AD26-7-000 · 2026-07-16 · Pennsylvania Department of Policy
Pre-filed Statement of Jacob Finkel, Deputy Secretary of Policy for Pennsylvania Governor Josh Shapiro's Office, for the PJM Governance and Stakeholder…
PDF page 1
1
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
)
Technical Conference on PJM Governance and
)
Docket No. AD26-7-000
Stakeholder Reforms
)
Pre-Technical Conference Statement
Jacob Finkel, Office of Governor Josh Shapiro, Deputy Secretary of Policy
Thank you, Chairman Swett and Commissioners Rosner, See, Chang, and LaCerte, for convening this important conversation on the future of PJM. On behalf of the PJM Governors’ Collaborative,1 I was jointly nominated to this panel by Delaware Governor Matt Meyer, District of Columbia Mayor Muriel Bowser, Illinois Governor JB Pritzker, Indiana Governor Mike Braun, Maryland Governor Wes Moore, New Jersey Governor Mikie Sherrill, North Carolina Governor Josh Stein, Pennsylvania Governor Josh Shapiro, and Virginia Governor Abigail Spanberger.
This Technical Conference is necessary because of a fundamental gap that has emerged between those who are accountable for reliability and affordability in our region—the states and PJM’s Board of Managers—and those with significant authority over many of the solutions: the private Members. Those Members have a responsibility to pursue their own financial interests, and to their credit they do so zealously, but their collective input has failed to produce optimal, or often even coherent, direction at a time when clear, principled leadership is urgently needed. This failure matters far beyond the halls of Valley Forge, because the outcomes at PJM deeply affect the economic development of the PJM states and, even more importantly, if PJM stumbles, it directly threatens the health and safety of 67 million Americans.
1 The PJM Governors’ Collaborative was constituted by the region’s governors in September 2025 at the “Summit on the State of PJM” technical conference in Philadelphia, PA. It brings together the 13 PJM governors and the Mayor of the District of Columbia to jointly engage on, and share information about, issues of common importance across the PJM region. In January 2026, the 13 Governors signed a Statement of Principles with the U.S. Secretaries of Energy and Interior on the immediate need to bolster PJM’s approach to resource adequacy.
PDF page 2
2
To address this, PJM’s governance structure—which has not been substantially revisited in the three decades since it became an ISO—must be updated to realign authority with accountability.
First, PJM’s Board must be given the independence from its stakeholders necessary to enable clear and decisive action—and be charged with a renewed duty to act solely on behalf of the common interest, not the private interest of any Member—while the stakeholder process is reformed to become more nimble and more appropriately focused on issues where in-depth stakeholder engagement lends itself to positive outcomes.
Second, the governance structure needs to incorporate meaningful input from PJM’s most elemental regulatory partners, the PJM states, who have ultimate responsibility over resource adequacy and transmission siting in our region.
Without these two elements, we have repeatedly seen PJM struggle to craft durable solutions to the growing resource adequacy challenges our region faces. Governance solutions cannot themselves deliver resource adequacy, but more effective governance is a necessary first step to the development of suitable market reforms.
The PJM stakeholder process does serve to bring those with expertise and real-world understanding of how individual businesses and sectors work together for shared discussion. That input is necessary and it needs to continue in the right context. However, the stakeholder process should not be expected to perform an executive role it cannot effectively serve. Its complexity—which has grown to Byzantine proportions over the last three decades—renders it incapable of being an effective decision-making body for an organization that must tackle fast- moving challenges.
This should not be a surprise: no one should expect a diverse group of 1,146 self-interested Members to make decisions rapidly or boldly. That is why it is impossible to imagine any public
PDF page 3
3
corporation using such a process to make vital decisions. Simply put, such leadership should be the job of PJM’s Board2 and, in some areas of shared responsibility, of the PJM states. This does not require wholesale elimination of the Members’ input, but rather, better defining what role they can successfully play. Members should not be expected or permitted to determine PJM’s strategic direction, but should help to perfect the solutions that the PJM Board and the states identify are necessary. That realignment of authority and accountability is critical, because the private pecuniary interest of many Members will necessarily differ from the broader public interest that PJM, as a creation of this Commission, should be expected to deeply respect.3 Tracing back to Order 888, PJM’s raison d'être is emphatically not to maximize the profits of its individual stakeholders.4 The core mission of PJM, and every RTO, remains “to promote efficiency in wholesale electricity markets and to ensure that electricity consumers pay the lowest price possible for reliable service.”5
To effectuate this necessary realignment in leadership, the PJM Governors’ Collaborative (“Collaborative”) supports increasing the independence of PJM’s Board, making common-sense improvements to the mechanics of the stakeholder process, and providing the states with a meaningful role in decisions that affect areas of shared responsibility.
The Collaborative has worked closely with our State Commission colleagues in the Organization of PJM States, Inc. (“OPSI”) to develop a closely aligned set of recommendations for reform. Any set of solutions must include a strong and impactful role for both the Governors as
2 Including the CEO, who sits as an ex officio non-voting member of the Board.3 See Xcel Energy Servs. Inc. v. FERC, 41 F.4th 548, 551 (D.C. Cir. 2022) (“The Federal Power Act gives the Commission the authority to regulate ‘both the transmission and the wholesale marketing of electricity in interstate commerce’ to protect the public interest.” (quoting Public Citizen, Inc. v. FERC, 7 F.4th 1177, 1182-83 (D.C. Cir. 2021)); Towns of Alexandria, Minn. v. FPC, 555 F.2d 1020, 1028 (D.C. Cir. 1977) (describing a principal objective of the Federal Power Act as “the protection of consumers from excessive rates and charges”) (quotation omitted)).4 See Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities, Order 888, 61 Fed. Reg. 21,540 (FERC, May 10, 1996); Steve Isser, ELECTRICITY RESTRUCTURING IN THE UNITED STATES: MARKETS AND POLICY FROM THE 1978 ENERGY ACT TO THE PRESENT (2015) at 208-09 (explaining the core independence and financial conflict requirements of Order 888).5 Regional Transmission Orgs., Order No. 2000, FERC Stats. & Regs. ¶ 31,089 at 30,993 (1999).
PDF page 4
4
elected executives and OPSI as the technical experts who oversee retail ratemaking and who are ready to step up to shoulder new responsibilities similar to the other Regional State Committees across the country.
In seeking reasonable, implementable, and constructive solutions, the Collaborative solicited input from a wide array of stakeholders, including representatives of every PJM sector and other engaged entities. The Collaborative especially wants to acknowledge the selfless service to our region from the former Chairman of this Commission, the Honorable Pat Wood III, who again answered the call to serve and offered his valuable time this summer to improve PJM. Proposal for Reform
Competitive markets, designed properly, deliver real value to customers. But experience in recent years has shown repeatedly that PJM’s current governance process is failing to deliver on that promise. As already noted, improved governance will not by itself stabilize confidence in PJM’s markets, nor will it spontaneously resolve the resource adequacy challenges we must collectively address in short order. But it would be self-defeating to attempt to modify those markets without first addressing the governance shortcomings that led us to this juncture. For that reason, the Collaborative strongly supports this Commission’s focus on governance, not as the end goal, but as a necessary first step to ultimately improving market confidence and function. Two interconnected governance reforms are necessary: PJM must be empowered to act more decisively and the states must have a larger role in reaching decisions of shared importance.
1: Empowering PJM to Lead
Today, PJM faces challenging real-world conditions, including from large load additions, yet the PJM Board has too often been unwilling to act decisively, even in areas where it possesses the authority to do so. In order for the Board to provide effective leadership, its independence
PDF page 5
5
must be bolstered, the transparency of its decisions improved, and the function of the stakeholder process streamlined and more clearly defined.
•
The Board’s independence must be safeguarded, while becoming more accessible and transparent.
1. The Board members’ terms should be extended to five or more years, with service normally capped at ten or less years. This is needed to insulate Board members from considerations of retention when weighing difficult decisions.
2. Today strict limits exist on whom the Board may communicate with, including restricting conversations with the states, making PJM staff the Board’s primary source of information. Those well-meaning restrictions serve in practice to hamper the Board’s engagement with a wider range of perspectives. The appearance and reality of undue influence can be avoided, as it is in other RTOs, without such stringent limitations. The Board should have more regular and structured contact with Members and other stakeholders, avoiding backroom conversations while gaining more in-depth understanding from all sides.
3. That increased contact should be accompanied by improved transparency, including full reporting and disclosure of any stakeholder meetings, Board meetings being opened to the public, published Board votes, and minutes containing the Board’s decision-making rationale for key votes.
4. There should be a preference, but not a requirement, that Board members reside within the PJM region, adjusting conflict of interest rules to encourage the selection of qualified Board members who have direct experience with the consequences of decisions facing PJM. At the same time, new conflict restrictions should bar Board members from seeking employment with PJM Members for at least one year following their term on the Board.
PDF page 6
6
5. Section 7.2 of the Operating Agreement delineates seven categories of required experience for Board members. Those limited requirements—narrowly focused on specific financial, technical, and professional expertise—no longer matches the scope of PJM’s responsibilities. This represents a blind spot in the Board’s outlook and undermines its independence by unduly prioritizing Board members with experience that matches the interests of the private Members. These requirements should be updated to require at least one Board member with past experience in public service and at least one with direct exposure to the impact of RTO decisions on the 67 million customers PJM serves.
6. PJM benefits from excellent in-house counsel, but to maximize independence, the Board should retain its own non-conflicted counsel. The Board should entrust that counsel with any negotiations that affect its authority, including with the Members and the states.
7. Finally, alongside these measures to bolster its independence, the Board’s duty should be clearly defined for the first time. The Board should be expressly charged with acting to benefit the public interest of the region as a whole—as the Board chooses to conceive of it—not to advance the private interest of any individual Member.
•
The stakeholder process should be reformed to be more effective and efficient in providing clear input to the Board. This means ensuring that voting rules provide a consistent neutral framework throughout the process by using sector-weighted voting throughout the stakeholder process and eliminating affiliate voting at the lower level. Voting thresholds should be reduced to encourage more ways to get to “Yes.” Alongside these improvements, voting on all matters of substance throughout the process—including at the lower-level committees—should be entirely
PDF page 7
7
transparent with each vote recorded and publicly disclosed, while retaining the existing limits on verbatim meeting recordings to preserve candor and open dialogue.
2: A Meaningful State Role
The Collaborative embraces the need, as PJM CEO David Mills recently publicly requested, for states to assume more responsibility for resource adequacy decisions, and accordingly for those decisions to be shared to a greater degree between the states and PJM going forward.6 For this deeper collaboration to occur successfully—and its success is vital to the entire region and all market participants—the states must first be given real authority in the PJM process that accords with their unique role as sovereign partners. Specifically:
•
For matters of shared responsibility, PJM should agree to file an alternative state proposal when the RTO intends to submit a 205 filing. In every other multi- state RTO (i.e., ISO-NE, MISO, SPP), states have means to influence aspects of shared jurisdiction through the exercise of the RTO’s 205 filing rights under certain circumstances. In order to build a durable partnership with the states on issues of shared responsibility, PJM should agree to utilize the rights it holds under section 205 of the Federal Power Act when a supermajority of OPSI members prefer an alternative to a proposal that PJM intends to file. In those cases, PJM should voluntarily file that OPSI proposal alongside its own (a so-called “jump ball” filing). This jump-ball capability is a vital tool to foster a more collaborative process between the states and their RTO. Experience in each of PJM’s sister multi-state RTOs has shown that such arrangements are effective in producing more collaborative state/RTO partnerships and that, in practice, alternative filings are rarely necessary because state input is afforded respect as RTO
6 Letter From David E. Mills, PJM President and CEO (May 6, 2026), at 3, https://www.pjm.com/media/DotCom/library/reports-notices/special-reports/2026/20260506- powering-reliability-through-market-design.pdf (“Those choices belong to the people and institutions with democratic accountability for their consequences . . .”).
PDF page 8
8
proposals are developed, enabling superior coordination with the states and reducing regulatory uncertainty. The PJM states are the least well-equipped in this regard of any states in the nation and our region suffers as a result.
•
PJM’s tariff should recognize and fund the PJM Governors’ Collaborative, representing the 13 governors and the Mayor of the District of Columbia. The Governors’ proper role should be big-picture: working with the Board to establish the long-term strategic direction of the RTO, communicating preferences that serve the public interest, and encouraging action, agreement, and forward progress, not to block ideas. This complements the technical expertise of OPSI’s utility regulators—making OPSI the best-suited state entity to exercise jump-ball filing rights—and the more narrowly focused residential ratepayer advocacy of the Consumer Advocates of the PJM States. The Collaborative must be provided sufficient funding in the PJM tariff to serve three primary functions.
1. Develop and bring problem statements and issue charges directly to the PJM Board, avoiding the need to receive supermajority support from PJM Members to initiate stakeholder processes on issues that are important to the states. If the Board elects to accept an idea, it may be developed through a standard or expedited process like the Critical Issue Fast Path (CIFP).
2. On occasions when the Members are unable to reach consensus and no stakeholder proposal receives a supermajority vote in the Members Committee, the Board may solicit a timely indicative vote by the Collaborative. This would be a non-binding expression of the states’ preferences on a given subject—not limited to the areas where OPSI would hold jump-ball filing rights, as described above—and would be offered to the Board at the Collaborative’s discretion in those instances when Members cannot agree.
PDF page 9
9
3. Represent the
states in
the
PJM
Board
of
Managers
selection
process by appointing three members to the PJM Board Nominating Committee—for a total of 10 voting members. Absent exceptional circumstances, a Board candidate should receive support from at least one of those three state appointees for the Nominating Committee to recommend that candidate to the Members. o The private interests of the Members dominate the Nominating Committee with five seats (representing each Member sector), while the independent interests of PJM as an organization hold only two seats (both voting Board members). This makes it necessary to provide at least three seats to represent the public interest of the region as a whole in order for the possibility of balance to emerge for the first time: if the three state appointees were to join with the two independent Board members, they would collectively be capable of matching the influence of the five Member appointees. This is a necessary precondition for neutral and independent Board selections. The existing slanted numbers underscore the deep bias of the process that exists today whereby Members hold effectively unchecked control over both the Nominating Committee and the eventual confirmation of Board members by the Members Committee (a confirmation process that would remain unchanged). This systemic advantage held by financially self-interested Members in selecting the Board must be addressed.
o The Collaborative commits to establish binding internal rules that will ensure its three appointees represent the diverse perspectives of the 14 PJM jurisdictions (e.g., representing importing and exporting states, restructured and vertically integrated states). Those three Collaborative appointees would observe the same rules of conduct as the other Nominating Committee members and, in the event of a 5-5 tie, the Nominating Committee Chair, a member of the Board of Managers who normally holds an ex officio non-voting seat, would break the tie.
PDF page 10
10
Conclusion
The challenges that PJM faces today cannot be solved by the RTO or the Members alone. Both have crucial roles to play, but only by working collaboratively with the states can these issues be coherently addressed. Simply put, durable solutions are impossible without better alignment of authority with accountability, which means a more independent Board, a more nimble stakeholder process directed at the right type of engagement, and greater involvement from the states in PJM’s decision-making processes. Such durable solutions are needed, and needed quickly.
The Governors’ Collaborative seeks near-term action to address these issues so that we can collectively move forward in improving the resource adequacy situation of our region. To effectuate that, the Collaborative looks forward to engaging vigorously with the Commission, the Members, and PJM itself in this important conversation in the days ahead.