EL25-49-000 · 2026-02-20 · Constellation Energy Generation, LLC
Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC in response to the Independent Market Monitor for PJM’s Answer et al
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
Docket No. EL25-49-000
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
MOTION FOR LEAVE AND ANSWER OF
CONSTELLATION ENERGY GENERATION, LLC
Constellation1 moves for leave and submits this answer in response to the Independent Market Monitor for PJM’s answer2 to Constellation’s Request for Clarification, or in the Alternative, Request for Rehearing3 of the Commission’s December 18, 2025 Order.4 In relevant part, Constellation sought clarification that generators selling non-firm electricity to co-located large loads do not need to delist their capacity.5 The Commission should not force a generator to delist its capacity when the generator’s co-located load obligation is non-firm and service can be curtailed by both PJM and the generator. In such an arrangement, the generator’s output remains
1 Constellation Energy Generation, LLC (“Constellation”) submits this answer and motion for leave pursuant to Rules 212 and 213 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.212 and 385.213. Constellation respectfully submits there is good cause for the Commission to accept this answer as it is intended to aid the Commission in its decision-making.2 Answer and Motion for Leave to Answer of the Independent Market Monitor for PJM (Feb. 5, 2026) (“Market Monitor Answer”). Hereafter, the Independent Market Monitor for PJM is referred to as “Market Monitor.”3 Request for Clarification or, in the Alternative, Rehearing of Constellation Energy Generation, LLC (Jan. 20, 2026) (“Clarification Request”).4 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18th Order”).5 See Clarification Request at 2.
PDF page 2
2
available to the grid when needed to support resource adequacy. In opposing the request, the Market Monitor mischaracterizes Constellation’s position and misstates the law, facts, and record.6 The Commission should reject the Market Monitor Answer, consistent with past practice.7
First, the Market Monitor mischaracterizes the Clarification Request as “advocat[ing] for
the ability to sell capacity twice.”8 That is wrong. The generator’s capacity would be sold only once – to PJM. The Market Monitor is conflating energy and capacity. They are not the same
product. “Electric energy is the actual electricity that electric generators produce and which residential and business customers ultimately use. By contrast, electric capacity is the ability to produce [energy] when called upon.”9 The Clarification Request contemplated allowing existing generators to continue “serving”—that is, selling non-firm energy to—Co-Located Load without
6 Market Monitor Answer at 2-7.7 The Commission prohibits answers to rehearing requests unless otherwise ordered by the decisional authority. 18 C.F.R. §§ 385.213(a)(2), 385.713(d)(1); see also PJM Interconnection, L.L.C., 190 FERC ¶ 61,081, at P 27 (2025) (rejecting IMM answer to rehearing request); Indep. Mkt. Monitor for PJM Interconnection, L.L.C. v. Am. Elec Power Serv. Corp., 166 FERC ¶ 61,043, at P 8 (2019) (rejecting IMM answer to rehearing request). Unauthorized answers are only accepted if the Commission finds good cause to waive Rule 213(a)(2), e.g., if the unauthorized answer “provides … information … that … assist[s] in our decision-making process and [does] not cause undue delay.” Dominion Transmission, Inc., 163 FERC ¶ 61,128, at P 8 (2018).8 Market Monitor Answer at 4; see also id. at 3 (claiming that Constellation “asserts that even when capacity is sold to a data center that it can also sell the same capacity to PJM customers in the PJM capacity market”); id. at 2 (“generators should not be permitted to sell capacity twice”) (capitalization removed); id. at 5 (“CEG proposes to extend the concept to mean that any generation owner could remove its capacity from the PJM Capacity Market by selling the capacity to a data center.”); id. (“CEG is not content to simply remove its capacity from the capacity market. CEG proposes to sell its capacity to a data center and also sell the same capacity for the same time period to the PJM market.”).9 PPL EnergyPlus, LLC v. Solomon, 766 F.3d 241, 247 (3d Cir. 2014) (internal citations omitted); see also Affirmed Energy, LLC v. FERC, No. 25-1091, Slip Op. at 42 (D.C. Cir. Feb. 10, 2026) (“Capacity is not actual electricity, but rather a ‘commitment to produce electricity or forgo the consumption of electricity’ in a future delivery year.”); Cent. Hudson Gas & Elec. Corp. v. FERC, 783 F.3d 92, 98 (2d Cir. 2015) (“[S]uppliers sell a commitment to produce electric energy if called upon to do so during a specified future time period, rather than electric energy itself.”); FERC, Understanding Wholesale Capacity Markets (last visited Feb. 12, 2026), https://www.ferc.gov/media/understanding-wholesale-capacity-markets (“A capacity market does not pay for the energy produced but instead pays for the ability to produce power when needed.”) (emphasis omitted).
PDF page 3
3
delisting as a capacity resource so long as “the capacity resource remains available to serve the grid when needed,”10 consistent with its obligations.
Second, the Market Monitor suggests that such an arrangement is inconsistent with “[t]he
obligations of capacity resources,” which “include the requirement to offer their full [capacity] in the energy and reserves markets every day.”11 But the Commission has previously clarified that PJM’s “must-offer requirement, when implemented, should not impede resources from exporting energy on a non-firm or recallable basis, i.e., that the must-offer requirement will not operate in [a] manner that requires the resource to sit idle.”12 Thus, a capacity resource is not required to sit idle by the phone 8,760 hours per year waiting to see if PJM might call.13 To the extent the generator can demonstrate that its obligation to provide energy to the co-located load is non-firm or recallable, and the load demonstrates that it will either curtail or be served by backup supply when generator and grid supply are unavailable, there is simply no reason for the generator to delist and exacerbate any supply shortfall. To the contrary, there is every reason for the Commission to encourage such arrangements, which allow new large loads to interconnect without
10 Clarification Request at 1 (emphasis added). The Clarification Request also stated, “[a]s Constellation stated in its April 23, 2025 Reply Comments, ‘Constellation’s view is that any Existing Generation Capacity Resources that would prioritize serving co-located load over following PJM dispatch should instead seek removal of Capacity Resource status or otherwise seek appropriate replacement capacity to cover its capacity supply obligation.’” Id. at 5 n.9 (quoting Constellation April 23, 2025 Reply Comments at 92-93).
11 Market Monitor Answer at 4.12 PJM Interconnection, L.L.C., 139 FERC ¶ 61,057, at P 205 (2012).13 See generally PJM Manual 11, § 2.3.3.1 (stating Capacity Resource Offer Rules); Constellation April 23, 2025 Reply Comments, Exhibit 2 at 46:7-14 (Testimony of Zachary Ming) (“For any generator to participate in the capacity market, it is expected to provide output to the grid when system conditions require and when ordered to by PJM. If a co-located generator clears in the capacity market, this means that, at a minimum, it must output to the grid when needed or face performance penalties, even if that means interruption of the co-located load, either through curtailment or backup generation. I agree with PJM’s statement that ‘no portion of a committed Capacity Resource (whether composed of one or multiple physical generating units) may prioritize serving load that PJM is not responsible for serving.’”) (citations omitted).
PDF page 4
4
impacting resource adequacy. The Clarification Request seeks nothing more than the same type of treatment already afforded non-firm exports.14 Constellation acknowledges that there may have to be adjustments to the energy offer price rules to accommodate the non-firm supply of co-located load from a capacity resource. Adjustments to energy offer price rules have occurred from time to time over the years15 and Constellation is not advocating for a “radical change in the structure of PJM markets.”16
Third, the Market Monitor asserts that the Clarification Request proposed to “remove … capacity from the capacity market.”17 The Clarification Request proposed the exact opposite. Constellation sought clarification to avoid a scenario where a capacity resource that remained available to serve the grid when needed would be forced to delist and “needlessly remove available capacity from serving the grid.”18
Fourth, the Market Monitor incorrectly states “[t]he Commission has not approved” “that existing generating capacity and its energy output can be sold directly to a data center, outside PJM markets….”19 The Commission expressly contemplated this scenario and, to effectuate it efficiently, “direct[ed] PJM to file Tariff changes” addressing “an Interconnection Customer
14 Clarification Request at 1.15 See, e.g., PJM Interconnection, L.L.C., 126 FERC ¶ 61,145, order on clarification, 127 FERC ¶ 61,188 (2009) (directing PJM to propose an approach for addressing the incorporation of opportunity costs in mitigated offers).16 Market Monitor Answer at 2.17 Id. at 6.18 Clarification Request at 1. 19 Market Monitor Answer at 2.
PDF page 5
5
seeking to serve Co-Located Load using an existing generating facility….”20 If the Market Monitor disagreed, it should have sought timely rehearing of the December 18th Order.21 Finally, the Market Monitor provides no substantive support for its bald assertion that Constellation’s “request for clarification on jurisdiction issues is not just and reasonable and should be denied.”22 The Market Monitor neither specifically mentions nor engages with Constellation’s request that the “Commission … clarify that it did not intend to change the scope of its jurisdiction over a generator’s wholesale sales and transmission.”23 As such, the Market Monitor’s assertion should be disregarded.
CONCLUSION
For the foregoing reasons, the Commission should reject the Market Monitor Answer as it fails to comply with Rule 213 of the Commission’s Rules of Practice and Procedure and cannot support the Commission in its decision making.
20 December 18th Order, 193 FERC ¶ 61,217 at P 176.
21 16 U.S.C. § 825l(a).22 Market Monitor Answer at 7.23 Clarification Request at 2.
PDF page 6
6
Respectfully submitted,
/s/ Paul F. Wight
February 20, 2026
Carrie Hill Allen
Sr. Vice President & Deputy General Counsel Seth T. Lucia
Assistant General Counsel
Constellation Energy Generation, LLC 250 Massachusetts Ave. NW, Suite 760 Washington, D.C. 20001
carrie.allen@constellation.com
seth.lucia@constellation.com
Christopher A. Wilson
Managing Director, Federal Regulatory Affairs Constellation Energy Generation, LLC 250 Massachusetts Ave. NW, Suite 760 Washington, D.C. 20001
202-347-7500
FERCe-filings1@constellation.com
Paul F. Wight
Carolyn E. Clarkin
DLA Piper LLP (US)
500 Eighth Street NW
Washington, D.C. 20004
703-773-4058
paul.wight@us.dlapiper.com
carolyn.clarkin@us.dlapiper.com
Sophia Browning
4365 Executive Drive
Suite 1100
San Diego, CA 92121
858-677-1455
sophia.browning@us.dlapiper.com
Jacob I. Chefitz
DLA Piper LLP (US)
1251 Avenue of the Americas
New York, NY 10020
212-335-4500
jacob.chefitz@us.dlapiper.com
Counsel for Constellation Energy
Generation, LLC
PDF page 7
7
CERTIFICATE OF SERVICE
I hereby certify that I have on this 20th day of February 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2024).
/s/ Sophia Browning
Sophia Browning
DLA Piper LLP (US)
4365 Executive Drive
Suite 1100
San Diego, CA 92121
sophia.browning@us.dlapiper.com