AD26-7-000 · 2026-08-21 · PJM Power Providers Group
Post-Technical Conference Comments and Responses of The PJM Power Providers Group re PJM Governance and Stakeholder Reforms
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Governance and Stakeholder Reforms
)
Docket No. AD26-7-000
POST-TECHNICAL CONFERENCE COMMENTS AND
RESPONSES TO COMMISSION QUESTIONS OF
THE PJM POWER PROVIDERS GROUP (P3)
The PJM Power Providers Group ("P3") submits these post-technical conference comments in response to the Federal Energy Regulatory Commission's ("Commission" or "FERC") July 30, 2026, Notice Requesting Post-Conference Comments in Docket No. AD26-7-000. P3 is a non- profit organization dedicated to promoting properly designed and well-functioning competitive markets in the PJM Interconnection, L.L.C. ("PJM") region. Combined, P3 members own and operate over 108,000 MWs of generation assets and produce enough power to supply over 63 million homes across 13 states and the District of Columbia.1
I. CORE GOVERNANCE PRINCIPLES
• Anchor All Reforms in Market Integrity & Merchant Capital Investibility: PJM's core mandate must remain operating robust, competitive wholesale markets that ensure reliability at the lowest reasonable cost. Governance reforms must not become a vehicle for compromising Regional Transmission Organization (“RTO”) independence or upending the stakeholder model. PJM's success hinges on attracting private merchant capital; reforms that introduce political volatility or regulatory uncertainty will damage investor confidence at a moment in time when investor confidence must be paramount.
• Uphold Section 205 Balance of Filing Rights: The division of Federal Power Act (“FPA”) Section 205 filing rights is a core structural feature of the PJM region. Suggestions to unilaterally broaden the PJM Board's or any state/stakeholder body's filing rights over matters traditionally
1 The comments contained herein represent the position of P3 as an organization, but not necessarily the views of any particular member with respect to any issue.
PDF page 2
reserved for Transmission Owners or the Members Committee risk destabilizing the careful balance struck in PJM. FPA Section 205 rights belong exclusively to jurisdictional service providers and cannot be involuntarily reallocated.
• Resist Expansion of Unilateral Board Authority: While the Board possesses necessary Tariff authority to act in true emergencies, unilateral action must remain an extraordinary tool. Routine expansion of unilateral Board authority erodes transparency, bypasses stakeholder expertise, and results in poorly formulated filings that burden the Commission and courts.
• Preserve Board Independence: Having an independent Board that is accountable to the mandate of the PJM Operating Agreement is essential to the integrity of the PJM mission. Where they are authorized to act, Board members should act in the best interest of the grid and the market after hearing input from PJM members and states. PJM’s mission is defined in the Operating Agreement and that should be the standard by which the Board is evaluated.
•
Respect Core Mission vs. Political Priorities: PJM sits at the crossroads of 14 jurisdictions with divergent policy goals. PJM's core mission is to reliably operate an interstate grid and dispatch lowest-cost resources via a competitive market. PJM must not be diverted from this mission and must remain focused on the market that serves state in the entire region.
II. RESPONSES TO SPECIFIC QUESTIONS IN APPENDIX
#
Question / Theme
P3 Position
Detailed Explanation & Justification
1
Should Board members' terms
be extended to five or more
years?
Yes
P3 believes the current three-year term is
too short and should be extended. Five-
year terms seem appropriate.
2
Should there be a maximum
number of years that a Board
member may serve (e.g., 10
years)?
Neutral
P3 does not have a strong view on term
limits.
3
Should Board member
qualification rules be revised
to provide a preference for
Yes
P3 supports a preference, but not a
requirement, that at least one board member
resides in the PJM footprint.
PDF page 3
some Board members that
reside in the PJM region?
4
Should conflict-of-interest
rules be revised to reduce the
cooling off period for Board
members from two years to
one year?
Yes
P3 believes that a one year cooling off period is sufficient and will widen the pool of qualified candidates.
5
Should restrictions on Board
communications be relaxed to
enable more communication
between the Board and
stakeholders?
Yes
P3 appreciates the efforts that the Board has made in recent years to increase
communications with stakeholders
including the Liaison Committee and Board participation at the Members Committee meeting. That said, any revised rules should not allow for preferential access by any particular constituency.
6
In order to increase
transparency, should Board
votes be made public or the
Board be required to explain
its reasoning?
Yes
Written explanations for major tariff or policy decisions enhance regulatory
transparency, can provide crucial market clarity, and build confidence among market participants and investors. P3 is not yet prepared to endorse disclosure of specific board member votes which could
undermine Board independence.
7
In order to increase
transparency, should some
Board meetings be open or
available to the public?
Yes
If done properly, opening non-confidential, strategic Board sessions to public
observation fosters trust and alignment. Confidential executive sessions should remain for market sensitive rule changes, proprietary, personnel, or legal matters. 8
Should PJM's governing
documents be revised to
explicitly state that the
responsibility of PJM and its
No
PJM's core mandate is to operate an
interstate grid and robust competitive markets under the Federal Power Act. 'Public interest' is an ambiguous, ill-defined standard in wholesale market governance
PDF page 4
Board is to serve the public
interest?
that risks politicizing decisions and forcing PJM to balance conflicting state social policies rather than focusing on market efficiency and reliability. The PJM Board should not be responsible for determining what is in the “public interest” for the 13- state PJM region. Also, on August 19, the PJM members approved a change to the PJM Operating Agreement that makes clear that the PJM market should be designed and operated for the benefit of consumers. 9
Should state representatives
have at least one voting
member on the Nominating
Committee?
Potentially.
P3 supports state participation in the Nominating Committee, however, given the unique nature of public officials
participating in a very sensitive process, PJM members need to be comfortable that states can participate without undermining the integrity of the Nominating Committee process. P3 believes that the best path forward is to allow a state representative to observe and understand the Nominating Committee process before determining whether a state voting role is appropriate and desired by the states.
10
Should PJM adopt public
performance metrics and tie
management compensation to
their achievement?
No position.
P3 does not understand what is meant by “public performance metrics,” but as a general matter feels that management compensation is a matter between the PJM Board and PJM management.
11
Should the stakeholder
process be advisory, i.e.,
stakeholder votes only inform
the Board?
No
Demoting the stakeholder process to purely advisory status would damage market
participant engagement and investor
confidence and is inconsistent with the governance balance struck in PJM as
discussed above. Sector-weighted voting
PDF page 5
provides critical commercial discipline and ensures well-vetted proposals reach FERC. 12
Should PJM have section 205
filing rights over energy and
ancillary services
unencumbered by the 2/3
Members Committee
approval?
No
FPA Section 205 filing rights belong strictly to jurisdictional entities providing market services. Unilaterally granting PJM unencumbered filing rights over
energy/ancillary services upsets the balance and bypasses essential stakeholder review. 13
Should PJM have section 205
filing rights over Regional
Transmission Expansion
Planning (RTEP)
unencumbered by 2/3
Members Committee
approval?
No
Transmission planning involves massive capital allocations and cost shifts across states and market participants. Retaining required stakeholder oversight and
protecting Transmission Owners' statutory rights prevents unvetted, costly expansion mandates.
14
Should OPSI have 'jump ball'
rights over resource adequacy
and transmission cost
allocation filings when a
supermajority of OPSI agrees?
No
Granting 'jump ball' filing rights to state regulators violates Section 205 of the FPA, which reserves filing rights exclusively to jurisdictional public utilities. Litigating this question is in no one’s best interest so it should not be pursued.
15
Should the Members
Committee have 'jump ball'
filing rights over portions of
the tariff where PJM has 205
rights when a supermajority
approves an alternative?
No
See comments above. The current
allocation of 205 rights in PJM is consistent with the Federal Power Act and the
introduction of “jump ball” rights in any form introduces legal questions that are best avoided.
16
Should the approval threshold
in the Members Committee be
lowered from two-thirds
sector-weighted voting?
No
The two-thirds sector-weighted voting threshold forces broad cross-sector
consensus, preventing any single sector or coalition from imposing harmful rules on others.
PDF page 6
17
Should the voting rules
barring affiliate votes, which
apply to senior standing
committees, also apply to
lower-level committees?
No position
P3 members have differing views on
affiliate voting in lower-level committees. 18
In addition to OPSI, should
there be a second state
representative group
consisting of governors'
representatives and/or state
legislators?
No
Creating a second state body would
duplicate efforts, confuse the stakeholder process, and further politicize technical market discussions. OPSI already serves as the recognized, effective liaison for state regulatory interests. P3 prefers that the PJM governors and commissioners unify under a single organization – which is our understanding of what is happening.
19
Should state representatives
have a formal voting role in
the stakeholder process
(limited to certain topics) in
addition to consumer advocate
votes?
No
State utility commissions act as regulators, not jurisdictional wholesale market
participants. Giving states direct voting rights creates potential conflicts of interest. Moreover, it is our understanding that states do not want voting rights in the Stakeholder process.
20
Should PJM be required to
consult with OPSI prior to
making a section 205 filing
related to resource adequacy
and transmission cost
allocation?
Yes
Consultation with state regulators via OPSI on critical resource adequacy and cost allocation matters is standard practice and enhances proposal durability. However, consultation must not amount to a state veto or delay urgent filings which would
undermine PJM independence. Nothing in the current rules prevents this consultation from occurring now.
PDF page 7
III. COMMENTS
The governance reforms under consideration in this proceeding cannot be evaluated in a vacuum. PJM stands at a critical juncture in its history, defined by unprecedented demand expansion and a generational transformation of the power fleet. Driven by the explosive growth of data centers and widespread electrification, electricity demand across the 13-state and District of Columbia footprint is growing at rates never seen.
At the same time, power developers are stepping up to meet this moment with extraordinary commercial interest. Today, over 55 GW of new generation capacity has already cleared PJM’s interconnection queue and stands ready for construction, while PJM's recent interconnection queue Cycle 1 saw a record-shattering wave of project applications totaling over 220 GW.2 Furthermore, PJM’s request for information for generation developers interested in serving large loads drew over 130 GW of developer proposals eager to contract directly with new energy-intensive customers.3
The overwhelming regulatory mandate facing PJM and the Commission is clear: the region must turn its immediate, undivided focus toward executing contracts for new supply, establishing clear federal and state rules related to the integration of large loads, expanding transmission capacity, and delivering power reliably to the grid. Meeting this challenge will require billions of dollars in private, at-risk merchant capital and it is axiomatic that investor capital flows where regulatory and market rules are predictable, stable, and transparent.
Distracting PJM, state regulators, and market participants with prolonged structural governance debates—or worse, adopting governance changes that politicize PJM Board decisions, dilute sector-weighted voting, or destabilize FPA Section 205 filing rights—risks fracturing investor confidence at the exact moment it is needed most. PJM’s existing market structure and stakeholder
2 PJM recently announced that 200 GWs advanced to the next step and are qualified to be studied. See, https://insidelines.pjm.com/over-700-new-generation-projects-accepted-into-first-cycle-of-reformed- interconnection-process/3 See, https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260527/20260527-informational- only---reliability-backstop-rfi-summary---charles-river-associates.pdf.
PDF page 8
model have proven their resilience through prior energy transitions. Recent challenges are more reflective of decisions within the governance structure, which includes a large role for the Commission, rather than a flaw in the governance structure itself. Rather than upending a governance framework that largely works despite some imperfections, the Commission and PJM should maintain market integrity, preserve core negotiated and statutory balances, and stay focused on the monumental work of ensuring grid reliability and market efficiency for the millions of consumers PJM serves.
IV. CONCLUSION
WHEREFORE, for the foregoing reasons, P3 respectfully requests that the Commission take these comments and responses to the Commission’s specific questions under consideration in taking any further action with respect to PJM’s governance and stakeholder processes.
Respectfully submitted,
The PJM Power Providers Group
By: /s/ Glen Thomas__________
Glen Thomas
Laura Chappelle
GT Power Group
101 Lindenwood Drive, Suite 225
Malvern, PA 19355
gthomas@gtpowergroup.com
(610) 768-8080
Dated: August 21, 2026