ER26-1479-000 · 2026-04-14 · Exelon Corporation

Answer of Exelon Corporation to the Motion for Leave and Supplemental Protest of Constellation Energy Generation, LLC filed on 04/08/2026

PDF page 1

PUBLIC – Confidential Material Redacted
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.

)
Docket No. ER26-1088-000
PJM Interconnection, L.L.C.

)
Docket No. ER26-1479-000
(not consolidated)
ANSWER OF EXELON CORPORATION TO THE MOTION FOR LEAVE AND
SUPPLEMENTAL PROTEST OF CONSTELLATION ENERGY GENERATION, LLC
Pursuant to Rule 2131 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”), Exelon Corporation on behalf of its subsidiaries2 (collectively, “Exelon”) submits this Answer to the Motion for Leave and Supplemental Protest that was filed by Constellation Energy Generation, LLC (“Constellation”) on April 8, 2026 (“Constellation’s Motion”).

Constellation’s Motion adds nothing to the Commission’s analysis and should be rejected. The motion suggests that Constellation’s limited engagement with one PJM transmission owner about one proposed design implies a perverse policy of not only that one utility but of all PJM transmission owners.  The motion goes on to imply that Constellation’s one experience somehow undermines the justness and reasonableness of PJM’s proposal.  Exelon files this Answer to correct any implication that Exelon, the ultimate parent corporation of various PJM transmission owners, or those various transmission owners are attempting to prevent large loads, co-located or otherwise, and their load serving entities from receiving transmission services in the Exelon utilities’ service territories.

1
See 18 C.F.R. § 385.213(d)(1) (“Any answer to a motion or to an amendment to a motion must be made within 15 days after the motion or amendment is filed, except as described below or unless otherwise ordered.”).

2 Exelon’s subsidiaries are as follows: Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company (“ComEd”), Commonwealth Edison Company of Indiana, Inc., Delmarva Power and Light Company, PECO Energy Company, and Potomac Electric Power Company.

PDF page 2

PUBLIC – Confidential Material Redacted

2
I. REQUEST FOR CUI//PRIV//HC TREATMENT
In accordance with section 388.112 of the Commission’s regulations,3 Exelon requests
privileged treatment for a portion of this Answer containing certain confidential information. Exelon understands that the involved counterparty may view this information as competitively sensitive and the relevant Exelon utility also treats such information as non-public.  Accordingly, good cause exists for the Commission to grant this request for privileged treatment of this information.

Exelon is filing both a public version of this Answer with necessary redactions and a non- public version of this Answer that contains the confidential information.  The non-public version has been labelled “CUI//PRIV//HC” and should be made subject to privileged document protection by the Commission.  In accordance with 18 C.F.R. § 388.112(b)(2)(i), a proposed form of protective agreement modeled on the Commission’s Model Protective Order is enclosed as Attachment B.  To respect the competitive concerns of its customer, the Protective Order has been modified to provide additional protections for material deemed “Highly Confidential Privileged Material.”  Similar provisions have been included in other approved protective orders in recent years.4  Any questions regarding this request for privileged treatment should be directed to the undersigned.

3 18 C.F.R. § 388.112.
4 See, e.g., PJM Interconnection, L.L.C., Docket No. ER23-2214-000, Order of Chief Judge Adopting Protective Order, at P 1 (Dec. 4, 2023) (adopting proposed protective order that “deviates from the Commission’s Model Protective Order by deleting inapplicable provisions related to oil pipeline proceedings” and also “includes provisions to bar disclosure of commercially sensitive information to ‘Competitive Duty Personnel.’” (citation omitted)); DCR Transmission, L.L.C., Docket No. ER23-2309-000, Order of Chief Judge Adopting Protective Order, at P 16 (Jan. 18, 2024); see also Duke Energy Progress, LLC, Docket No. ER25-3483-000, Application, at Attach. G (Sept. 22, 2025) (protective order in Federal Power Act section 205 filing with Highly Confidential Privileged Material provisions).

PDF page 3

PUBLIC – Confidential Material Redacted

3
II. ANSWER
In its motion, Constellation points to a recent communication with a PJM transmission owner concerning a large load interconnection request.  Constellation argues that the transmission owner “informed Constellation that it would not study Constellation’s proposed design unless Constellation agreed to transfer ownership of the ring bus facilities to the Transmission Owner.” Constellation does not address the circumstances in which that communication purportedly occurred, its formality or finality, or the seniority of the individuals involved.  Nonetheless, Constellation argues that this interaction demonstrates the inadequacy of PJM’s proposed definition of co-located load.  This is not correct.  <BEGIN CUI//PRIV//HC>

  <END CUI//PRIV//HC> Constellation’s purported experience indicates neither a
nefarious policy of one utility nor a reason for modifying PJM’s proposal.
<BEGIN CUI//PRIV//HC>

.5
<END CUI//PRIV//HC> As explained in earlier filings, the Exelon companies have seen numerous recent requests for service to new large loads, imposing potentially immense new demands.6   The Exelon utilities are in the business of delivering power to electric customers, and any notion that they are antagonistic to delivering power to certain categories of load is absurd.  Exelon is totally

5
See Declaration of David Weaver, PE, ¶ 11 (“Weaver Declaration”).  The Weaver Declaration is enclosed as Attachment A.

6 See, Exelon December 8, 2025 Answer to Constellation in Docket No. EL25-49, et al.

PDF page 4

PUBLIC – Confidential Material Redacted
4
supportive of service to new large loads, so long as the service is consistent with safe and reliable service, adheres to state and federal legal and regulatory requirements, and properly contributes to the services provided at both the transmission and distribution level.  For example, the effort by ComEd to develop solutions to serve new large loads can be seen in recent filings concerning Transmission Security Agreements (“TSAs”) to accommodate these new arrangements.7 <BEGIN CUI//PRIV//HC>

 <END CUI//PRIV//HC> Constellation provides no support (sworn
or otherwise) for its assertion that the transmission owner “informed Constellation that it would not study Constellation’s proposed design.” <BEGIN CUI//PRIV//HC>

.8
.9
.10
7 See, e.g., Commonwealth Edison Co., 194 FERC ¶ 61,181 (2026) (accepting TSA relating to a new data center). 8 Weaver Declaration ¶ 14. 9 Weaver Declaration, ¶ 12 & 15. 10 Id. ¶ 13. <END CUI//PRIV//HC>

PDF page 5

PUBLIC – Confidential Material Redacted
5
.11
 <END CUI//PRIV//HC>
Constellation argues that this is all very important to PJM’s proposed definition, which includes the concept of the “Point of Change of Ownership.”  But whether a transmission owner owns certain equipment does not necessarily answer the question of where “the Project Developer’s Interconnection Facilities connect to the Transmission Owner’s Interconnection 11

Weaver Declaration ¶ 12–13.
< BEGIN CUI//PRIV//HC>

PDF page 6

PUBLIC – Confidential Material Redacted
6
Facilities.”12  A utility could and sometimes does own switches, breakers, or other equipment in a substation or facility owned by a customer, potentially with easement rights to ensure access. Thus, a conversation about who will own certain equipment in Constellation’s proposed arrangement is not only too preliminary to inform the Commission’s review, but also not informative for the Commission’s review of the proposed PJM definition that refers to the “Point of Change in Ownership”.  PJM’s proposed definition is just and reasonable, as explained in various pleadings submitted in the above-captioned proceedings.13

Constellation’s Motion does not inform the Commission’s review and should be denied. Respectfully submitted,

/s/ Bradley R. Perkins
Bradley R. Perkins
Vice President and Deputy General Counsel
Exelon Corporation
Chase Building
10 S. Dearborn, 52nd Floor
Chicago, IL 60603
Telephone: 312-394-2632
Email: bradley.perkins@exeloncorp.com
On behalf of Exelon Corporation
Dated: April 14, 2026
12 See PJM Interconnection, L.L.C. Open Access Transmission Tariff, Part VII, Subpart A, section 300, Definitions P (defining “Point of Change in Ownership”).
13 See e.g., PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access Transmission Tariff to Comply with Commission Order in Docket No. EL25-49, et al., Docket No. ER26-1479-000, at 31-35 (filed Feb. 23, 2026); Indicated PJM Transmission Owners, Answer of the Indicated PJM Transmission Owners, Docket No. ER26-1088-000 (filed Feb. 27, 2026).

PDF page 7

PUBLIC – Confidential Material Redacted
ATTACHMENT A

PDF page 8

PUBLIC – Confidential
Material Redacted
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.

)
Docket No. ER26-1088-000
PJM Interconnection, L.L.C.

)
Docket No. ER26-1479-000
(not consolidated)
DECLARATION OF DAVID WEAVER, PE
INTRODUCTION
1. My name is David Weaver.  I am the Vice President of Transmission Strategy for Exelon Corporation (“Exelon”).  I oversee the transmission strategy organization with responsibility for transmission planning and analysis across all of the Exelon operating companies.  I began my career with Exelon in January 1996.  I have served in various roles at Exelon in engineering, investment strategy, transmission operations, transmission planning, substation design, project management, and business planning.  Before joining Exelon, I worked at Delmarva Power and Light as an engineer in Substation Design and Transmission Planning.  With more than 35 years of experience in the utility industry, I also served as chair of NERC’s Planning Committee, President and board member of the WIRES transmission industry trade group, and board member of the North American Transmission Forum.  I received my bachelor’s degree in Electrical Engineering from Drexel University and I am a licensed professional engineer.

PURPOSE OF THE DECLARATION
2. I am providing this Declaration on behalf of Exelon and its transmission-owning subsidiaries: Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth

PDF page 9

PUBLIC – Confidential
Material Redacted
2
Edison Company (“ComEd”), Commonwealth Edison Company of Indiana, Inc., Delmarva Power and Light Company, PECO Energy Company, and Potomac Electric Power Company (collectively, the “Exelon Utilities”).

3. I am responding to the Motion for Leave and Supplemental Protest that was filed by Constellation Energy Generation, LLC (“Constellation”) on April 8, 2026 (“Constellation’s Motion”).  In its motion, Constellation points to recent discussions with a PJM transmission owner concerning a data center interconnection request.  Constellation argues that the transmission owner “informed Constellation that it would not study Constellation’s proposed design unless Constellation agreed to transfer ownership of the ring bus facilities to the Transmission Owner.” <BEGIN CUI//PRIV//HC>

 <END CUI//PRIV//HC>
EXELON LARGE LOAD STUDY PROCESS
4. The Exelon Utilities, like others utilities around the nation, have received an unprecedented influx of requests to interconnect new large loads to serve data centers.  At ComEd, for instance, over the past two years, there have been many requests, with projected demands of tens of thousands of megawatts.  The projected demands exceed ComEd’s all-time system peak, which is to say that they would more than double ComEd’s overall demand.

5. The Exelon Utilities are committed to serving these customers—that is their business and obligation.  It is what we do.  But it has to be done in a way that ensures that service is safe and reliable for both existing customers and new customers alike, and thus each request is subject to study.

PDF page 10

PUBLIC – Confidential
Material Redacted
3
6. The details of the study process are evolving, but in general, we have found that it is better for all concerned to conduct studies in clusters, with projects submitted within particular time windows studied in synchrony.  To this end, the Exelon Utilities define study “windows” during which they collect requests from new large loads across their respective service territories.  Each window has a set deadline for submission, and a new window opens once the previous window closes. The utility then aggregates the demand schedules, or “ramp rates,” of all projects submitted during the same window and studies them collectively to determine the cumulative impact on the transmission system.  Through this analysis, the utility also identifies whether any transmission or high voltage system reinforcements or expansions are needed to ensure the safety, reliability, and efficiency of those systems, as well as the utility’s ability to serve all its customers.  A cluster study includes the determination of how customers are interconnected to the grid, a planning analysis to identify any necessary transmission upgrades to maintain reliability, and preliminary engineering, scope, cost, and schedule to connect customers and complete necessary network upgrades. Once a cluster study is complete, customers that execute a transmission security agreement and remain committed to interconnect, have their direct connection needs and any necessary network upgrades detail engineered and planned for actual construction.  That mode of analysis is well-established at Exelon where ComEd, for instance, is completing study of Cluster 2 and preparing to begin Cluster 3.

7. The cluster studies were implemented because one-by-one studies delayed the utility’s ability to provide customers with critical information about potential in-service dates and sometimes required repeated re-studies as new projects entered and exited the queue.  The cluster study process resolves these issues by allowing the utility to evaluate projects together, improving

PDF page 11

PUBLIC – Confidential
Material Redacted
4
responsiveness to customers and capturing economies of scale in study and planning processes.  This approach also provides a more comprehensive and transparent view of the collective impacts of large demand growth.  When multiple projects are proposed in similar timeframes, studying them as clusters enables the utility to better assess overall system reliability and the interrelationship of nearby loads—insights that cannot be achieved through isolated, piecemeal evaluations.  As a result, cluster studies produce more accurate, efficient, and forward-looking outcomes for both applicants and the broader customer base.

8. Because these are studies of service requests for new end users, aspects of their conduct and their application to those retail service applications are subject to regulation by state utility commissions.  For example, the ComEd process was the subject of a proceeding at the Illinois Commerce Commission evaluating proposed tariff amendments to address service to such loads.   That ICC proceeding recently adopted the process proposed by ComEd.  See, https://www.icc.illinois.gov/docket/P2025-0677/documents/377910/files/662669.pdf.

9. It is typical that prior to the study being conducted, there will be one or more informational meetings with the customer to clarify the details of the project to be studied.  These meetings are an early opportunity for engagement, well before the actual studies occur.  The customer may seek clarification on the parameters of the upcoming study, and the utility may obtain information to refine its understanding of the proposal.  Which is to say that the meetings are a two-way street, each side developing a better understanding of what should be studied. These meetings do not include policy or legal teams, and are thus not a place where decisions get resolved.  Where a policy or legal question may arise, those at the meeting will follow an established escalation path to ensure appropriate review by those with decision-making authority.

PDF page 12

PUBLIC – Confidential
Material Redacted
5
10. The Exelon Utilities use similar informational meetings when other interconnection-related issues arise.  Because of this, Constellation is very familiar with the process.  For example, Constellation owns several generation facilities that used to be owned by ComEd, scattered around the ComEd transmission system, and thus such meetings between ComEd and Constellation are routine.  Constellation understands the limited role of those who participate in the informational meetings, but also understands how to escalate an issue to Exelon utility leadership when a dispute arises.

<BEGIN CUI//PRIV//HC>
11. 12.
13. < END CUI//PRIV//HC>

PDF page 13

PUBLIC – Confidential
Material Redacted
6
14. 15.
<END CUI//PRIV//HC>
CONCLUSION
16. It is troubling to me that the engagement with the transmission owner the Constellation Motion references is being used to make a legal case.  For Exelon, informational meetings with customers are never intended to be a place where policy or legal decisions are made. They are intended in good faith as a place and time where engineers can talk freely so that studies can be well conducted, and customers can move through the process and come online as expeditiously and efficiently as possible.  If instead, each party “lawyers up” before each <BEGIN CUI//PRIV//HC>

PDF page 14

PUBLIC – Confidential
Material Redacted
7
such meeting, I doubt that the meetings will have such free-flowing conversation or that they will continue to serve much of a useful purpose.

17. <BEGIN CUI//PRIV//HC>
 <END CUI//PRIV//HC>
The suggestion in the Constellation Motion that Exelon utilities, as PJM transmission owners, have a policy of denying service based on this issue is incorrect. <BEGIN CUI//PRIV//HC>

 <END CUI//PRIV//HC>

PDF page 15

PUBLIC – Confidential
Material Redacted
VERIFICATION
I declare under penalty of perjury that the foregoing Declaration is true and correct to the best of my information, knowledge, and belief.

Executed this 14th day of April 2026.
/s/ David Weaver
Vice President, Transmission Strategy
Exelon Corporation

PDF page 16

PUBLIC – Confidential Material Redacted

ATTACHMENT B

PDF page 17

PUBLIC – Confidential Material Redacted

9

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.

)
Docket No. ER26-1088-000

PJM Interconnection, L.L.C.

)
Docket No. ER26-1479-000
(not consolidated)

PROTECTIVE AGREEMENT

This Protective Agreement (“Agreement”), entered into this ___day of _______, 20_   by and between Exelon Corporation on behalf of its subsidiaries14 (“Exelon”) and ___________ (“Intervenor”), shall govern the use of all Privileged, Highly Confidential Privileged Material, and/or Critical Energy/Electric Infrastructure Information (“CEII”) Material produced by Exelon to Intervenor, or vice versa, in connection with the captioned proceeding before the Federal Energy Regulatory Commission (the “Commission”).  Exelon and Intervenor are sometimes referred to herein individually as a “Participant” or jointly as the “Participants.”

1. Exelon filed in the above-referenced proceeding Privileged Material, Highly Confidential Privileged Material, and/or CEII, as those terms are defined herein.  Intervenor is a Participant in such proceeding, as the term Participant is defined in 18 C.F.R. Section 385.102(b), or has filed a motion to intervene or a notice of intervention in such proceeding.  Exelon and Intervenor enter into this Agreement to govern the use of Privileged Material, Highly Confidential Privileged Material, and/or CEII produced by, or on behalf of, Exelon and/or Intervenor in the above-referenced proceeding.  Notwithstanding any order terminating such proceeding, this Agreement shall remain in effect unless and until specifically modified or terminated by the Commission or a court of competent jurisdiction.  In the event this Agreement terminates, the obligations of Reviewing Representatives to maintain the confidentiality of Privileged Material, Highly Confidential Privileged Material, and/or CEII as provided hereunder shall remain in effect for 18 months following the date of termination.

2. The Commission’s regulations15 and its policy governing the labelling of controlled unclassified information (“CUI”)16 establish and distinguish the respective designations of Privileged Material and CEII.  As to these designations, this Protective Agreement provides that a Participant:

14  Exelon’s subsidiaries are as follows: Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power and Light Company, PECO Energy Company, and Potomac Electric Power Company.
15  Compare 18 C.F.R. § 388.112, with 18 C.F.R. § 388.113.  This Protective Agreement does not alter the respective requirements imposed by these sections on Privileged Material or CEII.
16  Notice of Document Labelling Guidance for Documents Submitted to or Filed with the Commission or Commission Staff, 82 Fed. Reg. 18,632 (Apr. 20, 2017) (issued by Commission Apr. 14, 2017).

PDF page 18

PUBLIC – Confidential Material Redacted

10

A. may designate as Privileged Material any material which customarily is treated by that Participant as commercially sensitive or proprietary or material subject

to a legal privilege, which is not otherwise available to the public, and which if disclosed, would subject that Participant or its customers to risk of competitive disadvantage or other business injury; and

B. must designate as CEII, any material that meets the definition of that term as provided by 18 C.F.R. §§ 388.113(a), (c).

3. For the purposes of this Protective Agreement, the listed terms are defined as follows:

A. Participant(s): As defined at 18 C.F.R. § 385.102(b).
B. Privileged Material:17
i. Material (including depositions) provided by a Participant in response to
discovery requests or filed with the Commission, and that is designated
as Privileged Material by such Participant;18
ii. Material that is privileged under federal, state, or foreign law, such as
work-product privilege, attorney-client privilege, or governmental
privilege, and that is designated as Privileged Material by such
Participant;19
iii. Any information contained in or obtained from such designated
material;
iv. Any other material which is made subject to this Protective Agreement
by the Presiding Administrative Law Judge (Presiding Judge) or the
Chief Administrative Law Judge (Chief Judge) in the absence of the
Presiding Judge or where no presiding judge is designated, the
Commission, any court, or other body having appropriate authority, or
by agreement of the Participants (subject to approval by the relevant
authority);

17  The Commission’s regulations state that “[f]or the purposes of the Commission’s filing requirements, non-CEII subject to an outstanding claim of exemption from disclosure under FOIA will be referred to as privileged material.”  18 C.F.R. § 388.112(a).  The regulations further state that “[f]or material filed in proceedings set for trial-type hearing or settlement judge proceedings, a participant’s access to material for which privileged treatment is claimed is governed by the presiding official’s protective order.”  Id. § 388.112(b)(2)(v).
18  See infra P 11 for the procedures governing the labeling of this designation.
19  The Commission’s regulations state that “[a] presiding officer may, by order . . . restrict public disclosure of discoverable matter in order to . . . [p]reserve a privilege of a participant.” 18 C.F.R. § 385.410(c)(3).  To adjudicate such privileges, the regulations further state that “[i]n the absence of controlling Commission precedent, privileges will be determined in accordance with decisions of the Federal courts with due consideration to the Commission’s need to obtain information necessary to discharge its regulatory responsibilities.”  Id. § 385.410(d)(1)(i).

PDF page 19

PUBLIC – Confidential Material Redacted

11

v. Notes of Privileged Material (memoranda, handwritten notes, or any other form of information (including electronic form) which copies or discloses Privileged Material);20 or

vi. Copies of Privileged Material.
vii. Privileged Material does not include:

1. Any information or document that has been filed with and accepted into the public files of the Commission, or contained in the public files of any other federal or state agency, or any federal or state court, unless the information or document has been determined to be

privileged by such agency or court; or
2. Information that is public knowledge, or which becomes public
knowledge, other than through disclosure in violation of this
Protective Agreement.
C. Highly Confidential Privileged Material: A Participant may use this designation for those materials that are of such a commercially sensitive nature among the Participants or of such a private, personal nature that the producing Participant is able to justify a heightened level of confidential protection with respect to those materials.  Highly Confidential Privileged Material shall include Privileged Material that present a higher risk of competitive injury if disclosed to Competitive Duty Personnel as determined in good faith by the producing Participant and includes materials such as: (1) information regarding contract negotiations and contract buyouts and (2) strategic business or financial plans. Except for the more limited list of persons who qualify as Reviewing Representatives for the purposes of Reviewing Highly Confidential Privileged Material (i.e., Reviewing Representatives that are not Competitive Duty Personnel), such materials are subject to the same provisions in the Protective Agreement as other Privileged Material.

D. Critical Energy/Electric Infrastructure Information (“CEII”): As defined at 18 C.F.R. §§ 388.113(a), (c).

E. Non-Disclosure Certificate: The certificate attached to this Protective Agreement, by which Participants granted access to Privileged Material, Highly Confidential Privileged Material, and/or CEII must certify their understanding that such access to such material is provided pursuant to the terms and restrictions of this Protective Agreement, and that such Participants have read the Protective Agreement and agree to be bound by it.  All executed Non-Disclosure Certificates must be served on all Participants on the official service list maintained by the Secretary of the Commission for this proceeding.

20  Notes of Privileged Material are subject to the same restrictions for Privileged Material except as specifically provided in this Protective Agreement.

PDF page 20

PUBLIC – Confidential Material Redacted

12

F. Reviewing Representative: A person who has signed a Non-Disclosure Certificate and who is:

i. Commission Trial Staff designated as such in this proceeding;
ii. An attorney who has made an appearance in this proceeding for a Participant;

iii. Attorneys, paralegals, and other employees associated for purposes of this case with an attorney who has made an appearance in this proceeding on behalf of a Participant;

iv. An expert or an employee of an expert retained by a Participant for the purpose of advising, preparing for, submitting evidence or testifying in this proceeding;

v. A person designated as a Reviewing Representative by order of the Presiding Judge, the Chief Judge, or the Commission; or

vi. Employees or other representatives of Participants appearing in this proceeding with significant responsibility for this docket.

G. The term “Reviewing Representative” for purposes of reviewing Highly Confidential Privileged Material defined in Paragraph 3(C) shall mean a person who has signed a Non-Disclosure Certificate who is:

i. Listed in Paragraph 3(F), but is not Competitive Duty Personnel as defined in Paragraph 3(H); or

ii. Designated as a Reviewing Representative for purposes of reviewing Highly Confidential Privileged Material by agreement of the producing Participant or by order of the Presiding Judge.

H. The term “Competitive Duty Personnel” shall mean any individual(s) whose scope of employment or engagement includes the marketing, sale, or purchase of coal, natural gas, or electricity (collectively, “Energy”), the direct supervision of any employee or employees whose duties include the marketing of Energy, or other Energy services in competition with the producing Participant, all of which are considered “Competitive Duties,” except that Competitive Duty Personnel shall not include employees of the Commission, any state utilities commission which is a Participant, in-house or outside counsel, and/or an outside consultant retained by a Participant for the purpose of advising, preparing for, submitting evidence, or testifying in this proceeding.

4. Privileged Material, Highly Confidential Privileged Material, and/or CEII shall be made available under the terms of this Protective Agreement only to Participants and only to their Reviewing Representatives as provided in Paragraphs 6–10 of this Protective Agreement. The contents of Privileged Material, Highly Confidential Privileged Material, CEII or any

PDF page 21

PUBLIC – Confidential Material Redacted

13

other form of information that copies or discloses such materials shall not be disclosed to anyone other than in accordance with this Protective Agreement and shall be used only in connection with this specific proceeding.

5. All Privileged Material, Highly Confidential Privileged Material, and/or CEII must be maintained in a secure place.  Access to those materials must be limited to Reviewing Representatives specifically authorized pursuant to Paragraphs 7–9 of this Protective Agreement.

6. Privileged Material, Highly Confidential Privileged Material, and/or CEII must be handled by each Participant and by each Reviewing Representative in accordance with the Non- Disclosure Certificate executed pursuant to Paragraph 9 of this Protective Agreement. Privileged Material, Highly Confidential Privileged Material, and/or CEII shall not be used except as necessary for the conduct of this proceeding, nor shall they (or the substance of their contents) be disclosed in any manner to any person except a Reviewing Representative who is engaged in this proceeding and who needs to know the information in order to carry out that person’s responsibilities in this proceeding.  A Reviewing Representative shall not disclose Highly Confidential Privileged Material to Competitive Duty Personnel, except as authorized pursuant to Paragraph 3(G).  Reviewing Representatives may make copies of Privileged Material, Highly Confidential Privileged Material, and/or CEII, but such copies automatically become Privileged Material, Highly Confidential Privileged Material, and/or CEII.  Reviewing Representatives may make notes of Privileged Material, which shall be treated as Notes of Privileged Material if they reflect the contents of Privileged Material.

7. If a Reviewing Representative’s scope of employment includes any of the activities listed under this Paragraph 7, such Reviewing Representative may not use information contained in any Privileged Material, Highly Confidential Privileged Material, and/or CEII obtained in this proceeding for a commercial purpose (e.g., to give a Participant or competitor of any Participant a commercial advantage):

A. Energy marketing;
B. Direct supervision of any employee or employees whose duties include energy marketing; or

C. The provision of consulting services to any person whose duties include energy marketing.

8. If a Participant wishes to designate a person not described in Paragraph 3(F) above as a Reviewing Representative, the Participant must seek agreement from the Participant providing the Privileged Material, Highly Confidential Privileged Material, and/or CEII.  If an agreement is reached, the designee shall be a Reviewing Representative pursuant to Paragraph 3(E) of this Protective Agreement with respect to those materials.  If no agreement is reached, the matter must be submitted to the Presiding Judge or the Commission for resolution.

9. A Reviewing Representative shall not be permitted to inspect, participate in discussions regarding, or otherwise be permitted access to Privileged Material, Highly Confidential

PDF page 22

PUBLIC – Confidential Material Redacted

14

Privileged Material, and/or CEII pursuant to this Protective Agreement until three business days after that Reviewing Representative first has executed and served a Non-Disclosure Certificate.21  However, if an attorney qualified as a Reviewing Representative has executed a Non-Disclosure Certificate, any participating paralegal, secretarial and clerical personnel under the attorney’s instruction, supervision or control need not do so.  Attorneys designated Reviewing Representatives are responsible for ensuring that persons under their supervision or control comply with this Protective Agreement, and must take all reasonable precautions to ensure that Privileged Material, Highly Confidential Privileged Material, and/or CEII are not disclosed to unauthorized persons.  Reviewing Representatives that are Competitive Duty Personnel as defined in Paragraph 3(H) must execute a Non-Disclosure Certificate for Competitive Duty Personnel in the form attached hereto.  All executed Non- Disclosure Certificates must be served on all Participants on the official service list maintained by the Secretary of the Commission for the proceeding.

10. Any Reviewing Representative may, consistent with the requirements in Paragraph 3(G), disclose Privileged Material, Highly Confidential Privileged Material, and/or CEII to any other Reviewing Representative as long as both Reviewing Representatives have executed a Non-Disclosure Certificate.  In the event any Reviewing Representative to whom Privileged Material, Highly Confidential Privileged Material, and/or CEII are disclosed ceases to participate in this proceeding, or becomes employed or retained for a position that renders him or her ineligible to be a Reviewing Representative under Paragraph 3(F) of this Protective Agreement, access to such materials by that person shall be terminated.  Even if no longer engaged in this proceeding, every person who has executed a Non-Disclosure Certificate shall continue to be bound by the provisions of this Protective Agreement and the Non-Disclosure Certificate for as long as the Protective Agreement is in effect.22

11. All Privileged Material, Highly Confidential Privileged Material, and/or CEII in this proceeding filed with the Commission, submitted to the Presiding Judge, or submitted to any Commission personnel, must comply with the Commission’s Notice of Document Labelling Guidance for Documents Submitted to or Filed with the Commission or Commission Staff.23 Consistent with those requirements:

A. Documents that contain Privileged Material must include a top center header on each page of the document with the following text: CUI//PRIV or

CUI//PRIV//HC for Highly Confidential Privileged Material.  Any corresponding electronic files must also include this text in the file name.

B. Documents that contain CEII must include a top center header on each page of the document with the following text: CUI//CEII.  Any corresponding electronic files must also include this text in the file name.

21  During this three-day period, a Participant may file an objection with the Presiding Judge or the Commission contesting that an individual qualifies as a Reviewing Representative, and the individual shall not receive access to the Privileged Material, Highly Confidential Privileged Material, and/or CEII until resolution of the dispute.
22  See infra P 19.
23  82 Fed. Reg. 18,632 (Apr. 20, 2017) (issued by Commission Apr. 14, 2017).

PDF page 23

PUBLIC – Confidential Material Redacted

15

C. Documents that contain both Privileged Material and CEII must include a top center header on each page of the document with the following text:

CUI//CEII/PRIV.  Any corresponding electronic files must also include this text in the file name.

D. The specific content on each page of the document that constitutes Privileged Material and/or CEII must also be clearly identified.  For example, lines or individual words or numbers that include both Privileged Material and CEII shall be prefaced and end with “BEGIN CUI//CEII/PRIV” and “END

CUI//CEII/PRIV”.
12. If any Participant desires to include, utilize, or refer to Privileged Material (or Highly Confidential Privileged Material) or information derived from Privileged Material (or Highly Confidential Privileged Material) in testimony or other exhibits during the hearing in this proceeding in a manner that might require disclosure of such materials to persons other than Reviewing Representatives, that Participant first must notify both counsel for the disclosing Participant and the Presiding Judge (or the Commission), and identify all such Privileged Material (or Highly Confidential Privileged Material).  Thereafter, use of such Privileged Material (or Highly Confidential Privileged Material) will be governed by procedures determined by the Presiding Judge (or the Commission).

13. Nothing in this Protective Agreement shall be construed as precluding any Participant from objecting to the production or use of Privileged Material, Highly Confidential Privileged Material, and/or CEII on any appropriate ground.

14. Nothing in this Protective Agreement shall preclude any Participant from requesting the Presiding Judge (or the Chief Judge in the Presiding Judge’s absence or where no presiding judge is designated), the Commission, or any other body having appropriate authority, to find this Protective Agreement should not apply to all or any materials previously designated Privileged Material (or Highly Confidential Privileged Material) pursuant to this Protective Agreement.  The Presiding Judge (or the Chief Judge in the Presiding Judge’s absence or where no presiding judge is designated), the Commission, or any other body having appropriate authority may alter or amend this Protective Agreement as circumstances warrant at any time during the course of this proceeding.

15. Each Participant governed by this Protective Agreement has the right to seek changes in it as appropriate from the Presiding Judge (or the Chief Judge in the Presiding Judge’s absence or where no presiding judge is designated), the Commission, or any other body having appropriate authority.

16. Subject to Paragraph 17, the Presiding Judge (or the Chief Judge in the Presiding Judge’s absence or where no presiding judge is designated), or the Commission shall resolve any disputes arising under this Protective Agreement pertaining to Privileged Material (or Highly Confidential Privileged Material) according to the following procedures.  Prior to presenting any such dispute to the Presiding Judge, the Chief Judge or the Commission, the Participants to the dispute shall employ good faith best efforts to resolve it.

PDF page 24

PUBLIC – Confidential Material Redacted

16

A.  Any Participant that contests the designation of material as Privileged Material (or Highly Confidential Privileged Material) shall notify the Participant that provided the Privileged Material (or Highly Confidential Privileged Material) by specifying in writing the material for which the designation is contested.

B.  In any challenge to the designation of material as Privileged Material (or Highly Confidential Privileged Material), the burden of proof shall be on the Participant seeking protection.  If the Presiding Judge, the Chief Judge, or the Commission finds that the material at issue is not entitled to the designation, the procedures of Paragraph 17 shall apply.

C. The procedures described above shall not apply to material designated by a Participant as CEII.  Material so designated shall remain subject to the

provisions of this Protective Agreement, unless a Participant requests and obtains a determination from the Commission’s CEII Coordinator that such

material need not retain that designation.
17. The designator will have five (5) days in which to respond to any pleading requesting disclosure of Privileged Material (or Highly Confidential Privileged Material).  Should the Presiding Judge, the Chief Judge, or the Commission, as appropriate, determine that the information should be made public, the Presiding Judge, the Chief Judge, or the Commission will provide notice to the designator no less than five (5) days prior to the date on which the material will become public.  This Protective Agreement shall automatically cease to apply to such material on the sixth (6th) calendar day after the notification is made unless the designator files a motion with the Presiding Judge, the Chief Judge, or the Commission, as appropriate, with supporting affidavits, demonstrating why the material should continue to be privileged.  Should such a motion be filed, the material will remain confidential until such time as the interlocutory appeal or certified question has been addressed by the Motions Commissioner or the Commission, as provided in the Commission’s regulations, 18 C.F.R. §§ 385.714 and 385.715.  No Participant waives its rights to seek additional administrative or judicial remedies after a Presiding Judge or Chief Judge decision regarding Privileged Material (or Highly Confidential Privileged Material) or the Commission’s denial of any appeal thereof or determination in response to any certified question.  The provisions of 18 C.F.R. §§ 388.112 and 388.113 shall apply to any requests under the Freedom of Information Act (5 U.S.C. § 552) for Privileged Material (or Highly Confidential Privileged Material) and/or CEII in the files of the Commission.

18. Privileged Material, Highly Confidential Privileged Material, and/or CEII shall remain available to Participants until the later of 1) the date an order terminating this proceeding no longer is subject to judicial review, or 2) the date any other Commission proceeding relating to the Privileged Material, Highly Confidential Privileged Material, and/or CEII is concluded and no longer subject to judicial review.  After this time, the Participant that produced the Privileged Material, Highly Confidential Privileged Material, and/or CEII may request (in writing) that all other Participants return or destroy the Privileged Material, Highly Confidential Privileged Material, and/or CEII.  This request must be satisfied with within fifteen (15) days of the date the request is made.  However, copies of filings, official transcripts and exhibits in this proceeding containing Privileged Material, Highly Confidential Privileged Material, or Notes of Privileged Material, may be retained if they are maintained in accordance

PDF page 25

PUBLIC – Confidential Material Redacted

17

with Paragraph 5 of this Protective Agreement.  If requested, each Participant also must submit to the Participant making the request an affidavit stating that to the best of its knowledge it has satisfied the request to return or destroy the Privileged Material, Highly Confidential Privileged Material, and/or CEII.  To the extent Privileged Material, Highly Confidential Privileged Material, and/or CEII are not returned or destroyed, they shall remain subject to this Protective Agreement.

19. Regardless of any order terminating this proceeding, this Protective Agreement shall remain in effect until specifically modified or terminated by the Presiding Judge, the Chief Judge, or the Commission.  All CEII designations shall be subject to the “[d]uration of the CEII designation” provisions of 18 C.F.R. § 388.113(e).

20. Any violation of this Protective Agreement and of any Non-Disclosure Certificate executed hereunder shall constitute a violation of an order of the Commission.

For Exelon:
Signed:  ______________________________
Printed Name:  ________________________
Date: ________________________________

For Intervenor:
Signed:  ______________________________
Printed Name:  _________________________
Date:  ________________________________

PDF page 26

PUBLIC – Confidential Material Redacted

UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

)
Docket No. ER26-1088-000

PJM Interconnection, L.L.C.

)
Docket No. ER26-1479-000
(not consolidated)

NON-DISCLOSURE CERTIFICATE FOR NON-COMPETITIVE DUTY PERSONNEL
I hereby certify my understanding that access to Privileged Material, Highly Confidential Privileged Material, and/or Critical Energy/Electric Infrastructure Information (CEII) is provided to me pursuant to the terms and restrictions of the Protective Agreement in this proceeding, that I have been given a copy of and have read the Protective Agreement, and that I agree to be bound by it.  I understand that the contents of Privileged Material, Highly Confidential Privileged Material, and/or CEII, any notes or other memoranda, or any other form of information that copies or discloses such materials, shall not be disclosed to anyone other than in accordance with the Protective Agreement. I acknowledge that a violation of this certificate constitutes a violation of an order of the Federal Energy Regulatory Commission.

By: ______________________________________
Printed Name: ______________________________
Title: _____________________________________
Representing: ____________________________
Date: _____________________________________

PDF page 27

PUBLIC – Confidential Material Redacted

UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

)
Docket No. ER26-1088-000

PJM Interconnection, L.L.C.

)
Docket No. ER26-1479-000
(not consolidated)

NON-DISCLOSURE CERTIFICATE
FOR COMPETITIVE DUTY PERSONNEL
I hereby certify my understanding that access to Privileged Material in the above-captioned case is provided to me pursuant to the terms and restrictions of the Protective  Agreement in this proceeding, that I have been given a copy of and have read the Protective Agreement, and that I agree to be bound by it.  I understand that the contents of Privileged Material, any notes or other memoranda, or any other form of information that copies or discloses Privileged  Material shall not be disclosed to anyone other than in accordance with the Protective Agreement and shall be used only in connection with this proceeding.  I acknowledge that my duties and responsibilities include “Competitive Duties” as described in the Protective Agreement and, as such, I understand that I shall neither have access to, nor disclose, the contents of the Highly Confidential Privileged Material that are marked as “CUI//PRIV//HC,” any notes or other memoranda, or any other form of information that copies or discloses Privileged Material that is marked as “CUI//PRIV//HC.”  I acknowledge that a violation of this certificate constitutes a violation of an order of the Federal Energy Regulatory Commission.

 By:

By: ______________________________________
Printed Name: ______________________________
Title: _____________________________________
Representing: ____________________________
Date: _____________________________________

PDF page 28

PUBLIC – Confidential Material Redacted

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Chicago, IL this 14h day of April, 2026.

/s/ Geneva Kennedy
Geneva Kennedy
Exelon Corporation