Exhibit No. PTO-0003Page 1 of 3
Summary of Calculated Grid Reliance Charge (GRC) Percentages by Company Line No.
Utility
GRC Percentage
(A)
(B)
(C)
1
Atlantic City Electric
37.1%
2
Appalachian Power Co
22.1%
3
Indiana Michigan Power Co
22.1%
4
AEP-East A
Kentucky Power Co
22.1%
5
Group
Kingsport Power Co
22.1%
6
Ohio Power Co
22.1%
7
Wheeling Power Company
22.1%
8
AEP Appalachian Transmission Co
21.8%
9
AEP Indiana Michigan
21.8%
10
AEP Kentucky Transmission Co
21.8%
11
AEP Ohio Transmission Co
21.8%
12
West Virginia Transmission Co
21.8%
13
Mon Power
22.5%
14
South FE Group Potomac Edison
22.5%
15
West Penn Power (FE)
22.5%
16
Keystone ATC
48.7%
17
ATSI
24.6%
18
Baltimore Gas and Electric
30.5%
19
ComEd
32.1%
20
Dayton Power and Light
14.8%
21
Duke Energy Ohio & Kentucky
18.3%
22
Virginia Electric Power Co
25.4%
23
Delmarva Power and Light Co
31.8%
24
Old Dominion Electric Coop
73.2%
25
Duquesne Light Co
20.4%
26
JCPL
35.4%
27
MAIT
29.2%
28
PECO Energy
29.6%
29
PEPCO
21.3%
30
PPL Electric
20.0%
31
UGI Utilities
18.3%
32
PSEG
28.3%
33
NEET MidAtlantic
14.1%
34
Silver Run Electric
25.8%
35
TAILCo
21.2%
36
Transource WV
18.2%
37
Average Grid-Reliance Charge Percentage
25.8%
Excludes:
- AMP - AEP
- AMP - ATSI
- AMP - DAYTON
- East Kentucky Power Coop
- Ohio Valley Electric Cooperative
- Rockland Electric Company
- SMECo
- Transource MD
- Transource PA
- Valley Link MD
- Valley Link VA
- Valley Link MD
AEP-East B
Group
PDF page 2
Exhibit No. PTO-0003
Utility:
Atlantic City Electric
Page 2 of 3
Transmission O&M Work Table
(Inputs taken from FF1 pp. 320-323)
Line No.
Excluded / Included
Account
O&M Account
Amount
(A)
(B)
(C)
(D)
(E)
Operation Expense
1
Excluded
560
Operation Supervision and Engineering
5,430,906
2
Included
561
Load Dispatching
29,347
3
Included
562
Station Expenses
4
Included
563
Overhead Line Expenses
5
Included
564
Underground Line Expenses
6
Excluded
565
Transmission Electricity by Others
7
Excluded
566
Miscellaneous Transmission Expenses
4,428,115
8
Excluded
567
Rents
TOTAL Operation
9,888,368
Maintenance Expense
9
Excluded
568
Maintenance Supervision and Engineering
10
Excluded
569
Maintenance of Structures
326,679
11
Included
570
Maintenance of Station Equipment
7,087,049
12
Included
571
Maintenance of Overhead Lines
8,979,626
13
Included
572
Maintenance of Underground Lines
14
Excluded
573
Maintenance of Miscellaneous Transmission Plant
190,367
15
TOTAL Maintenance
16,583,721
16
TOTAL O&M Transmission Expenses (Operation Total + Maintenance Total) 26,472,089
17
Total Included (= sum of all "included" accounts)
16,096,022
18
Total Included Percentage (line 17 / line 16)
60.8%
PDF page 3
Exhibit No. PTO-0003
Utility:
Atlantic City Electric
Page 3 of 3
Line No.
Line No.
Corresponding to
Attachment H-1A
Atlantic City Electric Attachment H-1A
Description
Amount
GRC Percentage
GRC Amount
(= GRC % *
Amount)
(A)
(B)
(C)
(D)
(E)
(F)
1
85
O&M
$ 38,519,879
2
60
Transmission O&M (a subsection of the line above)
$ 26,375,673
60.80% 1 6,037,397
3
97
Depreciation & Amortization
$ 74,781,788
4
86
Transmission Depreciation Expense (a subsection of the line above)
$ 71,962,130
100.00% 7 1,962,130
5
157
Net Revenue Requirement
$ 237,470,160
8 7,999,528
6
GRC Percentage of Net Revenue Requirement = (F) line 5 / (D) line 5
37.1%
7
175
Network Service Rate ($/MW/Year)
$ 8 3,665
8
Average Grid-Reliance Charge Percentage
25.8%
9
[*]
GRC Rate ($/MW/Year) = GRC Percentage * Network Service Rate (line 7 x line 8) $ 2 1,556
[*] Does not account for any adjustment for the difference between the measure of demand used to calculate the transmission rates for NITS, Interim, Non-Firm Service, and Firm Contract Demand Service, and the appropriate measure of demand used to design the final GRC rate.