Post Technical Conference Comments of the Illinois Commerce Commission re PJM Governance and Stakeholder Reforms
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Governance and Stakeholder Reforms
)
Docket No. AD26-7-000
ILLINOIS COMMERCE COMMISSION
POST TECHNICAL CONFERENCE COMMENTS
Pursuant to the Commission’s invitation extended on July 23, 2026, to provide post- technical conference comments in this docket, and the Notice Requesting Post-Conference Comment issued July 30, 2026, the Illinois Commerce Commission (“ICC”) does hereby provide these post-technical conference comments for consideration. The ICC is the public utility commission in the State of Illinois. Illinois has utilities in both PJM Interconnection, L.L.C. (“PJM”) and the Midcontinent Independent System Operator, Inc. (“MISO”). The ICC submitted a notice of intervention in this docket on August 5, 2026, so it is an interested party. The ICC appreciates the Commission convening the technical conference on July 23, 2026 (“Technical Conference”) and provides these comments in support of the needed reforms to improve PJM’s Board of Directors (“PJM Board” or “Board”) independence, more effective PJM leadership in the stakeholder process, increased state input into the process, and clear direction that PJM should be working in the public interest.
PDF page 2
2
I. COMMENTS
A. The Commission Should Direct PJM to More Effectively Lead the RTO and its Stakeholders to Address High Priority Issues in a Timely Manner.
In Order No. 2000, the Commission set forth the minimum functions and characteristics for the formation of regional transmission organizations (“RTOs”).1 Notably, the Commission did not impose any restrictions on state agencies participation and encouraged the states to participate in the formation of the RTOs.2 The Commission took a flexible approach. It made the point that “states will play a key role in RTO formation and development”3 but it declined to “specify generically a state's role in governance.”4 The Commission said, “State involvement is important for several reasons, especially where RTOs are a critical element of the retail choice programs of many states. State commissions are in a unique position to assess whether a particular RTO design will help or hinder their efforts to promote retail competition.”5 In response, states formed a regional state committee (“RSC”), the Organization of PJM States, Inc. (“OPSI”). The ICC is a member of OPSI and the Organization of MISO States, Inc. (“OMS”), the RSC in the MISO region. OPSI and its member states have actively collaborated and participated in the formation and development of the PJM processes. Recent events, however, such as the generation fleet transition, tremendous load growth, and public policy changes have transformed the energy landscape such that an increased state role and public interest focus has become crucial. These changes have increased costs while threatening reliability. The PJM existing stakeholder process has struggled to meet this moment. Given the stakes, it is reasonable to revisit the PJM process to ensure PJM provides economically efficient
1 Regional Transmission Organizations, Order No. 2000, 89 FERC ¶ 61,285 (1999) (“Order No. 2000”). 2 Order No. 2000 at 230-231.3 Id. at 628.4 Id.5 Id. at 231.
PDF page 3
3
and reliable electric service and elevates public concerns in the PJM stakeholder process.
The ICC cares about the viability of PJM and sees the need to improve the PJM stakeholder process. As a restructured state, Illinois relies significantly on our participation in competitive RTO markets to ensure resource adequacy and reliability for our ratepayers at an affordable price. As discussed at the Technical Conference, many key reliability and economic issues get lost in the sometimes seemingly obtuse stakeholder process in which related issues are often split between various committees, subcommittees, task forces and work groups. To combat this problem, PJM should develop a clear process of both (1) better collaboration with state entities (detailed further in section B below) and (2) setting an annual work plan, requiring each committee and subcommittee to do the same, including a plan to prioritize each work plan action item. If PJM is unwilling to set a clear work plan, set timelines, and ultimately follow through, the Commisssion should direct PJM to achieve this. An example of how to efficiently prioritize work plan action items is to determine key priorities then give each issue/work plan item a prioritization ranking according to high, medium or low risk. Each committee, subcommittee and task force follows through with a focus first on those items considered highest priority. Such a system in which PJM has developed a clear work plan and action items with a prioritization on high-priority items, should help PJM and stakeholders stay focused. If a time sensitive issue appears throughout a year, there should be clear plans from PJM on how to address time-sensitive issues to reduce reliance on Critical Issue Fast-Paths, something that has become a normalized process in the PJM stakeholder process over the past few years.
Further, while the ICC agrees that stakeholder discussions can be productive, these discussions should be led with the purpose of accomplishing goals in a more-timely manner.
PDF page 4
4
Solutions exist today that can accomplish noticeable change. Specifically, PJM stakeholder meetings should be streamlined and more rigorously moderated to make them more productive. Committee and subcommittee leadership should consider limiting participants to one or two questions before going back into the queue to allow more voices and diverse opinions to be heard, similar to MISO stakeholder processes. Moreover, PJM should streamline obtuse committee structures that bifurcate related issues and force stakeholders to guess when and where their key issues will be discussed. PJM agendas should be clear and respect time schedules to help stakeholders know how best to allocate what may be scarce resources. A feedback process like MISO has may be a useful tool. These suggestions could be implemented quickly and would require little work on PJM Staff to incorporate.
B. The Retail Jurisdictions Need A Larger Voice in the PJM Stakeholder Process To Better Represent Their 67 Million Residents.
PJM’s current structure and culture largely relegate retail jurisdictions to the sidelines. States and the District of Columbia (“DC”), despite their key role in providing resource adequacy, lack a functional way to directly participate in PJM’s governance process. PJM governance will be improved by allowing states and DC, all of whom represent ratepayers and raise necessary questions about issues like affordability, a greater voice in the stakeholder process. This enhanced voice for states and DC should come in two specific forms. First, while it is not a public utility under the Federal Power Act, OPSI needs an enhanced voice in the PJM section 205 rate filing process under the Federal Power Act.6 At a minimum, OPSI should be provided the opportunity for input and to provide alternative proposals when PJM makes a section 205 filing at the Commission. OPSI is the primary vehicle for states and the
6 Federal Power Act, Section 205, 16 U.S.C. § 824d (.”. . . Utilities are required to file schedules of rates, charges, and contracts with FERC and make them publicly available, . . “
PDF page 5
5
DC to communicate preferences and concerns to the PJM Board, Staff, and stakeholders. Despite this crucial role, OPSI does not currently have sufficient opportunity for meaningful input to help shape PJM’s direction.
States and the DC lack a formal voice at PJM, a significant problem. They are responsible for resource adequacy and are important representatives of their ratepayers’ concerns. In addition, state regulators bring technical expertise and state policy background that would enhance PJM filings. Given states regulators’ important function in the PJM region, it is sensible for the Commission to require PJM to make any necessary tariff changes to allow OPSI the opportunity to provide input as well as alternative proposals to the Commission when PJM makes section 205 filings. Failure to do so directly results in an underdeveloped and incomplete stakeholder process. After all, ratepayers are directly impacted by the cost and reliability issues that flow from such filings, as well as any resource adequacy and transmission cost allocation decisions made in the PJM stakeholder process.
Given this, it is crucial for states and DC to have a greater voice in shaping any PJM section 205 filings, particularly with respect to resource adequacy and transmission cost allocation matters. Specifically, states and DC should be provided alternative proposal “jump ball” rights that require PJM to file state and DC preferences alongside PJM Board filings. Giving PJM states and DC more input into PJM filings would bring PJM in alignment with other RTOs. RSCs in the Southwest Power Pool (“SPP”), ISO New England (“ISO-NE”) and the MISO regions have some version of this option over certain policy areas. The ICC supports OPSI’s request to have at the very least the same level of valuable input into PJM’s section 205 filings. This simple change will improve PJM’s proposals by bringing more perspectives,
PDF page 6
6
notably the currently largely overlooked state and DC voices, more centrally into the PJM process
Second, ICC also supports a meaningful voice in the process for the Governors’ Collaborative. Importantly, this group should have formal recognition at PJM. Bringing the region’s executives into the PJM’s stakeholder and governance processes in a more meaningful way will elevate important voices in conversations on the most pressing issues the region faces.
C. The PJM Board Should Have Greater Independence To Enable the Board to
Make Necessary, Difficult Decisions.
The PJM Board requires greater independence to meet current and future challenges. For PJM to accomplish its duty of providing reliable power at the lowest price possible to consumers, it is crucial that PJM – and the PJM Board – have sufficient independence to enact the policies they believe are right at any given moment while balancing its responsibilities to stakeholders and its 67 million residents. RTOs, such as PJM, require careful interaction of numerous technical aspects to accomplish their mission. RTOs exist at the intersection of prudent market design, thoughtful transmission planning, careful legal reasoning, and policy implementation. Each of these areas requires the PJM Board, at times, to make the right decision based on feedback from PJM’s technical staff, not simply to implement the most popular choice of the voting members.
PJM’s current governance structure too often impedes the Board’s decision-making authority. PJM Members’ ability to file tariff changes on their own with a supermajority vote and without Board support as well as their power to remove Board members after only three years, means that PJM’s Board is often restricted in its choices. PJM’s Board needs sufficient protection to ensure non-discriminatory tariffs and important revisions to the PJM operating manuals are implemented. Stakeholder input and expertise is undeniably central to PJM’s
PDF page 7
7
process, particularly to developing nuanced, workable solutions for market and transmission problems. PJM Members, however, are also unavoidably (and reasonably) tied to their own interests and perspectives. Too often PJM Members’ entrenched preferences have resulted in PJM’s stakeholder process breaking down and failing to converge on workable solutions. PJM Board’s independence can come in many forms, such as longer terms for its members. The Commission should consider ways to expand PJM Board’s independence without wholly undermining PJM Board’s responsiveness to its members and other stakeholder concerns.
II. SURVEY RESPONSE
In the July 30, 2026, Notice Requesting Post-Technical Conference Comments, the Commission directed commenters to include responses to the survey attached in Appendix A to the Notice. As described below, many of the individual changes proposed by the ICC must accompany others and cannot stand alone. Changes can make PJM better able to address the challenges that it faces today. As Chairman Swett said at the Technical Conference, there are ways to “right the ship.” What has been made clear in the last few years, PJM ratepayers are experiencing the highest costs from PJM while being the least protected from abuses and scarcity prices. Empowering and incorporating states government, including the public service commissions tasked with balancing protection ratepayers, is critical to ensuring PJM works for the consumers who ultimately pay the bills, not just powerful market sector interests. The ICC provides the following responses to the survey:
PDF page 8
8
PJM Board Independence
Questions/Comments
Yes No
1) Should Board members’ terms be extended to five or more years?
x
Comments:
PJM’s Board members’ term should be lengthened to five years. It was made clear at the July 23 Technical Conference that PJM Board and Staff must take a greater leadership role in guiding PJM, its planning, its operation, and the markets it oversees.
Much of this leadership role is utilizing the tools and authority PJM already has. There are difficult choices to make, and term lengths greater than three years will help ensure stability in Board leadership to make tough choices. Five-year terms, for example, would help ensure Board member positions are not a revolving door and there is stability when the Board needs to make important, sometimes unpopular, decisions, while also ensuring Board Members are responsible to the stakeholders of PJM.
2) Should there be a maximum number of years that a Board member may serve (e.g., 10 years)?
x
Comments:
There should be a maximum number of years any Board member may serve. This is not dependent on other changes that Commission or PJM may undertake to improve governance and PJM’s health. Reasonable board turnover is good for the longevity of any organization. While there should be a limit on the number of years any Board member may serve, the total should allow for Board members to stay on for a reasonable amount of time. ICC recommends around 10 years (or two five-year terms) to strike a reasonable balance between encouraging institutional expertise on the Board while also ensuring new perspectives.
3) Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region?
Comments:
While the ICC does not believe that residency in PJM is a necessary requirement to serve on PJM Board, residency in the PJM territory should not be a barrier to being considered and selected as a board member.
4) Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?
Comments:
PDF page 9
9Questions/CommentsYes No
The ICC does not take a position on this issue at this time.
5) Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders?
Comments:
The ICC does not take a position on this issue at this time. Ex parte rules currently do not apply to the ICC, as the ICC is not a PJM Member. Any reduction in ex parte communication should also be accompanied by greater transparency.
Of note, PJM has a culture of limiting communication and contact directly and informally between Board members and the retail jurisdictions.
Communication must be increased between the Board members and government entities, especially public utility commissions. Public utility commissions must implement many actions that PJM cannot and are tasked with protecting their jurisdictions and residents’ interest. This requires open and frequent communication between PJM Board members and the governments. Frequent and informal conversations with individual jurisdictions, as well as collectively, will help improve actions taken at PJM and ultimately improve and speed up processes by addressing problems early on. Board members should meet with state officials on individual and more frequent basis in both formal and informal settings.
6) In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?
x
Comments:
In keeping with the public interest goals, Board votes should be held in public, made public, and explained. This will increase confidence in the Board actions. PJM Board’s secrecy is undermining faith in the RTO and the actions it is taking.
7) In order to increase transparency, should some Board meetings be open or available to the public?
x
Comments:
Board meetings should be open to the public with exceptions for information that needs to be kept confidential. This will increase confidence in the Board’s actions. PJM Board’s secrecy is undermining faith in the RTO and the actions it is taking.
8) Should PJM’s governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest? x
Comments:
The governing documents should be revised to explicitly state that the responsibility of PJM and the PJM Board is to serve the public interest. This will direct the Board not
PDF page 10
10Questions/CommentsYes No
just to move forward with any proposal that is reasonable but to push for the best one for the residents of PJM and the overall system based on its duty established in Order No. 2000, “to promote efficiency in wholesale electricity markets and to ensure that electricity consumers pay the lowest price possible for reliable service”, as intended by the Commission. This change is critical especially if the Board receives expanded 205 filing rights to ensure that Board independence results in the best outcome for PJM and its residents.
9) Should state representatives have at least one voting member on the Nominating Committee?
x
Comments:
State, including DC, representatives should have no less than three representatives on the PJM Board Nominating Committee.
10) Should PJM adopt public performance metrics and tie management
compensation to their achievement?
Comments:
The ICC does not take a position on this at this time.
Section 205 Filing Rights
Questions/Comments
Yes No
11) Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board?
x
Comments:
The ICC supports the stakeholder process becoming advisory only if states are given an unencumbered pathway to exercising rights to include an alternative to PJM’s section 205 filings on certain matters and under certain conditions (e.g., supermajority OPSI vote).
12) Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?
x
Comments:
Yes, but only if states are given an unencumbered pathway to exercising rights to include an alternative to PJM’s 205 filing on certain matters and under certain
PDF page 11
11Questions/CommentsYes No
conditions (e.g., supermajority OPSI vote). This means providing PJM with 205 rights over all aspects of the Operating Agreement.
13) Should PJM have section 205 filing rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the requirement to obtain
approval of two-thirds of the Members Committee?
x
Comments:
Yes, but only if states are given an unencumbered pathway to exercise rights to include an alternative proposal to PJM’s section 205 filings on certain matters and under certain conditions (e.g., supermajority OPSI vote). This means providing PJM with 205 rights over all aspects of the Operating Agreement.
14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?
x
Comments:
OPSI should have at least the same jump ball rights within PJM as has been granted to other regions’ RSCs. States assign costs associated with PJM’s resource adequacy construct and transmission planning process, promote resource adequacy to enable PJM to maintain reliability in real time, and site much of the transmission that PJM approves. Despite these crucial roles, OPSI does not have an adequate opportunity to help direct PJM’s decisions, unlike public utility commissions in other RTOs, such as SPP, MISO and ISO-NE. States’ work is intertwined with PJM’s work, and our residents are directly impacted by PJM’s decisions. The retail jurisdictions need a stronger voice in the section 205 filing process, including the ability to proffer a state alternative proposal under section 205, or “jump ball” rights, when PJM makes a filing. This opportunity will improve the dialogue between the retail jurisdictions and PJM even if those rights are not utilized.
15) Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?
Comments:
The ICC does not take a position on this at this time.
PDF page 12
12
Stakeholder Process
Questions/Comments
Yes No
16) Should the approval threshold in the Members Committee be lowered from two-thirds sector-weighted voting?
Comments:
The ICC does not take a position on this at this time.
17) Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?
x
Comments:
Voting rules that apply to senior standing committees should apply to lower-level committees. This reflects the true structure and nature of the voting members and may help streamline PJM committee meetings. The voting should be consistent.
State Participation
Questions/Comments
Yes No
18) In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’
representatives?
x
Comments:
The ICC is supportive of the formal recognition of the Governors’ Collaborative that complements OPSI’s role at PJM.
19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes?
x
Comments:
The ICC does not support a formal voting role in the stakeholder process for states and DC. This reflects the position OPSI, including the ICC, consistently has held. If retail
PDF page 13
13Questions/CommentsYes No
jurisdictions had a voting role, then retail jurisdictions would have 14 out of 1,137 votes but represent 67 million residents. A small number of votes in the stakeholder process is an inadequate mechanism for reflecting the voice of the states in the PJM stakeholder process.
20) Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation?
x
Comments:
PJM should consult with OPSI prior to making such a filing. However, this should not be limited to a mere consultation. It must include unencumbered jump ball filing rights should the states so choose. The ICC does not support binding consultation in lieu of OPSI being able to exercise jump ball filing rights by providing alternative proposals for a PJM section 205 filing when the RSC so chooses, however. Having only a consultation without meaningful input and recognition is not a significant shift from the status quo, which prevents the regulatory jurisdictions, and the ratepayers that we represent, a true seat at the table.
PJM should consult with OPSI and its members on a regular basis. It is particularly important for PJM to consult with OPSI and its members before PJM makes a section 205 filing, however, to provide OPSI and its members with an opportunity to discuss and provide an alternative proposal if appropriate.
III. CONCLUSION
WHEREFORE, for the reasons set forth above, the ICC does hereby submit these post- technical conference comments for your consideration. The ICC appreciates your attention to these important issues.
Respectfully submitted,
/s/ Christine F. Ericson
____________________________
Christine F. Ericson
Special Assistant Attorney General
Illinois Commerce Commission
Office of General Counsel
160 N. LaSalle St., Suite C-800
Chicago, IL 60601
PDF page 14
14
(312) 814-3706
Christine.Ericson@Illinois.gov
Counsel on behalf of the
ILLINOIS COMMERCE COMMISSION
Dated: August 19, 2026
PDF page 15
CERTIFICATE OF SERVICE
I hereby certify that I caused copies of the foregoing document of the Illinois Commerce Commission to be served this day upon each person designated on the official service list compiled by the Secretary in this proceeding in accordance with the requirements of Rule 2010 of the Commission's Rules of Practice and Procedure.
Dated at Chicago, Illinois, this 19th day of August, 2026.
/s/ Christine F. Ericson
_____________________________
Christine F. Ericson
Special Assistant Attorney General
Illinois Commerce Commission
Office of General Counsel
160 N. LaSalle St.
Suite 800-C
Chicago, IL 60601
(312) 814-3706