EL26-71-000 · 2026-06-18 · Commissioners and Immediate Staff (the Commission)secretary of the Commission - FERC

Order Instituting Proceeding Under Section 206 of the Federal Power Act re California Independent System Operator Corporation et al

Text extracted from the eLibrary original (SHA-256 f77fa21ad3c97259…). Download the original from the official source.

Contents · 17 sections
  1. I. Background 6.
  2. A. Growth of Large and Co-Located Loads and ANOPR 6.
  3. B. Recent Proceedings Addressing Large and Co-Located Loads 11.
  4. II. CAISO’s Existing Processes 19.
  5. A. Existing Tariff Processes 19.
  6. B. Recent Stakeholder Proceedings in CAISO 28.
  7. III. Discussion 31.
  8. A. Transmission Service to Eligible Customers on Behalf of Large Loads 38.
  9. B. Cost Shifting Risk Among Transmission Customers 65.
  10. C. Co-Location Arrangements and Load with Behind the Meter Generation 85.
  11. D. Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads 103.
  12. E. Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load 106.
  13. F. Informational Report 120.
  14. IV. Briefing Questions 123.
  15. Background
  16. Discussion
  17. Conclusion

Topics in the text: Connecting load and generation · Cost allocation · Filing procedure

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

195 FERC ¶ 61,214 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Laura V.
Read this passage

I. Background 6.

printed heading

I.
Read this passage

A. Growth of Large and Co-Located Loads and ANOPR 6.

printed heading

Growth of Large and Co-Located Loads and ANOPR 6.
Read this passage

B. Recent Proceedings Addressing Large and Co-Located Loads 11.

printed heading

Recent Proceedings Addressing Large and Co-Located Loads 11. 1.
Read this passage

II. CAISO’s Existing Processes 19.

printed heading

II.
Read this passage

A. Existing Tariff Processes 19.

printed heading

A.
Read this passage

B. Recent Stakeholder Proceedings in CAISO 28.

printed heading

B.
Read this passage

III. Discussion 31.

printed heading

III.
Read this passage

A. Transmission Service to Eligible Customers on Behalf of Large Loads 38.

printed heading

Transmission Service to Eligible Customers on Behalf of Large Loads 38. 1.
Read this passage

B. Cost Shifting Risk Among Transmission Customers 65.

printed heading · Topic match: Cost allocation

Cost Shifting Risk Among Transmission Customers 65. 1.
Read this passage

C. Co-Location Arrangements and Load with Behind the Meter Generation 85.

printed heading

Co-Location Arrangements and Load with Behind the Meter Generation 85. 1.
Read this passage

D. Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads 103.

printed heading

Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads 103.
Read this passage

E. Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load 106.

printed heading · Topic match: Connecting load and generation

Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load 106.
Read this passage

F. Informational Report 120.

printed heading

F.
Read this passage

IV. Briefing Questions 123.

printed heading · Topic match: Connecting load and generation

Over the past year, the Commission has taken action in numerous dockets[fn:2] to address issues related to (a) unprecedented increases in requests for transmission service to serve large loads[fn:3] and (b) growing interest in the co-location of loads with generating facilities (co-location…
Read this passage

Background

printed heading · Topic match: Connecting load and generation

PJM Co-Location Proceedings On February 20, 2025, the Commission initiated a show cause proceeding against PJM and the PJM transmission owners regarding the lack of tariff provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to…
Read this passage

Discussion

printed heading · Topic match: Connecting load and generation

Several commenters discuss the risk of cost shifting among transmission customers that could result from transmission service requests by Eligible Customers on behalf of large loads.[fn:177] Commenters also argue that retail-level large load tariffs do not protect wholesale transmission customers…
Read this passage

Conclusion

printed heading · Topic match: Cost allocation

While this is a long journey, even so, we must continue to move at breakneck pace to win the AI race.
Read this passage

Footnotes

Word notes · Topic match: Connecting load and generation

DD, § 3 (Interconnection Requests) (17.0.0), 3.4 (Surplus Interconnection Service); id. app.
Read this passage