AD26-7-000 · 2026-08-21 · Sierra Club, Natural Resources Defense Council and 3 others
Comments of Sierra Club et al. re PJM Governance and Stakeholder Reforms
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, LLC
)
Docket No. AD26-7-000
Comments on PJM Stakeholder Governance Reform
of Public Interest Organizations
Introduction
FERC’s July 23rd Technical Conference was a Constitutional Convention for PJM, the need for which we have seen evinced time and again in this most recent year of upheaval. Indeed, the first-of-its-kind Multi-state Summit on the State of PJM, held last September at the National Constitution Center, featured calls for such an event from across the political and stakeholder spectrum. We applaud the Commission’s timely attention to the problems plaguing PJM’s current governance structures, and focus on identifying substantive solutions, fast.
As we celebrate 250 years since our nation’s founding, we must credit the institutional ideals and governing documents that underpin America’s longevity. Today, with electricity such a critical part of a functional, modern society, our grid governance requires a similar North Star to guide us. Nowhere is that need more evident than in PJM, our nation’s largest and longest-standing regional grid, which, as Chair Swett well noted, is facing “a grave legitimacy crisis.” PJM is also approaching a momentous anniversary – its 100th birthday – and we must ensure the RTO sets itself up to thrive for the new century to come. We are ready to work with PJM and stakeholders to do so.
Our organizations – RMI, Sierra Club, Earthjustice, Natural Resources Defense Council, and Southern Environmental Law Center (collectively “Public Interest Organizations”) – represent a coalition of regular participants in the PJM stakeholder process. Many of the undersigned organizations are members of the PJM Public Interest Environmental Organization User Group (PIEOUG). While other signatories are not members of the PIEOUG, all of the undersigned organizations are participants in PJM stakeholder processes and are affected by PJM’s governance practices. For all of us, PJM governance issues have been a long-standing concern that have impacted our efforts, and we value the opportunity to respond to the specific issues raised at the conference.1 We are encouraged to see the issues so clearly identified by the Commission for further public comment. We look forward to continued dialogue in the Dispute Resolution Service process and building on PJM’s proposal.
Before addressing the questions individually, we introduce our principal concerns and remedies for PJM’s governance:
1 Simeone, Christina. Kleinman Center for Energy Policy. 2017. “PJM Governance: Can Reforms Improve Outcomes?” Report. Available at https://kleinmanenergy.upenn.edu/research/publications/pjm-governance-can-reforms-improve-outcomes/ 1 of 17
PDF page 2
First, PJM must embed the public interest within its governance structure. By public interest, we are thinking expansively about the interests of the 67 million people who reside and pay electric bills in the PJM region, as well as the region’s businesses – large and small. Making a commitment to the public interest explicit is key, and underpins many of the other contemplated changes. Three specific reforms would help achieve this end:
1. PJM’s governing documents should clearly state that the RTO has an obligation to serve the public interest. This idea is reflected in several pre-conference comments, including those of former FERC Chair Pat Wood.2 What’s more, other RTOs already do this, as Abe Silverman noted during the July 23rd event: MISO is set up as a 501(c)(4) organization “operated exclusively to promote social welfare,” while CAISO is set up as a “nonprofit public benefit corporation.”3
2. It is equally critical that the PJM Board, leadership, and staff maintain an orientation towards serving the public interest, and not merely PJM members. The Independent Market Monitor, Joe Bowring, emphasized this in his conference remarks, noting not only the importance of the Board acting in the public interest, but also their directing PJM leaders and staff to do the same.4 Pat Wood suggests adopting public annual performance metrics, and tying compensation to their achievement, as in MISO. We agree that performance metrics linked to ensuring that PJM leadership serves the public interest would offer value in the form of both clearly defined outcomes and accountability in pursuing them.
3. Finally, explicit inclusion of the public interest in PJM’s mission would necessitate a more substantive and formal role for states and consumer advocates within the stakeholder process, as representatives of the public. The breadth and diversity of state voices in the PJM region presents both challenge and opportunity in this regard, but the need for a stronger voice is real. Pat Wood notes that, among the four multi-state RTOs, he views PJM states’ voice within stakeholder and decision-making processes as “the most muted.” We therefore see merit to the idea of a PJM States’ Committee on Electricity (PJM-SCOE), with defined rights that could include issue identification and prioritization via a direct channel to the Board, consultative authority (particularly around matters regarding resource adequacy, over which states have significant
responsibilities), and jump ball filing rights.5
Centering the public interest is urgently needed to address the growing energy affordability concerns affecting many American families. Polling by Third Way recently found that one in four Americans say they already struggle to pay their utility bills, and another 40 percent said they would have difficulty paying if costs increased further.6 Meanwhile, in July, the average US residential electric bill hit a record of $217 – with some of the biggest price
6https://www.thirdway.org/memo/asking-americans-whats-causing-high-energy-prices-and-how-do-we-fix-it5 Further details on how this body could function within existing structural and decision-making processes are provided within the detailed question responses (specifically questions 18 and 19).4 Comments by PJM Independent Market Monitor, Joe Bowring, ibid.3 Comments by panelist, Abe Silverman, Johns Hopkins, July 23rd, FERC Technical Summit on PJM Stakeholder Governance, https://www.ferc.gov/news-events/events/PJM-Governance-Stakeholder-Reforms2 Pre-conference comments by Pat Wood, July 2026, posted on personal platform, available at https://lnkd.in/p/e8BJsVjV 2 of 17
PDF page 3
spikes occurring in the mid-Atlantic.7 The price of electricity cannot continue to be a source of financial strain for the majority of Americans, or PJM residents. To address this growing issue, PJM should adopt cost impact analyses to evaluate many of the proposed rule changes and reforms it is contemplating today, to ensure they do not further exacerbate (and ideally mitigate) these rising price pressures. This is just one public interest issue among several that would be better addressed by an RTO where these concerns are core to the mission.
Second, PJM must remedy the dysfunction of its current stakeholder process. We have participated in enough PJM committee and task force meetings to be able to say with certainty that they leave much room for improvement, as DOE Deputy Secretary Danly similarly raised in his opening remarks.8 Meetings are frequently side-tracked and bogged down by unwieldy question/comment queues, and lack the requisite procedural and decision-making structures to promote meaningful dialogue. Instead, obfuscation and grandstanding proliferate. Unresolved disputes, outstanding questions, and lack of clarity on future direction are common at meetings’ end, even if the meeting has taken up an entire day. The end result of this is an inability to act, even when issues demand immediate attention.
The CIFP process (which literally has “Fast Path” in the name) initiated by the PJM Board last August is a case in point: set up to yield a decision by the end of 2025, it instead resulted in a dozen or so solution proposals, an inconclusive vote at year’s end, and a second round of CIFP stakeholder discussions initiated early this year, continuing into summer 2026. After PJM stakeholders debated – inconclusively – what to do for nearly a year, the issue of large load integration is just now approaching resolution, with serious implications for the capacity prices and reliability threats the region is facing. To fix this, PJM must address two tandem types of reform: structural changes and administrative/operational enhancements.
Structural changes
1. At the highest level, this entails a shift to an advisory stakeholder structure. The stakeholder process has become dominated by incumbent interests and far too prone to inertia and delay. By removing decision-making authority from the collective stakeholder body, the incentive to stonewall or slow-walk needed changes (especially insofar as they preserve the current status quo or protect incumbents) is lessened, and the whole process stands to become more streamlined and collaborative. Former FERC Chair Mark Christie recently noted that “those who stand to profit from the rules should not be writing them.” 9 We agree. We acknowledge that this shift might entail corresponding reforms to ensure efficacy, for which we provide more detailed thoughts in our response to question 11 below.
2. Streamline the committee structure and meeting schedules. PJM has altogether too many meetings, and an overhaul could facilitate more cohesive, transparent, and accountable decision-making around a set of prioritized issues for stakeholders to be 9 Former FERC Chair Mark Christie, personal comments via Linkedin on the FERC technical summit on PJM governance, July 24th, 2026, available at: https://lnkd.in/p/gPdJRYfe8 Comments by guest speaker James Danly, DOE Deputy Secretary, July 23rd, 2026, FERC Technical Summit on PJM Stakeholder Governance, https://www.ferc.gov/news-events/events/PJM-Governance-Stakeholder-Reforms7https://heatmap.news/sparks/average-electricity-bills-july-2026 3 of 17
PDF page 4
considering at a particular time. As one specific example, a “shot clock” or clear sunset dates should be added to stakeholder deliberations. While the timing could be varied based on the complexity of the issue, we propose a deadline of a year for coming to resolution on bigger issues, and a 6-month process for smaller issues to be resolved. Embedded in this structural reform must be a recognition that when the time for decision-making expires (i.e., the end of a CIFP window), then the decision must be made, not the process extended.
3. PJM should refresh and rebalance its stakeholder sectors, to correct for imbalances in representation that we see present in the PJM stakeholder community today. The number of sectors should be expanded to reflect the growing diversity of PJM’s members, and voting shares must accordingly be updated. As a first order, consider provisions for the creation of new sector(s) to reflect specific stakeholder member groups. For example, a “public interest sector” should be created that offers an accessible, expanded participation role for organizations such as ours, many of which have contributed meaningfully to stakeholder discussions for years.10 Additionally, distributed energy resources and demand response providers, as a unique type of market participant, could benefit from their own sector. In ISO-NE, NEPOOL’s industry sectors include “Alternative Resources,” designed to provide a voice for distributed generation and other emerging technologies. There is also precedent for an expanded number of stakeholder sectors in MISO, which has 11 sectors, including one specifically for environmental organizations.
Administrative and operational enhancements
1. Issue prioritization must become a core feature of the stakeholder process, as several noted during the Technical Conference. This will support both making most effective use of PJM staff’s valuable time, as well as giving PJM stakeholders the clarity and discipline they need to participate most effectively in informing issue resolution. The recently proposed stakeholder process for the Regional Organization for Western Energy (ROWE) – the result of collaborative discussion and a look across the existing RTO landscape in search of pitfalls and best practices – offers a compelling model.11 The process they describe for the annual development of an Issue Catalogue and Roadmap could support more focused stakeholder discussions for the PJM region. 2. The time is ripe to reconsider how input is solicited in the stakeholder process – in what form, and by whom.
a. To the question of form, greater reliance on notice and comment, as exemplified by CAISO, may be appropriate at times in PJM.12 PJM staff seem to be trialing this with the call for white papers recently announced as part of the Powering Reliability Through Market Design workshops, which we find to be a more compelling way of gathering informed input on this topic from an array of
12 CAISO Stakeholder Center, “Policy initiatives and stakeholder process” and December 2025 Stakeholder Process Guide, available at https://www.caiso.com/documents/stakeholder-process-guide.pdf11https://www.westernenergyboard.org/wp-content/uploads/JunePUBLIC_StakeholderProcessNarrative.pdf10 This includes sponsoring issue charges, crafting solution proposals, and working collaboratively with PJM members and staff on an array of issues, from the recent CIFP discussions, to surplus interconnection service enhancements, capacity market reforms, and more. 4 of 17
PDF page 5
stakeholders. Rules should also be established for the manner and timing of PJM response to such stakeholder contributions.
b. When it comes to who should be providing input, stakeholder representatives might offer a useful model, and here again the ROWE stakeholder process offers a promising example: they introduce the idea of a Stakeholder Representatives Committee, as a forcing mechanism for similar stakeholder types to coordinate and find alignment where possible.13 This would both streamline meetings by keeping attendance to more manageable numbers of directly affected and
engaged stakeholders, and spare PJM staff the job of parsing hundreds of perspectives in search of alignment that might prove elusive. Stakeholder representatives would be shouldering some of that responsibility themselves, and creating alignment from the ground up.
3. Finally, PJM meetings require internal facilitation reforms, as well as transparency and accessibility improvements. Based on some of our facilitation expertise, we see room for more structure and more diversity in the discussion formats that PJM uses; for example, more reliance on panels, and other forms of mediated, interactive dialogue, rather than presentations followed by lengthy Q&As that do not fully resolve questions. In addition, to support transparency and accessibility, PJM should post meeting transcripts or detailed summary notes, recordings, and votes on a better-organized PJM website.
The work that PJM is undertaking, and that FERC and a wide array of stakeholders now aim to shape, is critical to the ongoing success and ultimate functionality of the RTO in a rapidly changing world. As plainly stated by panelists at the technical conference, both sitting and former FERC commissioners, and across the stakeholder membership at PJM, things cannot continue as they are. We are grateful for the opportunity to weigh in as a collaborative of multiple members within a key PJM sector on how these reforms should take shape, and are excited for swift transition from strategy development to implementation this fall.
Responses to Individual Questions
Topic: PJM Board Independence
1) Should Board members’ terms be extended to five or more years? Yes
Comments:
We support five-year terms, but not longer. Longer Board terms will help Board members remain more independent, in the sense they are not subject to as frequent “re-election pressures,” and allow the Board to serve as a more stabilizing, decisive force. However, if the term extends too long, members may become too divorced from accountability, and the stakes of individual Board member elections too large. A five-year term would already put the PJM
13 Western Interstate Energy Board, West-Wide Governance Pathways Initiative, Draft Chapter 8: “ROWE Stakeholder Process,” August 14, 2026. Available at: https://www.westernenergyboard.org/wwgpi/ 5 of 17
PDF page 6
Board term as the longest of any RTO; the vast majority of RTOs cycle on a 3-year Board term.14 The term length cannot be considered in isolation, however. Individual members should be elected in a staggered fashion, to ensure some degree of continuity for serving Board members, and to prevent wholesale turnover and loss of institutional experience during the onboarding of any new Board member. Per the subsequent question, Board members should also be limited to a maximum service term, and a maximum of two (2) consecutive terms.
It is also important to set rules for the removal of Board members for cause, to mitigate against the risk that a longer Board term engenders. The Board should be set up to be self-policing in this way, such that a super-majority vote could remove a sitting Board member, and we also believe that a unanimous vote of the Nominating Committee should be able to effect a Board member’s departure.
2) Should there be a maximum number of years that a Board member may serve (e.g., 10 years)? Yes
Comments:
Setting a maximum number of years for Board service helps ensure the Board keeps up with the changing times. Too long a term duration could dampen the incentive to act quickly, and lock in perspectives that could become myopic. The change to the overall service limit should reflect the specifics of the extended term length. For example, if five years is chosen for a Board term, a reasonable limit would be ten (10) years, reflecting two consecutive terms. This is consistent with the proposal put forth by PJM themselves.15
In extenuating circumstances, Board members should be able to apply for an exemption to a term limit. The criteria for extenuating circumstances should be defined in coordination with PJM staff. Examples could include their ability to contribute unique or extraordinary perspective, unique insight into a PJM geography or subregion, or unique insight into a key aspect of business operations. A Board member should only be eligible for one application and approval for exemption. If a Board member applies for an exemption and is not approved, they are not eligible to apply again. Unless another alternative is brought forward, the approval should remain within the purview of the Nominating Committee, which currently oversees Board appointments. Further discussion is necessary on whether the Nominating Committee should be able to approve the exemption with or without the Member vote that typically follows a Nominating Committee appointment determination.
3) Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region? Yes
15 PJM, FERC Mediation Term Sheet, August 14, 2026, available at https://www.pjm.com/-/media/DotCom/committees-groups/committees/mc/2026/20260819/20260819-item-08---1-ferc -mediation-term-sheet.pdf14 PJM’s current 3-year term is consistent with other RTOs/ISOs. ISO-NE, CAISO, MISO, SPP all have 3-year Board terms, though re-election varies. NYISO directors (their board members) serve for 4-year terms, and are restricted to a maximum of three terms (totaling 12 years). 6 of 17
PDF page 7
Comments:
More specifically, we see value in stating a preference for a Board member (or members) from a state regulator and/or consumer advocate background in the PJM region. This would help to ensure that state regulatory and consumer perspectives are represented on the Board adequately. Implemented in this fashion, this reform also supports our prerogative of better centering the public interest across PJM governance structures.
4) Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year? No
Comments:
The conflict-of-interest rules are one of the few precautionary protections in place to ensure that PJM Board decisions are unencumbered by bias and prior loyalties. We see no justification or advantage to reducing the cooling off period.
5) Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders? Yes
Comments:
While some restrictions make sense and were enacted for a reason – to prevent undue influence – we worry the PJM Board has become too aloof to be able to discharge its duties optimally. Thus, while “relaxed” is a somewhat vague term to convey the nature of necessary reform, reform to current communications between Board and stakeholders offers potential benefit. As inspiration, we can look to examples from other RTOs:
1. MISO: MISO heavily funnels communication through an Advisory Committee and 11 distinct stakeholder sectors. Board communication is restricted outside of structured public updates or explicit board retreats. Under its updated governance guides, decorum and official channels are tightly policed by committee chairs.
2. SPP: SPP features a built-in Regional State Committee (RSC) made up of state utility commissioners. Because state regulators hold primary authority over cost allocations, SPP’s board communications are uniquely exposed to state political/regulatory viewpoints, requiring high transparency to ensure individual market participants are not frozen out of multi-state negotiations.
3. ISO-NE and NYISO: Both New England and New York utilize highly structured, formalized rules where the independent board acts as a separate entity from the stakeholder committees. Private communication regarding pending market rules or active appeals is generally prohibited; stakeholders must rely on formal, scheduled joint board-stakeholder symposia to air grievances collectively.
4. CAISO: Because CAISO manages a single-state grid but operates a multi-state Western Energy Imbalance Market (WEIM), it balances strict California state transparency requirements with broader western stakeholder engagement. Ex parte protocols are deeply influenced by whether a topic involves a CPUC docket or a FERC market filing.
7 of 17
PDF page 8
These demonstrate that there are ample ways that the communication between the Board and stakeholders could be different. One specific improvement we recommend is that the PJM Board annually invites sector(s) to sit down and discuss general sector concerns or consider educational materials. These regular-cadence meetings can offer an incredibly informative and important space for dialogue and relationship building. The PJM Board has historically and should continue to host these, however, they should be revised so that all sector-specific meetings are open to attendance by observers, including the media.
6) In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning? Yes
Comments:
If the Board is to be granted more decision-making authority, corresponding transparency and accountability enhancements are warranted. As the saying goes, with great power comes great responsibility, and stakeholders must be able to monitor and evaluate the extent to which the Board is discharging their responsibilities well. However, this question asks two things. ● First, should Board votes be made public: Yes, as a general rule, Board votes should be made public. This is a useful transparency measure, and, if Board members’ re-nomination worries are lessened due to longer term lengths, there should be little to fear from making votes on the record.
● Second, should the Board be required to explain its reasoning? Yes. Regardless of the public nature of the vote, the Board should be required to explain its reasoning; this is core to good governance and a reasonable requirement to ask of PJM’s leaders.
7) In order to increase transparency, should some Board meetings be open or available to the public? Yes
Comments:
Yes, as above, increasing transparency into Board proceedings offers meaningful improvements that will help (re)build trust in PJM leadership and the stakeholder process. Board meetings should be public, with limited exception for discussion on sensitive or confidential items, and any related private votes. This hybrid model is not new. PJM can look to other RTOs to see models of where this works. SPP MISO, ERCOT, and CAISO all practice a combination of closed and public Board meetings. At present, only NYISO and PJM have closed meetings. However, efforts to increase Board transparency cannot stop here.
PJM can go one step further and in adopting a primarily open (or hybrid) model, enhance some of the inefficiencies seen at other RTOs with similar practices. For example, in SPP, meetings may be characterized as open, and any stakeholder is allowed to register and attend to a point (i.e., when discussing confidential or sensitive information). However, the transition from open to closed meeting is not always clear on the meeting agendas, and without attending every meeting, one may not know that a portion of the meeting was closed at all. Explicit labeling (public/closed) in meeting agendas, and potentially creating a “hybrid” meeting designation in the PJM stakeholder event center would offer significantly improved clarity on what parts of a meeting are open (though again, the default should be most).
8 of 17
PDF page 9
8) Should PJM’s governing documents be revised to explicitly state that the
responsibility of PJM and its Board is to serve the public interest? Yes
Comments:
This is a linchpin reform, which could flow through to an array of additional governance and stakeholder process enhancements, and deliver materially better outcomes for the region. As noted in our introductory remarks, by public interest, we are thinking expansively about the interests of the 67 million people who reside and pay electric bills in the PJM region, as well as the region’s businesses – large and small. Making the obligation to serve the public interest (defined in this way) an explicit feature of PJM’s governing documents is key; it cannot merely be implied. Doing so is essential for enabling some of the other, complementary reforms envisioned, such as developing performance metrics for the Board and leadership, which could include accountability to public interest provisions. There is support for this idea in several pre-conference comments, including those of former FERC Chair Pat Wood. What’s more, other RTOs already do this, as Abe Silverman noted during the July 23rd event: MISO is set up as a 501(c)(4) organization “operated exclusively to promote social welfare,” while CAISO is set up as a “nonprofit public benefit corporation.”
This should also manifest as another attempt to update the PJM mission. An attempt was made to update the mission statement on January 27, 2026 that would have explicitly incorporated affordability and public interest language. The draft language read: “As the primary task, to ensure the safety, reliability and security of the bulk electric power system. [In addition], understand customer needs and deliver valued service to meet those needs in an affordable and cost-efficient manner. Create and operate robust, competitive and non-discriminatory electric power markets. Achieve productivity through the efficient union of superior knowledge workers and technology advances.” 16
While that update to the mission was not adopted, it serves as a blueprint for the type of thinking that needs to be encouraged to ensure the mission of PJM reflects not only affordability, but also the public interest. An example of a further updated mission statement that explicitly integrates both could be the following: “As the primary task, to ensure the safety, reliability, affordability and security of the bulk electric power system on behalf of the public interest…”
9) Should state representatives have at least one voting member on the Nominating Committee? Yes
Comments:
State representatives and consumer advocates should have a presence on the Nominating Committee. Specifically, we support the consumer advocate proposal to have one seat for a state executive branch appointee, one for a state regulator, and one for a consumer advocate. This is another reform that would help make the public interest a living value within PJM. 16 PJM Draft Mission Statement. Updated January 27, 2026 to include “an affordable and cost-efficient manner,” to the secondary objective, ultimately was not adopted. Draft language available at https://www.pjm.com/-/media/DotCom/committees-groups/user-groups/arrcug/2026/20260127/20260127-item-03---pj m-mission-statement---affordability-redline.pdf
9 of 17
PDF page 10
10) Should PJM adopt public performance metrics and tie management compensation to their achievement? Yes
Comments:
Tying executive leadership compensation directly to a series of performance metrics is industry best practice for many of the businesses and organizations that comprise PJM’s membership. Some combination of inability, lack of incentive, or unwillingness of current leadership to execute amidst complicated stakeholder headwinds has made itself evident. Without a clear nexus between PJM’s performance and direct consequences for leadership, it is unlikely that change will organically emerge.
Development of the public performance metrics should follow the work done in devising the FERC Order 1920 benefit metrics, which sought to holistically capture the value that wholesale markets offer the region. PJM (either at the Board or leadership level) should similarly be empowered to articulate performance metrics that recognize the holistic set of roles articulated in their own updated mission statement, in which they aim to address four objectives: 1. To ensure the safety, reliability and security of the bulk electric power system. 2. Understand customer needs and deliver valued service to meet those needs in an affordable and cost-efficient manner.
3. Create and operate robust, competitive and non-discriminatory electric power markets. 4. Achieve productivity through the efficient union of superior knowledge workers and technology advances.”17
Building on our response to Question 8, we would like to see inclusion of the public interest in this mission statement, and thus tied in to PJM’s performance metrics.
Topic: Section 205 Filing Rights
11) Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board? Yes
Comments:
The stakeholder process should be advisory to streamline and clarify decisional authority, which is uniquely fractured in PJM today. The stakeholder process has become dominated by incumbent interests and far too prone to inertia and delay. By removing decision-making authority from the collective stakeholder body, the incentive to stonewall or slow-walk needed changes (especially insofar as they preserve the current status quo or protect incumbents) is lessened, and the whole process stands to become more streamlined and collaborative. Former FERC Chair Mark Christie recently noted that “those who stand to profit from the rules should not be writing them.” We agree. The shift to advisory voting further offers opportunity for urgently
17 PJM Updated Mission Statement, updated January 27, 2026, available at https://www.pjm.com/-/media/DotCom/committees-groups/user-groups/arrcug/2026/20260127/20260127-item-03---pjm-mission- statement---affordability-redline.pdf 10 of 17
PDF page 11
needed improvements to decision-making processes. PJM staff and the Board should be developing and deciding on the rules for the regional grid and its markets, not the members themselves.
That said, this change cannot be considered in isolation. There are critical accompanying transparency and accountability measures that are necessary to making this shift efficacious. This includes opportunities for jump ball filing rights that should be developed in tandem with the transition to an advisory role. As is often true on contentious issues, we believe the best answer might be found when FERC has several well-founded filings to consider, and not just one. The accompanying reforms necessary for making this shift work include:
● Performance metrics for PJM leadership, and periodic evaluation of Board
decision-making efficacy by the Nominating Committee
● Transparency enhancements to PJM meetings, including Board meetings, that enable discussions and decisions to be more easily understood and audited
● Jump ball filing rights for PJM members (who have authentically valuable perspectives to contribute, and whose voice should not simply be ignored as soon as member voting became advisory); these should be conditional on a two-thirds sector-weighted majority ● Jump ball filing rights for states (as described in response to question 18).18
12) Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee? Yes
Comments:
PJM should have section 205 filing rights over the energy markets and ancillary services. This supports the streamlined decision-making authority we noted as necessary in question 11.
13) Should PJM have section 205 filing rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the requirement to obtain approval of two-thirds of the Members Committee? Yes
Comments:
PJM should have section 205 filing rights over the RTEP process. Effective regional transmission planning is essential to PJM’s mission to provide reliable and affordable electric service to the region. However, as explained in response to other questions, PJM’s independent exercise of section 205 filing rights should be balanced by providing jump-ball filing rights to OPSI and to PJM Members where those entities achieve super-majority support for an alternative filing.
In addition, we should reconsider which section 205 filing rights are retained by the PJM Transmission Owners and whether certain filing rights need to be shifted to PJM. For instance, the PJM Transmission Owners’ retention of section 205 filing rights over local transmission
18 From our responses to question 18: Any state representatives’ groups should have jump-ball filing rights, provided they reach a super-majority threshold of support for their jump-ball filing. 11 of 17
PDF page 12
planning can make it more difficult for PJM to effectively execute smart regional transmission planning.19 Consolidating more transmission-related section 205 filing rights with PJM would lead to more efficient regional planning outcomes.
14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? Yes
Comments:
PJM’s governance has, for too long, been effectively isolated from legitimate state concerns about how market rules interact with state authority over elements of resource adequacy, including generation siting, procurement, and other elements of energy policy. PJM’s governance has also all but ignored states' real political exposure to the consequences of market disorder and the current affordability crisis within PJM’s footprint. While we are interested in several institutional and cultural changes to give states a greater role in representing the public interest during PJM proceedings, we view jump ball filing rights as a critical method for states to make themselves heard when necessary. This would incent both the Board and the members to communicate proactively with OPSI throughout the stakeholder process and integrate state perspectives within relevant proposals. In short, a jump ball for OPSI should complement other reforms to give states, as agents of the public, a greater voice in PJM governance.
15) Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal? Yes
Comments:
In tandem with fully advisory stakeholder voting, yes.
As further described in response to question 11: There are critical accompanying transparency and accountability measures that are necessary to make a shift to an advisory role for stakeholders efficacious. This includes opportunities for jump ball filing rights that should be developed in tandem with the transition to an advisory role. As is often true on contentious issues, we believe the best answer might be found when FERC has several well-founded filings to consider, and not just one.
The accompanying reforms necessary for making this shift work include:
● Performance metrics for PJM leadership, and periodic evaluation of Board decision-making efficacy by the Nominating Committee,
● Transparency enhancements to PJM meetings, including Board meetings, that enable discussions and decisions to be more easily understood and audited, and
19 RMI, Mind the Regulatory Gap, 2024, https://rmi.org/insight/mind-the-regulatory-gap/ 12 of 17
PDF page 13
● Jump ball filing rights for PJM members (who have authentically valuable perspectives to contribute, and whose voice should not simply be ignored as soon as member voting became advisory); these should be conditional on a two-thirds sector-weighted majority, ● Jump ball filing rights for states: Any state representatives’ groups should have jump-ball filing rights, provided they reach a super-majority threshold of support for their jump-ball filing. Providing jump-ball filing rights to multiple state representative groups could result in multiple competing filings before the Commission if state representative groups have differing views. However, such competing jump-ball filings would benefit the public by providing FERC with greater discretion to choose the most just and reasonable option among the competing jump-ball filings. Any new state representative entity must have “jump ball” 205 filing rights to do anything meaningful.
Topic: Stakeholder Process
16) Should the approval threshold in the Members Committee be lowered from two-thirds sector-weighted voting? N/A
Comments:
We do not have a strong view on this, given our preference for member voting to be advisory.
17) Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees? Yes
Comments:
PJM’s stakeholder process is overly captured by incumbent interests, and reforms such as this
– in tandem with expanded stakeholder sectors (more on this below) – would help to re-weight stakeholder representation in a manner more reflective of the growing, diversifying range of perspectives seeking insight and input into PJM rules. PJM should also consider how to regularly assess and refresh its mechanisms for responding to evolving needs of stakeholders, recognizing that voting sectors and member types may evolve, and representation structures should not be allowed to become outdated or ineffective. Examples of these types of durable process reforms include:
● Make votes at every level public
● Introduce a process for new sector designation, including any criteria or threshold that such a sector might be required to meet
● Create clear rules for attendance for “Open” versus “Closed” meetings
● Establish standard expectations for participation during meetings
● Expand report-out requirements from working group decisions to clarify the composition of the vote
● Establish protocols for representation of meeting outputs in subsequent stakeholder and decision-making bodies
A number of additional reform opportunities, at both the structural and administrative levels, exist to address the stakeholder process. As noted in the introduction, these include: 13 of 17
PDF page 14
● Streamline the committee structure and meeting schedules. PJM has altogether too many meetings, and an overhaul (including elimination of some lower level committees) could facilitate more cohesive, transparent, and accountable decision-making around a set of prioritized issues for stakeholders to be considering at a particular time. For one specific example, a “shot clock” or clear sunset dates should be added to stakeholder deliberations. While the timing could be varied based on the complexity of the issue, we propose a deadline of a year for coming to resolution on bigger issues, and a 6-month process for smaller issues to be resolved. Embedded in this structural reform must be a recognition that when the time for decision-making expires (i.e., the end of a CIFP window), then the decision must be made, not the process extended.
● PJM should refresh and rebalance its stakeholder sectors, to correct for imbalances in representation that we see present in the PJM stakeholder community today. The number of sectors should be expanded to reflect the growing diversity of PJM’s members, and voting shares must accordingly be updated. As a first order, a “public interest sector” should be created that offers an accessible, expanded participation role for organizations such as ours, and many of which have contributed meaningfully to stakeholder discussions for years.20 Additionally, distributed energy resources and demand response providers, as a unique type of market participant, could benefit from their own sector. In ISO-NE, NEPOOL’s industry sectors include “Alternative Resources,” designed to provide a voice for distributed generation and other emerging technologies. There is also precedent for an expanded number of stakeholder sectors in MISO, which has 11 sectors, including one specifically for environmental organizations.
● Issue prioritization must become a core feature of the stakeholder process, as several noted during the Technical Conference. This will support both making most effective use of PJM staff’s valuable time, as well as giving PJM stakeholders the clarity and discipline they need to participate most effectively in informing issue resolution. The recently proposed stakeholder process for the Regional Organization for Western Energy (ROWE) – the result of collaborative discussion and a look across the existing RTO landscape in search of pitfalls and best practices – offers a compelling model on this front.21 The process they describe for the annual development of an Issue Catalogue and Roadmap could support more focused stakeholder discussions for the PJM region.
● The time is ripe to reconsider how input is solicited in the stakeholder process – in what form, and by whom. Key PJM stakeholder meetings can be tremendously overcrowded with hundreds of attendees, making practical discussions unlikely. To the question of form, greater reliance on notice and comment, as exemplified by CAISO, may be appropriate at times in PJM.22 PJM staff seem to be trialing this with the call for
22 CAISO Stakeholder Center, “Policy initiatives and stakeholder process” and December 2025 Stakeholder Process Guide, available at https://www.caiso.com/documents/stakeholder-process-guide.pdf21https://www.westernenergyboard.org/wp-content/uploads/JunePUBLIC_StakeholderProcessNarrative.pdf20 This includes sponsoring issue charges, crafting solution proposals, and working collaboratively with PJM members and staff on an array of issues, from the recent CIFP discussions, to surplus interconnection service enhancements, capacity market reforms, and more. 14 of 17
PDF page 15
white papers recently announced as part of the Powering Reliability Through Market Design workshops, which we find to be a more compelling way of gathering informed input on this topic from an array of stakeholders. Rules should also be established for the manner and timing of PJM response to such stakeholder contributions. When it comes to who should be providing input, stakeholder representatives might offer a useful model, and here again the ROWE stakeholder process offers a promising example: they introduce the idea of a Stakeholder Representatives Committee, as a forcing mechanism for similar stakeholder types to coordinate and find alignment where possible.23 This would both streamline meetings by keeping attendance to more manageable numbers of directly affected and engaged stakeholders, and spare PJM staff the job of parsing hundreds of perspectives in search of alignment that might prove elusive. Stakeholder representatives would be shouldering some of that responsibility themselves, and creating alignment from the ground up.
● Finally, PJM meetings require internal facilitation reforms, as well as transparency and accessibility improvements. In our experience, meetings are routinely derailed from their agendas and delayed by individual participants who, knowingly or unknowingly, speak at excessive length, wasting countless stakeholders’ time. Based on some of our facilitation expertise, we offer the following suggestions: ○ Concrete agendas with objectives should be published in advance of meetings and strictly enforced by facilitators, who should be empowered to head off interruptions and tangents in the interest of said agenda;
○ Discussions should be more structured based on an array of possible formats (for example, more reliance on panels, and other forms of mediated, interactive dialogue, rather than presentations followed by lengthy Q&As that do not fully resolve questions);
○ Committee meetings should be open, recorded (with recordings published online), and summarized with detailed, easy-to-follow transcripts on a better-organized PJM website.
Topic: State Participation
18) In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’ representatives? No
Comments:
Governors and legislators should have a clear role in the PJM stakeholder process. However, it is our view that there should not be two bodies offering or purporting to serve the role of the states’ perspective. We believe just one state representative group, that includes or subsumes OPSI, will best support a greater state role in the region and coherent, streamlined decision-making. This new entity (which we refer to as “PJM-SCOE” to link it conceptually to the
23 Western Interstate Energy Board, West-Wide Governance Pathways Initiative, Draft Chapter 8: “ROWE Stakeholder Process,” August 14, 2026. Available at: https://www.westernenergyboard.org/wwgpi/ 15 of 17
PDF page 16
NESCOE model) should include the option for representation from state Governor’s offices, energy offices, and legislators, as well as regulators. OPSI could remain a sub-group within PJM-SCOE, with defined roles and responsibilities of its own, selected to reflect OPSI members’ valuable technical and regulatory expertise. Here, Pat Wood’s suggestions for “clarifying the RSC’s authority” in his pre-filed comments are compelling.24
The new entity should be staffed and funded sufficiently to enable it to discharge its expanded responsibilities. Additionally, any state representatives’ group(s) should have jump ball filing rights, provided they reach a super-majority threshold of support for their jump ball filing. We view jump ball filings generally as benefitting the public by providing FERC with greater discretion to choose the most just and reasonable option among the competing jump ball filings.
19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? No
Comments:
State representatives are not ordinary stakeholders in the PJM process and should not be limited to expressing their views through voting in the PJM stakeholder process. Instead, state representatives should have jump ball section 205 filing rights where they reach super-majority support for a proposal that differs from one that PJM wishes to advance. Providing state representatives with jump ball filing rights better recognizes the important role of the states, especially with regard to issues such as resource adequacy that are in large part subject to state jurisdiction. In contrast, limiting state representatives to a voting role within the PJM stakeholder process creates inappropriate risks that state perspectives may be ignored and that the Commission will not have the opportunity to evaluate and approve policies that states in the PJM region support.
20) Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation? Yes
Comments:
Given the direct impact to states, and the role that states would ultimately play in implementing filings on such matters, consultation is appropriate. PJM staff and/or the Board should be consulting with OPSI (or the new state entity) throughout the process of developing resource adequacy and transmission cost allocation rules, and certainly, at minimum, before making the filing. The direct engagement PJM is pursuing with states on the questions of market design associated with the Powering Reliability Through Market Design effort is a laudable example of this.
The relationship between PJM and states has become strained in recent years, and establishing direct consultation channels on topics of overlapping jurisdiction represents one clear opportunity to rebuild it. Collaborative RTO-state relations, in which each party acknowledges
24 Pre-filed comments of Former FERC Chair Pat Wood 16 of 17
PDF page 17
the valuable role the other plays in matters affecting the regional grid, are essential for stabilizing PJM and executing the needed changes before the RTO with efficacy. Furthermore, there may be cases in which OPSI lacks the two-thirds majority necessary for its own jump ball filing, but the states should still be consulted on the relevant filings.
Sincerely,
/s/ Katie M. Siegner
Katie M. Siegner
Manager, Markets & Grids
RMI
1100 15th St. NW
Washington, DC 20005
ksiegner@rmi.org
/s/ Nick Lawton
Nick Lawton
Senior Attorney
Earthjustice
1400 L St NW Lobby 2, Unit 34117
Washington DC 20005
nlawton@earthjustice.org
/s/ Justin Vickers
Justin Vickers
Senior Attorney
Sierra Club
50 F St NW,
Washington, DC 20001
Justin.Vickers@SierraClub.Org
/s/ Jessi Eidbo
Jessi Eidbo
Senior Strategic Advisor
Sierra Club
50 F St NW,
Washington, DC 20001
Jessi.Eidbo@SierraClub.Org
/s/ Nicholas J. Guidi
Nicholas J. Guidi
Senior Attorney
Southern Environmental Law Center
500 New Jersey Avenue NW, Suite 600
Washington, DC 20001
nguidi@selc.org
/s/ Claire Lang-ree
Claire Lang-Ree
Advocate, Sustainable FERC Project
Natural Resources Defense Council
40 W 20th St.
New York, NY, 10011
clangree@nrdc.org
/s/ Katherine L. Rogers
Katherine L. Rogers
Associate Attorney
Southern Environmental Law Center
500 New Jersey Avenue NW, Suite 600
Washington, DC 20001
krogers@selc.org
17 of 17