AD26-7-000 · 2026-07-23 · PJM Legislators' Collaborative

Pre-Conference Comments of The PJM Legislators’ Collaborative re the PJM Governance and Stakeholder Reforms

PDF page 1

PJM LEGISLATORS’ COLLABORATIVE – EXECUTIVE SUMMARY

1
Before the Federal Energy Regulatory
Commission
PJM Governance and Stakeholder Reforms
Docket No. AD26-7-000
PRE-CONFERENCE COMMENTS OF THE PJM LEGISLATORS’ COLLABORATIVE
The PJM Legislators’ Collaborative (Collaborative) is a bipartisan coalition of state legislators representing the 13 states and the District of Columbia within PJM's footprint. The Collaborative was formed in 2025 in response to growing concerns over rapidly rising electricity costs, resource adequacy, and the unprecedented increase in electricity demand driven by large data centers and other emerging loads. As the Collaborative sought regional solutions to these challenges, PJM's existing governance and stakeholder processes were unable to respond with the speed, transparency, or accountability required. The issues surrounding data center load growth illustrate these broader structural challenges and underscore the need for governance reform. In preparation for this Technical Conference, the Collaborative surveyed states to identify areas of common concern regarding PJM governance and the extent to which its current structures continue to serve the public interest. While individual states differ in their specific policy priorities, responses across the nine participating states revealed broad agreement that PJM's governance framework has not kept pace with the modern electric grid or evolving state energy policy. Across the region, states expressed concerns that the current governance model does not provide sufficient transparency, accountability, or meaningful opportunities for state participation, despite the fact that state governments ultimately bear responsibility for utility regulation, consumer protection, energy policy implementation, and responding to the ratepayer impacts of PJM's decisions. Many states also pointed to specific experiences that illustrate these broader structural concerns. For example, Illinois described a delay of more than four years in PJM incorporating the state's Climate and Equitable Jobs Act into regional planning, frustrating the implementation of duly enacted state law. Pennsylvania cited its successful efforts to establish a FERC-approved capacity market cap—which has already saved ratepayers approximately $45 billion—as evidence that states can improve outcomes through active engagement. However, Pennsylvania emphasizes that such interventions are an inefficient substitute for meaningful participation in PJM decision- making. States also raised concerns regarding limited access to the data and analytical assumptions underlying major planning decisions.

Collectively, these responses reflect a shared view that PJM's governance framework must evolve to better recognize the role of states as public institutions responsible for protecting affordability, reliability, and the public interest. Although participating states differ on certain implementation details, they expressed broad bipartisan agreement on five mutually reinforcing governance reforms that would strengthen public accountability, improve state participation, enhance transparency, and better align PJM's governance with its public-interest responsibilities.

PDF page 2

PJM LEGISLATORS’ COLLABORATIVE – EXECUTIVE SUMMARY

2
Together, states in the Collaborative support establishing a governance framework that (1) clearly defines PJM's public-interest mission, (2) gives states a meaningful institutional role, (3) strengthens Board independence and accountability, (4) modernizes decision-making, and (5) improves transparency and oversight. Specifically, the Collaborative recommends:

1. Establish a Public Interest Governance Mandate. FERC should direct PJM to restructure its governance framework to operationalize the Board’s duty to serve the broader public interest across the region.  This includes amending its foundational operating agreements to legally balance system reliability and affordability.

2. Create a Formal State Governance Role. There should be an independent regional state committee, composed of Governors, legislators, and regulators, funded through the RTO tariff and governed by state-appointed managers. This group should have "jump ball" or direct filing rights to submit proposals to FERC regarding cost allocation and market rules

– the same authorities available to states in many other RTOs. This committee should have explicit authority to commission independent studies, paired with mandatory disclosure of PJM’s major planning assumptions and methodologies so external experts can evaluate them. PJM should be required to undergo a formal reconciliation process with the state committee before submitting major filings to FERC.

3. Strengthen Board Independence and Accountability.  To better align the Board with state and ratepayer interests, FERC should direct PJM to expand Board qualification requirements to include experience in public service and expertise regarding consumer and ratepayer impacts. FERC should also require formal, quantifiable performance metrics against which the Board is evaluated by FERC. In addition, the regional state committee should have a formal role in nominating PJM Board members.

4. Modernize the Stakeholder Process. PJM should enhance the Board’s ability to act when stakeholder processes reach deadlock and should extend weighted voting to prevent large firms from dominating votes via affiliate voting. In addition, PJM should provide formal governance roles, as well as technical assistance and other resources to state representatives and consumer advocates.

5. Strengthen Transparency and Accountability.  PJM should record and archive all stakeholder and Board meetings, votes, and Board rationales in a searchable database.  PJM should provide appropriate and secure access to raw data, planning assumptions, and standardized, reproducible load-forecasting models for state utility commissions and consumer advocates. FERC should designate an Independent Transmission Monitor to provide impartial oversight of transmission planning, cost allocation, and speculative interconnection.

The recommendations reflect the overarching principles that should guide PJM governance reform: restoring accountability, improving responsiveness, and ensuring that PJM's decisions are aligned with state policy priorities and the interests of ratepayers. Compared with other Regional Transmission Organizations (RTOs), PJM provides states with a more limited formal role in governance and key decision-making processes. The Collaborative's recommendations draw on governance structures that have been successfully implemented in other RTOs while reflecting

PDF page 3

PJM LEGISLATORS’ COLLABORATIVE – EXECUTIVE SUMMARY

3
PJM's unique regional responsibilities. The following sections examine each major area of PJM governance in greater detail, outlining the specific reforms the Collaborative believes are necessary to modernize PJM's governance, strengthen the role of states, and promote a more transparent, accountable, and effective regional planning process.

1. Institutional Governance Reform

The energy landscape in which PJM operates is undergoing fundamental changes, with the increase in data center development and associated surge in demand, a shift in energy resources as older coal and gas-fired facilities face retirement, and growing consumer affordability challenges. At the same time, PJM has failed to address large load growth without radically increasing customer bills, which has created uncertainty about future resource adequacy, grid reliability, and cost management.

Across the comments submitted by the Collaborative, states expressed broad agreement that PJM's current governance structure is outdated and no longer capable of managing the modern energy transition. Legislators consistently describe a governance model that responds too slowly to emerging challenges, is structurally incapable of adapting to a rapidly changing electric system, and increasingly forces states to intervene individually on issues such as resource adequacy, grid reliability, and consumer protection. Ohio emphasizes that PJM’s governance allows the generation portfolio to remain dominated by "outdated, high-cost legacy generation" despite cleaner projects being faster and easier to finance, directly harming affordability. Pennsylvania characterizes the growing disconnect between the pace of grid transformation and PJM's decision- making as a direct threat to residents, while Illinois emphasizes that state actions should complement PJM—not compensate for its inability to act.

States also share a common concern that PJM's governance framework fails to adequately represent the public interest or the state authorities charged with protecting it. Multiple states note that PJM's foundational documents impose no affirmative obligation on the Board to consider affordability, ratepayer impacts, or broader public policy objectives, leaving decisions to be primarily driven by the interests of corporate market participants. At the same time, states argue they are systematically excluded from meaningful governance despite bearing primary responsibility for energy policy, resource adequacy, and consumer protection. Existing mechanisms such as the Organization of PJM States, Inc. (OPSI) remain advisory, with no requirement that PJM incorporate state recommendations, leaving the organization insufficiently accountable to the 67 million ratepayers who ultimately fund the system. Maryland and Pennsylvania suggest re-chartering PJM, LLC as an interstate compact public benefit entity. They use the Port Authority of New York and New Jersey and the Delaware River Basin Commission as examples in which the federal government recognized that shared regional infrastructure could not be managed by fragmented, competing jurisdictions.

PDF page 4

PJM LEGISLATORS’ COLLABORATIVE – EXECUTIVE SUMMARY

4
Recommendations

1. To address the institutional and structural PJM faces, the Collaborative recommends the following reforms:

1.1 Codify a Public Interest Mandate: FERC should direct PJM to amend its foundational governing documents to legally mandate that the organization is accountable to the public interest and balances system reliability and affordability.

1.2 Reconfigure the corporate structure of PJM: FERC should restructure the foundational model of PJM’s governance to ensure that there is accountability for the outcome of PJM’s decisions and to ensure that accountability serves the public interest. Among the Collaborative’s members, a range of suggestions were put forth on what fundamental governance restructuring should be. But overwhelmingly, consensus among states is that PJM’s current governance structure cannot quickly and effectively respond to the current challenges of the evolving energy landscape. Thus, the Collaborative does not prescribe a single structural model but recommends that FERC ensure that a restructured governance model for PJM creates a grid operator that can be flexible and adaptable to new challenges, can be held accountable for its decisions and outcomes, and can ensure that accountability serves the ratepayers who fund it. These recommendations aim to create a modern governance framework in which PJM is both structurally accountable to the public interest and institutionally capable of responding quickly, transparently, and responsibly to the evolving challenges facing the regional grid.

2. States Roles & Filing Rights

Under PJM’s current structure, states are limited in their role in PJM’s decision-making process. The public utility commissions in each member state provide state representation through their membership in OPSI, which is a non-voting member of PJM.

According to PJM, OPSI should play a role in supporting a cooperative regional approach among the states on PJM issues and in advising PJM on regulators’ concerns and viewpoints. PJM, however, is not legally mandated to incorporate any of OPSI’s recommendations. Instead, states in the Collaborative find that OPSI’s role at PJM falls more to that of a non-binding consultant, ultimately leaving states with no formal authority within PJM’s governance structure. Many states note that the decisions made by PJM ultimately impact the states. As an example, some states discussed how PJM’s slowness to clear the interconnection queue backlog resulted in lost generation projects, which impacted job growth in the states and contributed to rate increases. Those who are impacted by PJM’s decisions - residents and businesses - look to the states to answer for rising energy costs and grid reliability issues, not PJM.

The responses from PJM states demonstrate a clear, unified demand for formal, institutionalized authority rather than the current model of non-binding consultation. Indiana, which is served by both PJM and MISO, has direct experience with different regional governance models. They

PDF page 5

PJM LEGISLATORS’ COLLABORATIVE – EXECUTIVE SUMMARY

5
suggest that at minimum, states should be able to participate in the PJM Board nomination process and receive early notice of major changes in load forecasts, reliability projections, or planning assumptions. Other states agree that as the entities responsible for protecting ratepayers and implementing energy laws, they require a "seat at the table" that carries legal weight. Recommendations

2. To establish a formal role for states in PJM’s decision-making process, the Collaborative recommends the following reforms:

2.1 Grant States a Role in Board Member Nominations: States should have a formal role in the Board of Managers nomination or selection process. Maryland and Illinois suggest modeling this after MISO, where representatives from the states sit directly on the Board Nominating Committee.

2.2 Mandate Administrative Reconciliation: Many states recommend that FERC require PJM to undergo a formal reconciliation process with states before submitting major filings to FERC. States should also have the ability to request regular joint technical sessions with the PJM Board to ensure state policies are embedded in the planning process from the start. 2.3 Establish a formal structure for state engagement: There should be established an independent regional state committee, composed of Governors, legislators, and regulators, funded through the RTO tariff and governed by state-appointed managers. In addition to the Collaborative, Pennsylvania points to the PJM Governors Collaborative as an example of structured state engagement with PJM. Maryland highlights how the New England States Committee on Electricity provides ISO-NE states the authority to engage with ISO-NE. 2.4 Grant States Section 205 Filing Rights: FERC should provide states with "jump ball" or direct filing rights to submit their own proposals to FERC regarding cost allocation and market rules. Illinois, Maryland, New Jersey, and Pennsylvania all explicitly call for states to have Section 205 direct filing rights. This would allow states to submit their own proposals to FERC on matters like cost allocation and resource adequacy, rather than only reacting to PJM’s filings. These recommendations aim to embed states as formal, empowered partners in PJM’s governance structure—ensuring that state policy priorities and ratepayer interests are integrated into PJM decisions from the outset rather than treated as external commentary after the fact.

3. Board Reform and Accountability

The PJM Board is intended to satisfy FERC’s directive that each RTO’s governance structure be independent of financial or other conflicting interests in the RTO’s markets and stakeholder groups. States in the Collaborative generally agree that the current Board lacks sufficient accountability to public interests, particularly the interests of the 67 million ratepayers who ultimately bear the financial and reliability risks of Board decisions. Some states noted that the

PDF page 6

PJM LEGISLATORS’ COLLABORATIVE – EXECUTIVE SUMMARY

6
Board’s primary fiduciary duty is directed toward its corporate market members, and question whether this allows the Board to truly act independently of its stakeholders.

Many states note that there is no formal accountability structure, such as performance metrics or external review, for Board members or the Board as a whole. Pennsylvania and Maryland note that when markets fail or interconnection queues stall, there is no mechanism to compel the Board to take immediate action to remedy the issues. In response, Maryland suggests that the PJM Board should be granted independent Section 205 filing rights that do not rely on stakeholder consensus. Some states additionally note that the Board is beholden to the Members Committee for certain reforms, giving stakeholders de facto veto authority and blocking necessary action. Most responding states also note that the Board’s decisions are frequently reactive to problems rather than proactively improving efficiency or processes. This makes PJM unacceptably slow to respond to emerging issues.

Recommendations
3. To address the issues with the Board’s independence and accountability, the Collaborative recommends the following reforms:

3.1 State Representation: Nearly all specifically noted that they would like states to have a role in nominating or selecting board members, with some citing MISO as an example. 3.2 Require Diverse Expertise Requirements for Board Members: Many states note that the Board lacks accountability to public interests, including ratepayer interests. Illinois and Pennsylvania suggest that there should be a requirement for some Board members to have experience in state regulatory commissions or consumer advocacy organizations. 3.3 Implement Binding Performance Metrics: Some states, including Pennsylvania and Maryland, noted in their response that there should be formal and quantifiable performance metrics that the Board should be held accountable to. Maryland specifies load forecasting accuracy and queue execution speed as performance metrics.

These recommendations aim to strengthen Board accountability by ensuring states can shape Board membership, require diverse public‑interest expertise, and hold PJM’s leadership to clear, measurable performance standards.

4. Stakeholder Process & Voting Mechanics

Across participating states, there was broad agreement that PJM's stakeholder process is no longer functioning as an effective mechanism for regional decision-making. States consistently identified PJM’s stakeholder process as one of the principal barriers to timely and effective governance. While the process was designed to build consensus among market participants, many respondents believe it has instead resulted in a system in which it is increasingly difficult to implement reforms needed to maintain reliability, address affordability, and respond to rapidly emerging challenges. Rather than facilitating collaboration, the stakeholder process too often rewards maintaining the status quo, even when broad agreement exists that reforms are needed, according to participating states.

PDF page 7

PJM LEGISLATORS’ COLLABORATIVE – EXECUTIVE SUMMARY

7

The current voting structure allows relatively small coalitions of stakeholders to block proposals indefinitely, resulting in regulatory paralysis and making it difficult for PJM to modernize market rules or respond to changing grid conditions. The current governance model does not provide the Board with sufficient flexibility to act in the broader public interest when the stakeholder process reaches an impasse.

In addition, the stakeholder process disproportionately reflects the interests of incumbent market participants while providing woefully insufficient representation for the 67 million residential ratepayers who have paid into the system for generations. States are often left to pursue lengthy and resource-intensive proceedings before the Federal Energy Regulatory Commission when the stakeholder process fails to produce timely or appropriate reforms.

Meaningful participation in PJM's committees requires substantial time, financial resources, and technical expertise, creating barriers for many non-industry stakeholders. Although hundreds of organizations are eligible to participate in PJM's voting process, relatively few actively do so, allowing well-organized stakeholder coalitions to exert outsized influence over outcomes.

Collectively, these concerns reflect a broader view that PJM's governance structure has not kept pace with the evolving responsibilities of states or the increasingly significant financial and reliability consequences of regional market decisions.

Recommendations
4. To better balance efficient decision-making with meaningful stakeholder participation, the Collaborative recommends the following reforms:

4.1 Strengthen States and Consumer Representatives: Provide formal governance roles and greater influence over major decisions.

4.2 Reduce Participation Barriers: Provide technical assistance and other resources for consumer advocates and state representatives.

4.3 Expand Sector-Weighted Voting: Extend weighted voting to all standing committees to prevent large firms from dominating via affiliate voting.

4.4 Empower Board Flexibility: Enhance the ability for the Board to act when stakeholder processes reach deadlocks or fail to address urgent reliability or affordability concerns. These recommendations aim to create a stakeholder system that is both faster and more representative - one that preserves meaningful participation while giving PJM the flexibility, balance, and structural support needed to act decisively in the public interest.

5. Data Transparency & Independent Verification

The responses from the Collaborative reflect consensus: the current operational structure of PJM has caused a structural transparency deficit that undermines regulators’ ability to protect ratepayers

PDF page 8

PJM LEGISLATORS’ COLLABORATIVE – EXECUTIVE SUMMARY

8
and ensure costs are incurred appropriately. Furthermore, the closed and opaque nature of stakeholder deliberations limits public confidence in PJM's decision-making and makes meaningful oversight more difficult for state policymakers.

States are forced to rely on PJM’s internal conclusions for forecasts that represent billions of dollars in ratepayer costs without the ability to independently review them. Because PJM does not provide access to the underlying data, models, or methodologies, states and consumer advocates cannot reproduce or validate the results that drive transmission spending, capacity accreditation outcomes, and long-term resource adequacy decisions. This dynamic leaves state officials accountable for costs they cannot meaningfully interrogate.

In response, several PJM states have passed or introduced legislation requiring independent validation of utility load forecasts before they are submitted to PJM, yet PJM itself bears no comparable transparency or accountability obligation for the forecasts that underpin regional planning decisions despite the significant cost impacts of inaccuracy. Illinois notes that few, if any, PJM proposals have cost information before a vote and suggests it should be standard practice to evaluate the cost impacts of any proposal as part of the First Read at the Markets and Reliability Committee/Members Committee. Indiana recommends that public record should show who created the need for each project, who benefits from it, whether competitive alternatives were considered, and how the costs will be assigned.

States also highlight that PJM’s stakeholder process compounds these transparency issues by privileging well-resourced, fully staffed, commercial and industrial participants. This creates an uneven playing field for states and consumer advocates in which critical planning decisions are shaped without balanced representation.

Recommendations
5. To rebuild transparency, strengthen independent oversight, and ensure planning is accountable to those ultimately bearing the costs, the Collaborative recommends the following reforms:

5.1 Independent Verification and Data Access: Provide appropriate and secure access for public utility commissions and consumer advocates to raw data, planning assumptions, and forecasting models; establish a secure clearinghouse for confidential data; and create standardized, reproducible load-forecasting processes.

5.2 Governance Transparency: Record and archive all stakeholder meetings; publish all committee votes; and establish searchable archives of decisions, votes, and Board rationales. Require cost impacts to be published with Board decisions.

5.3 Enhanced State Communication: Require that PJM proactively communicate with relevant states when decisions are being made which directly impact them.

5.4 Independent Studies: The regional state committee should have explicit rights to commission independent studies on affordability, reliability, and emerging load trends, paired

PDF page 9

PJM LEGISLATORS’ COLLABORATIVE – EXECUTIVE SUMMARY

9
with mandatory disclosure of PJM’s major planning assumptions so external experts can evaluate them.

5.5 Improve Transmission and Load-Forecasting Integrity: Create an Independent Transmission Monitor to provide impartial oversight of transmission planning and cost allocation, as well as eliminate opportunities for speculative interconnection and duplicate load submissions which undermine the accuracy of load forecasting.

These recommendations would establish a more transparent, accountable, and independently verifiable planning and decision-making process. They would provide states and consumer advocates with meaningful access to the information, analytical tools, and oversight mechanisms necessary to evaluate PJM's decisions, strengthen the integrity of transmission and load forecasting, and ensure that planning outcomes are subject to independent scrutiny before billions of dollars in costs are imposed on ratepayers.

Conclusion

Collectively, these recommendations would transform PJM's governance from one driven primarily by member dialogue into one that is accountable to the broader public interest, with meaningful institutional roles for the states responsible for protecting consumers. Together, they would establish a clear public-interest mandate, strengthen state participation and independent oversight, enhance Board accountability, modernize decision-making, and improve transparency throughout PJM's governance and planning processes. These reforms would better equip PJM and states to address emerging challenges while restoring public confidence in regional decision- making. They would provide PJM, FERC, and states with the governance tools necessary to identify problems earlier, resolve disagreements more effectively, and implement timely regional solutions that better protect reliability, affordability, and the public interest. The Collaborative appreciates the opportunity to provide these comments and looks forward to the Technical Conference on July 23.

Respectfully Submitted,

Senator Katie Fry Hester
Maryland, District 9 - Howard and Montgomery Counties
Chair, Energy Subcommittee, Senate Education, Energy and Environment Committee 304 James Senate Office Building, 11 Bladen Street

Annapolis, MD 21401
410-841-3671
KatieFry.Hester@senate.maryland.gov

On Behalf of the PJM Legislators’ Collaborative
Dated: July 22, 2026

PDF page 10

PJM LEGISLATORS’ COLLABORATIVE – EXECUTIVE SUMMARY

10

About The PJM Legislators’ Collaborative

In response to rising energy costs and the limited influence of states over PJM policies due to the current governance structure, state legislators from across the region came together to form the PJM Legislators’ Collaborative. The Collaborative brings together state legislators from all 13 states and the District of Columbia within the PJM footprint who share a bipartisan commitment to reliable, affordable energy for the ratepayers we represent. As legislators, we occupy a unique position in the energy ecosystem: we enact the laws governing utilities, oversee state regulatory frameworks, and are directly accountable to the constituents affected by PJM and FERC decisions. The Collaborative has engaged directly with PJM to ensure that state perspectives are meaningfully incorporated into regional market reforms and other decisions with significant implications for reliability, affordability, and cost allocation.  Specifically, we have engaged as follows:

● Submittal of Protecting Ratepayers Proposal during the CIFP Process (November, 2025)
● Letter in response to PJM's CIFP Proposal (November, 2025)
● Letter regarding Reliability Backstop Procurement (RBP) Process (March, 2026)
● Requested PJM to change the problem statement and issue charge, and include taking large loads out of the capacity market in the RBP process at their Markets and Reliability Committee Meeting (April, 2026)

● Attended the PJM Annual Meeting and met with PJM Board Members and FERC staff (May, 2026)

● Letter regarding supported principles for the Connect and Manage and RBP Process (June, 2026)

PDF page 11

DELAWARE - STATE COMMENTS
11
Delaware - State Comments

State Representatives’ names, titles, and emails: (please list the lead author as well as those collaborating on this document)

Sen. Stephanie Hansen, Chair of Senate Environment, Energy and Transportation Committee, Stephanie.Hansen@delaware.gov (lead author)

Rep. Frank Burns, Member of House Natural Resources and Energy Committee, Frank.Burns@delaware.gov

State energy descriptors: (regulated or deregulated; net importer/exporter; etc.):

Delaware is a deregulated state and a net energy importer. Delmarva Power is our largest and only commission-regulated electric utility, followed by the Delaware Electric Cooperative, then our nine municipal electric companies organized as members of the Delaware Municipal Electric Corporation.

1. GOVERNANCE: Do we need to reform the governance of PJM? If so, why? For example, please consider how PJM’s current governance affects your state, other RTOs' governance, and your recommendations for reform.

There does not seem to be a formal way for states to make their issues known to the PJM Board and then track any movement on those issues.  No one seems to be accountable to the states.  There should be someone on the PJM Board that is selected or nominated by the states.

2. STATE ROLE: What role and influence should states have in PJM?  Please consider whether states should have a role: on the PJM Board or in the nominations process, engaged in joint technical sessions with the PJM Board, in a formal consultation process, enhanced observer status, or information rights before major filings, participating in independent reviews of load forecasting accuracy and major planning assumptions, receiving early-warning reporting when material changes occur in large-load forecasts, reliability assessments, or planning assumptions, and/or formally embedding state policy objectives into PJM's planning and market processes.

The states should have a role in either selecting or nominating a member to the PJM Board. There should also be formal outreach to the states before filings to gather information relevant to the subject matter of the filing.

3. BOARD: Is the current board authority and accountability effective? Please consider the board’s ability to act unilaterally, reforming Board composition to include state-selected or state-nominated seats; establishing formal board performance metrics

PDF page 12

DELAWARE - STATE COMMENTS
12
and periodic external accountability reviews; exploring Independent Representative Stakeholder (RSC) Board model used at other RTOs.

The states should have a role in either selecting or nominating a member to the PJM Board. In addition, as part of the decision-making process on matters before the Board, the issue of ratepayer affordability should be an explicit consideration.

4. STAKEHOLDER PROCESS: Is the existing stakeholder process and filing right structure working?  If not, should it be changed?  Please consider if the process accurately reflects the interests of those ultimately bearing reliability and affordability risk, particularly ratepayers and emerging large-load customers? Please consider: modifying the voting structure, improving transparency and information access, reviewing and refreshing filing rights, and/or strengthening FERC's use of its Section 206 backstop authority.

Transparency in the stakeholder voting process is lacking.  There should be some repository of items (searchable) that have been voted upon, the vote made by each stakeholder, and the date. In addition, the voting threshold should be lowered for the passage of proposals, perhaps employing ranked choice voting when multiple options are presented.

5. TRANSPARENCY: Does the PJM operational structure allow sufficient
engagement with independent information and transparency necessary to affect affordability?   Please consider whether regulators and consumer advocates have sufficient access to reproduce and independently evaluate the forecasts, congestion analyses, and planning assumptions that ultimately influence ratepayer costs. Should states be able to request studies on emerging affordability and reliability issues? Can we expand independent analytical access to PJM data while preserving market-sensitive confidentiality?

States would benefit from improved access to PJM’s operational and market data, particularly on resource adequacy and reliability risks. PJM should develop a searchable repository of this information. This should include stakeholder voting records and the rationale behind key decisions by the Board.

6. STRUCTURE: Is PJM currently structured in a way to operate effectively in today’s rapidly changing context?  Please consider whether PJM has sufficient visibility into emerging risks, sufficient authority to act on them, and sufficient accountability for the outcomes. Is it sufficient regardless of the governance reform? What recommendations do you have for the future structure of PJM?

PJM moves too slowly in coming to decisions on important, emerging issues.  More process is not better when decision-making is time-sensitive.

PDF page 13

DELAWARE - STATE COMMENTS
13

7. OTHER: Please add any other comments or respond to the FERC technical
conference panel questions specifically here:

There should be a route for the states to directly intervene at FERC in addition to having better input on PJM decision making.

PDF page 14

ILLINOIS - STATE COMMENTS
14
Illinois - State Comments

State Representatives’ names, titles, and emails: (please list the lead author as well as those collaborating on this document)

Sen. Rachel Ventura

State energy descriptors: (regulated or deregulated; net importer/exporter; etc.):

Restructured state; net exporter. Illinois is split between PJM and MISO, with the ComEd utility region (northern Illinois, including Chicagoland) in PJM. We have leading climate laws that require a transition to a carbon-free electricity system by 2045.

1. GOVERNANCE: Do we need to reform the governance of PJM? If so, why? For example, please consider how PJM’s current governance affects your state, other RTOs' governance, and your recommendations for reform.

PJM states have the least formal input of any RTO/ISO. This has led to an untenable situation whereby states are both responsible for fundamentals like resource adequacy but lack the ability to meaningfully effectuate their own laws. While OPSI and the Independent State Agencies Committee (ISAC) provides input to PJM, it is non-binding and often easy to ignore. For example, the ISAC submits a workbook of state policies that PJM should account for in its planning each year. However, PJM is inconsistent in how it accounts for those policy effects. For example, PJM did not begin accounting for our Illinois Climate and Equitable Jobs Act (passed in 2021) until the 2025 RTEP, and even then, it does not account for it holistically. For example, CEJA creates priority zones for transmission, but PJM does not account for that in its long-term planning. This frustrates the implementation of Illinois state laws.

2. STATE ROLE: What role and influence should states have in PJM?  Please consider whether states should have a role: on the PJM Board or in the nominations process, engaged in joint technical sessions with the PJM Board, in a formal consultation process, enhanced observer status, or information rights before major filings, participating in independent reviews of load forecasting accuracy and major planning assumptions, receiving early-warning reporting when material changes occur in large-load forecasts, reliability assessments, or planning assumptions, and/or formally embedding state policy objectives into PJM's planning and market processes.

205 filing rights: At minimum, OPSI should have 205 “jump ball” filing rights to enhance state input. This jump ball could be exercised with a majority vote of OPSI members and apply to transmission cost allocation, market rules, and resource adequacy, similar to Southwest Power Pool’s Regional States Commission. Given that states do not have a vote in the PJM stakeholder process (which would inappropriately place states on even footing with other PJM Members), having jump ball filing rights is fundamental to giving states formal

PDF page 15

ILLINOIS - STATE COMMENTS
15
input. 205 filing rights would also encourage OPSI members to come to agreement, since at least a majority would need to share a position in order to exercise the filing rights.

OPSI input: it should be standard practice that the Board formally consults with OPSI prior to major filings. Some of this can be achieved by OPSI increasing its engagement at the MRC/MC.

Liaison Committee: Nowhere is it more clear than in the Liaison Committee that states are systematically excluded from meaningfully engaging with the PJM process. See the West Virginia Commission’s litigation to join Liaison Committee, which was rejected by FERC. States should be allowed to attend Liaison Committee.

3. BOARD: Is the current board authority and accountability effective? Please consider the board’s ability to act unilaterally, reforming Board composition to include state-selected or state-nominated seats; establishing formal board performance metrics and periodic external accountability reviews; exploring Independent Representative Stakeholder (RSC) Board model used at other RTOs.

Nominating Committee: States should have a role in selecting PJM Board members. The Nominating Committee should have at least one seat designated for a representative of OPSI.

Board makeup: The PJM Board has membership requirements for expertise, but does not include requirements for state representation. The Board should always include a past regulator and someone with consumer advocacy experience.

4. STAKEHOLDER PROCESS: Is the existing stakeholder process and filing right structure working?  If not, should it be changed?  Please consider if the process accurately reflects the interests of those ultimately bearing reliability and affordability risk, particularly ratepayers and emerging large-load customers? Please consider: modifying the voting structure, improving transparency and information access, reviewing and refreshing filing rights, and/or strengthening FERC's use of its Section 206 backstop authority.

We have a number of specific recommendations for improving the stakeholder process:

Record meetings: With more PJM meetings than days in the year, PJM should record meetings—just as is standard practice in most state legislatures. The recordings need not be retained forever, but they should be available for a reasonable length of time. The issues discussed are highly technical and interested parties would benefit from reviewing recordings even if they attend the meetings live.

Voting disclosure: Currently, only votes in the Members Committee are fully disclosed. All votes of every committee, excluding the Nominating Committee, should be published with individual firm votes.

PDF page 16

ILLINOIS - STATE COMMENTS
16

Sector-weighted voting at Standing Committees: affiliate voting can easily dominate a decision at the Standing Committee level. For example, West Deptford (LS Power) alone controls 25 affiliate votes. The result is that decisions coming out of the Standing Committees are biased towards supply interests. The results can be balanced by extending sector-weighted voting to the Standing Committees, which would also encourage a wider range of stakeholders to participate.

5. TRANSPARENCY: Does the PJM operational structure allow sufficient
engagement with independent information and transparency necessary to affect affordability?   Please consider whether regulators and consumer advocates have sufficient access to reproduce and independently evaluate the forecasts, congestion analyses, and planning assumptions that ultimately influence ratepayer costs. Should states be able to request studies on emerging affordability and reliability issues? Can we expand independent analytical access to PJM data while preserving market-sensitive confidentiality?

Cost transparency: Few, if any, proposals have cost information prior to a vote. It should be standard practice to evaluate the cost impacts of any proposal as part of the First Read at the MRC/MC. Even where transmission cost information is provided, it is incomplete or inaccurate, as detailed in this analysis by David Gardiner and Associates.

Independent Transmission Monitor: just as PJM benefits from an Independent Market Monitor, who not only mitigates for market power but also provides cost information, PJM needs an Independent Transmission Monitor. By improving transmission oversight, states may be less likely to have concerns with individual lines.

6. STRUCTURE: Is PJM currently structured in a way to operate effectively in today’s rapidly changing context?  Please consider whether PJM has sufficient visibility into emerging risks, sufficient authority to act on them, and sufficient accountability for the outcomes. Is it sufficient regardless of the governance reform? What recommendations do you have for the future structure of PJM?

PJM is structurally deficient to protect the public interest. Its voting membership is overwhelmingly the regulated community — a clear example of regulatory capture. There are only 14 votes representing anything close to a state interest (consumer advocates). Nothing in PJM’s foundational documents compels the Board to prioritize or even consider affordability when making decisions. The Board is accountable only to PJM Members, who are overwhelmingly driven by profit interests. PJM membership and its accompanying sectors must be restructured to represent the interests of the 67 million consumers in the PJM footprint. Rather than looking to an existing RTO for guidance on this front, the West-Wide Governance Pathways Initiative provides important perspective.

PDF page 17

ILLINOIS - STATE COMMENTS
17
It is worth noting that governance reform at PJM is nigh impossible to achieve internally, since it requires a vote of the Members who would, presumably, be ceding their own power. This extends from seemingly smaller changes like publishing vote results to larger changes, like creating a new sector. The difficulty of making changes at PJM has forced states to consider whether the RTO best serves them.

7. OTHER: Please add any other comments or respond to the FERC technical
conference panel questions specifically here:

While PJM has a government affairs team, it does not adequately consult with the states. For example, PJM did not reach out to any Illinois stakeholders during the process of determining that ComEd should be separated out into its own zone for the purposes of setting net CONE. Once Illinois stakeholders became aware and asked for a delay in the process so they could engage, PJM refused. There should never be a case where a proposal targeting a specific state advances without proactive outreach by PJM to state entities, including the Commission and statutory consumer advocate(s).

PDF page 18

INDIANA - STATE COMMENTS
18
Indiana- State Comments

State Representatives’ names, titles, and emails: (please list the lead author as well as those collaborating on this document)

Rep. Sue Errington (HD34, Muncie) - errington@comcast.net

State energy descriptors: (regulated or deregulated; net importer/exporter; etc.):

Regulated. Electricity – Net Exporter. Fossil Fuels – Net Importer.

1. GOVERNANCE: Do we need to reform the governance of PJM? If so, why? For
example, please consider how PJM’s current governance affects your state, other RTOs' governance, and your recommendations for reform.

Yes. PJM's decisions directly affect electric reliability and affordability in Indiana, yet state regulators and consumer advocates have little formal authority compared with voting market participants. We should support a stronger formal role for states in major planning, transmission, and market decisions, including earlier access to forecasts and filings, regular consultation with the PJM Board, and clear deadlines when the stakeholder process cannot reach a decision.

2. STATE ROLE: What role and influence should states have in PJM?  Please consider whether states should have a role: on the PJM Board or in the nominations process, engaged in joint technical sessions with the PJM Board, in a formal consultation process, enhanced observer status, or information rights before major filings, participating in independent reviews of load forecasting accuracy and major planning assumptions, receiving early-warning reporting when material changes occur in large-load forecasts, reliability assessments, or planning assumptions, and/or formally embedding state policy objectives into PJM's planning and market processes.

States need a formal role in PJM because their residents ultimately bear the costs of its planning and market decisions. We support regular consultation and joint technical sessions with the PJM Board and early notice of significant changes in load forecasts or reliability projections. The state is served by both PJM and MISO, giving it direct experience with different regional governance models.

At minimum, states should be able to
1.Participate in the PJM Board nomination process.
2.Receive early notice of major changes in load forecasts, reliability projections, or planning assumptions.

3. BOARD: Is the current board authority and accountability effective? Please consider the board’s ability to act unilaterally, reforming Board composition to include state-selected or state-nominated seats; establishing formal board performance metrics and periodic external

PDF page 19

INDIANA - STATE COMMENTS
19
accountability reviews; exploring Independent Representative Stakeholder (RSC) Board model used at other RTOs.

No. PJM should consider board models used by other RTOs that provide states and stakeholders with a more direct role by adding state-nominated and independent consumer representatives to the Board, establishing public performance measures tied to reliability, affordability, and timely decision-making. The Board should retain authority to act when urgent action is needed, but those decisions should be transparent and subject to clear accountability.

4. STAKEHOLDER PROCESS: Is the existing stakeholder process and filing right structure working?  If not, should it be changed?  Please consider if the process accurately reflects the interests of those ultimately bearing reliability and affordability risk, particularly ratepayers and emerging large-load customers? Please consider: modifying the voting structure, improving transparency and information access, reviewing and refreshing filing rights, and/or strengthening FERC's use of its Section 206 backstop authority.

No. PJM's current process gives established market participants too much ability to delay or block needed changes. It has not produced timely answers on large-load interconnection, new generation, or other issues that directly affect reliability and customer bills. When PJM’s process cannot resolve urgent threats to affordability or reliability, FERC should be prepared to act under its existing authority.

5. TRANSPARENCY: Does the PJM operational structure allow sufficient
engagement with independent information and transparency necessary to affect affordability?   Please consider whether regulators and consumer advocates have sufficient access to reproduce and independently evaluate the forecasts, congestion analyses, and planning assumptions that ultimately influence ratepayer costs. Should states be able to request studies on emerging affordability and reliability issues? Can we expand independent analytical access to PJM data while preserving market-sensitive confidentiality?

Regulators and consumer advocates need enough information to independently evaluate PJM’s forecasts, transmission plans, and cost assumptions. Receiving PJM’s final conclusions is not sufficient. The public record should show who created the need for each project, who benefits from it, whether competitive alternatives were considered, and how the costs will be assigned.

6. STRUCTURE: Is PJM currently structured in a way to operate effectively in today’s rapidly changing context?  Please consider whether PJM has sufficient visibility into emerging risks, sufficient authority to act on them, and sufficient accountability for the outcomes. Is it sufficient regardless of the governance reform?  What recommendations do you have for the future structure of PJM?

PDF page 20

INDIANA - STATE COMMENTS
20
PJM’s current structure is not keeping pace with rapid load growth, generation retirements, and the time required to build replacement resources. Allowing major new loads to connect while available capacity is already insufficient creates additional risk for existing customers.

High-priority interconnection, reliability, and cost-allocation matters should follow mandatory schedules. When the normal stakeholder process reaches an impasse, a defined escalation process should allow action without eliminating public input or state oversight.

7. OTHER: Please add any other comments or respond to the FERC technical
conference panel questions specifically here:

PJM should bring new renewable generation and battery storage onto the grid more quickly, require large-load customers to account for the new supply and infrastructure they require, and clearly identify the costs created by those customers.

Transmission expenses caused primarily by data centers should not be spread across residential customers. Direct-connect facilities and related network upgrades should be identified and assigned to the customer creating the need whenever appropriate.

PDF page 21

MARYLAND - STATE COMMENTS
21
Maryland- State Comments

State Representatives’ names, titles, and emails: (please list the lead author as well as those collaborating on this document)

● Senator Brian J. Feldman, Chair, Senate Education, Energy, and the Environment Committee, District 15 (Montgomery County) — brian.feldman@senate.maryland.gov

● Senator Katie Fry Hester, State Senator, District 9 (Howard & Montgomery Counties)
— katiefry.hester@senate.maryland.gov
● Delegate Marc Korman, Chair, House Environment and Transportation Committee, District 16 (Montgomery County) — marc.korman@house.maryland.gov

● Delegate David Fraser-Hidalgo, Chair, Energy Subcommittee (House Environment and Transportation Committee), District 15 (Montgomery County) —

david.fraser.hidalgo@house.maryland.gov
● Delegate Lorig Charkoudian, State Delegate, District 20 (Montgomery County) — lorig.charkoudian@house.maryland.gov

● Delegate Linda Foley, State Delegate, District 15 (Montgomery County)
● Delegate Teresa Woorman, State Delegate, District 16 (Montgomery County)
● Delegate Kym Taylor, State Delegate, District 23 (Prince George’s County)
● Delegate Anne Healey, State Delegate, District 22 (Prince George’s County)

State energy descriptors: (regulated or deregulated; net importer/exporter; etc.):

Maryland operates a retail-restructured, deregulated electric market. The state is a significant net importer of electricity, a characteristic shared with a majority of jurisdictions within the PJM footprint. This structural reliance on imported power leaves retail ratepayers directly exposed to wholesale PJM market dynamics and regional capacity price volatility. Additionally, severe internal transmission constraints exist within major load centers, rendering regional grid coordination and objective cost-allocation mechanisms essential to ensuring state-level reliability and affordability.

Legal & Regulatory Framework

Administratively, Maryland’s utility oversight, ratepayer defense, and long-term energy strategy are driven by a distinct statutory framework:

● The Maryland Public Service Commission (PSC): Serves as the state's independent utility regulatory authority, holding primary jurisdiction over retail utility rate structures, service quality, and local grid certifications.

● The Maryland Office of People’s Counsel (OPC): Functions as the independent statutory advocate representing the interests of Maryland's residential utility

PDF page 22

MARYLAND - STATE COMMENTS
22
consumers, legally intervening in rate cases, grid planning, and wholesale regulatory matters.

● The Maryland Energy Administration (MEA): Acts as the state's dedicated executive energy office focused on deploying clean energy incentives, optimizing grant programs, and managing state energy investments.

● The Strategic Energy Planning Office (SEPO): Operates as a standalone office established via the Energy Resource Adequacy and Planning Act to introduce advanced data modeling, market auditing capabilities, and independent resource adequacy risk tools to the state's active defense framework.

Executive Action & Gubernatorial Leadership

Over the past year, the executive branch has pivoted toward interagency and regional solidarity to address grid constraints and wholesale market accountability:

● The Governor's Energy Subcabinet: Established via Executive Order 01.01.2025.27, this body coordinates a whole-of-government approach across executive agencies to align state assets, tackle generation gaps, and keep consumer affordability at the center of regional grid discussions.

● The PJM Governors' Collaborative: Operating on a regional scale, the Governor joined a historic bipartisan coalition of all 13 PJM footprint executives. On January 15, 2026, the coalition partnered with federal energy leaders to sign the landmark Statement of Principles Regarding PJM to freeze unjust capacity price hikes. Following up on this framework, the collaborative issued a formal joint position letter on April 9, 2026, demanding strict cost-causation rules. The coalition firmly asserts that large-load entities driving explosive demand growth, such as commercial data centers, must directly pay for their own network footprints and backstop capacity requirements rather than shifting massive infrastructure upgrades onto residential consumers

1. GOVERNANCE: Do we need to reform the governance of PJM? If so, why? For example, please consider how PJM’s current governance affects your state, other RTOs' governance, and your recommendations for reform.

Yes. The fundamental root of chronic delay and political pressure for affordability within PJM is its flawed governance system, which leaves the organization structurally blind to ratepayer impacts unable to adapt quickly to rapid shifts in our regional energy mix. This slowness traps the region in a continuous cycle of volatile capacity price shocks where captive retail ratepayers bear the ultimate financial risk.

This administrative gridlock is perfectly illustrated by PJM's handling of emerging grid pressures. PJM initially launched a Critical Issue Fast-Track Process (CIFP) in the fall of 2025, but this first attempt was completely punted. A replacement CIFP process to address the urgent Reliability Backstop Procurement (RBP) mechanism and the Connect & Manage (C&M) framework dragged on from January through June of 2026. Because this governance framework moves at a snail's pace, the Maryland General Assembly was

PDF page 23

MARYLAND - STATE COMMENTS
23
forced to pass consumer protection legislation during its session purely in anticipation of PJM’s delayed regulatory outcomes, rather than coordinating with them in real time.

A core part of the problem lies in the underlying motivating factors for the PJM Board. The Board currently operates under a primary fiduciary commitment to its corporate market members and the organization itself, lacking a parallel, binding requirement to serve the public interest or shield retail ratepayers from market failures. When analyzing governance models across the country, PJM stands out structurally; while PJM functions as a non-profit entity, it describes and operates itself fundamentally as a private membership organization. Conversely, other RTOs and ISOs are organized with explicit public interest or ratepayer protections built directly into their foundational governing documents. For instance, the Midcontinent Independent System Operator (MISO) incorporates clear, enforceable public interest requirements within its operational design, while the Southwest Power Pool (SPP) balances its framework by utilizing a separate, formally defined state committee to give states a binding voice in the process.

Fundamentally, PJM doesn’t have the appropriate constitutional form for governance, as this Delaware LLC model no longer meets the needs of our region. Long term, a structural overhaul could include a shift from a private LLC to an interstate compact public benefit entity. This compact could provide a governance framework for the institution itself, including its mission, fiduciary duties, transparency, etc. In essence, this adds a governance constitution on top of FERC's existing regulatory framework and could be achieved through the passage of legislation across PJM states. For example, in the WMATA operates in this manner as does the Port Authority of NY NJ.  Although there are no national models for this, internationally, Australia has found success with this model with the Energy and Climate Change Ministerial Council, created by legislation in 2022 which has oversight over the Australian Energy Market Commission (the rule maker and market development adviser) and the Australian Energy Market Operator (the system operator.) Near-term reforms can make PJM’s governance more visible; however, only re- chartering can make the organization accountable.

1. Asks for FERC to Implement:
1.1.
Codify an Explicit Public Interest Mandate: FERC should direct PJM to amend its foundational operating agreements to legally mandate that the organization balance system reliability and market efficiency with public interest objectives, explicitly including ratepayer cost containment and state public policy alignment.

1.2.
Reconfigure the Corporate Structure: FERC should order the transition of PJM away from its restrictive "membership organization" framework toward an independent grid operator model with an explicit public utility mission, ensuring management performance and corporate bonuses are tied to consumer cost-mitigation benchmarks rather than member satisfaction.

2. STATE ROLE: What role and influence should states have in PJM?  Please consider whether states should have a role: on the PJM Board or in the nominations process, engaged in joint technical sessions with the PJM Board, in a formal consultation process,

PDF page 24

MARYLAND - STATE COMMENTS
24
enhanced observer status, or information rights before major filings, participating in independent reviews of load forecasting accuracy and major planning assumptions, receiving early-warning reporting when material changes occur in large-load forecasts, reliability assessments, or planning assumptions, and/or formally embedding state policy objectives into PJM's planning and market processes.

States need a formal, institutional role in PJM planning and governance that ensures a fair and balanced representation of state interests alongside industry participants. As the directly elected representatives of retail customers who ultimately pay the bills, states should have an equal voice to industry in the decision-making process. State regulators need clear information rights and a formal say in any major filings that go to FERC, not just an early warning or informational notice. We need to be part of independent reviews of load forecasting, especially with the rapid growth of large-load customers like data centers that spike our regional costs. We should have joint technical sessions with the PJM Board so state policy objectives and realistic planning assumptions are built directly into the process from the start, rather than treated as an afterthought.

To coordinate state-level input, the Organization of PJM States, Inc. (OPSI) was formed in 2005 as an inter-governmental non-profit corporation comprising the utility regulatory agencies across the 14 jurisdictions within the PJM footprint (13 states and the District of Columbia).  However, the current Memorandum of Understanding between PJM and OPSI relies strictly on information sharing and non-binding consultation, which therefore systematically fails to grant states a functional check on operational outcomes that directly impact retail ratepayers. Furthermore, given OPSI is composed of the regulatory agencies only, it omits the formal policy leadership from Governors and Legislators in the PJM process.

2. Asks for FERC to Implement:
2.1.
Transition to an Alternative Regional Structural Model FERC should direct PJM to adopt the model of state participation after the New England State Committee on Electricity (NESCOE) model, creating an independent regional state committee funded via an RTO tariff and governed by a board of managers appointed directly by state governors.  Under this model, state technical experts and energy managers have structured access to independent information to evaluate RTO data directly, while holding regular, mandatory joint technical sessions with the Board. In addition, EXPAND the NESCOE model's state legal authority by providing these state committees with formal Federal Power Act Section 205 filing rights.  The state authority should also include formal input mechanisms over regional planning assumptions, PJM’s load forecasting models, congestion analyses, and long-term transmission planning assumptions, transmission cost allocation, and resource adequacy metrics, requiring a formal administrative reconciliation process before major filings are submitted to FERC.

PDF page 25

MARYLAND - STATE COMMENTS
25
2.2.
Alternatively, FERC could Optimize and Expand the Current OPSI
Framework. FERC could direct PJM to expand OPSI’s institutional charter to transition the body from a purely consultative liaison group into an entity with formal, defined authority over specific regional planning processes. This includes expanding state legal authority by providing formal Federal Power Act Section 205 filing rights or structured input options during the filing process for specific tariff revisions impacting resource adequacy and regional planning.

3. BOARD: Is the current board authority and accountability effective? Please consider the board’s ability to act unilaterally, reforming Board composition to include state- selected or state-nominated seats; establishing formal board performance metrics and periodic external accountability reviews; exploring Independent Representative Stakeholder (RSC) Board model used at other RTOs.

No, the current board structure lacks sufficient institutional accountability to the states and the consumers who ultimately fund regional transmission system expansions and capacity procurements. While the Board possesses the authority to act unilaterally, its interventions are frequently reactive rather than proactive, responding to structural crises after they manifest in the marketplace.

For example, the Board permitted the interconnection queue backlog to balloon to an over eight-year average and generation supply to tighten; this prolonged administrative delay in transitioning to a modernized framework directly caused the catastrophic consequence of regional capacity auction costs exploding from $2.2 billion to nearly $14.7 billion, forcing a subsequent scramble to implement a cluster study process. Similarly, the Board failed to proactively modernize its tariff architecture to manage explosive large-load growth from commercial data centers, leaving states vulnerable to massive cost-shifting.

As a critical component of this integration, the governance framework must provide a formal, heightened platform for state-level technical experts and engineers who possess a granular understanding of localized system constraints and regional operational nuances.

As detailed in the preceding section, comprehensively optimizing and empowering OPSI or transitioning to an alternative regional state mechanism (such as an RSC or NESCOE model) is an absolute necessity. These structural state-level reforms are foundational to resolving PJM’s gridlock. Beyond those external governance adjustments, specific reforms to the PJM Board itself are required to ensure deep institutional accountability.

3. Asks for FERC to Implement
3.1.
Codify a State-Driven Regulatory Counterweight: FERC should formalize a streamlined system of structural checks and balances. Under this framework, an upgraded state committee holds defined review authority or formal input mechanisms over regional planning assumptions, transmission cost allocation,

PDF page 26

MARYLAND - STATE COMMENTS
26
and resource adequacy metrics, requiring a formal administrative reconciliation process before major filings are submitted to FERC.

3.2.
Mandate Structured State Participation in Board Nominations: FERC
should direct PJM to model its recruitment after the MISO framework, where state regulatory representatives from the Organization of MISO States (OMS) participate directly as formal members of the Board of Directors Nominating Committee, ensuring that public interest perspectives are structurally embedded in the recruitment and vetting of future independent board directors. 3.3.

Grant Independent Board Section 205 Filing Rights: FERC should grant the PJM Board independent Federal Power Act Section 205 filing rights, separate and distinct from the Members Committee membership process. Granting the Board independent filing authority—to be exercised in parallel with enhanced state filing rights—will structurally insulate the Board from corporate membership pressure, eliminate the industry's de facto veto power, and allow independent leadership to respond swiftly to regional reliability crises 3.4.

Develop a Formal Decision-Making Responsibility Matrix: FERC should
direct PJM to develop a comprehensive Responsible, Accountable, Consulted, and Informed (RACI) matrix mapping out all corporate and operational grid decisions. This matrix must explicitly require formal consultation with state entities before major operational policies are advanced.

3.5.
Enforce Binding Public Interest Performance Metrics: FERC should
condition PJM's administrative outcomes and board evaluations on transparent, quantifiable metrics tailored to core deliverables like load forecasting accuracy and queue execution speed. These formal metrics must be linked directly to the new foundational governance charters and interstate compact documents to guarantee that public interest metrics are permanently embedded in PJM's planning framework.

4. STAKEHOLDER PROCESS: Is the existing stakeholder process and filing right structure working?  If not, should it be changed?  Please consider if the process accurately reflects the interests of those ultimately bearing reliability and affordability risk, particularly ratepayers and emerging large-load customers? Please consider: modifying the voting structure, improving transparency and information access, reviewing and refreshing filing rights, and/or strengthening FERC's use of its Section 206 backstop authority.

No, the existing stakeholder process is structurally defective and fails to accurately reflect the interests of the states, consumer advocates, and the captive retail ratepayers who ultimately bear the foundational financial and reliability risks. The current framework is heavily weighted toward corporate market participants with narrow financial interests rather than public interest goals. Specifically, PJM’s sector-weighted voting thresholds require high consensus supermajorities to pass rule changes, making it far too easy for vocal industry minorities or narrow segments to block critical updates, cause market

PDF page 27

MARYLAND - STATE COMMENTS
27
design deadlocks, and delay essential regulatory modernization—such as the grid rules needed for large-load data center interconnections.

The operational realities of participating in PJM's committee structure also introduce severe barriers to entry. Navigating the stakeholder process is a highly resource-intensive and expensive endeavor, which prevents meaningful and sustained participation from consumer advocates, public interest groups, and emerging non-traditional market entrants. This cost barrier contributes directly to a lack of representative democratic engagement: approximately two-thirds of the registered members who technically hold a vote within PJM's stakeholder committees have never actually cast a ballot. Because a large portion of the electorate remains passive, highly organized corporate coalitions can disproportionately leverage existing sector-weighted thresholds to preserve the status quo. This structural inertia frequently stalls market and grid affordability reforms indefinitely, leaving states to rely on burdensome Federal Power Act Section 206 complaints where the legal burden of proof is high and administrative relief is painfully slow.

To maintain proper oversight, state policy influence should remain at the Governance Level (per Sections 1 and 2) rather than establishing a separate voting bloc within the stakeholder membership.

4. Asks for FERC to Implement:
4.1.
Lower the Cost of Participation: FERC should mandate the establishment of an RTO-administered technical support fund or formal technical liaison positions to offset the high costs of legal and engineering participation for consumer advocates and state representatives, shifting the active voting pool to better reflect public interests.

4.2.
Establish an Empowered State Core: FERC should require that a newly
restructured, state-led committee (such as an empowered OPSI or a NESCOE- style board) is legally integrated into PJM's governance as a central point of action for reviewing, advising, and co-filing on high-priority grid issues, shielding public policy from private market deadlocks.

4.3.
Proactively Deploy FERC's Section 206 Authority: FERC should actively
use its Federal Power Act Section 206 backstop authority to issue region- specific "Show Cause" orders—as it successfully executed at its June 18, 2026 Open Meeting—finding RTO tariffs potentially unjust and unreasonable

regarding large-load grid integration, thereby legally forcing RTOs and transmission owners to increase cost transparency and demonstrate clear cost recovery metrics.

5. TRANSPARENCY: Does the PJM operational structure allow sufficient engagement with independent information and transparency necessary to affect affordability? Please consider whether regulators and consumer advocates have sufficient access to reproduce and independently evaluate the forecasts, congestion analyses, and planning assumptions that ultimately influence ratepayer costs. Should states be able to request

PDF page 28

MARYLAND - STATE COMMENTS
28
studies on emerging affordability and reliability issues? Can we expand independent analytical access to PJM data while preserving market-sensitive confidentiality?

No, state regulators and consumer advocates do not have sufficient independent access to the raw data, congestion analyses, and underlying forecasting models that ultimately drive up retail ratepayer costs. Relying entirely on PJM's internal conclusions without an independent mechanism for verification is structurally insufficient. This level of transparency is critical to ensure that market participants are paying their fair share of grid expansion and network upgrade costs, rather than shifting those financial obligations onto captive retail ratepayers.

State-level technical staff and engineers are uniquely positioned to understand localized system nuances that heavily impact PJM’s broader regional planning assumptions. Consequently, these technical experts must have a structured seat and defined authority to evaluate data, address local system issues, and push back on flawed regional modeling assumptions. Utilizing open, high-quality data is the most reliable method to address emerging grid and market challenges. States require a clear, defined right to request independent studies on emerging affordability issues, alongside analytical access to replicate and evaluate PJM’s planning assumptions directly, while maintaining strict protections for market-sensitive confidentiality.

5. Asks for FERC to Implement:
5.1.
Eliminate Closed-Door Barriers and Mandate Public Streaming and
Archiving: FERC should direct PJM to establish that all meetings across every level of the organization must be streamed live, allow public media

participation, officially recorded, and archived online for permanent public access. This reform must directly eliminate PJM's restrictive meeting architecture, which currently requires specific group memberships to attend or access sessions, removing these gatekeeping rules so that any public interest advocate, consumer representative, or state entity can observe and audit the decision-making process at any time.

5.2.
Mandate Universal Record Disclosure and Reporting Timelines: FERC
should require the immediate public disclosure of voting records, meeting minutes, and underlying technical workpapers across all subcommittees and temporary task forces. Standardizing immediate reporting timelines will ensure that private market coalitions cannot utilize lower-level technical spaces— where data access is entirely lacking compared to high-level committees—to quietly shape regional planning and load-forecasting assumptions before external oversight can intervene.

5.3.
Establish Independent Data Replication Protocols: FERC should mandate the creation of secure, tariff-protected data clearinghouses that allow state regulatory commissions and designated consumer advocates to directly replicate and evaluate PJM’s raw congestion data and load forecasts while fully preserving commercial confidentiality.

5.4.
Codify State-Initiated Study Rights: FERC should grant states the explicit statutory and tariff authority to compel PJM to perform independent,

PDF page 29

MARYLAND - STATE COMMENTS
29
specialized studies on emerging reliability risks, data center load spikes, and retail ratepayer affordability impacts.

5.5.
Implement Mandatory Cost Allocation Verifications: FERC should direct
PJM to align its data access rules with the Commission's June 18, 2026 Section 206 "Show Cause" orders, explicitly requiring the elimination of unjustified wholesale cost-shifting and enforcing total transparency into large-load network upgrade costs.

6. STRUCTURE: Is PJM currently structured in a way to operate effectively in today’s rapidly changing context?  Please consider whether PJM has sufficient visibility into emerging risks, sufficient authority to act on them, and sufficient accountability for the outcomes. Is it sufficient regardless of the governance reform?  What recommendations do you have for the future structure of PJM?

No, PJM’s operational structure is not aligned to meet the dual challenges of a rapid energy transition and unprecedented large-load growth from data centers and electrification. While PJM maintains technical visibility over broad system metrics, its operational model lacks the agility to respond proactively to rapid market shifts. PJM has historically claimed that it cannot control rapid large loads from coming onto the system, but throwing its hands up completely directly contradicts the RTO's core reliability purpose. This operational abdication has resulted in reactive interventions and an unprecedented interconnection queue backlog that compromises regional resource adequacy.

This structural dysfunction stems directly from PJM's institutional orientation as a private membership organization. Because leadership remains primarily accountable to the generators, transmission owners, and market participants who vote within the committee system, the RTO—by its nature—routinely prioritizes narrow corporate financial interests over public interest mandates. Captive retail ratepayers—who bear 100% of the long-term reliability and affordability risks—are completely excluded from the core accountability loop. This creates a severe structural defect where market costs are systematically socialized while profit metrics are privatized.

The consequences of this structure are evident in recent regional transmission expansion plans, where legacy cost-allocation methodologies pass billions of dollars in regional network upgrade costs down to neighboring states' ratepayers to serve localized, out-of- state data center load growth. Forcing individual states to continually intervene at FERC or pass defensive, uncoordinated state legislation to insulate their consumers from wholesale market failures creates an inefficient, fragmented regional network. True structural reform requires establishing explicit public interest mandates and updating regional tariff architecture to reflect strict cost-causation principles in the governing documents.

Many of the structural components related to governance, state role, board authority, and stakeholder defects are discussed above.  These are also relevant here and include the following.

PDF page 30

MARYLAND - STATE COMMENTS
30

1. RTO Governance & Corporate Restructuring
1.1.
Public Interest Mandate: Require PJM to legally amend its foundational operating agreements to balance grid reliability and market efficiency with public interest objectives, specifically ratepayer cost containment and state policy alignment.

1.2.
Independent Operator Model: Shift PJM away from its restrictive "membership organization" framework toward an independent grid operator model with a public utility mission. Tie management performance bonuses directly to consumer cost-mitigation benchmarks rather than member satisfaction.

2. Enhancing the State Role
2.1.
The NESCOE Model: Create an independent regional state committee (similar to New England's NESCOE) funded via an RTO tariff and governed by state- appointed managers. Expand this model by granting states formal FPA Section 205 filing rights and requiring a formal reconciliation process on load forecasting, transmission planning, and resource adequacy before filings go to FERC.

2.2.
The OPSI Model: Alternatively, optimize the current Organization of PJM States (OPSI) by transitioning it from a consultative liaison group into an entity with formal, defined authority and Section 205 filing or structured input rights over planning and resource adequacy tariffs.

3. Reforming Board Authority & Accountability
3.1.
State-Driven Balance: Formalize structured checks and balances by giving a state committee defined review and reconciliation authority over regional planning assumptions and cost allocations before major FERC submissions. 3.2.

Board Nomination Input: Model recruitment after the MISO framework, allowing state regulatory representatives to sit directly on the Board of Directors Nominating Committee to embed public interest perspectives into director vetting.

3.3.
Independent Board Filing Rights: Grant the PJM Board independent FPA Section 205 filing rights separate from the stakeholder Members Committee. This eliminates industry veto power and lets the Board act in parallel with enhanced state filing rights.

3.4.
RACI Decision Matrix: Implement a formal Responsibility Assignment (RACI) matrix mapping all corporate/operational decisions to explicitly require formal state consultation before major policies advance.

3.5.
Binding Performance Metrics: Link board evaluations and outcomes to quantifiable metrics (e.g., load forecasting accuracy, interconnection queue speed) embedded in PJM’s foundational charters.

4. Overhauling the Stakeholder Process
4.1.
Lowering Participation Costs: Establish an RTO-administered technical support fund or liaison positions to offset legal and engineering costs for consumer advocates and state representatives, balancing the active voting pool.

PDF page 31

MARYLAND - STATE COMMENTS
31
4.2.
Empowered State Core: Legally integrate a state-led committee into PJM's architecture as a central body for reviewing, advising, and co-filing on high- priority grid issues to bypass private market deadlocks.

4.3.
Proactive FERC Backstop (Section 206): Urge FERC to actively deploy its FPA Section 206 "Show Cause" authority—mirroring its June 18, 2026 Open Meeting actions—to force cost transparency and clear cost-recovery metrics regarding large-load grid integration.

In addition, because PJM's foundational framework is inextricably linked to market equity issues including the cost-allocation frameworks required to manage rapid large-load growth, the following are required.

6. Asks for FERC to Implement:
6.1.
Enforce Direct Cost Recovery Agreements and Establish Federal Tariff Preemption: FERC should mandate a federal transmission-level backstop that explicitly prohibits PJM from granting grid access or delivering wholesale transmission capacity to a connecting utility until a binding 100% cost-recovery underwriting contract is executed with the incoming large-load entity. This federal requirement explicitly addresses and preempts the traditional retail utility position that local "duty to serve" mandates afford them no discretion or guardrails to delay or deny massive commercial load connections, providing necessary regulatory air cover to protect captive residential ratepayers from stranded asset risks and localized distribution upgrade cost-shifting. 6.2.

Eliminate Regional Cost Socialization: FERC should direct PJM to update its regional transmission cost-allocation methodologies to ensure that baseline reliability and network expansion costs are directly assigned to the specific utility zones or jurisdictions where the load growth is generated, eliminating the upstream leakage of out-of-state infrastructure subsidies onto neighboring retail customers.

6.3.
Implement Fast-Track Interconnection and Technology Tracks: FERC
should require PJM to restructure its tariff provisions to mandate the immediate evaluation of alternative transmission technologies—such as grid-enhancing technologies—to maximize existing system capacity rapidly while accelerating clean, lower-cost resource deployment without incurring redundant infrastructure builds.

7. OTHER: Please add any other comments or respond to the FERC technical conference panel questions specifically here:

The purpose of this final section is to capture critical regulatory issues and operational gaps that fall outside the standard stakeholder definitions but are essential to answering the core panel questions issued under FERC Docket No. AD26-7-000 (PJM Governance and Stakeholder Reforms Technical Conference). Specifically, this response addresses panel inquiries regarding how the current division of Federal Power Act (FPA) Section 205 filing rights impacts PJM's ability to act quickly, and whether the RTO's governing

PDF page 32

MARYLAND - STATE COMMENTS
32
documents contain impediments that delay essential tariff updates. By examining these underlying structural issues, this section establishes a comprehensive, forward-looking policy position from the Maryland perspective.

A primary regulatory gap embedded within PJM's current Operating Agreement is the lack of a formal mechanism to reconcile the division of FPA Section 205 filing rights with state public policy mandates. The current framework allows the PJM Board or private Transmission Owners (under the Consolidated Transmission Owners Agreement) to make unilateral wholesale filings at FERC that can quietly undermine or financially penalize state-level consumer protection and clean energy laws. This division of rights means that the very corporate entities profiting off massive grid expansions hold the legal keys to the regional tariff kingdom, bypassing state technical inputs entirely. This procedural gap forces individual jurisdictions into a reactive, litigious posture to protect their retail consumers.

Furthermore, as PJM prepares its compliance filings for the June 18, 2026 Section 206 "Show Cause" orders regarding large-load grid integration, the RTO’s governing documents completely lack fast-track, time-bound review procedures to handle grid- stalling commercial interconnections without triggering massive wholesale cost-shifting onto residential rate bases.

The Maryland Perspective

Maryland faces distinct operational vulnerabilities because the state is a net energy importer, similar to a majority of jurisdictions within the PJM footprint, relying on neighboring jurisdictions for approximately 40% of its electricity supply. Consequently, Maryland ratepayers are disproportionately exposed to upstream PJM market failures, unmitigated transmission congestion, and the socialization of out-of-state network upgrade costs.

To insulate its consumers, the state has actively deployed aggressive legislative and regulatory counter-strategies. The Maryland General Assembly enacted the Utility RELIEF Act of 2026 (Chapter 353 of the 2026 Laws of Maryland) to actively suppress unfair utility cost recovery, enhance consumer transparency, and lower the retail threshold definition of a "large-load customer" to 25 megawatts (MW) with a 60% load factor to force incoming data centers into specialized utility tariff tracks.

Furthermore, through major legislative packages enacted across the 2025 and 2026 sessions, Maryland has systematically expanded incentives for in-state generation and resource adequacy to address looming capacity deficits. This includes championing comprehensive target programs aimed at adding 4,000 MW of utility-scale and distributed solar capacity, updating the Renewable Energy Certainty Act (Chapter 623 of the 2025 Laws of Maryland) to optimize the utility siting and deployment of resources, and modernizing the state's portfolio standard through the Next Generation Energy Act (Chapters 625 and 626 of the 2025 Laws of Maryland) to make zero-emission nuclear energy—including small modular reactors—eligible for compliance credits.

PDF page 33

MARYLAND - STATE COMMENTS
33

Additionally, the state has established expedited regulatory pathways for dispatchable resources—including a fast-track review component for high-efficiency natural gas infrastructure to bridge immediate capacity shortfalls—as well as both transmission-level and distribution-level energy storage systems, firmly positioning multi-tiered storage as a core pillar of Maryland's resource adequacy strategy to proactively insulate Marylanders from backlogged RTO queue processes.

Looking forward, the newly enacted Strategic Energy Planning Office (SEPO) is legally mandated to begin issuing its comprehensive Wholesale Energy Markets and Bulk Power System Risk Report by September 2028. This report will serve as the mechanism to model PJM’s market-clearing flaws, audit resource adequacy, and design cost-effective reliability solutions. PJM's regional framework must be structurally updated to accommodate, rather than penalize, these active and upcoming state-level consumer protections.

7. Asks for FERC to Implement:
7.1.
Implement Strict Large-Load Anti-Aggregation Rules: FERC should direct PJM to revise its planning manuals to implement strict anti-aggregation rules that prevent multi-facility data center developers from artificially splitting massive campus footprints into sub-50 MW connection requests to bypass rigorous studies, while establishing formal pathways to harmonize regional data with granular state-level retail thresholds like Maryland’s 25 MW definition. 7.2.

Eliminate Phantom Load Risks with Performance Milestones: FERC
should require PJM to enforce strict, use-it-or-lose-it capacity reservation milestones to penalize speculative developers and stop them from hoarding valuable grid interconnection capacity without active, near-term commercial deployment.

7.3.
Mandate Cross-RTO Duplicate Load Tracking: FERC should order a
mandatory cross-RTO information-sharing framework that requires PJM to actively track and identify instances where a developer has proposed the exact same load footprint across different areas both inside and outside the PJM footprint to prevent regional gaming and capacity double-counting.

7.4.
Exclude Speculative Requests from Regional Load Forecasting: FERC
should direct PJM to integrate only actual, contractually verified proposals into its official regional load forecasting, completely excluding speculative requests to ensure grid expansion planning is driven by real-world deployment rather than artificial queue inflation.

7.5.
Implement Fast-Path Review Procedures for Critical Issues: FERC should require PJM to formally amend the Operating Agreement to establish clear, time-bound limitations within the PJM Senior Task Force architecture, ensuring any market rule or interconnection update directly tied to large-load data center integration automatically bypasses lower-level committee deadlocks and advances to a final board determination within 60 days.

PDF page 34

NEW JERSEY - STATE COMMENTS
34
New Jersey - State Comments

State Representatives’ names, titles, and emails: (please list the lead author as well as those collaborating on this document)

Lead Authors: Senator Bob Smith and Assemblyman David Bailey

Additional Signatures on this document:

Senate President Nicholas Scutari
Senate Majority Leader Teresa Ruiz
Senator John McKeon
Senator John Burzichelli
Senator Gordon Johnson
Senator Angela McKnight
Senator Vin Gopal
Senator Linda Greenstein
Senator Patrick Diegnan
Assemblyman Clinton Calabrese
Assemblyman Robert Karabinchak

State energy descriptors: (regulated or deregulated; net importer/exporter; etc.):

New Jersey is a deregulated state and a net importer of electricity.

1. GOVERNANCE: Do we need to reform the governance of PJM? If so, why? For example, please consider how PJM’s current governance affects your state, other RTOs' governance, and your recommendations for reform.

Yes. PJM is unable to respond to current challenges, including capacity procurement, interconnection delays, and a host of other major issues. PJM’s inability to overcome obstacles has resulted in an enormous financial burden on businesses and residents in New Jersey. Below is the text of a Joint Resolution passed by both houses of the New Jersey Legislature and signed by former Governor Murphy in 2025 that details the Legislature’s position on PJM’s inability to resolve these issues.

SJR154 of the 2024-2025 Legislative session:

JOINT RESOLUTION NO. 11

A Joint Resolution respectfully directing the Board of Public Utilities to investigate PJM Interconnection, L.L.C.’s Reliability Pricing Model; and directing the State of New Jersey to collaborate with neighboring states to promote affordable energy practices and to urge PJM

PDF page 35

NEW JERSEY - STATE COMMENTS
35
Interconnection, L.L.C. to implement market reforms and expeditiously review new electricity generation applications.

Whereas, PJM Interconnection, L.L.C. (PJM) is the regional transmission organization responsible for coordinating the movement of electricity and ensuring reliable and cost- effective energy distribution in New Jersey, several other states, and the District of Columbia; and

Whereas, PJM’s Reliability Pricing Model, commonly referred to as PJM’s capacity market, is intended to ensure that adequate resources exist on the grid to maintain reliability at the lowest possible cost through a competitive auction; and

Whereas, PJM, on behalf of New Jersey’s electricity customers, administers a capacity market auction to procure capacity for future years; and

Whereas, In New Jersey, under the “Electric Discount and Energy Competition Act”, electric public utilities are required to procure electricity for basic generation service at prices consistent with market conditions and then provide basic generation service to customers who have not switched to a third-party supplier; and

Whereas, The rising cost of capacity in PJM’s capacity market auctions, which contributes to the overall increase in electricity bills for ratepayers, raises concerns about the alignment of capacity prices with the principles of affordability and transparency outlined in the “Electric Discount and Energy Competition Act”; and

Whereas, Energy demand is expected to grow by 2.3 percent annually over the next 10 years across the region served by PJM and by 1.55 percent annually over the next 10 years across New Jersey; and

Whereas, In addition, delays in PJM’s interconnection queue have prevented new electric generation resources from becoming operational in a timely manner; and

Whereas, As a result, these new resources that are required to maintain reliability at lower costs will be unable to compete in PJM’s capacity market auctions in the near future; and

Whereas, Energy price hikes disproportionately affect low-income families and vulnerable populations, aggravating existing inequalities and creating additional financial hardships; and

Whereas, The BPU, alongside utility agencies in other states, has sent multiple letters to the PJM Board of Managers since PJM’s June 2024 capacity market auction and has sent multiple filings to the Federal Energy Regulatory Commission (FERC) on how to improve PJM’s capacity market rules before the upcoming July 2025 auction; and

Whereas, The State of New Jersey, through the BPU, has been working vigorously to incentivize the development of new generation sources to help meet the growing energy demand and, thereby, help prevent increases in energy and capacity prices; and

PDF page 36

NEW JERSEY - STATE COMMENTS
36
Whereas, The BPU has been actively working to protect ratepayers from price increases and coordinating with other PJM states to push for capacity market reforms; and

Whereas, The BPU’s initiatives, led by Governor Murphy, are accompanied by the actions of consumer advocates, including the New Jersey Division of the Rate Counsel and Pennsylvania Governor Josh Shapiro, who have furthered the region’s efforts to reduce prices through additional complaints at FERC, which the BPU has pledged to support; now, therefore,

     Be It Resolved by the Senate and General Assembly of the State of New Jersey:

     1.    The Board of Public Utilities shall investigate whether PJM’s Reliability Pricing Model is serving its intended design to obtain resource adequacy at the lowest possible cost.  The board shall report the results of this investigation to the Governor and the Legislature, pursuant to section 2 of P.L.1991, c.164 (C.52:14-19.1), no later than 12 months following the effective date of this resolution.

     2.    The State of New Jersey shall work collaboratively with neighboring states within PJM’s jurisdiction to promote equitable practices, prioritize carbon-free energy sources, reduce the impacts of climate change on energy demand and costs, and to urge PJM to implement market reforms that protect ratepayers from rising capacity prices and to expeditiously review new electricity generation applications.

     3.    Copies of this resolution, as filed with the Secretary of State, shall be transmitted by the Clerk of the General Assembly or the Secretary of the Senate to the Commissioners of the Board of Public Utilities and to each member of the PJM Board of Managers, as the members are identified on PJM’s Internet website.

     4.    This joint resolution shall take effect immediately.

     Approved August 15, 2025.

2. STATE ROLE: What role and influence should states have in PJM?  Please consider whether states should have a role: on the PJM Board or in the nominations process, engaged in joint technical sessions with the PJM Board, in a formal consultation process, enhanced observer status, or information rights before major filings, participating in independent reviews of load forecasting accuracy and major planning assumptions, receiving early-warning reporting when material changes occur in large-load forecasts, reliability assessments, or planning assumptions, and/or formally embedding state policy objectives into PJM's planning and market processes.

States should have a formal and defined role in PJM’s structure and processes. States should have information rights before all major filings. Additionally, states should have filing rights over core functions that directly impact states, particularly with respect to resource adequacy.

PDF page 37

NEW JERSEY - STATE COMMENTS
37
Finally, states should have more direct influence over the members and make up of PJM’s Board of Managers, such as a reserved seat on the PJM Board’s Nominating Committee.

3. BOARD: Is the current board authority and accountability effective? Please consider the board’s ability to act unilaterally, reforming Board composition to include state-selected or state-nominated seats; establishing formal board performance metrics and periodic external accountability reviews; exploring Independent Representative Stakeholder (RSC) Board model used at other RTOs.

The current PJM Board’s authority and accountability is not effective, for the reasons stated in the answer to Question 1 above. Additionally, there are legitimate concerns over the PJM Board’s independence. States should have a role in determining the members of the PJM Board, including potentially reserving a seat on the PJM Board’s Nominating Committee for a representative from the states. PJM and FERC should additionally consider reforms that would increase the independence of the PJM Board members, including critical examination of PJM Board member terms and ex parte rules.

4. STAKEHOLDER PROCESS: Is the existing stakeholder process and filing right structure working?  If not, should it be changed?  Please consider if the process accurately reflects the interests of those ultimately bearing reliability and affordability risk, particularly ratepayers and emerging large-load customers? Please consider: modifying the voting structure, improving transparency and information access, reviewing and refreshing filing rights, and/or strengthening FERC's use of its Section 206 backstop authority.

The existing stakeholder process in PJM is structured to block action rather than to find and implement solutions to issues. This has made PJM slow to respond to emergency issues and ineffective in resolving the challenges facing the PJM region. Additionally, residential ratepayers are not adequately represented through PJM’s current stakeholder process. PJM’s stakeholder process should be restructured to ensure that PJM is able to act quickly to protect reliability and affordability across the region.

5. TRANSPARENCY: Does the PJM operational structure allow sufficient
engagement with independent information and transparency necessary to affect affordability?   Please consider whether regulators and consumer advocates have sufficient access to reproduce and independently evaluate the forecasts, congestion analyses, and planning assumptions that ultimately influence ratepayer costs. Should states be able to request studies on emerging affordability and reliability issues? Can we expand independent analytical access to PJM data while preserving market-sensitive confidentiality?

PDF page 38

NEW JERSEY - STATE COMMENTS
38
PJM should be working directly with states to ensure that states have the information they need to advance policies and ratepayer relief within their jurisdictions to the maximum extent possible.

PJM should also consider implementing reforms to ensure transparency in their stakeholder meetings. These reforms should include, at a minimum, that votes are made public and that recordings of stakeholder meetings are made publicly available.

6. STRUCTURE: Is PJM currently structured in a way to operate effectively in today’s rapidly changing context?  Please consider whether PJM has sufficient visibility into emerging risks, sufficient authority to act on them, and sufficient accountability for the outcomes. Is it sufficient regardless of the governance reform? What recommendations do you have for the future structure of PJM?

PJM is not currently structured in a way that allows it to respond quickly to emergent challenges, as noted in the answers to Questions 1 and 4 above.

PDF page 39

OHIO - STATE COMMENTS
39
Ohio - State Comments

State Representatives’ names, titles, and emails: (please list the lead author as well as those collaborating on this document)

Senator Kent Smith (smith@ohiosenate.gov); Kaitlyn May, Senior Policy Advisor (kaitlyn.may@ohiosenate.gov)

State energy descriptors: (regulated or deregulated; net importer/exporter; etc.):

Ohio has been a deregulated state since 1999. Due to heavy industry, the state is a net importer of energy. This is unlikely to change given the rapid expansion of data centers in Ohio, there are already over 200 data centers in the state with many more planned. The Ohio Power Siting Board has exclusive jurisdiction for major utility facilities (generation over 50 MW, transmission lines over 100 kV). The exception to this exclusive jurisdiction is wind and solar facilities, Ohio townships and counties can ban wind and solar generation. Of Ohio’s 88 counties, there is a wind or solar ban in at least 27—standing in direct opposition to the Ohio legislature’s “all of the above” generation approach. With existing load and the expansion of data centers, restricting one of the cheapest and fastest generation sources is counterproductive and inconsistent with a competitive energy marketplace. Finally, Ohio requires transmission operators to be a member of a FERC approved RTO.

1. GOVERNANCE: Do we need to reform the governance of PJM? If so, why? For
example, please consider how PJM’s current governance affects your state, other RTOs' governance, and your recommendations for reform.

If PJM’s current governance structure can allow more clean generation to enter the market, then perhaps reforms may not be necessary. However, the reality is, even though wind, solar, and storage projects are the quickest generation to get to market, and it is easiest to finance, the PJM generation portfolio is dominated by outdated, high-cost legacy generation. PJM’s failures are harming the reliability and affordability of the grid that delivers power to Ohio residents and businesses. Therefore, something must change.

2. STATE ROLE: What role and influence should states have in PJM?  Please consider whether states should have a role: on the PJM Board or in the nominations process, engaged in joint technical sessions with the PJM Board, in a formal consultation process, enhanced observer status, or information rights before major filings, participating in independent reviews of load forecasting accuracy and major planning assumptions, receiving early-warning reporting when material changes occur in large-load forecasts, reliability assessments, or planning assumptions, and/or formally embedding state policy objectives into PJM's planning and market processes.

PDF page 40

OHIO - STATE COMMENTS
40
PJM must facilitate increased state involvement across every state within the RTO. Decisions made at PJM have impacts on what state regulators do and decisions made by state regulators impact transmission planning and the construction of generation. Though states should not directly control PJM, the organization should allow for states to have meaningful participation in the decision making process, meaningful participation for all states is important because of the diverse policy goals of each state in the RTO. Unlike PJM, state governments have to answer for rate increases. Given the significant impact within Ohio by decisions made by the PJM Board, Ohio would request any or all of the following: enhanced observer status, access to information before major filings, participating in independent reviews of load forecasting accuracy and major planning assumptions, and receiving preliminary reports when substantial changes occur in large-load forecasts, reliability assessments, or planning assumptions.

3. BOARD: Is the current board authority and accountability effective? Please consider the board’s ability to act unilaterally, reforming Board composition to include state-selected or state-nominated seats; establishing formal board performance metrics and periodic external accountability reviews; exploring Independent Representative Stakeholder (RSC) Board model used at other RTOs.

The Board must operate in the best interests of ratepayers, at this moment, it seems as though they are not meeting that goal. Ohioans are promised affordable and reliable electric service, but instead of this, they continually face rate increases with less reliable service. Under the current system, there is no motive for the Board to change directions–but it is clear that this current system does not work. Instead of acting to address the needs of all to provide affordable and reliable service, the Board serves the wants of a few by helping existing generation companies pad their pockets. Additionally, it seems that the Board takes far too long in the decision making process, they could take a nod from Ohio’s recently passed HB 15 which implemented clear regulatory timelines for the Public Utilities Commission of Ohio.

4. STAKEHOLDER PROCESS: Is the existing stakeholder process and filing right structure working?  If not, should it be changed?  Please consider if the process accurately reflects the interests of those ultimately bearing reliability and affordability risk, particularly ratepayers and emerging large-load customers? Please consider: modifying the voting structure, improving transparency and information access, reviewing and refreshing filing rights, and/or strengthening FERC's use of its Section 206 backstop authority.

The existing stakeholder process is not serving ratepayers despite the fact that the ratepayers are the ones who the system should be designed to serve. Large-load customers, specifically data centers, are one of the biggest issues facing the electric grid at this moment. Ohio created a Select Committee on Data Centers where we heard from data centers, governments, and citizens. In that committee, hyperscalers made it clear that they wanted to pay their fair share. While PJM has correctly taken the initiative to host this fall’s backstop auction, it will do little to help PJM ratepayers who saw their bills spike in 2024, 2025, and 2026. Ratepayers, especially residential ratepayers, are the ones who need their interests to be fought for, but this

PDF page 41

OHIO - STATE COMMENTS
41
group is all but left out of the process. Consumer representatives need a seat at the table, not just transmission and generation owners.

5. TRANSPARENCY: Does the PJM operational structure allow sufficient
engagement with independent information and transparency necessary to affect affordability?   Please consider whether regulators and consumer advocates have sufficient access to reproduce and independently evaluate the forecasts, congestion analyses, and planning assumptions that ultimately influence ratepayer costs. Should states be able to request studies on emerging affordability and reliability issues? Can we expand independent analytical access to PJM data while preserving market-sensitive confidentiality?

Transparency is the most important reform that PJM could make. At a minimum, this should include the video recording and transcription of Board meetings. For far too long, utilities have failed to disclose important and necessary information for the betterment of the grid under the guise of trade secrets. Standardizing what information must be disclosed so that regulators and consumer advocates have appropriate information to ensure affordable and reliable electric service is necessary. Specifically, reforms need to be made to make load forecasts transparent and standardized. Ratepayers should not be on the hook for unnecessary buildout of transmission and generation if load never actually comes. Ohio is attempting to require our utilities to submit better and more accurate forecasts to PJM through the Electricity Forecast Integrity Act.

6. STRUCTURE: Is PJM currently structured in a way to operate effectively in today’s rapidly changing context?  Please consider whether PJM has sufficient visibility into emerging risks, sufficient authority to act on them, and sufficient accountability for the outcomes. Is it sufficient regardless of the governance reform? What recommendations do you have for the future structure of PJM?

The reality is that this is not the same electric grid that PJM was dealing with in the 1990s, but that is no excuse for the lack of current action. PJM is well aware of the issues that are facing it–there is substantial load growth and that load growth is not being met with sufficient supply. While PJM was designed to look at generation and transmission, those two pieces do not happen in a vacuum and the end user of this generation and transmission can no longer be ignored given the immense demand of new users. Faster interconnection of renewable energy is necessary, there must be greater emphasis on new technologies to conduct upgrades to existing transmission systems, and more adoption of existing demand response technologies. Ratepayers are actively paying for PJM’s inaction and will continue to face rate increases and faltering reliability. Legislators across PJM want to advocate for affordable and reliable energy, we know that PJM and FERC share these goals. Ohio, and the legislators within the PJM footprint, look forward to charting a course of progress for the benefit of all current and future PJM ratepayers.

PDF page 42

PENNSYLVANIA - STATE COMMENTS
42
Pennsylvania - State Comments

State Representatives’ names, titles, and emails: (please list the lead author as well as those collaborating on this document)

Rep. Danielle Friel Otten (HD155, Chester County) - dotten@pahouse.net
Rep. Arvind Venkat (HD30, Allegheny) - RepVenkat@pahouse.net
Rep. Christina Sappey (HD158, Chester) - CSappey@pahouse.net
Rep. Greg Scott (HD54, Montgomery) - gscott@pahouse.net
Rep. Perry Stambaugh (HD86, Perry/Juniata) - pstambaugh@pahousegop.com
Sen. Carolyn Comitta (SD19, Chester) - senatorcomitta@pasenate.com
Rep. Joe Webster (HD150, Montgomery) - jwebster@pahouse.net
Rep. Jim Prokopiak (HD140, Bucks) - Jprokopiak@pahouse.net
Sen. Maria Collett (SD12, Montgomery/Bucks) - senatorcollett@pasenate.com Rep. Mary Isaacson, (HD175, Philadelphia)

State energy descriptors: (regulated or deregulated; net importer/exporter; etc.):

Deregulated. Net exporter. Fossil fuel and legacy generation dominant.

1. GOVERNANCE: Do we need to reform the governance of PJM? If so, why? For example, please consider how PJM’s current governance affects your state, other RTOs' governance, and your recommendations for reform.

Yes. The gap between how fast the grid is changing and how fast PJM responds is a direct threat to Pennsylvania families. Capacity prices have risen tenfold in two years. Interconnection queues remain a binding constraint on new supply. PJM's governance was not built for this moment. Pennsylvania has had to act at the state level on grid reliability and ratepayer protection because the regional process has not kept up. That is not a sustainable division of responsibility.

The cost consequences are real. Capacity prices rose from $28.92 per MW-day in 2024/2025 to $329.17 in 2026/2027, the FERC-approved cap. The Independent Market Monitor attributed roughly 63% of that increase to data center demand, equal to $9.3 billion in additional capacity costs. The Natural Resources Defense Council projects average household bills will rise approximately $70 per month by 2028 without intervention. Governor Shapiro's legal action against PJM's flawed auction design, and the resulting price collar, has already saved PJM customers across the region an estimated $45 billion. That is what engaged state oversight produces. But price suppression is not a solution. Downward pressure on capacity prices without fixing the underlying market failures, including phantom load and speculative data

PDF page 43

PENNSYLVANIA - STATE COMMENTS
43
center demand in PJM's forecasts, creates the conditions for an even sharper price spike when the collar comes off. Pennsylvania is not asking FERC to choose between short-term relief and long-term reform. We are asking for both.

Speed alone is not the fix. A faster PJM that still cannot show its work on how costs get allocated will move problems downstream faster. Reform must pair timeliness with real transparency, especially around the forecasting and planning assumptions that ultimately land on customer bills. That is the standard Pennsylvania has set for itself. It is the standard we are asking FERC to set region wide.

Our recommendations: require PJM to articulate a clear and legally recognized structure of ownership and accountability; grant PJM states Section 205 filing rights equivalent to MISO and SPP states; and establish mandatory timelines for committee action on priority issues with clear escalation paths when deadlines are missed.

2. STATE ROLE: What role and influence should states have in PJM?  Please consider whether states should have a role: on the PJM Board or in the nominations process, engaged in joint technical sessions with the PJM Board, in a formal consultation process, enhanced observer status, or information rights before major filings, participating in independent reviews of load forecasting accuracy and major planning assumptions, receiving early-warning reporting when material changes occur in large-load forecasts, reliability assessments, or planning assumptions, and/or formally embedding state policy objectives into PJM's planning and market processes.

State legislators across the PJM footprint currently have no formal authority within PJM governance. The PJM State Legislators Collaborative was founded last fall because of that gap, beginning with the CIFP process on large load additions and now expanding to this broader governance reform effort. That Collaborative exists because states needed an organized voice. A Collaborative is not a substitute for formal filing rights, structured consultation, or data access. Those require FERC action.

Pennsylvania and other PJM states should receive Section 205 filing rights equivalent to what MISO and SPP states already hold. In MISO, the Organization of MISO States can force a competing submission to FERC on cost allocation. In SPP, the Regional States Commission holds direct authority over cost allocation, market rules and resource adequacy. PJM states received no equivalent authority at founding. We are asking for parity.

The PJM Governors Collaborative, formed after Governor Shapiro convened all thirteen PJM governors in 2025, is another example of what structured state engagement looks like when states build it themselves. Pennsylvania supports formalizing that model at the legislative level, with defined consultation windows, joint technical sessions with the PJM Board, and information rights before major filings.

PDF page 44

PENNSYLVANIA - STATE COMMENTS
44

Pennsylvania supports the following formal state participation rights:

1. Receive major planning documents and forecasts before they are finalized.
2. Request independent studies on affordability or reliability concerns specific to Pennsylvania.

3. Nominate or vote on PJM Board members.
4. Participate in regular joint sessions with the PJM Board on key decisions.

3. BOARD: Is the current board authority and accountability effective? Please consider the board’s ability to act unilaterally, reforming Board composition to include state-selected or state-nominated seats; establishing formal board performance metrics and periodic external accountability reviews; exploring Independent Representative Stakeholder (RSC) Board model used at other RTOs.

No. The consensus is clear across party lines and both chambers.

The PJM Board makes final calls on major decisions. Members are selected through an industry-driven process, not by states or elected officials. There are no formal public performance metrics. There is no external accountability review. When outcomes are poor, as in three consecutive capacity auctions clearing at or near the administrative cap, there is no mechanism to hold the board responsible.

Pennsylvania supports the following board reforms:

1. The board should include independent consumer or ratepayer advocates.
2. States should be able to nominate or approve at least some board members.
3. Formal public performance metrics with periodic external accountability reviews.
4. PJM should look at how other grid operators structure their boards and adopt what works.

Strengthening existing accountability tools should not wait on restructuring board composition. Pennsylvania supports pursuing both in parallel, with accountability reforms treated as the immediate priority.

4. STAKEHOLDER PROCESS: Is the existing stakeholder process and filing right structure working?  If not, should it be changed?  Please consider if the process accurately reflects the interests of those ultimately bearing reliability and affordability risk, particularly ratepayers and emerging large-load customers? Please consider:

PDF page 45

PENNSYLVANIA - STATE COMMENTS
45
modifying the voting structure, improving transparency and information access, reviewing and refreshing filing rights, and/or strengthening FERC's use of its Section 206 backstop authority.

No.

The data behind this assessment is documented. Penn State University's Seth Blumsack and the RTO Governance Research and Practice Network compiled voting records showing PJM's sector-weighted system, which requires 3.35 of 5 electoral votes for passage, routinely produces blocking coalitions. Any two of five sectors can stop any proposal. In practice, generation owners and transmission owners have sufficient combined weight to block proposals that threaten their interests.

The consequences are not just procedural. The same blocking dynamic that prevented agreement on twelve large load interconnection options in 2025 applies to new supply reaching the grid at all. When incumbent generators hold effective veto power to overrule changes, the process is structurally biased against innovation and toward the status quo. New resources, new technologies and new market structures face a higher barrier than existing ones. That is not a feature of a well-functioning market. It is a symptom of governance that serves its current members rather than the region. Deregulation has produced industry- controlled processes that are status-quo oriented and resistant to innovation. Pennsylvania asks FERC to consider how governance reform creates space for new supply and new solutions to reach the grid, not just faster process refinement within the current structure.

A structural inequity compounds this problem. Residential ratepayers are folded into the same stakeholder sector as large commercial and industrial customers, who have the staff and resources to work the PJM process full-time. That leaves the people with the least ability to absorb a rate spike with the least structured way to be heard. Any reform to the voting structure must address that imbalance specifically and must guarantee residential ratepayers real notice and a genuine opportunity to participate, not just the commercial and industrial customers who already know how to work PJM's process.

On Section 205 filing rights: Pennsylvania legislators raised specific concern about the Section 205 versus 206 authority split. PJM is more responsive to FERC under Section 205, while states currently have no comparable filing standing. Granting states Section 205 filing rights would address this imbalance within the existing Federal Power Act framework, without requiring new Congressional authority.

5. TRANSPARENCY: Does the PJM operational structure allow sufficient
engagement with independent information and transparency necessary to affect affordability?   Please consider whether regulators and consumer advocates have sufficient access to reproduce and independently evaluate the forecasts, congestion

PDF page 46

PENNSYLVANIA - STATE COMMENTS
46
analyses, and planning assumptions that ultimately influence ratepayer costs. Should states be able to request studies on emerging affordability and reliability issues? Can we expand independent analytical access to PJM data while preserving market-sensitive confidentiality?

No. This question produced the strongest consensus of anything we surveyed.

PJM's planning assumptions, load forecasts and congestion analyses drive billions of dollars in infrastructure decisions and directly determine what Pennsylvania families pay on their electric bills. Pennsylvania's state regulators and consumer advocates cannot independently reproduce those forecasts or verify PJM's assumptions. That is a structural barrier to effective state oversight of decisions that Pennsylvania ratepayers must fund.

Pennsylvania has already acted on this. We signed Electricity Load Forecast Accountability provisions into law in 2025, giving our PUC authority to review and validate the load forecasts utilities submit to PJM, so large new energy users are not double-counted, and consumers are not paying for phantom demand. We are asking FERC and PJM to meet that same standard region-wide: regulators and consumer advocates need the ability to independently reproduce PJM's forecasts and congestion analyses, not just review PJM's own conclusions.

Pennsylvania colleagues who responded support the following, listed by level of support:

1. Full access by the Pennsylvania PUC and consumer advocates to PJM planning assumptions, load forecasts and congestion analyses sufficient to allow independent replication and verification. (86%)

2. The right to commission independent studies on affordability and reliability issues at Pennsylvania's request. (71%)

3. Public disclosure of PJM's major planning assumptions so independent researchers, consumer advocates and state legislators can evaluate them. (57%)

On residential ratepayer equity in transparency: access to PJM data and the ability to participate in proceedings is not equally distributed. Large commercial and industrial customers have dedicated staff to monitor PJM's processes. Residential ratepayers do not. Any transparency reform must include access and real notice for residential consumer advocates, not just expanded data portals that only well-resourced actors can use.

6. STRUCTURE: Is PJM currently structured in a way to operate effectively in today’s rapidly changing context?  Please consider whether PJM has sufficient visibility into emerging risks, sufficient authority to act on them, and sufficient accountability for the outcomes. Is it sufficient regardless of the governance reform? What recommendations do you have for the future structure of PJM?

PDF page 47

PENNSYLVANIA - STATE COMMENTS
47

No. PJM's footprint has grown faster than its visibility into what is driving demand. Large- load growth is reshaping planning assumptions region-wide, and the governance structure was not built for this pace.

The structural problem is best described by the three clocks framework identified by Dr. Jeanine Johnson, former PJM Board Member, in her 2026 paper: infrastructure operates on multi-year timelines; governance operates on stakeholder cycle timelines of months to years; and information now operates at AI-accelerated software speed of seconds to minutes. Risk concentrates in the gap between these tempos.

The foundational question that must be answered before any structural model is chosen: who owns PJM, who is accountable for its outcomes and does that accountability serve the public interest? As Duane and Clark identified in 2021, PJM's structure dissipates any locus of control, blurs ultimate accountability and often fails to reach consensus. A faster PJM that still cannot show its work on how costs get allocated will move problems downstream faster. Speed and accountability must go together.

The economic case for structural reform begins with a fact that often goes unstated: PJM is a natural monopoly. There is no competing grid operator serving the same 13 states. No customer, state or utility can opt out and go elsewhere. Standard economic theory, applied to railroads, water infrastructure and pipelines for over a century, holds that natural monopolies require public regulation with genuine accountability. Voluntary stakeholder processes where incumbent market participants hold blocking power are not a substitute for public accountability. When incumbents can veto change, accountability disappears.

A workable institutional model for a multi-state public resource already exists in Pennsylvania's backyard. The Delaware River Basin Commission was created in 1961 when Pennsylvania, Delaware, New Jersey, New York and the federal government recognized that shared regional infrastructure could not be managed through fragmented, competing jurisdictions. Before the DRBC, 43 state agencies, 14 interstate agencies and 19 federal agencies all claimed overlapping authority over the same river system. The result was splintered authority and no clear accountability for outcomes. The solution was an interstate compact with the force of law, equal state and federal partners and defined decision-making authority. The Commission has operated for more than six decades. It governs a physically interconnected regional resource without regard to political boundaries. The parallel to PJM is not perfect. PJM is larger, more technically complex and already exists as a functioning institution. A DRBC-style redesign would require time and Congressional action. Pennsylvania raises this model not as a prescription but as proof of concept: structured public accountability over a shared regional resource is achievable. The question is whether FERC and the states have the will to move in that direction.

PDF page 48

PENNSYLVANIA - STATE COMMENTS
48
On structural reform, Pennsylvania respondents were split. Four of seven survey respondents supported moving toward a multi-state public authority model. Two did not have enough context to weigh in. One, who selected the stronger option on the survey, clarified in follow-up that his real position is closer to Section 205 parity plus other structural mechanisms from existing ISOs, short of a full public authority model. Senator Collett expressed that Pennsylvania should not advocate for breaking PJM apart; this submission does not advocate for dissolution.

Given that range of views, Pennsylvania does not prescribe a single structural model. We do advocate for FERC to begin answering the ownership and accountability question explicitly, rather than deferring it through incremental adjustments.

Specifically:

1. Grant Pennsylvania and other PJM states Section 205 filing rights over cost allocation equivalent to those held by MISO and SPP states. This is the floor, not the ceiling.

2. Direct PJM to establish fast-track decision authority with mandatory timelines for high- priority issues and defined escalation paths when the stakeholder process cannot produce a decision.

7. OTHER: Please add any other comments or respond to the FERC technical
conference panel questions specifically here:

Pennsylvania is one of PJM's largest net exporters of electricity. Our ratepayers carry real exposure to how this footprint is governed. Governor Shapiro's legal action against PJM's flawed auction design, and the price collar that followed, has already saved PJM customers across the region an estimated $45 billion. That is the direct result of engaged state oversight. But price suppression is not a solution. Downward pressure on capacity prices without fixing the underlying market failures, including phantom load and speculative data center demand in PJM’s forecasts, creates the conditions for an even sharper price spike when the collar comes off. Pennsylvania is not asking FERC to choose between short-term relief and long-term reform. We are asking for both.

District-specific issues Pennsylvania asks FERC to include in the record:

● Rep. Arvind Venkat (HD30, Allegheny County): Rising energy bills driven by grid management failures are a top constituent concern.

PDF page 49

PENNSYLVANIA - STATE COMMENTS
49
● Rep. Christina Sappey (HD158, Chester County); Rep. Danielle Friel Otten (HD155, Chester County): Constituents are experiencing consistently rising rates and reliability concerns.

● Rep. Greg Scott (HD54, Montgomery County): Data center siting near his district and rising electric costs for constituents.

● Rep. Perry Stambaugh (HD86, Perry and Juniata Counties): The proposed 765-kV Kammer-Juniata Transmission Line is routed through New Bloomfield in HD86. Mitigation of new rights-of-way must be a priority in transmission planning.

● Rep. Jim Prokopiak (HD140, Bucks County): Data center expansion and rising electric costs are top constituent concerns.

● Sen. Maria Collett (SD12, Montgomery/Bucks): Senator Collett has fought to renew Chapter 14 consumer protections and pushed back when PECO sought a rate increase she did not find justified. She asks FERC to hold PJM to that same standard: reforms that make decisions faster should also make them more accountable to the people paying for them.

PDF page 50

VIRGINIA - STATE COMMENTS
50
Virginia- State Comments

State Representatives’ names, titles, and emails: (please list the lead author as well as those collaborating on this document)

(speaking only for themselves)

Delegate Rip Sullivan,   delrsullivan@house.virginia.gov
Senator Kannan Srinivasan, senatorsrinivasan@senate.virginia.gov

State energy descriptors: (regulated or deregulated; net importer/exporter; etc.):

Regulated, net importer, clean energy goals

1. GOVERNANCE: Do we need to reform the governance of PJM? If so, why? For example, please consider how PJM’s current governance affects your state, other RTOs' governance, and your recommendations for reform.

Yes. PJM’s organizational structure puts its members’ interests ahead of the public interest, is opaque, and results in a decision-making process that is too slow for the accelerated energy demand environment we are facing. A re-design is definitely required.

2. STATE ROLE: What role and influence should states have in PJM?  Please consider whether states should have a role: on the PJM Board or in the nominations process, engaged in joint technical sessions with the PJM Board, in a formal consultation process, enhanced observer status, or information rights before major filings, participating in independent reviews of load forecasting accuracy and major planning assumptions, receiving early-warning reporting when material changes occur in large-load forecasts, reliability assessments, or planning assumptions, and/or formally embedding state policy objectives into PJM's planning and market processes. market processes.

It is hard to answer this question without knowing what a newly-designed PJM would look like or how it would be governed. And the question begs another question: would “states role and  influence” implicate governors, state legislators, and/or state utility commissions? Suffice it to say that all three of those should be involved in PJM decision-making in a way that goes beyond being merely stakeholders in the process, and recognizes and empowers their responsibilities to ratepayers to deliver reliable, affordable electricity to the PJM region.

3. BOARD: Is the current board authority and accountability effective? Please consider the board’s ability to act unilaterally, reforming Board composition to include

PDF page 51

VIRGINIA - STATE COMMENTS
51
state-selected or state-nominated seats; establishing formal board performance metrics and periodic external accountability reviews; exploring Independent Representative Stakeholder (RSC) Board model used at other RTOs.

No. In the absence of a major restructuring along the lines of an interstate compact or other RTO models, the current board is not positioned to be effective. With the slow stakeholder process the board is often unable to act in a timely manner to respond to challenges. This system may have been effective when demand growth was low, but the board needs to be reformed and put in position to make decisions to meet the current moment. In addition,  the lack of  representation from states (governors, legislators, and regulators) leaves the board responsive only to the stakeholders who comprise private generators, utilities, and transmission operators who do not necessarily have the best interests of ratepayers first in mind.

4. STAKEHOLDER PROCESS: Is the existing stakeholder process and filing right structure working?  If not, should it be changed?  Please consider if the process accurately reflects the interests of those ultimately bearing reliability and affordability risk, particularly ratepayers and emerging large-load customers? Please consider: modifying the voting structure, improving transparency and information access, reviewing and refreshing filing rights, and/or strengthening FERC's use of its Section 206 backstop authority.

No. The stakeholder process has significant flaws that need to be addressed. The consensus requirements slow decisions and recommendations delivered to the board (if they are not outright vetoed by the stakeholder process). Other RTOs, like ERCOT, have moved from consensus models to more advisory models which allow action to be taken more swiftly and approvals from FERC to be expedited.

5. TRANSPARENCY: Does the PJM operational structure allow sufficient
engagement with independent information and transparency necessary to affect affordability?   Please consider whether regulators and consumer advocates have sufficient access to reproduce and independently evaluate the forecasts, congestion analyses, and planning assumptions that ultimately influence ratepayer costs. Should states be able to request studies on emerging affordability and reliability issues? Can we expand independent analytical access to PJM data while preserving market-sensitive confidentiality?

No. Load forecasts and congestion analyses are typically submitted by utilities with little or no opportunity for independent evaluation by regulators or consumer advocates.

6. STRUCTURE: Is PJM currently structured in a way to operate effectively in today’s rapidly changing context?  Please consider whether PJM has sufficient

PDF page 52

VIRGINIA - STATE COMMENTS
52
visibility into emerging risks, sufficient authority to act on them, and sufficient accountability for the outcomes. Is it sufficient regardless of the governance reform? What recommendations do you have for the future structure of PJM?

See answers in 3 and 4 regarding structural issues within PJM.

PDF page 53

WEST VIRGINIA - STATE COMMENTS
53
West Virginia- State Comments

State Representatives’ names, titles, and emails: (please list the lead author as well as those collaborating on this document)

George Street, WV House of Delegates, george.street@wvhouse.gov

State energy descriptors: (regulated or deregulated; net importer/exporter; etc.):

Regulated, Net Exporter

1. GOVERNANCE: Do we need to reform the governance of PJM? If so, why? For example, please consider how PJM’s current governance affects your state, other RTOs' governance, and your recommendations for reform.

Governance reform appears necessary, particularly to grant states a more meaningful voice in PJM's decision-making processes. However, the specific mechanics of how this should be structured require further exploration, as there are still outstanding questions regarding how to implement such changes effectively.

2. STATE ROLE: What role and influence should states have in PJM?  Please consider whether states should have a role: on the PJM Board or in the nominations process, engaged in joint technical sessions with the PJM Board, in a formal consultation process, enhanced observer status, or information rights before major filings, participating in independent reviews of load forecasting accuracy and major planning assumptions, receiving early-warning reporting when material changes occur in large-load forecasts, reliability assessments, or planning assumptions, and/or formally embedding state policy objectives into PJM's planning and market processes.

While the concept of increased state engagement and influence is supported, the details and long-term ramifications of implementation raise significant questions. Key concerns include how PJM would manage potential ideological conflicts between states with differing energy generation preferences, such as fossil fuels, wind, solar, and nuclear. Additionally, there are critical equity issues for power-exporting or passthrough jurisdictions like West Virginia. These areas often face local protests over major transmission line projects that appropriate rural land to serve high-demand urban centers to the east without offering direct local benefits. A clear mechanism is needed to resolve these interstate disparities.

3. BOARD: Is the current board authority and accountability effective? Please consider the board’s ability to act unilaterally, reforming Board composition to include state-selected or state-nominated seats; establishing formal board performance metrics

PDF page 54

WEST VIRGINIA - STATE COMMENTS
54
and periodic external accountability reviews; exploring Independent Representative Stakeholder (RSC) Board model used at other RTOs.

States should have direct representation on the PJM Board. However, the precise level of authority and input remains to be defined, and safeguards must be considered to prevent larger states from disproportionately outvoting smaller states.

4. STAKEHOLDER PROCESS: Is the existing stakeholder process and filing right structure working?  If not, should it be changed?  Please consider if the process accurately reflects the interests of those ultimately bearing reliability and affordability risk, particularly ratepayers and emerging large-load customers? Please consider: modifying the voting structure, improving transparency and information access, reviewing and refreshing filing rights, and/or strengthening FERC's use of its Section 206 backstop authority.

The current stakeholder process does not appear to be functioning optimally, as concerns over grid instability and potential facility shutdowns indicate underlying system issues. While there are complex technical aspects to this process that require deeper study, the current outcomes point to a clear need for improvement.

5. TRANSPARENCY: Does the PJM operational structure allow sufficient
engagement with independent information and transparency necessary to affect affordability?   Please consider whether regulators and consumer advocates have sufficient access to reproduce and independently evaluate the forecasts, congestion analyses, and planning assumptions that ultimately influence ratepayer costs. Should states be able to request studies on emerging affordability and reliability issues? Can we expand independent analytical access to PJM data while preserving market-sensitive confidentiality?

PJM's operational structure likely does not provide sufficient transparency or independent information access. However, a highly technical assessment of these specific information- sharing gaps is outside the respondent's current areas of primary expertise.

6. STRUCTURE: Is PJM currently structured in a way to operate effectively in today’s rapidly changing context?  Please consider whether PJM has sufficient visibility into emerging risks, sufficient authority to act on them, and sufficient accountability for the outcomes. Is it sufficient regardless of the governance reform? What recommendations do you have for the future structure of PJM?

PJM may not be optimally structured for today's rapidly changing environment. While increased state-level control is highly desirable, there is a valid concern that expanding state

PDF page 55

WEST VIRGINIA - STATE COMMENTS
55
decision-making authority could inadvertently lead to regional gridlock and reduce operational efficiency.

7. OTHER: Please add any other comments or respond to the FERC technical
conference panel questions specifically here:

Further legislative education is essential to fully grasp the technical complexities of these issues. It is difficult to confidently propose specific structural fixes without first establishing a clearer, shared consensus on exactly which components of the system are failing.