ER26-1479-000 · 2026-04-08 · Constellation Energy Generation, LLC
Motion for Leave and Supplemental Protest of Constellation Energy Generation, LLC to advise FERC of an important factual development underscoring why FERC…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
PJM Interconnection, L.L.C.
)
)
Docket No. ER26-1088-000
Docket No. ER26-1479-000
(Not consolidated)
MOTION FOR LEAVE AND SUPPLEMENTAL PROTEST OF
CONSTELLATION ENERGY GENERATION, LLC
Constellation Energy Generation, LLC moves for leave1 to submit this supplemental
protest to advise the Commission of an important factual development underscoring why the Commission must reject PJM’s proposal to define Co-Located Load in relation to the “Point of Change in Ownership” which PJM proposed to do in both its 30-day and 60-day compliance
filings.2
The Commission’s December 18, 2025 Order3 was explicit in defining Co-Located Load
as “a ‘configuration [that] refers to end-use customer load that is physically connected to the facilities or planned Customer Facility on the Interconnection Customer’s side of the Point of Interconnection to the PJM Transmission System.’”4 The Commission will recall that PJM’s
1 Constellation Energy Generation, LLC (“Constellation”) submits this protest and motion for leave pursuant to Rules 211 and 212 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.211 and 385.212(2025). Constellation respectfully submits there is good cause for the Commission to accept this supplemental protest as it is intended to aid the Commission in its decision-making.2 See Comments and Conditional Protest of Constellation Energy, Docket No. ER26-1088-000 (Feb. 10, 2026) (“Constellation’s Thirty-Day Compliance Filing Comments”); id. at 5 (“The Commission must ensure that Transmission Owners are not permitted to exploit the interconnection process to continue to deny, delay, encumber, or tie interconnection services for large load configurations that they disfavor. Accordingly, the Commission should reject PJM’s new definition of Co-Located Load.”). See also Protest and Comments of Constellation Energy Generation, LLC, Docket No. ER26-1479-000 (Mar. 16, 2026) (“Constellation’s Sixty-Day Compliance Filing Comments”); id. at 3 (“Using the ‘Point of Change in Ownership’ could give the Transmission Owner an additional tool to discriminate against competing projects.”).3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18th Order”). 4 December 18th Order, 193 FERC ¶ 61,217 at P 164.
PDF page 2
2
compliance filings diverged from the December 18th Order and instead sought to define Co- Located Load in reference to the “Point of Change in Ownership” rather than the “Point of Interconnection.”
In its protest of both PJM’s 30-day and 60-day compliance filings, Constellation explained that PJM’s deviation from the Commission’s order would allow Transmission Owners to effectively block co-location arrangements. Specifically, a Transmission Owner could refuse to interconnect load located on the generator’s side of the Point of Interconnection unless the generator acquiesced to the Transmission Owner’s ownership of all facilities connecting that load to the Point of Interconnection. While such load would still be Co-located Load under the December 18th Order’s definition—it is still on the generator’s side of the Point of Interconnection, notwithstanding the Transmission Owner’s ownership of facilities on that side— it would no longer count as Co-located Load under PJM’s alternative definition focused on the Point of Change in Ownership.
Unfortunately, recent experience has borne out Constellation’s concern. As part of a load interconnection application for NITS, Constellation submitted to a PJM Transmission Owner a ring bus design to co-locate load at one of its generating stations. The interconnection application reflected a ring bus located on the generator’s side of the Point of Interconnection that would allow the load to access supply from the generation facility and the grid. Constellation’s protest to PJM’s 60-day compliance filing depicted this as follows:
PDF page 3
3
During the week of March 30, 2026, the Transmission Owner informed Constellation that it would not study Constellation’s proposed design unless Constellation agreed to transfer ownership of the ring bus facilities to the Transmission Owner. Under the December 18th Order’s definition, Constellation could do so, and the load—located on the generator’s side of the Point of Interconnection—would still qualify as Co-Located Load. But under PJM’s definition, transferring ownership of the ring bus facilities would mean that the load no longer would be on the generator’s side of the Point of Change in Ownership. By conditioning the load’s interconnection on the Transmission Owner’s ownership of those facilities, the Transmission Owner will have effectively blocked Constellation’s ability to host Co-Located Load at that site and eliminated the co-located load’s ability to use the new transmission services adopted in the December 18th Order. The fact that Transmission Owners are leveraging their monopoly position to stymie Co- Location should come as no surprise. After all, the Transmission Owners’ joint comments to PJM’s 60-day filing are unabashed in restating that “some” of those Transmission Owners “strongly disagree” that “the new transmission services” adopted in the December 18th Order should
PDF page 4
4
“ultimately [be] required to be implemented.”5 Such statements from Transmission Owners—and the actions described herein—run exactly counter to the principal motivation of the Commission’s December Order to accommodate new ways for large loads to site more quickly.6 Given the depth of Transmission Owner resistance to the Commission’s December 18th Order, the Commission must be on guard for attempts by the Transmission Owners to effectively block access to these new transmission services, even while purporting to facially comply with the Order. PJM’s proposal to define Co-Located Load with reference to the Point of Change in Ownership, rather than the Point of Interconnection, enables exactly that kind of gamesmanship and risks rendering the Commission’s December 18th Order a dead letter. The Commission should reject PJM’s
proposal in both the 30-day and 60-day compliance dockets.
5 Joint Response of the Indicated PJM Transmission Owners, Docket Nos. EL25-49, et al. (Mar. 25, 2026) at 2-3.6 See December 18th Order, 193 FERC ¶ 61,217 at P 201 (“This willingness to curtail would potentially allow them to obtain service more quickly.”); see also id. (Rosner, Comm’r, concurring at PP 3-4) (“Because of this, a business- as-usual approach to load growth—planning for generation and load separately—will not suffice to timely meet growing demand while also keeping prices reasonable. Today’s order helps break the logjam.”); id. (Rosner, Comm’r, concurring at P 4) (“And co-located large loads and generators can get online faster and easier than would otherwise be the case. Grid operators like PJM should allow and encourage large loads and generators to pursue these time- and cost-saving co-location arrangements.”); FERC, Fact Sheet: FERC Directs Nation’s Largest Grid Operator to Create New Rules to Embrace Innovation and Protect Consumers (Dec. 18, 2025), https://www.ferc.gov/news-events/news/fact-sheet-ferc-directs-nations-largest-grid-operator-create-new-rules- embrace?new= (“As technology leaps forward, clear and fair regulations must keep pace to support advancement ….”); FERC, News Release, FERC: Directs Nation’s Largest Grid Operator to Create New Rules to Embrace Innovation and Protect Consumers (Dec. 18, 2025), https://www.ferc.gov/news-events/news/ferc-directs-nations- largest-grid-operator-create-new-rules-embrace-innovation-and?new= (“‘Clarifying new rules will help release the bottleneck of large load investments across the PJM footprint,’ said Chairman Swett.”); FERC, Transcript of 1131st Commission Meeting, at 24:25 to 25:1-2 (Dec. 18, 2025), https://www.ferc.gov/media/transcript-december-18- 2025-open-meeting (“[W]hen done right co-location can be both a consumer forward tool and a critical avenue in beating our national imperative of speed to power and winning the AI race.”) (remarks of Commissioner See); id. 26:4-7 (“FERC is meeting the urgent demand for speed to power by creating flexibility for a rapidly evolving industry without sacrificing reliability and affordability.”) (remarks of Commissioner See); id. at 37:11-12 (“We can’t just pretend large loads don’t exist and wish them away.”) (remarks of Commissioner LaCerte); id. at 37:15- 16 (“PJM is in dire need of leadership for their stakeholders.”) (remarks of Commissioner LaCerte); FERC, Transcript of 1132nd Commission Meeting, at 10:2-5 (Jan. 26, 2026) (“I warmly welcome engagement from great operators who share my commitment to helping ensure that datacenters can interconnect quickly and reliably.”) (remarks of Chairman Swett).
PDF page 5
5
Respectfully submitted,
/s/ Paul F. Wight
April 8, 2026
Carrie Hill Allen
Sr. Vice President & Deputy General Counsel Seth T. Lucia
Assistant General Counsel
Constellation Energy Generation, LLC 250 Massachusetts Ave. NW, Suite 760 Washington, D.C. 20001
carrie.allen@constellation.com
seth.lucia@constellation.com
Christopher A. Wilson
Managing Director, Federal Regulatory Affairs Constellation Energy Generation, LLC 250 Massachusetts Ave. NW, Suite 760 Washington, D.C. 20001
202-347-7500
FERCe-filings1@constellation.com
Paul F. Wight
Carolyn E. Clarkin
DLA Piper LLP (US)
500 Eighth Street NW
Washington, D.C. 20004
703-773-4058
paul.wight@us.dlapiper.com
carolyn.clarkin@us.dlapiper.com
Sophia Browning
4365 Executive Drive
Suite 1100
San Diego, CA 92121
858-677-1455
sophia.browning@us.dlapiper.com
Counsel for Constellation Energy
Generation, LLC
PDF page 6
CERTIFICATE OF SERVICE
I hereby certify that I have on this 8th day of April 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2025).