AD26-7-000 · 2026-07-21 · Ohio Federal Energy Advocate

Comments of the Public Utilities Commission of Ohio's Office of the Federal Energy Advocate re the PJM Governance and Stakeholder Reforms Technical Conference

PDF page 1

1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Governance and Stakeholder Reforms                )                          Docket No. AD26-7-000

COMMENTS OF THE PUBLIC UTILITIES COMMISSION OF OHIO’S
OFFICE OF THE FEDERAL ENERGY ADVOCATE

On May 12, 2026, the Federal Energy Regulatory Commission (Commission or FERC) announced a Commission-led technical conference in this proceeding to be held on July 23, 2026. The purpose of the technical conference is to discuss PJM Interconnection, L.L.C.’s (PJM) governance and stakeholder process, with a focus on identifying and evaluating actionable reforms to improve PJM’s ability to address system needs in a timely and efficient manner. The Public Utilities Commission of Ohio’s Office of the Federal Energy Advocate (Ohio FEA), fulfilling its statutory duty to advocate on behalf of Ohio’s retail electricity consumers,1 offers the following comments for the Commission’s consideration.

I. Introduction
FERC’s consideration of PJM governance at this critical time for our region is important. It is undisputed that the current energy landscape in PJM is driven by historic demand, primarily from data centers. That historic demand, combined with tightening supply from resource retirements, stalled new generation projects, and significant uncertainty over future supply/demand conditions, is the central issue facing the region. The heightened scrutiny of PJM’s governance is a byproduct of that energy landscape. A robust governance structure, that is

1 Ohio Revised Code 4928.24.

PDF page 2

2
transparent and accountable, will be vital as PJM, its Members, and the states collaboratively work together to move the region from where we are today to where we need to be tomorrow. As a restructured state and the largest load in PJM, Ohio seeks to be a constructive partner in working with the Commission and PJM to find solutions that address the energy demands of the region. Ohio relies on PJM to ensure resource adequacy and reliability at least cost. While restructured states have a role in the partnership and are responsible for protecting retail customers, PJM’s competitive markets must deliver the generation resources necessary to meet load across the region. Ohio is doing its part to facilitate a competitive environment for project developers to build new generation resources here.

In 2024, Governor DeWine identified the need for more dispatchable generation to be studied and connected by PJM quickly. Ohio supported both PJM’s Reliability Resource Initiative and subsequent Expedited Interconnection Track to enable PJM to respond quickly to shovel-ready projects. In 2025, the Ohio General Assembly passed Substitute House Bill 15, setting a pathway for new generation in Ohio. This bill shortens generation siting processes, offers tax incentives for new generation equipment, and expands opportunities for behind-the- meter generation, which serves as an important tool for data centers to begin operations without impacting the regional grid. Governor DeWine also announced the creation of the Energy Opportunity Initiative, a $100 million fund to provide grants and low-interest loans over a five- year period to help offset costs related to natural gas and nuclear power production in Ohio. Ohio has already seen positive impacts. We are encouraged and excited by energy project development across Ohio that will benefit the region. Since January 2025, more than 17,000 MW of natural gas projects have been announced, filed applications, or were approved at the Ohio Power Siting Board. Nuclear is also playing an increasingly important role in meeting growing

PDF page 3

3
demand, with three projects announced in Ohio totaling more than 3,500 MW. Ohio will continue to support efforts to bring new resources online to serve new loads and ensure grid reliability.

In January, Governor DeWine joined the National Energy Dominance Council and the other PJM governors in signing a “Statement of Principles Regarding PJM,” which provides a framework for achieving our shared goal of reliable and affordable energy, including providing revenue certainty to new generation and allocating costs to data centers. The Statement of Principles is indicative of the type of joint and collaborative engagement Ohio is prepared to provide to ensure three things: 1) the success of PJM’s competitive markets; 2) affordability, as we grow the grid responsibly and protect other ratepayers from costs associated with data centers; and 3) grid reliability. Each of these are regional concerns that require regional dialogue like never before.

II. Comments
A. PJM Board and Filing Rights
Notwithstanding the significant challenges currently facing the region, the Ohio FEA acknowledges the consistent effort of the PJM staff to maintain open communication with the states as well as other stakeholders. Additionally, the relatively recent formation of PJM’s State Policy Solutions group meaningfully increased regular dialogue between PJM staff and state commission staff as well as other stakeholders. In any conversation on PJM’s going forward organizational structure, the vital expertise of PJM staff on the highly complex and technical matters related to the electric grid must be maintained.

The Ohio FEA encourages the Commission to take a pragmatic view on the role of the PJM Board. Like other corporations, the PJM Board should set the organizational direction,

PDF page 4

4
serve as a check on upper management, act in the best interest of its members and the public, and be responsive to external constituents.

The Ohio FEA strongly supports the ability of the PJM Board to act independently when necessary and encourages the Commission to position the PJM Board similarly to other RTO/ISOs across the country in this regard. Specifically, as other commenters in this docket have highlighted, the PJM Board does not have authority to act on every governing document related to the grid enterprise it administers. For example, the PJM Board could act on matters related to the capacity market because the capacity market rules are contained in sections of PJM’s Tariff and Reliability Assurance Agreement where filing rights under section 205 of the Federal Power Act (FPA) are held by PJM. Conversely, other components of PJM governance such as the energy and ancillary services markets, emergency procedures, and regional transmission planning are contained in PJM’s Operating Agreement (OA) where filing rights under section 205 of the FPA are held by the PJM Members. As a result, the PJM Board cannot act independently to change components of the OA without a threshold of 2/3 support from the PJM Members.

This limitation on the independence of the PJM Board must be remedied. It greatly hampers the ability of the Board to act on substantial portions of PJM’s governing documents, including areas of concern to Ohio like the scope of PJM’s regional transmission plan. With virtually every aspect of transmission in the region, including local projects, controlled solely by the transmission owners, there is no way for the PJM Board, or the states, to have any meaningful input. For example, the 2025 Regional Transmission Expansion Plan approved approximately $1.04 billion in supplemental projects in Ohio that are not required for reliability, economic efficiency, or operational performance. These projects receive limited review, with

PDF page 5

5
PJM’s study focused only on ensuring that there will be no adverse impact to the grid, rather than considering factors such as the cost or need for the project. This is unacceptable and we would ask that PJM be directed to address this issue, in collaboration with the states and transmission owners.

Constraints on the PJM Board are magnified by the difficulty the PJM Members have in finding consensus on certain issues. Currently, if the PJM Members do not reach supermajority support on changes to the OA, no changes are proposed to the Commission. The PJM Board should have the authority to independently and unilaterally propose changes to the OA under section 205 of the FPA.

Further, the Ohio FEA agrees that the states should have an expanded role in PJM governance and an ability to bring proposed solutions before the Commission, whether through “jump ball” rights like ISO New England or other means. As the need for difficult policy decisions across the region increases, it is incumbent on the states to collaborate with PJM and bring state resources and engagement to bear in tackling the road ahead. Giving states an avenue to advance proposals to the Commission without compromising PJM’s authority to do so could be beneficial in driving the PJM stakeholder process to timely and durable solutions to the critical matters at hand. The Ohio FEA views state filing authority on resource adequacy and cost allocation as a tool to be applied in limited circumstances and emphasizes its opinion that the Organization of PJM States, Inc. (OPSI), as the states’ technical experts, act upon such authority only when strong support of its member states is achieved. As an alternative approach, the Ohio FEA also agrees with Pat Wood’s recommendation that PJM consult with OPSI before it submits a section 205 filing and that the filing include OPSI’s vote and load weighted positions.

PDF page 6

6
B. PJM Stakeholder Process
Just as a robust governance structure is important to meet the moment, so too is a transparent and collaborative stakeholder process. However, something is not working if PJM’s stakeholder process is not reaching consensus or able to determine a course of action on pressing issues in a timely manner. The current process suffers under its own weight with many private interests involved and no timeframe or deadline for action. The Ohio FEA agrees that efforts to streamline PJM’s stakeholder process in reasonable ways, such as by establishing timeframes or deadlines for action could, if combined with PJM Board and state filing rights, assist stakeholders in more readily moving solution packages to the Board for consideration. We also agree with Pat Wood’s recommendation that the Commission should consider whether to transition to an advisory role for PJM Members. Although the Members provide valuable input in the stakeholder process, the PJM Board should be able to render independent decisions on the matters before it, as is the case in other RTO/ISOs.

C. Additional State Input
Separately, the Ohio FEA supports and stands ready to work with the newly formed Governors’ Collaborative. There is no question that the states in the PJM region are diverse, and the challenge of regional decision making will not go away. It is our hope that the Governors’ Collaborative, as collective representatives of the diverse PJM region, will limit individual state political and policy preferences from entering the energy equation, which will improve the noted challenges with PJM’s stakeholder process and enhance the future of regional coordination and well-functioning markets. The Ohio FEA views a critical opportunity in the creation of the Governors’ Collaborative: to facilitate regional dialogue and consensus-building, which, in turn, should facilitate PJM’s ability to return to its core mission of providing reliability at least cost.

PDF page 7

7
The Ohio FEA feels strongly that any formal actions of the Governors’ Collaborative should, at a minimum, represent the diverse political and energy characteristics of the PJM states. In addition to the formal recognition of the Governors’ Collaborative, the organization should be vested with the authority to bring issue charges and problem statements to the PJM Board, to provide state perspectives directly to the Board when Member consensus cannot be reached, and to appoint three members to the PJM Board Nominating Committee.

III. Conclusion
The Ohio FEA appreciates the Commission’s leadership and the ability to offer comments on the important topic of PJM governance and stakeholder reform. Ohio depends on a strong partnership with PJM, and on its competitive markets to deliver abundant, affordable, and reliable energy supplies. Ohio is ready to collaborate with FERC, PJM, and our fellow states to achieve these goals.

Respectfully submitted,
D. Andrew Wilson
Ohio Attorney General

John H. Jones
Section Chief

/s/ Thomas G. Lindgren
Thomas G. Lindgren
Assistant Attorney General
Public Utilities Section
30 East Broad Street, 16th Floor
Columbus, Ohio 43215-3414
614.644.8768 (telephone)
866.818.6152 (facsimile)
Thomas.Lindgren@OhioAGO.gov

On Behalf of the Public Utilities
Commission of Ohio’s Office of the
Federal Energy Advocate
July 21, 2026

PDF page 8

8
CERTIFICATE OF SERVICE

I hereby certify that I have on this date caused a copy of the foregoing document to be served on each person included on the official service list maintained for this proceeding by the Commission’s Secretary, by electronic mail or such other means as a party may have requested, in accordance with Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010.  Dated this the 21st day of July 2026, at Columbus, Ohio.

/s/ Thomas G. Lindgren
Thomas G. Lindgren
Assistant Attorney General