AD26-7-000 · 2026-07-22 · PJM Cities and Communities Coalition

Comments of the PJM Cities and Communities Coalition re the PJM Governance and Stakeholder Reforms Technical Conference

PDF page 1

UNITED STATES OF AMERICA ​
BEFORE THE ​
FEDERAL ENERGY REGULATORY COMMISSION
Commission-Led Technical Conference on PJM Governance and Stakeholder Reforms​ Docket No.  AD26-7-000

COMMENTS OF THE PJM CITIES AND COMMUNITIES COALITION
The PJM Cities and Communities Coalition respectfully submits these written comments in connection with the Commission-led technical conference on PJM Governance and Stakeholder Reforms in Docket No. AD26-7-000.  We applaud the Commission’s focus on governance issues within PJM, and we hope to aid the Commission’s investigation into these matters via the comments below. About PJMCCC

The PJM Cities and Communities Coalition (PJMCCC) is a group of 21 local governments representing ~15% of the population within PJM's territory. Our members are energy managers and sustainability staff of large municipal end-users. As local governments, PJMCCC members are both large end-use consumers of energy and public-sector entities responsible for the health and well-being of our communities. This dual role places us in a unique position: we are affected by the impacts of PJM’s energy market decisions on our bills while being directly accountable to our approximately ten million residents who depend on reliable and affordable electricity. Furthermore, local government policy goals depend in part on consideration in PJM’s planning and decision-making so that the technologies and strategies needed to meet our mandates and goals are appropriately valued by markets. PJMCCC’s interests are unique and are not fully represented by any other stakeholder group, making our coalition a valuable partner in planning for PJM. For example, we are currently collaborating with PJM’s State Policy Solutions team to shape the development of the local policy portal to support PJM’s compliance with FERC Order 1920. We have been helping inform the policy fields to be used for aggregating local government policies, goals, siting opportunities, and siting restrictions. Additionally, we submitted local building and vehicle electrification objectives to PJM’s Load Analysis Subcommittee that were used in the 2024 load forecast. PJM is at a critical juncture, and decisions made now will be felt for decades to come. We strongly believe that local government policies and perspectives are crucial for ensuring that the future energy system is reliable, affordable, and sustainable.

PDF page 2

PJMCCC members’ experience with PJM

PJMCCC’s members’ experience attempting to interface with the PJM board via PJM staff has been, at best, a struggle.  While PJMCCC members have had an occasional successful encounter with PJM staff, these seem to be driven mostly by regulatory requirements rather than genuine efforts to facilitate constructive dialogue. PJMCCC did have a successful on-site meeting with PJM staff in 2023, but since then PJM staff has shown limited receptivity to outreach from PJMCCC.

PJM staff have been difficult to get hold of when requesting tours at PJM headquarters in Pennsylvania, for example.  Routine difficulties getting hold of PJM customer service presented themselves. Once we did get in contact with staff over the phone, they mentioned that the email information on PJM’s website was inaccurate. Where PJM staff have opted to engage with PJMCCC members, it has primarily been where they are required to do so – for example, to facilitate PJM’s compliance with Order No. 1920.  PJM staff have contacted PJMCCC sporadically with asks for engagement and assistance on Order No. 1920 implementation.  One PJMCCC member aptly characterized the relationship to PJM as “don’t call us, we’ll call you.” The realm of the possible: FERC authority, State authority, and

PJM politics
PJMCCC is excited to see FERC take proactive steps toward exercising its authority over RTO/ISO governance, particularly with respect to PJM. While FERC has long held authority over RTO/ISO governance, many issues with RTO/ISO governance have persisted without FERC action.1  The time for FERC to use its authority to address pervasive issues in RTO/ISO governance, particularly within PJM, is nigh.

FERC established minimum “independence” standards for RTO governance in Order No. 20002 and Order No. 719.3  As Travis Kavulla writes, “Independence” has been defined by FERC as having an ultimate decision-making body within an RTO that 3 Federal Energy Regulatory Commission; “Wholesale Competition in Regions with Organized Electric Markets;” (October 17, 2008) Docket Nos. RM07-19-000, AD07-7-000.

2 Federal Energy Regulatory Commission; “Order No. 2000: Regional Transmission Organizations;” (December 20, 1999) Docket No. RM99-2-000.

1 Kavulla, T.; “Problems in Electricity Market Governance: An Assessment;” R Street Policy Study No. 180; August 2019; https://www.rstreet.org/research/problems-in-electricity-market-governance-an-assessment/

PDF page 3

is not beholden to “market participants.”4  A major test of FERC’s assertion of the authorities it has via its independence criterion came when FERC attempted to find CAISO’s board selection process to be insufficient for meeting FERC’s independence criterion. FERC’s main premise for this was that California law required the governor of California to approve candidates for the CAISO board and that the state of California was also a major participant in CAISO markets.

However, the DC Circuit for the Court of Appeals rejected FERC’s attack on CAISO’s board selection process, writing that FERC had no authority to prescribe how a CAISO selects its board.5  While the DC Circuit preserved FERC’s authority over governance - noting that FERC could legitimately revoke an RTOs’ certification as an RTO on governance independence grounds - the DC Circuit found that FERC had overreached with regards to CAISO.  The DC Circuit noted that FERC’s arguments had no limiting principle, meaning these arguments could imply that FERC has authority over matters as minute as how CAISO procures office furniture.  While the DC Circuit left the door open for FERC to pursue further governance actions in CAISO, FERC declined to do so.

Despite CAISO v FERC, FERC has used its rates authority to assert authority over governance.  FERC used its rates authority to reject revisions to ISO-NE’s governance, specifically ISO-NE’s membership rules in the stakeholder process, stating that “stakeholder processes are a practice affecting rates.”6   FERC’s order on this was unchallenged.

​
That FERC’s authority over governance has been left unchallenged is a good thing, given the plethora of governance problems pervasive in PJM and the current market crisis that has resulted.  PJM’s governance structure itself has multiple problems that compromise its ability to meet FERC’s independence standards for RTOs.  A key issue with PJM is that its board is not truly independent from its members, who are also market participants.  PJM’s board is selected by its members, which limits the independence of the board from the outset.  Further, even if the PJM board tries to be independent, PJM members have so much influence that they can stifle action from the PJM board.  PJM members can effectively nullify any independent action that the board

6 Order Rejecting Revisions, New England Power Pool Participants Committee, Docket No. ER18-2208-001, Jan. 29, 2019, p. 19. https://elibrary.ferc.gov/idmws/file_list.asp?document_id=14740301
5 California Independent System Operator v. Federal Energy Regulatory Commission, 372 F.3d 395, 403 (D.C. Cir. June 22, 2004); https://caselaw.findlaw.com/court/us-dc-circuit/1344700.html
4  Kavulla, T.; “Problems in Electricity Market Governance: An Assessment;” R Street Policy Study No. 180; August 2019; https://www.rstreet.org/research/problems-in-electricity-market-governance-an-assessment/

PDF page 4

tries to take through the voting process and through the stakeholder issue agenda-setting process.  This is a serious problem for the PJM board, to the extent that the PJM board can’t arguably be said to control what happens in PJM.

A further governance challenge is that PJM’s stakeholder process has become compromised as well.  As law professor Shelly Welton explains, the congressional repeal of the Public Utility Holding Companies Act (PUHCA) has allowed for swaths of mergers within the utility industry.7 This has resulted in merging together entities that once represented different sides of a transaction - creating problems for the balances of interests that RTO governance might intend to create.  When a “load” stakeholder is owned by the same entity as a “generation” stakeholder, neither is truly representative of its interests in an RTO stakeholder process. As professor Welton writes, these mergers “...create challenges by concentrating economic and political power in a small number of companies—not least for theories of RTO governance, which rely upon internal industry checks to legitimate RTO decision-making.  These internal checks presume opposing interests that do not exist because holding companies have consolidated across demand- and supply-side affiliates.”8  Professor Welton’s cross-RTO assessment of this issue holds true for PJM.

As such, FERC’s authority over governance can be usefully deployed at this critical moment to resolve serious issues in PJM - and FERC should feel empowered to do so.  While there might be potential naysayers regarding FERC action toward PJM governance, FERC’s clear authority and rebuttals to these naysayers is neatly summarized in the following paragraph from law professor Ari Peskoe:

“Should FERC impose governance reforms, opponents would likely argue that RTO governance is too ‘remote’ to directly affect rates, and that the [Supreme Court] did not hold that FERC’s authority extends beyond ‘rate structures.’ FERC could respond that the CAISO panel held only that FERC ‘does not have the authority to reform and regulate the governing body of a public utility.’ This holding is strictly limited to the facts of that case and does not limit FERC’s jurisdiction over governance matters that directly affect rates. FERC can also point to its orders about unduly discriminatory regional IOU alliances, as

8 Welton, S.; “Rethinking Grid Governance for the Climate Change Era;” (2021) California Law Review; Vol. 109; pp. 237; https://www.californialawreview.org/print/rethinking-grid-governance-for-the-climate-change-era
7 Welton, S.; “Rethinking Grid Governance for the Climate Change Era;” (2021) California Law Review; Vol. 109; pp. 234-237; https://www.californialawreview.org/print/rethinking-grid-governance-for-the-climate-change-era

PDF page 5

summarized in part IV, to argue that there is nothing ‘unheralded’ or
‘transformative’ about its regulation of RTO governance.”9

Professor Peskoe even goes further to suggest that FERC could challenge and overturn the D.C. Circuit’s findings in CAISO v FERC:

“FERC could also argue that the CAISO court’s policy arguments are irrelevant. The D.C. Circuit feared that if it upheld FERC’s order firing CAISO’s board, FERC might use that authority to hire and fire IOU board members.  The panel observed that other agencies, such as the Securities and Exchange Commission, regulate corporate governance, and that FERC authority over corporate boards would be redundant or even conflicting. But no such overlap would exist for RTO governance. FERC’s assertion over internal RTO decisionmaking structures and processes would not extend to analogous processes at IOUs. IOUs do not have ‘members’ engaged in similar decisionmaking processes that directly affect FERC filings. Moreover, no other regulator can claim authority over RTO governance. This would be a winnable case for FERC.”10

​
To aid FERC’s deployment of its governance authority, there is fortunately an abundance of literature suggesting a wide variety of reforms regarding RTO governance generally.11  Many of these reforms would be good solutions for PJM governance in particular.  This literature also includes recommendations for FERC to perform a more holistic revisitation of RTO/ISO governance, including explications of governance principles implicit in its prior orders and expansions of the governance principles FERC requires RTOs/ISOs to implement.12  Underscoring the need for governance reform, this literature also includes empirical demonstration that the governance structure of RTOs

12 Simeone, C.E.; “Reforming FERC’s RTO/ISO Stakeholder Governance Principles;” The Electricity Journal, Vol 34 (2021); https://www.sciencedirect.com/science/article/pii/S1040619021000452?via%3Dihub
11 See e.g. Lenhart, S., and Fox, D.; “Participatory Democracy in Dynamic Contexts: A Review of Regional Transmission Organization Governance in the United States;” Energy Research & Social Science; vol. 83 (2022); https://www.sciencedirect.com/science/article/pii/S2214629621004369?via%3Dihub
10  Peskoe, A.; “Replacing the Utility Transmission Syndicate’s Control;” Energy Law Journal, Volume 44.3, pp.612; https://eelp.law.harvard.edu/wp-content/uploads/2024/10/Replacing-the-Utility-Transmission-Syndicates- Control-FINAL.pdf
9  Peskoe, A.; “Replacing the Utility Transmission Syndicate’s Control;” Energy Law Journal, Volume 44.3, pp.611-612; https://eelp.law.harvard.edu/wp-content/uploads/2024/10/Replacing-the-Utility-Transmission-Syndicates- Control-FINAL.pdf

PDF page 6

can have profound impacts on market outcomes, specifically PJM’s governance capacity market.13

In these comments, we attempt to focus only on literature that suggests reforms relevant to PJMCCC’s experience with PJM.  We note that other reforms beyond these might be valid and helpful, but we rely on other commenters to offer those reforms.

Responses to Panel Questions
Please find our responses to the panel questions below.
Panel 1: PJM Governance Mechanics – Board Authority, States’ Role, Filing Rights, and Document Architecture

1.​ What is the PJM Board’s role in ensuring that PJM is sufficiently tackling the region’s operational and market challenges?  How does the Board evaluate its effectiveness in that role?  How often, and under what circumstances, does the Board act unilaterally, and should this change?

PJMCCC believes that the PJM board’s role is to make responsible decisions for the entire PJM region, including all stakeholders, rather than simply reflecting the preferences of member utilities. As such, PJMCCC believes that the PJM board should be made more representative of regional stakeholders and their interests. However, the PJM board is unlikely to become representative in this way under the current process used to select PJM board members. Under the current process, only PJM members vote to decide who sits on the PJM board - a process that can only guarantee that the PJM board will only represent PJM members and, more specifically, PJM member utilities that have the most voting power. This in turn sets up PJM to be led by a board that prefers policies favoring member utilities’ interests over other stakeholders and the public interest.

Solution:
PJM’s board selection process should be re-organized to require participation from stakeholders other than PJM Members.  PJM’s board selection process should include input from states, consumer advocates, and other stakeholders so as to deliver a board that is representative not only of PJM member utilities but of the region’s many other stakeholder sectors as well.  This would deliver a board that is both representative

13 Blumsack, S., and Yoo, K.; “RTO Governance Structures Can Affect Capacity Market Outcomes;” Proceedings of the 53rd Hawaii International Conference on System Sciences, 2020; https://hdl.handle.net/10125/64119

PDF page 7

of, and responsive to, the region’s needs.  PJMCCC agrees with Jacob Finkel’s comments on behalf of the PJM Governors’ Collaborative, which provide more useful details on issues with independence of the PJM board and solutions to make the PJM board more independent.14

Who would do it, under what authority, and how:
FERC could facilitate change to PJM’s board selection process by issuing an order to show cause requiring PJM to demonstrate how its board selection process meets FERC’s independence requirements for RTOs.  FERC could preliminarily find that, by restricting the board selection process to member votes, PJM fails to retain its independence from market participants.  FERC could argue that literature demonstrating the vulnerability of PJM’s board to its members’ influence creates grounds for preliminarily finding that PJM’s board is not sufficiently independent to meet Order No. 2000’s requirements. However, in proposing a just-and-reasonable remedy, FERC should not mandate an alternative selection process for PJM’s board; instead, FERC could propose to reconsider whether PJM should keep its status as an RTO.

FERC’s potential action here would accommodate the D.C. Circuit’s finding in CAISO v FERC (2004).15  Since board selection processes have been squarely identified by the D.C. Circuit as a practice that FERC cannot control under the Federal Power Act, FERC should avoid attempting to dictate a new process to PJM (even if PJM needs one).  Instead, FERC should take the path identified by the D.C. Circuit as squarely within its jurisdiction - challenging an RTO’s compliance with FERC’s standards for independence.  This avoids the challenge of establishing a new limiting principle for FERC’s authority over governance via its authority over rates.

Alternatively, PJM could file with FERC under Federal Power Act section 205 to voluntarily re-organize its board selection process into one that allows votes from non-member stakeholders.  Models exist from which PJM could borrow, such as the Regional Organization for Western Energy (ROWE)’s process for board selection.16 ROWE is being developed by western stakeholders to provide new governance for the

16 See West-wide Governance Pathways Initiative; “Launch Committee Step 2 Final Proposal;” pages 57-61; https://www.westernenergyboard.org/wp-content/uploads/Pathways-Initiative-Step-2-Final-Proposal.pdf
15 California Independent System Operator v. Federal Energy Regulatory Commission, 372 F.3d 395, 403 (D.C. Cir. June 22, 2004). https://caselaw.findlaw.com/us-dc-circuit/1344700.html.
14 “Pre-Technical Conference Statement: Jacob Finkel, Office of Governor Josh Shapiro, Deputy Secretary of Policy;” (July 16, 2026) Docket No. AD26-7-000. https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260716-4005&optimized=false&sid=140709 8d-e46c-4292-acf1-eb7310602cdc

PDF page 8

Western Energy Imbalance Market (WEIM) and Extended Day-ahead Market (EDAM).17 In that selection process, regulators from state public service commissions have an input on what candidates are chosen to serve on the ROWE board.  This allows for better representation of the ROWE’s regional stakeholders and, as such, has much greater potential to deliver good policymaking.

2.​ How should states, through the Organization of PJM States, Inc. (OPSI) or other structures, interface with the Board to enable the region to meet operational and market challenges while respecting PJM’s independence?

A better PJM governance structure would include mandatory, regular, and responsive check-ins with the states and other stakeholders on a broader variety of policy topics.  PJMCCC believes that PJM should have a dedicated and regular forum to allow non-member stakeholders to provide input on PJM policy issues.  PJMCCC believes that FERC is asking the right question when inquiring if states’ input should be reaching the PJM board, and FERC should ask a broader question about how other stakeholders reach the board as well.

As with board selection, an example of how best to do broader stakeholder engagement from which PJM should borrow is that of the ROWE.  ROWE’s structure requires the ROWE board to consult with states and other non-utility stakeholders regularly.  PJM’s governance structure would benefit from a similar structure and a direct line of contact between the PJM board, on the one hand; and states and other stakeholders in the region, on the other hand.

Who would do it, under what authority, and how
FERC has a variety of options to initiate this kind of restructuring in the PJM stakeholder process.  FERC could direct the PJM board to hold such talks with states and other stakeholders under its general power to direct convenings (e.g. this tech conference, the FERC+states collaborative, etc.).  However, this approach is likely to put significant strain on FERC resources, especially considering the rapidly growing plethora of issues facing PJM.  As a less-intensive alternative, FERC could also employ

17 The WEIM and EDAM are currently governed jointly by the California Independent System Operator (CAISO) and the Western Energy Market (WEM) governing board. See generally https://www.westernenergymarkets.com/governance/governing-body

PDF page 9

a Federal Advisory Committee process to convene PJM board members with other stakeholders and discuss relevant issues.18

As a third alternative, FERC could issue a show-cause order against PJM
arguing that its tariffs are unjust and unreasonable for lack of better engagement with non-member stakeholders.  As with its uncontested order on ISO-NE’s membership requirements, FERC could assert that PJM’s stakeholder processes are a practice affecting rates.19  FERC could then preliminarily find that PJM’s stakeholder processes, particularly their lack of regular engagement with broader stakeholders, are leading to unjust and unreasonable rates.  FERC could refer to ample literature on incumbency bias created by governance structures like PJM’s as grounds for this finding.20  As a just-and-reasonable remedy, FERC could propose that PJM adopt more regular engagement with a broader array of stakeholders, such as the engagement processes proposed for the ROWE.

3.​ What governance reforms would best improve accountability and
responsiveness?

​
PJMCCC believes that improving the accountability and responsiveness of PJM goes beyond the PJM board selection process and engagement with the states. PJMCCC sees further opportunity with the PJM stakeholder process to improve PJM’s responsiveness.  As noted by professor Peskoe, “In PJM, the board now routinely calls for staff-driven processes that bypass standard committee-led deliberative processes.”21 Moreover, empirical analysis has found that PJM culture has changed over time to rely more heavily on these fast-track processes that circumvent the deliberative stakeholder

21 Peskoe, A.; “Replacing the Utility Transmission Syndicate’s Control;” Energy Law Journal, Volume 44.3, pp.616; https://eelp.law.harvard.edu/wp-content/uploads/2024/10/Replacing-the-Utility-Transmission-Syndicates- Control-FINAL.pdf
20 See generally.  Peskoe, A.; “Replacing the Utility Transmission Syndicate’s Control;” Energy Law Journal, Volume 44.3; https://eelp.law.harvard.edu/wp-content/uploads/2024/10/Replacing-the-Utility-Transmission-Syndicates- Control-FINAL.pdf
19 Order Rejecting Revisions, New England Power Pool Participants Committee, Docket No. ER18-2208-001, Jan. 29, 2019, p. 19. https://elibrary.ferc.gov/idmws/file_list.asp?document_id=14740301
18 For examples from other agencies’ use of this process - notably CFTC’s - see Kavulla, T.; “Problems in Electricity Market Governance: An Assessment;” R Street Policy Study No. 180; August 2019; https://www.rstreet.org/research/problems-in-electricity-market-governance-an-assessment/

PDF page 10

processes.22  Legal scholars have offered a simple solution to this issue that is well within FERC’s authority.

The solution

As articulated by professor Peskoe, FERC could require PJM to provide
non-member stakeholders with the authority to initiate deliberative stakeholder processes within PJM’s existing structure.  This would allow issues that reflect regional stakeholder concerns to be put on the PJM stakeholder agenda, instead of issues that only the member utilities believe is important.  FERC could require this change under its general authority over governance processes as a practice affecting rates, as described elsewhere in these comments.

4.​ How does the division of Federal Power Act section 205[1] filing rights among PJM, Transmission Owners, and the Members Committee affect PJM’s ability to act effectively and quickly, when warranted, to address operational and market needs?

PJMCCC believes 205 filing rights are a key component of making PJM more responsive to regional stakeholders’ concerns.  The allocation of 205 filing rights currently stifles PJM board action and mainly facilitates a meager level of independence and responsiveness through the PJM board’s ability to file a 206 investigation against PJM itself.  This is obviously less than ideal for facilitating PJM reforms and also reflects the failure of PJM’s governance structure to create pathways for the PJM board to be responsive to regional stakeholders’ concerns.

The solution

PJMCCC believes that FERC should broaden the allocation of 205 filing rights in line with professor Peskoe’s recommendations.23 After the Atlantic City v FERC decision, FERC promised to investigate the allocation of 205 filing rights if utilities use those rights in a way that compromises RTO independence or causes undue

23 Peskoe, A.; “Replacing the Utility Transmission Syndicate’s Control;” Energy Law Journal, Volume 44.3, pp.614-616; https://eelp.law.harvard.edu/wp-content/uploads/2024/10/Replacing-the-Utility-Transmission-Syndicates- Control-FINAL.pdf
22Johnson, N., Lenhart, S., and Blumsack, S.; “The Evolution of Participatory Policymaking for Regional Power Grids;” Energy Law Journal; Vol. 44; pp. 533-546 (2023). https://scholarworks.boisestate.edu/cgi/viewcontent.cgi?article=1169&context=pubadmin_facpubs

PDF page 11

discrimination.24  On that note, law professor Joshua Macey has noted that “Utilities use their filing rights both to propose favorable market rules and to design governance structures that allow them to control the multi-member organizations that plan grid infrastructure and ensure resource adequacy.”25  Given issues with the responsiveness and independence of RTOs generally and PJM in particular, and the role that filing rights have played in that unresponsiveness, FERC could now follow through on its post-Atlantic promise.

PJMCCC believes that FERC should consider broadening the allocation of 205 filing rights. FERC could consider giving the PJM board independent 205 filing authority over topics like regional cost allocation and local planning. FERC could also consider allocating 205 filing rights to state regulators, who are ultimately responsible for setting the retail rates through which all investments are ultimately recovered.  State regulators with 205 filing rights could help represent the interests of broader stakeholders in PJM tariff changes.  It is worth noting that state regulators in MISO and SPP already have 205 filing rights over transmission cost allocation and resource adequacy.  Given PJM’s struggles with resource adequacy, as evidenced by its extreme capacity market prices in recent years, giving 205 filing rights over resource adequacy to PJM state regulators is well worth FERC’s consideration.

PJMCCC believes it would also be helpful for FERC to consider another remedy offered by professor Peskoe - requiring PJM to create a new stakeholder group centered around innovation and new technologies.26  FERC could then grant that stakeholder group 205 filing rights in order to empower the PJM governance process to make tariff reforms that facilitate innovation and new technologies.  PJMCCC agrees with professor Peskoe that enabling PJM to be more self-improving in this regard could be an even better path than the rulemaking processes FERC has engaged in thus far to accommodate new technologies.

26  Peskoe, A.; “Replacing the Utility Transmission Syndicate’s Control;” Energy Law Journal, Volume 44.3, pp.615-616; https://eelp.law.harvard.edu/wp-content/uploads/2024/10/Replacing-the-Utility-Transmission-Syndicates- Control-FINAL.pdf
25 Macey, J; “Outsourcing Electricity Market Design;” University of Chicago Law Review, Vol 91, pp. 1243:1330, https://chicagounbound.uchicago.edu/uclrev/vol91/iss5/1/ ​

24 Atlantic City Elec. Co., et al. v. FERC, 295 F.3d 1, 9‒11 (D.C. Cir. 2002).https://law.justia.com/cases/federal/appellate-courts/F3/295/1/597196/

PDF page 12

5.​ To what extent do provisions in PJM’s Operating Agreement, Transmission Owner Agreement, Open Access Transmission Tariff, Reliability Assurance Agreement, or Manuals impede timely decision-making by PJM?

While PJMCCC leaves it to others to comment on opportunities to reform PJM’s governing documents, PJMCCC believes that such reforms would add more value if suggested actions for FERC described elsewhere in these comments were adopted.

6.​ Recognizing regional differences, are there lessons from other regional transmission organization/independent system operator (RTO/ISO) governance structures that PJM could reasonably adopt to improve its responsiveness to the region’s operational and market challenges?

PJMCCC recommends that FERC and PJM should consider the new ROWE governance model being promulgated by western stakeholders as an example of best practices for improving PJM’s responsiveness to the region’s challenges.27  The ROWE’s governance model includes several provisions that will make the ROWE more responsive to regional issues and stakeholder concerns, including:

●​ ROWE board member selection by a wide array of stakeholders, including state regulators

●​ A thorough process and structure for stakeholder engagement, including requirements for the ROWE board to conduct engagement with state regulators and consumer advocates

●​ A balance of voting power that gives no stakeholder sector veto power over ROWE board decisions, making the ROWE boards actions truly independent ●​ Concentration of 205 filing rights within the ROWE board

​
PJMCCC encourages FERC to consider requiring PJM to enact some or all of the ROWE’s governance design features, many of which are specifically recommended elsewhere in these comments in response to the Commission’s particular questions. These features will lead PJM to be more responsive to the region’s challenges

27 See generally West-wide Governance Pathways Initiative; “Launch Committee Step 2 Final Proposal;” pages 57-61; https://www.westernenergyboard.org/wp-content/uploads/Pathways-Initiative-Step-2-Final-Proposal.pdf

PDF page 13

Panel 2: PJM Stakeholder Process – Design, Transparency, and Decision-Making 1.​ Do sector-weighted voting and existing voting thresholds strike the right balance between achieving consensus and taking timely action?

PJMCCC believes that non-utility stakeholders like local governments are underrepresented in the PJM’s stakeholder process.  Even if PJMCCC could become a member and vote in the process, PJMCCC would not have hardly any influence due to broader structural issues with PJM’s voting structure.  As described above, professor Welton explains how mergers and acquisitions have made the stakeholder sector definitions muddied when it comes to actually representing public interests.28

The solution

FERC should direct PJM to develop more cohesive sector formation and stricter requirements that a member must meet to join a sector, as well as a broader variety of sectors in order to represent stakeholder that currently aren’t eligible to become members.  In developing prescriptions for PJM’s stakeholder sector requirements, FERC could draw upon ROWE’s Stakeholder Representatives Committee design. ROWE’s design defines specific sectors and requirements that a member must have in order to vote with that sector.  Moreover, the sectors in ROWE’s design are broadly representative of a variety of stakeholders that PJM’s governance should aspire to represent as well.

Who would do it, under what authority, and how
As described for similar changes to the PJM stakeholder process, FERC could require PJM to make these changes under its own assertion that stakeholder processes are a practice affecting rates.  PJM could of course also voluntarily make these changes itself.

2.​ What transparency reforms would improve the quality of PJM’s stakeholder process and increase stakeholder confidence in its decision-making?

​
Professor Peskoe articulates that a general improvement in transparency, through a new FERC transparency principle, would improve RTO governance.

28 Welton, S.; “Rethinking Grid Governance for the Climate Change Era;” California Law Review; Vol. 109; 209;275; 2021; https://www.californialawreview.org/print/rethinking-grid-governance-for-the-climate-change-era

PDF page 14

PJMCCC agrees that this principle would improve PJM governance specifically.  As professor Peskoe identifies, confidential information-sharing between PJM and investor-owned utility members about routine rule changes benefits those utilities in FERC proceedings and “may forge inappropriate relationships between RTO staff and IOU members.”29

The solution

​
One potential implementation of this transparency principle would be for FERC to direct PJM to make board meetings transparent and make all meetings open to non-members.  As Travis Kavulla writes, “PJM’s board meets privately; important committee meetings are open only to members.”30  FERC could require PJM to reverse this through the authority it has asserted over stakeholder processes as a practice affecting rates.  Alternatively, PJM could of course do this of its own volition. PJMCCC agrees with Jacob Finkel’s comments on behalf of the PJM Governors’ Collaborative, which provide more useful details on issues with transparency of the PJM board and solutions to make the PJM board’s meetings and decisions public to stakeholders.31

3.​ Are there structured opportunities in the stakeholder process for state participation (e.g., defined consultation windows, joint technical sessions) to provide input on topics that are of interest to the states?

PJMCCC believes that local governments need more structured opportunities in the PJM stakeholder process. As highlighted by Dworkin and Goldwasser, “smaller organizations, regulatory representatives, and public interest groups have less money to participate and see more diluted benefits, so it is harder for them to meaningfully engage.”32  Moreover, as professor Welton writes, participation of such stakeholders

32 Dworkin, M.A., and Goldwasser, R.A.;  “Ensuring Consideration of the Public Interest in the Governance and Accountability of Regional Transmission Organizations.” Energy Law Journal, Vol. 28, pp. 543-601: https://www.eba-net.org/wp-content/uploads/2023/02/10-Governance_of_RTOs.pdf
31 “Pre-Technical Conference Statement: Jacob Finkel, Office of Governor Josh Shapiro, Deputy Secretary of Policy;” (July 16, 2026) Docket No. AD26-7-000. https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260716-4005&optimized=false&sid=140709 8d-e46c-4292-acf1-eb7310602cdc
30 Kavulla, T.; “Problems in Electricity Market Governance: An Assessment;” R Street Policy Study No. 180; August 2019; pp.11 https://www.rstreet.org/research/problems-in-electricity-market-governance-an-assessment/
29 Peskoe, A.; “Replacing the Utility Transmission Syndicate’s Control;” Energy Law Journal, Volume 44.3, pp. 613-614; https://eelp.law.harvard.edu/wp-content/uploads/2024/10/Replacing-the-Utility-Transmission-Syndicates- Control-FINAL.pdf

PDF page 15

with experiential knowledge of the effects of PJM’s policies and actions is educational for decision-makers like PJM’s board and PJM staff.33

Showing the courage of our convictions, PJMCCC has made efforts to achieve the kind of engagement with PJM that we would like to see become PJM’s standard practice. We are currently collaborating with PJM’s State Policy Solutions team to shape the development of the local policy portal to support PJM’s compliance with FERC Order 1920. We have been working closely to help inform the data fields to be used for aggregating local government policies, goals, siting opportunities, and siting restrictions. Additionally, we submitted local building and vehicle electrification objectives to PJM’s Load Analysis Subcommittee that were used in the 2024 load forecast.

​
PJMCCC has also engaged with PJM’s Transmission Expansion Advisory
Committee (TEAC), which has recently taken promising actions toward the kind of engagement necessary for all of PJM.  The leadership of PJM’s TEAC has taken commendable steps such as recently expanding the discussion time at TEAC meetings to allow more time for public stakeholders to raise questions and discuss issues in PJM transmission planning.  The TEAC leadership has also provided helpful details in response to questions about utilities’ local projects (i.e. supplemental projects).

Importantly, the leadership of PJM’s TEAC has made considerable efforts to keep the scope of discussion at TEAC meetings narrowed to PJM transmission planning, because stakeholders in the PJM region have many topics to discuss.  It is a fair assessment that stakeholders sometimes introduce topics that are outside the scope of TEAC meetings, but this is only a strong indication that PJM needs to expand its regular engagement with non-member stakeholders into other topic areas.  PJM should develop organizational routines and structures for similar engagement on all policy issues undertaken by PJM.

The solution

Similar to the reforms to create required, regular, and responsive meetings with PJM engagement states that are offered earlier in these comments, PJM should create structured opportunities for engagement with PJMCCC members and similarly situated non-member stakeholders who are neither states nor members.  PJM could borrow from the ROWE’s designs for stakeholder engagement for this purpose, particularly the

33 Welton, S.; “The Citizen and the Energy Regulatory Process;” University of Pennsylvania Journal of Law and Public Affairs (2023), Vol. 8, No. 1; pp.31-36; https://repository.law.upenn.edu/Documents/Detail/96471

PDF page 16

Office of Public Participation (OPP), the states’ policy committee, and the Consumer Advocate Organization.  FERC could require PJM to do this, or PJM could do this voluntarily.

4.​ Do existing governing document provisions (e.g., Operating Agreement, Manuals) impede stakeholder decision-making and what changes could be made to address them?

As indicated elsewhere in these comments, PJMCCC leaves it to other entities to opine on the opportunities for improving stakeholder decisions via the governing documents.  PJMCCC believes that such improvements would be exponentiated if combined with the reforms suggested elsewhere in these comments.

5.​ What reforms to the stakeholder process could ensure PJM can meet the region’s challenges?

​
Beyond the reforms outlined elsewhere in these comments, a further useful step would be for FERC to direct PJM to undertake the creation of an independent transmission monitor.34  An independent transmission monitor would be useful for providing review of the local transmission projects that are proposed by PJM utilities, which currently have no review and fall through a regulatory gap.  An independent transmission monitor would also be useful for ensuring consideration of non-transmission alternatives, like advanced transmission technologies, that would improve the overall efficiency of the PJM grid while also improving the affordability of electricity for PJM residents.

6.​ What near-term reforms to stakeholder representation could PJM and its Members take to improve speed in decision-making while preserving

stakeholder input?

34 Konidena, R.; “Why FERC Should Mandate an Independent Monitor at PJM;” (November 27, 2023) https://www.renewableenergyworld.com/solar/utility-scale/why-ferc-should-mandate-an-independent-moni tor-at-pjm/; See also https://acadiacenter.org/planning-the-future-electric-grid-the-need-for-an-independent-transmission-monit or/

PDF page 17

As indicated elsewhere in these comments, PJMCCC strongly believes that stakeholder input needs to be expanded at this juncture, rather than merely “preserved.” PJMCCC views a lack of effort on PJM’s part to gather and respond to non-member stakeholder input as a key factor in getting the PJM region into the crisis it faces today. Much of the contemporary discourse on PJM issues focuses on the PJM capacity market.  Empirical research has found that PJM governance influences PJM capacity market outcomes.35  So the assertion that PJM’s unresponsive governance has led to the capacity market crisis facing the region should come as no surprise.

As such, PJMCCC believes that the crisis will be resolved primarily through expanding stakeholder input rather than expediting decisions.  To that end, PJMCCC refers the Commission to its recommendations elsewhere in these comments as to how stakeholder input and engagement could be expanded.  In addition, the PJMCCC refers the Commission to its earlier recommendations to reform the PJM board as a means of achieving both faster and more responsive decision-making from PJM.

7.​ Are there elements of PJM’s committee structure that routinely contribute to delays?  Are there stakeholder processes or issues that could be expedited or changed to provide greater focus on key issues and allow faster or more unilateral action on others?

​
PJMCCC refers the Commission to the reforms outlined elsewhere in these comments.  PJMCCC appreciates FERC’s attention to the delays and desire to expedite PJM decisions.  PJMCCC believes that expanding non-member stakeholder input will be just as useful as expediting PJM decision-making, to the resolution of PJM’s current challenges, if not moreso.​

8.​ Should PJM increase the use of fast-path or time-bound review procedures to expedite committee action on high-importance topics?

35 Blumsack, S.; and Yoo, K.; “RTO Governance Structures Can Affect Capacity Market Outcomes;” (2020) Proceedings of the 53rd Hawaii International Conference on System Sciences. https://pure.psu.edu/en/publications/rto-governance-structures-can-affect-capacity-market-outcomes/

PDF page 18

PJMCCC notes that PJM has increasingly used fast-path procedures to address recent issues.36  However, In some cases those procedures have failed to deliver consensus and timely decision-making, such as the large load interconnection CIFP proceeding in which no proposal received enough votes to pass.37  As such, PJMCCC views the use of fast-path procedures as creating a strong risk of failing to resolve the underlying problems with PJM governance.  PJMCCC believes that the use of fast-path procedures goes against developing successful strategies for improving PJM decision-making in the way that the Commission’s questions indicate would be desirable.  PJMCCC encourages FERC to consider the reforms outlined elsewhere in these comments as better alternatives for addressing issues in PJM, rather than encouraging PJM to increase its use of fast-path procedures.

9.​ Recognizing regional differences, are there lessons from other RTO/ISO stakeholder processes that PJM could reasonably adopt to improve speed in voting processes and stakeholder representation?

As indicated elsewhere in these comments, PJMCCC believes that the ROWE’s newly proposed independent regional governance structure would be a valuable model for PJM.  The ROWE’s governance structure builds on lessons learned from other forms of regional market governance and develops robust processes for avoiding some of the failures seen in those other forms.  The ROWE’s structure moves away from a utility-centric governance model and toward one that gives more power to states, ratepayer advocates, and other public interest groups to influence market policies. FERC should consider the governance features of the ROWE and require PJM to adopt some of them, as outlined elsewhere in these comments.

Conclusion
Again, we applaud the Commission’s focus on governance issues within PJM, and we hope these comments will be of use to the Commission’s investigation into these issues.  We thank the Commission for the opportunity to comment, and we look forward to the Conference and to hearing remarks from both the panelists and Commissioners.

37 https://www.utilitydive.com/news/pjm-stakeholders-data-center-interconnection-cifp/806009/
36 See generally, Johnson, N., Lenhart, S., and Blumsack, S.; “The Evolution of Participatory Policymaking for Regional Power Grids;” Energy Law Journal; Vol. 44; pp. 533-546 (2023). https://scholarworks.boisestate.edu/cgi/viewcontent.cgi?article=1169&context=pubadmin_facpubs; See also Peskoe, A.; “Replacing the Utility Transmission Syndicate’s Control;” Energy Law Journal, Volume 44.3, pp.616; https://eelp.law.harvard.edu/wp-content/uploads/2024/10/Replacing-the-Utility-Transmission-Syndicates- Control-FINAL.pdf