AD26-7-000 · 2026-08-21 · Solar Energy Industries Association, MAREC Action

Comments of MAREC Action and Solar Energy Industries Association re PJM Governance and Stakeholder Reforms

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

)
Exploring The Current State of

)
 Docket No. AD26-7-000

PJM Governance

)

COMMENTS OF MAREC ACTION AND
THE SOLAR ENERGY INDUSTRIES ASSOCIATION

Pursuant to the July 30, 2026 notice inviting comments,1 MAREC Action2 and the Solar Energy Industries Association (“SEIA”)3 submit these recommended governance reforms for the PJM Interconnection, L.L.C. (“PJM”) Board and stakeholder process.

MAREC Action and SEIA represent developers of all different sizes and business models. These run the gamut from small rooftop solar installers to large multinational corporations. It includes both public and private companies, some are North American subsidiaries of international companies, some are owned by pension funds or private equity funds, are smaller owner-operated businesses. They have a variety of business models. Some are owner-operators, others build and sell projects, while others build projects under contract to other entities. But they all have something in common—they want to get generation projects built in the PJM region to serve the growing load.

Many of these developers represented by MAREC Action and SEIA have project
development experience outside of PJM, both in other Regional Transmission Organization (“RTO”) markets and in non-RTO regions. Some, that are subsidiaries of international

1 Notice Requesting Post-Conference Comment, Docket No. AD26-7 (July 30, 2026).
2 MAREC Action (informally, “Mid-Atlantic Renewable Energy Coalition”) is a coalition of over 40 utility-scale solar, wind, and battery storage developers and manufacturers dedicated to the growth and development of renewable energy across the PJM grid region. The views and opinions expressed in this filing do not necessarily reflect the official position of each individual member of MAREC Action.
3 The comments contained in this filing represent the position of SEIA as a trade organization on behalf of the solar industry, but do not necessarily reflect the views of any particular member with respect to any issue.

PDF page 2

2

companies, also have project development experience outside the US. Many are actively involved in the stakeholder processes in other regions and have first-hand experience in what works well and what needs improvement. The recommendations below are informed by these diverse business models and stakeholder experiences.4

As the Commission, PJM, and stakeholders begin the arbitration process, MAREC Action and SEIA request that these recommendations are considered and incorporated into the final reforms.

I. Stakeholders need insight into Board direction and decisions
Insight into Board decisions is sorely lacking in PJM. Stakeholders have very little knowledge of how and why the Board acts as it does s. Many decisions in the recent past seem to be rushed attempts to put out fires rather than deliberate well-planned decisions that would move PJM into the future. Short-term fixes seem to have become the norm. PJM has jumped from emergency to emergency, establishing reforms that are simultaneously rushed and too late. This can be seen in the multiple uses of the Critical Issues Fast Path Process over the last few years that have resulted in some major changes to the PJM markets with very little insight into how the Board arrived at those decisions.

Meanwhile, reforms that could address many of the fundamental problems, such as comprehensive transmission and generation interconnection planning, and energy and capacity market reforms, have fallen by the wayside. For years, as we watched other regions move to more granular markets, stakeholders have told themselves, “this is the year PJM will enact

4 MAREC Action and SEIA’s silence on a particular issue does not necessarily represent internal disagreement, acquiescence to the status quo, or agreement with any particular position taken in this proceeding.

PDF page 3

3

comprehensive market reforms that address systemic issues.” However, it seems these remain on the side-lines or are bogged down in endless debates in the stakeholder process. MAREC Action and SEIA applaud PJM for their recent commitment to exploring capacity market reforms,5 but we urge PJM to ensure that this is not an empty commitment. As PJM pursues these reforms, it must do so with the input of its stakeholders and it must be transparent in its choices.

A. Recommendation: The Board and PJM should work with stakeholders to
identify initiatives and develop an annual priorities plan.
Identifying initiatives and then setting annual priorities is fundamental to any organization. The Board and PJM staff need to work with stakeholders to identify critical needs and then prioritize the work. PJM has conducted some of this type of priority planning in the past but then failed to hold to those priorities. To be fair, the constant putting out of fires has interfered with this. However, if many of the long-time fundamental issues were identified earlier and worked on more holistically, the fires would not be as critical. Addressing these emergency needs must be done in the context of longer-term priorities. PJM just released a new strategy document, Shaping a Powerful Change, PJM Five-Year Strategy.6 While this is a start, the document is high-level and lacking in actionable elements. We hope that more is to come in the form of an actual roadmap and workplan outlining the detailed policies and procedures that should be prioritized and worked.

PJM need only look to its fellow Regional Transmission Organizations (RTOs) to see good examples of annual prioritization exercises and plan development. In the Midcontinent

5 See PJM Interconnection, L.L.C., Powering Reliability Through Market Design, May 6, 2026, https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability- through-market-design.pdf.
6 See PJM Interconnection, L.L.C., Shaping a Power Change, PJM Five-Year Strategy, August 2026. https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260819-shaping-a-powerful- change-pjm-five-year-strategy.pdf

PDF page 4

4

Independent System Operating, Inc. (MISO), Reliability Imperatives set the direction on an annual basis. “MISO, its members, and its states have a shared responsibility to address the urgent and complex challenges facing the electric grid. We call this the Reliability Imperative.”7 The Reliability Imperative Report (last updated in February 2026) is a living document created in collaboration with all stakeholders to outline strategic priorities. The report evolves, assesses, and responds to the Reliability Imperative.8

Southwest Power Pool, Inc. (SPP) has a Strategic Plan and Strategic Roadmap. The first strategic plan was launched in 2021, Aspire 2026.9 It was a five-year plan covering 2021-2026 that “sought to strengthen regional reliability, advance market development, and prepare its region and business for the challenges and opportunities that lay ahead.”10 Earlier this year, SPP released the 2027-2031 Strategic Plan,11 which will define SPP’s activities over the next five year. Complementary to, and aligned with, the Strategic Plan is the Strategic Roadmap that outlines the activities required to meet the goals of the Strategic Plan.12

Every year starting in January, the California Independent System Operator, Corp. (CAISO) conducts an Annual Policy Initiatives Catalog and Roadmap Development Process that “prioritizes and sequences market design enhancements by soliciting policy initiative proposals from stakeholders, assessing stakeholder support for proposed policy initiatives, and

7 Midcontinent Independent System Operator, Inc., Corporate Strategy, Reliability Imperative, https://www.misoenergy.org/meet-miso/MISO_Strategy/.
8 MISO, 2026 Reliability Imperative Report, February 2026, https://cdn.misoenergy.org/2026%20Reliability%20Imperative%20Report744320.pdf. 9 See SPP, Aspire 2026 July 14, 2021, https://www.spp.org/documents/65050/spp%20strategic%20plan%202021- 2026.pdf.
10 SPP, Strategic Plan, https://www.spp.org/about-us/strategic-plan/.
11 See SPP, Powering Progress Forward, https://www.spp.org/documents/76666/2027- 2031%20strategic%20plan.pdf.
12 SPP, Roadmap, https://www.spp.org/stakeholder-center/spp-roadmap/.

PDF page 5

5

documenting a work plan, called the roadmap, for future policy initiatives.”13 This year, CAISO bifurcated its annual stakeholder process to create the 2026 Market Policy Catalog and Roadmap14 and the 2026 Infrastructure Policy Catalog and Roadmap.15 These tracks prioritize and sequence 2027-2029 market design and transmission enhancements based on stakeholder proposals and CAISO strategic goals.

B. Improvements to Board Transparency
1. Recommendation: The Board should host open meetings, publish roll
call votes, and issue decisional memos with their directives.
PJM’s Board meetings are closed. Cursory, high-level minutes of those meetings are provided after the Board meetings. This is not indicative of good governance. Transparency measures must be implemented to ensure that Members, States, and other stakeholders can engage effectively and meaningfully with the PJM Board. Essential transparency measures include open Board meetings, published roll call Board votes, detailed Board meetings minutes that show the rationale for the Board’s vote, and decisional memos between the Board and PJM Staff.

2. Recommendation: Board members should schedule regular meetings
with Members, States, and Stakeholders.
Access to the Board would be another important step towards good governance. Although the Board meets with the Liaison Committee and has private meetings with the Organization of PJM States, Inc. (“OPSI”) Board three times a year, these meetings are not

13 CAISO 2026 Annual Policy Initiatives Catalog and Roadmap Development Process, https://www.caiso.com/notices/2026-annual-policy-initiatives-catalog-and-roadmap-development-process--call-on- 1-15-26.
14 Id.
15 CAISO, 2026 Infrastructure Policy Catalog and Roadmap Process, https://stakeholdercenter.caiso.com/RecurringStakeholderProcesses/2026-Infrastructure-policy-catalog-and- roadmap-process.

PDF page 6

6

enough. The Board should schedule regular meetings with Members, States, and Stakeholders, along with detailed minutes of the meetings. Transparency of Board actions, as described above, coupled with access to the Board, will more closely align accountability with responsibility.

II. Recommendation: Consider moving to an advisory voting system.
As stated repeatedly throughout this proceeding, the PJM stakeholder process has become slow and unfocused. There are tools to speed up the process, like the Critical Issue Fast Path which is used to address “time-constrained major issues or existing work efforts that have not achieved, or are unlikely to achieve, consensus.”16 But, as PJM noted in its pre-conference comments, the CIFP has recently resulted in failures to achieve any sort of consensus in a timely manner.17 Such failures will likely continue to happen, since controversial issues cannot move forward without frustrating one group or another. PJM leadership and the Board must be empowered to make difficult decisions. Member advisory voting grants that power. As a practical matter, moving to an advisory voting structure does not change the status quo. According to PJM, “PJM and its stakeholders reach consensus on the majority of issues considered.”18 And with respect to the CIFP process, the votes are already advisory.19 The recommendations made in this proceeding will likely lead to more supported, and sustainable, proposals in the longer-term. However, in the near-term, PJM will be forced to make hard decisions, and it must have the ability to act quickly and decisively. By moving to a member

16 PJM Manual 34, Sec. 8.6.4, https://www.pjm.com/pjmfiles/directory/manuals/m34/index.html#Sections/Section_8_Consensus_Based_Issue_Res olution_at_the_Standing_Committee_Level_other_than_the_Senior_Standing_Committees.html.
17 See PJM Comments at 4; see also Jacob Finkle comments calling the recent CIFP a failure.
18 Prefiled Statement for Panelists from PJM Interconnection, L.L.C., for the PJM Governance and Stakeholder Reforms Technical Conference at 1 (“PJM Comments”).
19 PJM Manual 34, Sec. 8.6.4, https://www.pjm.com/pjmfiles/directory/manuals/m34/index.html#Sections/Section_8_Consensus_Based_Issue_Res olution_at_the_Standing_Committee_Level_other_than_the_Senior_Standing_Committees.html.

PDF page 7

7

advisory voting, PJM leadership and the Board can move forward without being bogged down by a drawn out, and as of recently, often-failing stakeholder process.

This advisory structure should not be viewed in isolation; it is one component of a broader set of reforms needed to make PJM’s stakeholder process more effective and responsive and if this change is made it needs to be combined with the reforms discussed below.

III. The PJM stakeholder process is in dire need of reform.
Over the years, the process has become slow, unfocused,20 and polarizing.21 The recommendations below would help create a stakeholder process that will ensure robust proposals that address concerns by different sectors and allow PJM to move quickly to address emerging issues.

A. Recommendation: At beginning of stakeholder process, PJM staff should establish the objectives any proposed solution must satisfy and what solutions cannot be entertained.

MAREC Action and SEIA appreciate that PJM leadership welcomes multiple viewpoints throughout the stakeholder process. Hearing from a wide range of stakeholders can create reforms that accomplish PJM’s goals while also reflecting operational realities and market needs. But PJM and its stakeholders should not be spending hours discussing proposals that have elements that cannot be implemented because they are operationally infeasible. To create meaningful reforms, PJM needs to refocus stakeholders on what solutions can be pursued. At the start of each stakeholder process, PJM must clearly define the problem they are seeking to solve, the timeframe for action, and any operational limitations that may limit solutions. PJM issue charges and problem statements do define the problem, set the timing, and

20 Pre-filed Statement of Glen Thomas, President of PJM Power Providers Group at 4 (P3 Comments).
21 PJM Comments at 3.

PDF page 8

8

define what is out of scope.22 However, the issue charge could be more precise. Instead of “intermediate,” “near term,” and “far term,” timelines should identify when the proposal would be filed at the Commission or when an appropriate Manual change will be made, such as “Q1 2027,” or “before December 31, 2026.” Further, while issue charges do outline what is “out of scope” in a proceeding, they do not reflect when a potential solution that is in scope may not be available because of operational limitations. To the extent possible, PJM should identify these issues upfront. If PJM cannot, then it must have discretion to edit proposals throughout the stakeholder process, by removing part of, or the entire proposal, from consideration. PJM staff must be able to state that a particular proposal is not operational and thus cannot be implemented.

A successful stakeholder process is one that sets forward clear guidelines earlier in the process and constant editing during the process. PJM must be clear in what it needs to accomplish, what it can do to meet those goals, and acknowledge where it does not have sufficient knowledge about a problem or market segment.

B. Recommendation: PJM should provide a pathway for written comments and
questions on proposals that are publicly posted to a central location.
Several panelists noted in their pre-filed comments that stakeholder meetings are sometimes derailed for multiple hours by a small number of participants engaging in extended, unfocused discussion.23 In order to get in feedback, stakeholders are forced to resort to other pathways to get PJM’s attention. Comments during stakeholder meetings, side conversations in

22 See e.g. Hybrid Resources Market Model Selection, Issue Charge, https://www.pjm.com/- /media/DotCom/committees-groups/committees/mic/2026/20260805/20260805-item-04-2---hybrid-resources- market-model-selection---issue-charge.pdf.
23 Pre-filed Statement of Susan Bruce, Counsel for PJM Industrial Customer Coalition at 17 (“PJM ICC Comments”).

PDF page 9

9

the hallways of Valley Forge, and unpublished emails to PJM staff should not be how PJM works with stakeholders to answer questions about its proposals and modify proposals to address legitimate stakeholder concerns. These pathways lack clarity and transparency. It also prevents PJM from hearing from critical voices that may not be able to be in the hallways during the plethora of  meetings.

While focusing stakeholder discussions, PJM should provide opportunities to provide written feedback on its proposals. PJM does, sometimes, provide for the opportunity to submit written feedback, however, these requests for feedback are often late in the process and comments are not always posted publicly. Further, there is little formality to the process, leaving stakeholders to guess as to when, or even if, PJM will accept written feedback. MAREC Action and SEIA recommend that PJM establish stakeholder feedback processes like those of the Midcontinent Independent System Operator, Inc. (MISO) and the California Independent System Operator, Corp. (CAISO). Both MISO and CAISO have dedicated pages on their websites where stakeholders can submit written feedback and ask clarifying questions.24 Both MISO and CAISO provide written responses to that feedback. And both MISO and CAISO seek out that feedback early and often in the stakeholder process, allowing them to acknowledge where there are gaps in their understanding.

In providing for written feedback, PJM can hear from, and respond to, voices that may be drowned out during stakeholder meetings. Further, it allows stakeholders to coordinate with each other and find common ground on proposals, ultimately leading to more supported proposals.

24 See e.g. MISO, LLWG: Generation and Large Load Alignment, Stakeholder Feedback, https://www.misoenergy.org/engage/stakeholder-feedback/2026/llwg-generation-and-large-load-alignment-llwg- 2026-6-20260716/; see also CAISO Initiative: Day-ahead market enhancements, https://stakeholdercenter.caiso.com/StakeholderInitiatives/Day-ahead-market-enhancements.

PDF page 10

10

C. Improvements to polling:
Because MAREC Action and SEIA are recommending that PJM consider moving to an advisory voting structure, the remaining recommendations in this section reflect changes to the polling process to allow PJM to gain more insight into the potential market impact on their tariff proposals.

1. Recommendation: Throughout the process, PJM should conduct
polling on specific elements of its proposals.
In addition to gaining critical input through written comments, PJM should seek input on individual elements of a proposal, and should do so early and often throughout the stakeholder process. Polling reports should be divided out by sector and by business type. Voting on entire proposals could result in situations in which small, but impactful elements of a proposal are voted down because they are attached to a proposal that has elements that are unworkable to certain market participants. Polling specific elements of a proposal will allow PJM to understand what changes are necessary to develop a more supportive, and therefore more successful, proposal.

2. Recommendation: When polling members, PJM should reflect poll
results with more granularity.
MAREC Action and SEIA’s member companies participate in PJM as generation
developers. Generation developers are spread between two different sectors: the Generation Owner sector and the Other Supplier sector. This split is because the Operating Agreement differentiates between incumbent resource owners, which are part of the Generation Owner

PDF page 11

11

sector,25 and non-incumbent resource owners, which are relegated to the Other Supplier sector.26 The Other Supplier sector also serves as a catch-all sector, serving as the sector for any company that does not fit within the requirements of the other sectors.27 Not only does this sector include non-incumbent generation developers, it includes financiers, power marketers, demand response aggregators, and consultants that specialize in representing wholesale market participants.28 While PSEG is technically correct when it notes that “the Generation Owner and Other Supplier sectors had less than half of their membership in attendance” at the most recent CIFP for Large Loads,29 the statement failed to consider that such a small percentage of the sectors voted in the recent CIFP because the proposal is likely only relevant to that small percentage.

PSEG’s statement reveals an underlying problem with the current sector structure: The sectors no longer reflect the diversity of stakeholders in PJM. This is not surprising. The sectors were established more than 25 years ago, as part of PJM’s Order No. 2000 compliance filing.30 And the qualifications for the sectors have not changed since. Over that time, PJM has shifted greatly. More independent power producers entered the market. Developers shifted from coal to gas to renewables. Distributed resources gained access to the wholesale markets.31 Large customers are shifting from traditional manufacturing to data centers that are both larger and

25 PJM Operating Agreement, Sec. 1, Definitions (defining Generator Owner as a resource shall have cleared an RPM auction and has a Commission-jurisdictional interconnection agreement or wholesale market participation agreement.)
26 PJM Operating Agreement, Sec. 1, Definitions (defining “Other Supplier” as a member that “(i) is engaged in buying, selling or transmitting electric energy, capacity, ancillary services, financial transmission rights or other services available under PJM's governing documents in or through the Interconnection or has a good faith intent to do so, and” (ii) is not otherwise part of another sector.)
27 Id.
28 https://www.pjm.com/about-pjm/member-services/membership-enrollment/full-member-enrollment
29 PSEG Comments at 8.
30 Pennsylvania-New Jersey-Maryland Interconnection, 81 FERC ¶ 61,257, 62,262 (1997) (“The Members Committee will consist of 5 sectors representing generation owners, other suppliers, transmission owners, electric distributors, and end-use customers.”)
31 Participation of Distributed Energy Resource Aggregations in Markets Operated by Regional Transmission Organizations and Independent System Operators, 172 FERC ¶ 61,247 (2020) (“Order No. 2222”).

PDF page 12

12

have different load profiles. The current sector structure never contemplated these market shifts and as a result, votes today do not tell the whole story of the industry impacts of a tariff change.

For PJM to get a better understanding of the impacts of its proposals, MAREC Action and SEIA recommend that, as PJM conducts polls, which again, should be early and often, PJM should reflect not just the sectors in the polls, but various lines of business as well. PJM does reflect the various lines of business in its voting reports, which are posted several days after the vote is conducted,32 but because these votes are conducted so late in the process, the voting results do little to provide PJM with any insights into what changes need to be made to the proposal to address industry concerns. Further, recent polls show that PJM does not delineate between lines of business.33 In order to reflect the lines of business in polling, MAREC Action and SEIA recommend that PJM adopt the categories of lines of business reflected in the voting reports.34

MAREC Action and SEIA do not recommend that PJM revise the Operating Agreement
to redefine the sectors, as more research would be necessary to fully define those sectors. Such a change is not necessary for PJM to modify its polling to capture and reflect industry feedback in a way that provides a better understanding of the impacts of its proposals.

32 See e.g. PJM Members Committee, Voting Results, Connect and Manage, at 6 (June 30, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/committees/mc/2026/20260630-special/mc-voting- results---agenda-item-3a---pjm-cm-proposal.pdf (showing the voting results broken down by line of business in PJM).
33 See PJM, Governance and Stakeholder Process Poll Results (Aug. 12, 2026), https://www.pjm.com/- /media/DotCom/committees-groups/committees/mc/2026/20260819/20260819-item-10---1-governance-and- stakeholder-process-poll-results.pdf; see also PJM, CIFP - Reliability Backstop Procurement / Connect & Manage Summarized Poll Results (July 16, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/postings/cifp-poll-results-with-comments.pdf.
34 See PJM Members Committee, Voting Results, Connect and Manage, at 6 (June 30, 2026), https://www.pjm.com/- /media/DotCom/committees-groups/committees/mc/2026/20260630-special/mc-voting-results---agenda-item-3a--- pjm-cm-proposal.pdf (reflecting the following lines of business: Ancillary Service Provider, Consumer Advocate, Curtailment Provider, Financial Trader, Industrial Customer, IOU, IPP, Project Developer, Public Power, Retail Marketer, and Wholesale Marketer).

PDF page 13

13

IV. Strengthening State Participation in the PJM Stakeholder Process
State retail regulators have a statutory responsibility to ensure resource adequacy at the lowest reasonable cost and are directly accountable to consumers for retail electricity rates. Yet many of the rules governing resource adequacy are developed through the PJM stakeholder process, in which state regulators lack a formal role sufficient to effectively advance and implement their solutions. This disconnect between state responsibility and stakeholder authority should be addressed by strengthening the states’ role in PJM governance.

MAREC and SEIA support reforms that would provide states, through OPSI, with a more meaningful and actionable voice in the PJM stakeholder process. Specifically, PJM Transmission Owners should make Section 205 filings on OPSI’s behalf when OPSI reaches consensus on cost allocation methods for regional transmission projects. In addition, if PJM is given authority to make unilateral Section 205 filings, PJM should also be required to make filings on OPSI’s behalf regarding regional transmission planning.

These changes would better align PJM’s governance structure with practices already in place in other RTOs. More importantly, these changes recognize the states’ statutory responsibilities and ensure that the economic regulators accountable to retail consumers have a meaningful, effective, and actionable voice in the PJM decisions that directly affect them.

PDF page 14

14

V. Conclusion
As the Commission, PJM, and stakeholders move through this dispute resolution process, MAREC and SEIA request that these recommendations are reflected in the reforms adopted in this proceeding.

Evan Vaughan,
Executive Director
MAREC Action
PO Box 3335
Silver Spring, MD 20918
(202) 431-4640
evaughan@marec.us
Melissa Alfano
Senior Director of Energy Markets and
Counsel
Solar Energy Industries Association
1425 K St NW Ste. 1000
Washington, DC 20005
(202) 566-2873
malfano@seia.org

PDF page 15

Appendix: List of Recommendations
Board Leadership and Transparency
1. The Board and PJM should work with stakeholders to identify initiatives and develop an annual priorities plan.

2. The Board should host open meetings, publish roll call votes, and issue decisional memos with their directives.

3. Board members should schedule regular meetings with Members, States, and Stakeholders.

Stakeholders voting rights
4. Consider moving to an advisory voting system.
Improvements to the Stakeholder Process
5. At beginning of stakeholder process, PJM staff should establish the objectives any solution must satisfy and what solutions cannot be entertained.

6. PJM should provide a pathway for written comments and questions on proposals that are publicly posted to a central location.

7. Throughout the process, PJM should conduct polling on specific elements of its proposals.

8. When polling members, PJM should reflect poll results with more granularity.