent System Operator, Inc.)

ER25-2454-002
Southwest Power Pool, Inc.

 )

ER25-2296-002
____________________________________ )

AD24-11-000

ANDREW HINZ’S REQUEST FOR REHEARING ON FEDERAL INTERCONNECTION
TARIFFS FOR LARGE LOADS CO-LOCATED AT GENERATING FACILITIES

The Federal Energy Regulatory Commission (FERC) December 18, 2025 Order in EL25- 49 Etal will cause unjust and unreasonable rates because:

1. The Order ignores the costs to ratepayers (wholesale, retail, interstate, intrastate) that will result from just-retired generating facilities, soon-to-retire generating facilities, or new state-sited generating facilities that increase CH4 and/or CO2 emissions, because those state-sited generating facilities and their increased emissions will increase cost burdens on ratepayers outside of their states (increased demand and costs for fuel supplies and climate change adaption) for economic benefits limited to the siting states.

2. The Order does not explicitly open access to the directed PJM tariff to any and all wholesale generating facilities or proposed generating facilities or Co-Located customer types.

3. The Order does not require that States and Indigenous Tribes or Nations have the ability to approve or reject any terms of any interconnection under any such tariff, regardless of whether they have previously sited a generation facility applying for the tariff.

PDF page 2

Request for Rehearing
Federal Tariffs for Large Loads Co-Located at Generating Facilities 2
4. The Order does not require fuel supply provisions for generating facilities using such tariffs to prevent fuel supply constraints from exacerbating costs to all

ratepayers (wholesale, retail, interstate, intrastate) in all or several states resulting from  congested grids during peak demand or public emergency responses,

regardless of whether those ratepayers receive any benefit from the Co-Location customers of those generating facilities.

Because of the deficiencies noted above, FERC must Rehear its December 18, 2025 Order in EL25-49. As an alternative, FERC may remedy the deficiencies noted above by amending the December 18, 2025 Order in EL25-49 as follows:

(D) Paper hearing procedures are established to evaluate the rates, terms, and conditions of the interim, non-firm transmission service, Firm Contract Demand transmission service, and Non- Firm Contract Demand transmission service. Those paper hearing procedures will seek comment on the following so the Commission can preclude unjust and unreasonable rates resulting from approved Tariffs for Large Loads Co-Located at Generating Facilities: emissions-related costs to all ratepayers, removal of barriers to such tariffs for all existing and proposed generating facilities and all existing and proposed large-load customers (beyond datacenters, including municipal microgrids etc.), state authority approving over each tariff agreement regardless of the state siting status of the applying generating facility, unintended peak usage and public emergency response rate impacts to all ratepayers due to fuel market supply constraints associated with co-located generating facilities for large load customers.

Dated: February 8, 2026

Respectfully submitted,

Andrew Hinz

PDF page 3

Request for Rehearing
Federal Tariffs for Large Loads Co-Located at Generating Facilities 3
DECLARATION OF SERVICE

FEDERAL INTERCONNECTION TARIFFS FOR LARGE LOADS CO-LOCATED AT
GENERATING FACILITIES
 (EL25-49-000, ER25-2454-002, ER25-2296-002, AD24-11-000 etal.)

I, Andrew Hinz, declare that I today, February 8, 2026, served the attached “ANDREW HINZ’S REQUEST FOR REHEARING ON FEDERAL INTERCONNECTION TARIFFS FOR LARGE

LOADS CO-LOCATED AT GENERATING FACILITIES”
by electronic mail, or by first-class mail if no e-mail address is provided, to each person on the official service list compiled by the Secretary in this proceeding.

Dated: February 8, 2026

By:

Andrew Hinz

1427 Park Avenue

Baltimore, MD  21217

ahinz61@outlook.com