Motion for Leave to Answer and Limited Answer of the Indicated PJM Transmission Owners in response to certain parties' responses to the 04/24/2026 Answer
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-1479-000
MOTION FOR LEAVE TO ANSWER AND LIMITED ANSWER OF
THE INDICATED PJM TRANSMISSION OWNERS
Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”), 18 C.F.R. §§ 385.212 and 385.213, the
Indicated PJM Transmission Owners1 submit this Limited Answer in response to certain parties’ responses to the PJM Transmission Owners’ April 24, 2026 answer submitted regarding PJM Interconnection, L.L.C.’s (“PJM”) 60-Day Compliance Filing in the above-captioned proceeding.2 This answer is limited to addressing replies to the PJM Transmission Owners on the issue of PJM’s proposed modifications to retail Behind the Meter-Generation (“Retail BTMG”) rules, in
compliance with the Commission’s December 18, 2025 Order in this proceeding (“December 18
1 For purposes of this filing, the Indicated PJM Transmission Owners are: American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; The Dayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; Public Service Electric and Gas Company; Rockland Electric Company; and the Southern Maryland Electric Cooperative (“PJM Transmission Owners”).2 To the extent required, the PJM Transmission Owners respectfully move for leave to answer. The Commission’s procedural rules generally prohibit answers to answers. However, the Commission has the discretion to waive its prohibition of answers to answers for good cause shown, i.e., to assist the Commission’s understanding and resolution of the issues raised or to ensure a complete record. See, e.g., Pioneer Transmission, LLC v. N. Ind. Pub. Serv. Co., 140 FERC ¶ 61,057, at P 94 (2012); Midwest Indep. Transmission Sys. Operator, Inc., 120 FERC ¶ 61,083, at P 23 (2007); Morgan Stanley Cap. Grp., Inc. v. N.Y. Indep. Sys. Operator, Inc., 93 FERC ¶ 61,017, at 61,036 (2000); CNG Transmission Corp., 89 FERC ¶ 61,100, at 61,287 n.11 (1999). This Answer is submitted to ensure a complete and accurate record. Accordingly, good cause exists to permit this answer.
PDF page 2
2
Order”),3 specifically the level of materiality threshold for Retail BTMG, as well as the proposed grandfathering provisions to ensure that existing Retail BTMG arrangements are not unfairly harmed by the transition to the new Retail BTMG rules required by the December 18 Order.4 For the reasons explained below, the Commission should reject arguments for a materiality threshold greater than 50 MW, while ensuring that grandfathering provisions are appropriately robust to avoid unfair impacts to existing customers that have substantially relied on PJM’s Retail BTMG rules.
I. ANSWER
In their April 24 answer, the PJM Transmission Owners explained that the Commission should reject arguments arguing for a Retail BTMG threshold higher than 50 MW because the 50 MW threshold strikes the appropriate balance between allowing continued use of Retail BTMG with the appropriate limitations to ensure reliability. In response, the Answering Parties contend that 50 MW is “arbitrarily low” and would include facilities that pose no reliability risk to PJM.5 These arguments broadly miss the point: the issue is less that existing Retail BTMG arrangements create substantial reliability risks on their own, but rather that the proliferation of large loads, including those that opt to utilize arrangements with on-site generation, pose an increasing risk due to the fact that Retail BTMG are not fully accounted for in resource adequacy planning and can shift costs onto other transmission customers contrary to cost causation principles.6
3
PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at PP 179, 221-224 (2025).
4
Specifically, the PJM Transmission Owners reply to the further answers filed by Eastman Chemical Company (“Eastman”), the PJM Industrial Customer Coalition (“Industrials”), and the BTMG Parties (collectively, “Answering Parties”).
5
Eastman at 3; Industrials at 3-4.
6
December 18 Order at P 186.
PDF page 3
3
These were the concerns underlying the Commission’s finding that PJM’s existing Retail BTMG arrangements are no longer just and reasonable, with the Commission specifically agreeing with PJM’s explanation that the existing BTMG rules were conceived and implemented for substantially smaller loads, and that problems could occur if large loads were allowed to use the existing BTMG rules.7 Although Commission did not make a finding as to a particular just and reasonable materiality threshold in the December 18 Order, it did note as “points of reference” that PJM requires individual metering for generators above 10 MW and that the Commission’s definition of a small generator is 20 MW.8 In this light, PJM’s 50 MW threshold is entirely reasonable, as it is high enough to exempt substantially-sized commercial and industrial facilities, but is not so high as to create ongoing reliability risks as well as shifting an unreasonable amount of costs to other ratepayers. The need to avoid cost-shifting is particularly apt given concerns over ratepayer affordability and subsidization, which will only increase as more large loads come online. For these reasons, the Commission should accept PJM’s 50 MW threshold. The Commission should also reject arguments that PJM failed to comply with the
December 18 Order because it proposed a Retail BTMG materiality threshold based on generation capacity rather than load size. As PJM explained, it reasonably based the threshold on generator size—measured by cumulative nameplate rating—because generator capacity is static and administrable, whereas load can fluctuate.9 None of the Answering Parties adequately address this point, instead focusing on the reference to the “amount of load” in the December 18 Order, particularly in Ordering Paragraph (F).10 However, that Ordering Paragraph made clear that PJM’s
7 Id.8 Id. at P 221.9 PJM Compliance Filing at 14.10 See BTMG Parties at 2-3.
PDF page 4
4
compliance obligation was “as discussed in the body” of the December 18 Order. In discussing potentially appropriate thresholds in the body of the December 18 Order, the Commission did not preclude a generation-based threshold. To the contrary, the Commission specifically provided two points of reference based on generator size, rather than the size of load itself. Answering Parties’ contentions that PJM’s proposal conflicts with the December 18 Order are therefore without merit.11
Finally, it is clear from Answering Parties arguments that their primary concern involves the treatment of existing Retail BTMG customers, rather than new large loads. The PJM Transmission Owners agree it is important that an appropriate materiality threshold rule should be paired with grandfathering provisions recognizing that industrial and commercial customers have relied on Retail BTMG rules. To that end, the PJM Transmission Owners indicated their support for certain additions and clarifications to PJM’s grandfathering proposal suggested by Answering Parties, and other commenters. The PJM Transmission Owners are open to additional suggestions as well as the development of further detail regarding the implementation of the grandfathering provisions in order to avoid substantial financial harm to existing Retail BTMG customers. However, the need for robust grandfathering provisions is not a convincing reason to increase the materiality threshold going forward. The two mechanisms address fundamentally different concerns—the grandfathering provisions are meant to protect existing customers that have relied on existing BTMG rules, while the materiality threshold is intended to ensure that the proliferation of new large loads does not compromise reliability or shift costs to other PJM ratepayers. The Commission should reject the attempts of the Answering Parties to conflate the two issues.
11 December 18 Order at P 221.
PDF page 5
5
II. CONCLUSION
The PJM Transmission Owners respectfully request that the Commission accept this answer and that any subsequent Commission orders addressing these issues be consistent with the discussion herein.
Respectfully Submitted,
/s/ Michael Kunselman
Michael Kunselman
Richard P. Sparling
Nicholas J. Cicale
Jonathan A. Namazi
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005
Counsel for the FirstEnergy
Companies
On behalf of the PJM
Transmission Owners
Dated: June 3, 2026