AD26-7-000 · 2026-08-21 · Duke Energy Ohio, Inc. and Duke Energy Kentucky, Inc.
Post-Technical Conference Comments of Duke Energy Ohio, Inc. and Duke Energy Kentucky, Inc. re PJM Governance and Stakeholder Reforms
PDF page 1
1
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Governance and Stakeholder Reforms
)
Docket No. AD26-7
)
POST-TECHNICAL CONFERENCE COMMENTS
OF
DUKE ENERGY OHIO, INC. AND DUKE ENERGY KENTUCKY, INC.
On July 23, 2026, the Federal Energy Regulatory Commission (“FERC” or the
“Commission”) convened a technical conference in this docket to discuss PJM Interconnection, L.L.C. (“PJM”) governance and stakeholder processes, with a particular focus on identifying and evaluating concrete, actionable reforms to improve PJM’s ability to address operational and market needs in a timely and efficient manner. On July 30, 2026, the Commission issued a notice inviting interested parties to file post-conference comments, including responding to a list of questions posed by the Commission regarding potential PJM governance reforms. Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc. (“collectively, “Duke Energy’) hereby submit comments to the questions posed by the Commission.1 Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc. are transmission-owning utilities within PJM and are PJM members in the Transmission Owner sector. Duke Energy provides electric service to 920,000 customers in Kentucky and Ohio. Duke Energy appreciates the Commission’s initiative and active engagement to investigate reforms that can improve PJM’s ability to meet the needs of the moment and ensure the independence and reliable operation of PJM in the long-term.
Listed below are the questions posed by the Commission and Duke Energy’s responses:
1 On August 17, 2026, Duke Energy Ohio, Inc. and Duke Energy Kentucky, Inc. submitted a doc-less motion to intervene in this docket.
PDF page 2
2
PJM Board Independence
1. Should Board members’ terms be extended to five or more years?
No. Duke Energy supports a three-year board term, with the opportunity for renomination, and opposes extending board terms to five years or more because shorter terms promote responsiveness to industry changes, facilitate replacement of directors when concerns arise, and align with prevailing RTO/ISO governance standard practice among RTOs/ISOs.
2. Should there be a maximum number of years that a Board member may serve (e.g., 10 years)?
Yes. Term limits reinforce both independence and accountability while preserving a board’s ability to benefit from experienced leadership. We recommend three, three-year terms for the maximum term of nine years. However, limited extensions can preserve needed expertise while maintaining the discipline of a term-limit framework. Consequently, Duke Energy supports stakeholder approval for exceeding the maximum nine-year term to no more than two, three-year terms.
3. Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region?
Yes. Duke Energy believes there is value in having a portion of the PJM Board reside within the PJM footprint. Regional residence can provide practical familiarity with the states, communities, reliability concerns, and consumer impacts within the PJM region. However, residency should be treated as a preference rather than a mandatory qualification. A strict requirement could unnecessarily limit the pool of qualified, independent candidates and should not outweigh the need to select Board members with the appropriate expertise, independence, and judgment to oversee PJM effectively.
4. Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?
Yes. Duke Energy supports reducing the cooling-off period from two years to one year. A one-year period provides meaningful separation from prior employment or stakeholder affiliations while avoiding an unnecessarily restrictive barrier to qualified candidates. Given the complexity and pace of change in PJM’s markets, reliability obligations, and transmission planning responsibilities, the Board benefits from access to individuals with current and relevant experience. Any remaining conflict concerns can be appropriately addressed through robust disclosure, recusal, and ongoing conflict-of-interest safeguards.
PDF page 3
3
5. Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders?
No. Duke Energy believes that PJM’s restrictions should remain in place because they preserve the independence and impartiality of the Board’s decision-making process. Permitting unrestricted communications between individual stakeholders and Board members could create the perception that certain interests receive preferential access or influence over Board deliberations. The current restrictions promote fairness, transparency, and stakeholder confidence that Board decisions are based on the record through PJM’s open stakeholder processes rather than private advocacy. However, PJM could adopt a “Board Reception” approach similar to other RTOs/ISOs where stakeholders are allowed to speak to Board members at events such as the PJM Annual Meeting concerning any issue of interest for up to 3 hours.
6. In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?
Yes, with some exception. Duke Energy supports increased transparency into Board voting and reasoning where appropriate, as doing so can enhance accountability and stakeholder confidence in PJM governance. However, any requirement to make Board sessions or explanations public should preserve the ability of the Board to maintain confidentiality for matters that are appropriately addressed in executive sessions, including personnel, compensation, legal, privileged, commercially sensitive, cybersecurity, or other confidential matters. This approach balances the value of transparency with the need for candid Board deliberation and responsible governance
7. In order to increase transparency, should some Board meetings be open or available to the public?
Yes, with some exception. Duke Energy supports making appropriate portions of some Board meetings open or publicly available to enhance transparency and stakeholder confidence. However, public access should not extend to matters appropriately addressed in executive sessions, including personnel, compensation, legal, privileged, commercially sensitive, cybersecurity, or other confidential matters. This strikes a balance between visibility into Board governance while preserving the Board’s ability to deliberate candidly and responsively on sensitive issues.
8. Should PJM’s governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest?
No. Duke Energy does not believe additional language is necessary. PJM’s governing documents already require the Board to oversee PJM in a manner consistent with the safe and reliable operation of the PJM Region, and the creation and operation of robust, competitive, and nondiscriminatory electric power markets. Those obligations are core expressions of public interest in the RTO context. Adding a separate, generalized public
PDF page 4
4
interest standard could create ambiguity and invite disputes over competing interpretations of that term, without improving PJM’s existing obligations to reliability, market integrity, nondiscrimination, and independence.
9. Should state representatives have at least one voting member on the Nominating Committee?
No. While Duke Energy believes that input from the states is important, we do not support giving state representatives a voting member on PJM’s Nominating Committee. PJM’s Nominating Committee is structured around representatives elected from the Members Committee sectors. Creating a voting role for state representatives would require a broader change to PJM’s sector-based governance structure and could disrupt the balance among existing stakeholder sectors. It could also blur the independence of the Board nomination process by creating the perception that Board selection is influenced by governmental or state policy priorities. State input is important and necessary, but it should continue to be provided through OPSI, stakeholder engagement and FERC proceedings rather than through a formal vote on Board nominations.
10. Should PJM adopt public performance metrics and tie management compensation to their achievement?
Yes. Duke Energy supports the development of PJM management performance metrics and believes stakeholder awareness and input are important. However, Duke Energy does not support posting those performance metrics broadly on PJM’s public website. Instead, PJM should circulate the proposed metrics to the Members Committee sectors for comment and input before the metrics are finalized, while preserving appropriate confidentiality for compensation-related and other sensitive information.
Section 205 Filing Rights
11. Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board?
Yes. While a deliberative stakeholder process is important to understanding various perspectives and enabling coordinated regional decision-making, under the current PJM governance structure, the stakeholder process can too often forestall action if the matter is financially significant to vested stakeholder interests, operationally sensitive, or otherwise polarizing. PJM needs to be able to take more timely and decisive action. Converting the stakeholder process to an advisory process would balance the need for stakeholder input with PJM’s need for independence and ability to take decisive action on critical issues.
PDF page 5
5
12. Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?
Yes. Duke Energy supports PJM having Section 205 filing rights over the energy and ancillary services market rules. Energy and ancillary services market operation and design are core to PJM operations, and PJM should have the unilateral authority to take timely and decisive action, informed by stakeholder input.
13. Should PJM have section 205 filing rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the requirement to obtain approval of two- thirds of the Members Committee?
Yes, with important limitations. Duke Energy supported the agreement between PJM and PJM transmission owners to provide PJM section 205 filing rights over the RTEP as a package with other revisions and updates to the Consolidated Transmission Owners.2 While that agreement and related filings were rejected by the Commission,3 Duke Energy continues to support PJM having Section 205 filing rights over the RTEP, as long as other key revisions and updates to the Consolidated Transmission Owners Agreement are also made.
14. Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?
No. Duke Energy does not support granting OPSI “jump ball” rights over resource adequacy or transmission cost allocation filings, even where a supermajority of OPSI supports an alternative proposal. Resource adequacy and transmission cost allocation are core tariff matters that require coordinated regional decision-making, stakeholder input, and independent PJM judgment subject to Commission review. Providing OPSI with separate filing rights on these issues would risk elevating state policy preferences over the balanced, sector-based stakeholder process and could undermine PJM’s independence in administering its FERC-approved responsibilities. OPSI’s perspectives are important and should continue to inform PJM through existing consultation, stakeholder processes, and participation in Commission proceedings, but those perspectives should not create a parallel filing pathway that could complicate or delay timely regional reforms.
2 See Duquesne Light Co., Amendments to the Consolidated Transmission Owners Agreement, Docket No. ER24- 2336-000 (filed Jun. 21, 2024).3 Duquesne Light Co., et al., 189 FERC ¶ 61,181 (2024), reh’g order, 192 FERC ¶ 61,051 (2025).
PDF page 6
6
15. Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?
No. Duke Energy does not support granting the Members Committee “jump ball” filing rights over portions of the tariff where PJM has section 205 filing rights, even where a supermajority of stakeholders supports an alternative proposal. Where PJM is assigned section 205 filing authority, PJM must be able to exercise that authority independently and efficiently to carry out its FERC-approved responsibilities for reliable operations, market administration, and timely regional reforms. Creating a parallel Members Committee filing right over the same tariff provisions would undermine the purpose of assigning those filing rights to PJM, risk duplicative or competing filings, and could delay needed reforms. Stakeholder input remains essential and should continue to inform PJM’s decision-making through the stakeholder process and Commission proceedings, but that input should not displace PJM’s independent filing authority in areas where the tariff assigns PJM section 205 rights.
Stakeholder Process
16. Should the approval threshold in the Members Committee be lowered from two- thirds sector-weighted voting?
No. Duke Energy does not support lowering the Members Committee approval threshold from the current two-thirds sector-weighted voting standard. The existing threshold helps ensure that significant stakeholder-supported changes reflect broad consensus across PJM’s diverse sectors rather than the preferences of a narrow majority or a single sector coalition. Maintaining the two-thirds sector-weighted vote protects the balance embedded in PJM’s stakeholder governance structure, encourages compromise among sectors with different interests, and reinforces confidence that proposals advancing through the Members Committee have substantial cross-sector support. Lowering the threshold could weaken that consensus-based model and increase the risk that contested reforms move forward without sufficient stakeholder alignment.
17. Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?
Yes. Duke Energy supports applying affiliate voting restrictions not only to senior standing committees but also to lower-level committees. Although lower-level committees may not make final decisions, they often shape, refine, and advance proposals that ultimately move through stakeholder process. Allowing affiliates to cast
PDF page 7
7
multiple votes at those lower-level stages can provide disproportionate influence over the development of proposals before they reach higher-level committees for consideration.
State Participation
18. In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’ representatives?
No. Duke Energy does not support creating a second state representative group consisting of governors’ representatives or state legislators’ representatives. OPSI already provides an established mechanism for state regulatory perspectives to be communicated to PJM and stakeholders. Creating an additional governmental organization could duplicate existing channels, create uncertainty regarding which entity speaks for a state, and add complexity to an already extensive governance and stakeholder process. While state input is important, it should be provided through clear and existing channels in a manner that preserves PJM’s independence, supports timely decision-making, and avoids introducing political considerations into technical reliability and market governance matters.
19. Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes?
No. Duke Energy does not support granting state representatives a formal voting role in the PJM stakeholder process. State input is important and should continue to be considered through OPSI, FERC proceedings, stakeholder engagement, and other existing channels. However, providing state representatives with formal voting rights could blur the distinction between state policy advocacy and PJM’s independent responsibility to administer reliable operations and nondiscriminatory markets under its FERC-approved governing documents. It also could disrupt the balance of PJM’s sector- based stakeholder process and add complexity to already challenging market, resource adequacy, and transmission cost allocation reforms.
20. Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation?
No. We are concerned that such a requirement would impede PJM’s independence. OPSI has opportunities to provide feedback through the current Stakeholder process. Additional consultation requirements could create delays and impediments to PJM taking decisive action when needed.
PDF page 8
8
Conclusion
We appreciate the Commission encouraging stakeholders and interested parties to share their recommendations and suggestions for ways to enhance the responsiveness of PJM to changing market and industry conditions while at the same time maintaining reliability and independence. We are looking forward to participating in the upcoming discussions and are hopeful that constructive revisions to the PJM process will result.
Respectfully submitted,
__/s/ Molly Suda_________________
Molly Suda
Deputy General Counsel
1301 Pennsylvania Ave. NW, Suite 200
Washington, DC 20004
202-824-8011
molly.suda@duke-energy.com
Attorney for Duke Energy
CC: Official Service List for Docket No. AD26-7