ER26-1479-000 · 2026-05-08 · Calibrant EnergyAntora Energy LLCConvergent Energy and Power LP, Eolian, LP and 2 others
Motion for Leave to Answer and Answer of Calibrant Energy et al. in response to the 04/24/2026 Answer of the Indicated PJM Transmission Owners
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, LLC
)
Docket No. ER26-1479-000
)
MOTION FOR LEAVE TO ANSWER AND ANSWER OF THE BTMG PARTIES
Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal
Energy Regulatory Commission (Commission), 18 C.F.R. §§ 385.212 and 385.213, Calibrant Energy (Calibrant), Antora Energy, Inc. (Antora), Convergent Energy and Power (Convergent), Eolian L.P. (Eolian), Mainspring Energy, Inc. (Mainspring), and Verrus, LLC (Verrus) (together, BTMG Parties) hereby move to answer and submit this Answer in response to the Answer of the Indicated PJM Transmission Owners (PJM TOs) filed on April 24, 2026, in the above-captioned proceeding.
I. MOTION FOR LEAVE TO ANSWER
Although the Commission’s procedural rules generally do not allow answers to answers,
the Commission may permit them for good cause.1 The Commission frequently accepts answers that clarify the issues before the Commission, ensure a complete record, or otherwise assist the Commission in its decision-making.2 BTMG Parties respectfully request that the Commission accept this answer to clarify certain issues and assist the Commission with its decision-making.
1 See 18 C.F.R. § 385.213.2 See, e.g., PJM Interconnection, L.L.C., 182 FERC ¶ 61,073, at P 13 (2023) (accepting answers to answers that “provided information that assisted us in our decision-making process”); New Fortress Energy LLC, 174 FERC ¶ 61,207, at P 7 (2021) (accepting answers because they provided information that assisted the Commission’s decision-making process); Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) (accepting answers that “clarify the concerns raised and provide information that has assisted in our decision making”); Saltville Gas Storage Co., L.L.C., 164 FERC ¶ 61,212, at P 2 n.6 (2018) (accepting answers that “assist the Commission in understanding the issues raised, and will ensure a complete record”).
PDF page 2
2
II. ARGUMENT
A. BTMG Parties and PJM TOs Agree That Workable and Broadly Construed
Grandfathering Provisions Are Necessary to Avoid Substantial Harm due to Reasonable Reliance on Retail Behind-the-Meter-Generation (BTMG) Rules.
The PJM TOs support PJM’s 50 MW threshold but advocate that “this threshold be paired with grandfathering provisions that appropriately recognize that industrial and commercial customers have relied on Retail BTMG rules and that eliminating the ability to continue relying on those provisions could cause them substantial financial harm.”3 While the BTMG Parties contest PJM TOs’ mischaracterization of the BTMG Parties’ protest, they agree with PJM TOs on a critical point: the limits on BTMG arrangements must be paired with workable grandfathering for projects that “would have been eligible for Retail BTMG treatment” but for imposition of the materiality threshold and “have made substantial progress toward completion” in order to protect the reasonable investment-backed expectations of PJM customers (and the BTMG developers) and to ensure just and reasonable rates.
1. PJM TOs Mischaracterize BTMG Parties’ Position on the Materiality
Threshold.
As an initial matter, PJM TOs do not accurately state the position of the BTMG Parties. PJM TOs claim that “[s]everal commentors argue that a nameplate-based threshold is inappropriate and urge the Commission to adopt a materially higher threshold, such as 200 MW.”4 PJM TOs do not address the substance of the BTMG Parties’ argument: BTMG Parties protested PJM’s proposed netting threshold because it did not comply with the directive in the Commission’s order directing PJM’s compliance in this proceeding (Co-Location Order).5 PJM TOs do not demonstrate that PJM’s proposal imposes a “MW threshold for the amount of load
3 PJM TOs Answer at 3.4 Id. at 2.5 See PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (Co-Location Order).
PDF page 3
3
that Network Customers may net by using BTMG” as directed in ordering paragraph (F) of the Co-Location Order, and therefore is non-responsive to BTMG Parties’ argument.6 Instead, PJM TOs argue that a different threshold based on nameplate capacity would also be a just and reasonable replacement rate.7 But the question before the Commission in this compliance docket is not whether a nameplate-based threshold could be just and reasonable, nor whether the Commission should have imposed a nameplate-based threshold replacement rate in the Co- Location Order (a matter to be contested only via a request for rehearing); rather the sole legal question before the Commission is whether PJM complied with the directives in Co-Location Order. Because PJM did not, that is the end of the matter.
2. BTMG Parties and the PJM TOs Agree that Workable
Grandfathering Provisions Are Essential to Ensure Just and Reasonable
Rates.
In any event, the BTMG Parties and the PJM TOs agree on a critical point regarding PJM’s proposed tariff revisions: the grandfathering provisions must be implemented so as to avoid substantial harm to the investment-backed expectations of customers who relied on the existing BTMG provisions, as the Commission required in its Co-Location Order. BTMG Parties agree with PJM TOs that:
• Grandfathering treatment should extend to projects that are not yet in service and would have been eligible for Retail BTMG treatment, but have made substantial progress towards completion.
• The “existing contract” exception to the application of the new Retail BTMG rules should be construed broadly to cover a wide range of contracts and recognition of renewal rights in those contracts.
6 BTMG Parties Protest at 1 (citing Co-Location Order at Ordering P (F) & PP 179, 221).7 PJM TOs Answer at 2-3 (“PJM reasonably based the threshold on generator size—measured by cumulative nameplate rating—because generator capacity is static and administrable, whereas load can fluctuate”).
PDF page 4
4
• Grandfathering treatment should be extended to existing Retail BTMG arrangements that have been physically in service and operating for a significant period of time to avoid disrupting these long-standing arrangements.8
As the BTMG Parties explained in their protest, developing BTMG resources takes years and millions of dollars in investment. Failure to grandfather projects that would have been eligible for Retail BTMG treatment and that have made substantial progress towards completion and/or have committed significant financial investments towards their development pursuant to contractual arrangements would be unjust and unreasonable.9 As PJM TOs explain, “eliminating the ability to continue relying on [previously applicable Retail BTMG rules] could cause [customers] substantial financial harm.”10 In their protest, BTMG Parties offered multiple ways to avoid this unjust and unreasonable outcome, including: extending the starting point from which grandfathering occurs (effectively providing more advance notice and opportunity to be eligible for grandfathering)11 to customers already developing projects that would have been eligible for Retail BTMG treatment; and/or increasing the size of the materiality threshold to 200 MW if the Commission elects to accept a materiality threshold based on nameplate capacity (effectively providing PJM customers more opportunity to realize the commercial benefit of their preexisting investment into BTMG projects).12 BTMG Parties agree with the PJM TOs’ proposal to ensure grandfathering of any projects that (1) “have made substantial progress towards completion”; (2) have an “existing contract,” within a broadly construed meaning of that phrase; or (3) are physically in service because such grandfathering is necessary to appropriately
8 Id. at 3-4.9 BTMG Parties Protest at 13-15 (narrow grandfathering provisions “could leave retail customers who have been developing projects for several years and have invested millions in infrastructure to serve loads wholly ineligible to net, upsetting commercial expectations and threatening project viability”).10 PJM TOs Answer at 3.11 BTMG Parties Protest at 13-16.12 Id. at 12-13.
PDF page 5
5
recognize the years and substantial financial investments of PJM customers based on Retail BTMG rules.
B. The Record Supports Expanding Transmission Services Eligibility to
Similarly Situated Customers that Do Not Have Generation with a PJM
Interconnection Agreement.
PJM TOs urge the Commission to “reject the Joint Parties’ request that it reject or defer action on PJM’s proposal to limit the new transmission service options to Co-Located Load.”13 They argue that “there is absolutely no evidence in the record to suggest that load-only customers should be entitled to utilize these transmission services”14 and that “the new services are tied to generator-specific attributes that ordinary load-only customers do not share, including an associated generator, separate metering from that generator, and the ability and willingness to prevent or limit withdrawals through the co-location configuration itself.”15 But the PJM TOs are wrong on both points:
(1) There is robust evidence in the record that load-only customers should be entitled to utilize these transmission services. The Commission’s core findings draw from pleadings that demonstrate why load-only customers should be allowed to access the new transmission services.
(2) The new services are not tied to generator-specific attributes. Even if they were, that would not justify denying service to co-location configurations where the generator does not inject into the PJM system.
Robust record evidence supports extending the new transmission services to load-only customers, including customers with BTMG. The evidence the Commission relied on in ordering
13 PJM TOs Answer at 6.14 Id.15 Id. at 7.
PDF page 6
6
PJM to develop the new transmission services applies both to co-location configurations
involving PJM-interconnected generation, as well as BTMG or inherently flexible load that enables the same capabilities to limit grid withdrawals. Specifically, the Antora comments the Commission relied upon16 explained that Antora’s thermal battery technology provides for an inherently flexible, low-load factor load, whether or not co-located with generation.17 As Antora explained with regard to these flexible loads, “[w]here a customer could have instead taken curtailable transmission service that allows PJM and/or the [Electric Distribution Company] to curtail its load if that service were offered, the failure to provide a service option that incorporates load flexibility will directly lead to costs for the interconnecting customer that do not appropriately reflect its flexibility and resulting ability to avoid using high value energy or grid capacity.”18
Further, the Co-Location Order makes clear that PJM should take measures “to
minimize the impact of [the BTMG rule] transition on existing BTMG customers,”19 and
emphasizes that these BTMG rule revisions apply broadly beyond the context of Co-Located Load.20 PJM is required to put forth a replacement rate for BTMG that is just and reasonable and not unduly discriminatory. The record demonstrates that customers with behind-the-meter
generation, like those with front-of-meter arrangements, can limit the amount of transmission
16 See Co-Location Order at P199 n. 423 (citing Antora, April 23 Reply Comments, Docket Nos. EL25-49 et al., at 11-12 (filed April 23, 2025)).17 Antora, April 23 Reply Comments, Docket Nos. EL25-49 et al., at 4 (April 23, 2025) (“Like electro-chemical batteries, a significant portion of Antora’s thermal battery value comes from flexibility. The battery is charged during periods of high energy production and low demand, thereby helping reduce curtailment of renewable resources and allowing the thermal battery to absorb low value/negatively priced electricity. Because thermal storage can provide 24/7 heat over a multi-day period by charging only roughly 1/3 of the time, it can fully avoid periods of high demand, high-capacity utilization and high electricity pricing.”). Id. at 6 (“PJM’s existing tariff is unjust, unreasonable, and unduly discriminatory because it does not offer any study process or form of transmission service that properly accounts for highly flexible and low load factor loads such as Antora’s thermal energy storage.”).18 Id. at 11-12 (cited by the Commission at n. 423). 19 Co-Location Order at P 222.20 Id. at P 186.
PDF page 7
7
they need, such that it would be not just and reasonable and unduly discriminatory to set forth a BTMG replacement rate that fails to offer the new transmission services opportunities to these customers. For example, PJM Industrial Customer Coalition explained that customers with BTMG may have an “identical impact to the transmission grid” as customers with PJM- interconnected generation, arguing that the Commission should provide a transmission service “methodology that does not discriminate between or among classes of transmission customers” and that focuses on actual use of the transmission system.21 Other comments similarly argued that transmission costs should follow the Commission’s cost causation principles, including accounting for where a facility is able to limit its use of the transmission system,22 and pointed out that “multiple viable configurations of co-located load and generation exist today, including both front-of-meter and behind-the-meter designs.”23 In addition, Joint Parties in this docket explained that “loads connected to behind-the-meter generation without interconnection rights” may demonstrate the same capabilities as Co-Located Loads to “limit their energy withdrawals from the transmission system.”24
PJM and the PJM TOs may reasonably seek assurance that the relevant load is in fact capable and obligated to limit its withdrawals. But the Commission can provide for such assurance in the relevant tariff provisions setting forth the new transmission service options rather than categorically excluding a class of market participants willing and able to limit
21 PJM Industrial Customer Coalition & Industrial Energy Consumers of America, April 23 Reply Comments, Docket Nos. EL25-49 et al., at 9-10 (filed April 23, 2025) (emphasis in original).22 Co-Location Order, 193 FERC ¶ 61,217 at P 63 (referencing Electricity Consumers Resource Council, April 23 Reply Comments, Docket Nos. EL25-49 et al., at 7 (filed April 23, 2025)).23 Data Center Coalition, April 23 Reply Comments, Docket Nos. EL25-49 et al., at 7 (filed April 23, 2025)24 Joint Parties Protest at 10.
PDF page 8
8
withdrawals. The Commission has ample record to assess the technical requirements necessary to ensure that any customer taking such service can appropriately limit withdrawals.25
Accordingly, the record of this compliance proceeding and the underlying show cause
proceeding contains ample evidence to support extending new transmission service eligibility to all customers willing and able to limit withdrawals from the grid, including load-only customers served by BTMG or otherwise able to consume flexibly.
Contrary to PJM TOs’ claims, nothing about such willingness and ability to limit
withdrawals is “tied to generator-specific attributes that ordinary load-only customers do not share, including an associated generator, separate metering from that generator, and the ability and willingness to prevent or limit withdrawals through the co-location configuration itself.”26 Rather than accepting PJM’s proposed restrictions, the Commission should require PJM to tailor new transmission service eligibility more closely to the Commission’s justification in issuing the Co-Location Order: the willingness and ability to limit withdrawals from the transmission system under specified circumstances. As noted above, loads beyond those co-located with generation with injection rights are also able to limit withdrawals and may be interested in subscribing to the new transmission services. These include loads served by BTMG as well as flexible loads like those identified by Antora, among others. PJM TOs do not specify what generator-specific attributes these loads lack that would prohibit them from complying with any curtailment
25 See, e.g., PJM, Initial Brief, Docket Nos. EL25-49 et al., Attachment A Illustrative Language for New Tariff, Part XI; Attachments F-3A and F-4; and Other Illustrative Tariff Revisions, §§710.4 & 710.5 (filed Feb. 23, 2026) (proposing technical and facilities installation requirements that Co-Located Loads must comply with before commencing contract demand transmission service).26 PJM TOs Answer at 7. Further, to the extent the Commission were to determine that any generator located at the same point of interconnection must be separately metered in order for the customer to qualify for the new transmission services, generation currently classified as BTMG could install the necessary equipment to meet the requirement. But the framework put forth by Commission goes significantly further by requiring interconnection, leaving any generation that falls above the netting threshold stranded. Such customers would find themselves not only exposed to transmission charges for the first time, but unable to appropriately leverage their existing generation to reduce transmission service requirements.
PDF page 9
9
requirements or instructions. And they cannot, because the ability to inject to the grid is not required to enable a load to limit withdrawals from the transmission system.
Even if PJM TOs were correct that something about the new transmission services necessitated the presence of an associated generator or other attributes that such a generator could provide, that would support, rather than preclude, extending new service eligibility at least to loads served by BTMG. These loads are associated with generation behind the point of interconnection. The fact that they lack interconnection agreements and attendant rights to inject is immaterial to their ability to allow loads to limit withdrawals from the transmission system.
If a load is able to meet technology-neutral technical requirements to demonstrate reliable curtailment eligibility, it should be allowed to enroll in the new transmission services.
Respectfully submitted,
/s/ Matt Barnes
/s/ Kim Smaczniak
Matt Barnes
Kim Smaczniak
Chief Commercial Officer
Miles Farmer
Calibrant Energy
Nathan Lobel
4830 W. Kennedy Blvd, Suite 600
Roselle LLP
Tampa, Florida 33609
300 New Jersey Ave. NW, Suite 300
matthew.barnes@calibrantenergy.com
Washington, DC 20001
kim.smaczniak@rosellellp.com
/s/ Noah Long
miles.farmer@rosellellp.com
Noah Long
nathan.lobel@rosellellp.com
Director, State and Regulatory Affairs
Antora Energy, Inc.
Counsel for Calibrant Energy
200 West De Vargas St
Santa Fe, NM 87501
noah.long@antora.com
PDF page 10
10
/s/ Katie Guerry
Katie Guerry
SVP Regulatory and Government Affairs
Convergent Energy and Power
7 Time Square, Suite 3504
NY, NY 10036
kguerry@convergentep.com
/s/ Eric Stoutenburg
Eric Stoutenburg
Chief Development Officer
Eolian L.P.
988 Howard Ave. Suite 200
Burlingame, CA 94010
eric.stoutenburg@eolianenergy.com
/s/ Brian Kauffman
Brian Kauffman
Direct, Wholesale Market Development
Mainspring Energy, Inc.
3601 Haven Ave.
Menlo Park, CA 94025
brian.kauffman@mainspringenergy.com
/s/ Jeff Bladen
Jeff Bladen
Head of Energy
Verrus, LLC
918 N Rengstorff Ave.
Mountain View, CA 94043
bladen@verrusdata.com
PDF page 11
11
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Commission in this proceeding.
Dated: May 8, 2026
/s/ Nathan Lobel
Nathan Lobel
Roselle LLP
300 New Jersey Ave. NW, Suite 300
Washington, DC 20001
nathan.lobel@rosellellp.com