AD26-7-000 · 2026-08-21 · Harvard Electricity Law Initiative

Post-Conference Comments of Harvard Electricity Law Initiative in response to Questions 12 and 13 re PJM Governance and Stakeholder Reforms

PDF page 1

1

UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION

PJM Governance and Stakeholder Reforms

)
)   Docket No. AD26-7
)
)
)

Harvard Electricity Law Initiative Response to
Questions 12 and 13 in the Notice Requesting
Post-Conference Comments1
Questions 12 and 13 in the Appendix to the Notice Requesting Post- Conference Comments ask whether PJM should have filing rights over energy and ancillary services markets and regional planning. These issues are currently in the PJM Operating Agreement (OA), and any section 205 filing amending the energy market rules or planning protocols must be approved by the Members Committee. Moving either Schedule 1 (energy market) or Schedule 6 (regional planning) from the OA to the Tariff would allow the PJM Board to file under section 205 without the Members Committee’s approval.  This comment anticipatorily rebuts arguments that transmission owners hold any control, beyond their share of the Members- Committee vote, over filing rights for matters housed in the OA. Two years ago, both the transmission owners and PJM asserted that transmission-owner consent, expressed through amendments to the Consolidated Transmission Owners’ Agreement (CTOA) filed by the transmission owners under section 205, was necessary to move Schedule 6 of the OA to the Tariff. The Commission denied PJM’s proposal to relocate Schedule 6 only because PJM

1 The Harvard Electricity Law Initiative is an independent organization based at Harvard Law School’s Environmental & Energy Law Program. These comments do not represent the views of Harvard University or Harvard Law School.

PDF page 2

2

packaged its filings with the transmission owners’ filing to amend the CTOA.2
Having concluded that the CTOA amendments went “beyond changes to enable this
transfer” and were unjust and unreasonable and unduly discriminatory for reasons
wholly unrelated to the proposed transfer, the Commission rejected the entire
package of filings.3
The Commission then took no position on whether transmission-owner
consent was necessary to move Schedule 6 from the OA to the Tariff.4 In this
comment, we argue that transmission-owner consent is not necessary to move
schedules from the OA to the Tariff. Should the Commission order or approve the
transfer of regional planning provisions from the OA to the Tariff, four non-
substantive changes to the CTOA suffice to maintain the document’s accuracy.
Moving OA Schedule 1 would not require any changes to the CTOA.
The Members Committee Has Exclusive Authority to Amend the
Operating Agreement with a Section 205 Filing
The relevant facts are uncontested. In 1997, the-then PJM utilities filed
several documents to create an independent PJM Interconnection LLC.5 Section 8.8
of the utility-filed Operating Agreement granted the PJM Members Committee
authority to “amend any portion of this Agreement, including the Schedules hereto

2 Duquesne Light Co., PJM Interconnection, 189 FERC ¶ 61,181 at P 22 (2024) (“having rejected the CTOA Amendments on the merits, we dismiss the PJM Complaint”) [CTOA Rejection Order]; Duquesne Light Co., PJM Interconnection, 192 FERC ¶ 61,051 at P 21 (2025) [CTOA Rejection Rehearing Order].
3 CTOA Rejection Rehearing Order at P 22.
4 CTOA Rejection Order at P 22, n. 47 (stating that the Commission took “no position as to whether PJM has the legal authority to effectuate the changes proposed in the PJM Complaint or PJM Transfer Filing in the absence of the CTOA Amendments or vice versa”); CTOA Rejection Rehearing Order at P 24.
5 Atlantic City Electric, et al., 81 FERC ¶ 61,257, at p. 62,235 (1997) (“On June 2, 1997, Supporting Companies submitted a comprehensive filing to restructure the PJM Pool.”); CTOA Rejection Order at PP 3‒4; CTOA Rejection Rehearing Order at P 6; see also PJM Initial Filing, Docket No. ER24-2338, at pp. 7–9  (Jun. 21, 2024); PJM Initial Filing, Docket No. EL24-119, at pp. 7–9  (Jun. 21, 2024); Utilities’ Initial Filing, Docket No. ER24- 2336, at pp. 17–19  (Jun. 21, 2024).

PDF page 3

3

. . . and file any such amendments . . . with FERC.”6  Since Commission approval of the Operating Agreement in 1997, the PJM Members Committee has enjoyed

exclusive authority over section 205 filings that amend the OA.7 PJM, the
transmission owners, and the Members Committee have acted accordingly for
nearly 30 years.8
The transmission owners cannot overwrite the Members Committee’s
privileges enshrined in the OA by amending the CTOA, and no CTOA amendments
are needed to express transmission-owner consent to moving OA schedules to the
Tariff.9 Having “chose[n] to voluntarily give up, by contract, some of their ratefiling freedom under section 205” when they filed the OA and the Commission approved it

in 1997,10 the utilities now have no authority to approve or veto the transfer of the planning protocol or other OA schedules to the PJM Tariff.

Only trivial conforming amendments to the CTOA might be needed to ensure
consistency across PJM documents should the Commission order the transfer of any
schedules from the OA to the Tariff. Acting under section 206, the Commission
could order the transmission owners to file any needed changes. The Mobile-Sierra
doctrine does not shield the CTOA from such trivial adjustments.11
Our analysis of the CTOA finds that that the document can already
accommodate a Commission order transferring OA Schedules 1 to the Tariff. If the

6 PJM Operating Agreement, sec. 8.8(ii) (emphasis added). The Appendix contains the OA filed in 1997, which includes the same language.
7 CTOA Rejection Order at P 5, n.13; CTOA Rejection Rehearing Order at PP 8, 10.
8 See, e.g., CTOA Rejection Order at P 8 (“Before the PJM Filings were submitted, PJM attempted to amend the OA by a vote of the Members Committee, which would have allowed PJM to file the OA revisions under FPA section 205.”).
9 See Harvard Electricity Law Initiative Protest, Docket No. ER24-2336, at pp. 8‒12 (Jul. 22, 2024); Harvard Electricity Law Initiative Response to Utilities’ Proposed Answer, Docket No. ER24-2336 (Sep. 4, 2024); Harvard Electricity Law Initiative Reply to Deficiency Letter Responses, Docket No. ER24-2336 (Oct. 30, 2024). 10 Atlantic City Electric, et al. v. FERC, 295 F.3d 1, 10 (D.C. Cir. 2002).
11 CTOA Rejection Rehearing Order at P 80 (finding that the relevant CTOA provisions are not entitled to Mobile-Sierra protections as a matter of law and do not warrant those protections as a matter of discretion).

PDF page 4

4

Commission orders the transfer of the regional planning provisions, we believe that, at most, four non-substantive changes to the CTOA would ensure consistency across PJM’s governing documents.

CTOA Changes Needed to Ensure Consistency Across PJM Documents if the Commission Orders Schedule 6 of the OA Moved to the Tariff

CTOA Section
Description of Conforming Change
Definitions
In the definition of Regional Transmission Expansion Planning Protocol, Replace “Schedule 6 of the Operating Agreement” with “PJM Tariff, Schedule [ ]”

4.1.4
Following “Operating Agreement,” add “and the PJM Tariff”
6.3.3
Delete “Operating Agreement and the”
6.3.4
Delete “or Operating Agreement”
The OA Does Not Require Transmission Owner Consent to Move
Schedules from the Operating Agreement to the Tariff
When it interprets an RTO governing document to determine which entity has authority over a particular issue, the Commisison follows a two-step approach rooted in caselaw. Applying this framework, the OA cannot be read to empower the transmission owners with special authority over how PJM transfers its filing rights. The Commission summarized its approach to interpreting RTO governing documents in a 2020 proceeding about whether the CTOA delegated to PJM consideration of end-of-life transmission projects.12 The Commission explained that to determine whether the PJM transmission owners delegated authority over a particular issue, it first considers whether the relevant contract “unambiguously addresses the matter at issue.”13

The Operating Agreement is unambiguous about the Members Committee’s exclusive role in authorizing section 205 filings that amend the OA. Section 8.8 specifies that to amend the OA the Members Committee must act in accordance

12 PJM Interconnection, 176 FERC ¶ 61,053 at P 13 (2021).
13 Id. at P 14 (quoting Transmission Agency of N. Cal. v. FERC, 628 F.3d 538, 547 (D.C. Cir. 2010)).

PDF page 5

5

with section 18.6.14 Both the original OA aproved by the Commission in 1997 and current section 18.6 stipulate that the OA may be amended “only upon”

i) submission of the amendment to the Board for its review and comments;
ii) approval by the Members Committee pursuant to its voting rules in section 8.4; and iii) Commission approval.15 None of these conditions suggest that the utilities retain any authority over amendments to the OA or that changes involving filing rights are handled differently from other amendments.

The Commission’s contract-interpretation framework provides that to
determine whether there is amiguity in an RTO governing document, it may consider the “entire agreement.”16 The specifics of this inquiry will depend on which provisions the Commission orders moved out of the OA. We briefly summarize relevant evidence about Schedule 6.

OA provisions about regional planning specify roles for the PJM Board, PJM Staff, and the Members Committee. For instance, section 10.4 empowers PJM staff to plan regional transmission expansion.17 Section 7.7 empowers the PJM Board to “[a]pprove The Regional Transmission Expansion Plan in accordance with the provisions of the Regional Transmission Expansion Planning Protocol set forth in Operating Agreement, Schedule 6.” Schedule 6 opens with: “[t]his Regional Transmission Expansion Planning Protocol shall govern the process by which the Members shall rely upon [PJM Staff] to prepare a plan for the enhancement and

14 There is a slight and non-substantive difference between the original 8.8(ii) and the current 8.8(ii). Original 8.8(ii): “In accordance with the provisions of Section 18.6 of this Agreement, amend any portion . . .” Current 8.8(ii): “In accordance with the provisions of Operating Agreement, section 18.6, amend any portion . . .”

15 CTOA Rejection Order at P 5, n.13 (emphasis added); see also Appendix.
16 PJM Interconnection, 176 FERC ¶ 61,053 at P 14 (quoting Xcel Energy Servs. Inc. v. Am. Transmission Co., LLC, 140 FERC ¶ 61,058, at P 60 (2012)).
17 See also CTOA Rejection Order at P 4 (noting that in 1997 the transmission owners transferred “to the Office of the Interconnection and the PJM Board, in accordance with the [OA], the responsibility for preparing a [RTEP] in accordance with the [RTEP] Protocol”); CTOA Rejection Rehearing Order at P 4.

PDF page 6

6

expansion of the Transmission Facilities.” None of these provisions can be read to hide a transmission-owner privilege to police PJM’s filing rights.18

Finally, the Commission can “look to extrinsic evidence,”19 including
“statements, course of conduct, and contemporaneous correspondence, aimed at
discerning the intent of the parties.”20 This inquiry would also be fact specific. With regard to Schedule 6, the utilities explained in the 2024 proceeding that their

surrender of control over the regional planning protocol was explicit, intentional, and complete. They summarize that in 1997 they wanted to retain control over the tariff while also attempting to comply with the Commission’s directive to give the new PJM ISO “primary responsibility for transmission planning.”21 To meet these

goals, the utilities placed the planning rules in the OA because “the transmission owners did not control” that document.22 In other words, ceding all control over regional planning was the primary reason they put the planning rules in the OA

and empowered the Members Committee with exclusive authority to authorize
amendments with section 205 filings.

18 The OA as filed by the utilities in June 1997 included section 18.1 that specified retained “transmission owner rights.” See Appendix. The Commission directed PJM to remove those provisions, “given that the same provisions are included in the Owners Agreement.” Atlantic City Electric, et al., 81 FERC ¶ 61,257, at p. 62,274 (1997). Nonetheless, none of those retained rights, which the Commission did not accept and were not part of the OA, suggest that the Members Committee’s authority over the regional planning protocol is non-exclusive. 19 PJM Interconnection, 176 FERC ¶ 61,053 at P 15 (citing Missouri River Energy Servs. v. FERC, 918 F.3d 954, 958 (D.C. Cir. 2019)).
20 Id. (quoting Farmland Industries, Inc. v. Grain Bd. of Iraq, 904 F.2d 732, 736 (D.C. Cir. 1990)).
21 Utilities’ Initial Filing, Docket No. ER24-2336, at pp. 17–18  (Jun. 21, 2024).
22 Id. at p. 18.

PDF page 7

7

The Commission Should Reject Arguments that the CTOA
Clandestinely Requires Transmission Owner Consent to Transfer
Schedules from the OA to the Tariff
PJM and the transmission owners floated several theories about the transmission owners’ apparent authority over the Operating Agreement and regional planning. We briefly recount and rebut the arguments they filed in 2024. Filing Rights Do Not “Ultimately Reside” with the Transmission Owners In 2024, PJM claimed that “the rights to plan the PJM Transmission Owners’ facilities, and any accompanying filing rights, ultimately reside with the PJM Transmission Owners and require PJM to obtain the Transmission Owners’ agreement to transfer.”23 As discussed, the filing rights currently reside with the Members Committee, and the utilities did not retain any filing rights over the regional planning protocol.

Filing rights “ultimately reside” with the utilities in a limited sense that has no relevance here. Commission approval of a utility’s withdrawal from PJM would terminate various contractual commitments. Assuming the withdrawing utility is not joining a different RTO, it would be out of compliance with the Commission’s Open Access transmission standards. The utility would likely have the right to file a new transmission tariff that meets Commission requirements, including about regional planning. In that sense, filing rights over matters that had been handled by the RTO would return to the transmission owner. That hypothetical would not be at issue if the Commission orders PJM to move schedules from the OA to the Tariff. So long as a utility remains a CTOA signatory, filing rights over regional planning do not “reside” with the utility.

23 PJM Initial Filing, Docket No. ER24-2338, at pp. 7–9  (Jun. 21, 2024).

PDF page 8

8

The “Scope and Configuration” of Planning Rights Do Not Encompass Filing Rights over the Planning Protocol

In 2024, PJM claimed that the CTOA “specifies the scope and configuration” of the right to plan regional transmission expansion.24 PJM pointed to CTOA provisions that delegate to PJM the responsibility to plan regional transmission expansion. PJM then presumed that control over regional-planning filing rights are hidden in these CTOA provisions. PJM’s conclusion cannot be squared with the Commission’s approach to contract interpretation.

As summarized above, to determine whether the PJM transmission owners delegated authority over a particular issue, the Commission first considers whether the relevant contract “unambiguously addresses the matter at issue.”25 PJM did not claim that the CTOA unambiguously allows the transmission owners to retain authority over regional planning filing rights. To the contrary, PJM claimed that the transmission owners’ rights are implied by the regional planning’s unambiguous delegation of planning rights.

Reading the “entire agreement” does not support PJM’s hidden-rights
theory.26 In CTOA Article 7, the parties used specific and unambiguous language to transfer and reserve filing rights over various issues.27 It is implausible the parties would have been so specific about transferring filing rights in Article 7 while also implying that utilities retain a veto over filing rights transfers in the “scope and configuration” of the regional planning delegation.

24 PJM’s Response to the Deficiency Letter, Docket No. ER24-2338-001, at pp. 6, 8 (Oct. 9, 2024)
25 PJM Interconnection, 176 FERC ¶ 61,053 at P 14 (2021).
26 Id.
27 See, e.g., CTOA 7.5.1 – Filing of Changes in Terms and Conditions Under Section 205. (i) PJM shall have the exclusive and unilateral rights to file pursuant to Section 205 of the Federal Power Act and the FERC’s rules and regulations thereunder to make changes in or relating to the terms and conditions of the PJM Tariff (including but not limited to provisions relating to creditworthiness, billing, and defaults) as well as all charges for recovery of PJM costs. . . .

PDF page 9

9
The CTOA Does Not “Define the Location” of the Planning Protocol
PJM claimed that the CTOA’s definition of the planning protocol demands transmission-owner consent to any transfer of Schedule 6 to the Tariff.28 The Commission should not infer any substantive meaning from this cross-reference. Article I of the CTOA defines the document’s key terms, including the “Regional Transmission Expansion Planning Protocol,” which “shall mean Schedule 6 of the Operating Agreement, or any successor thereto.” That definition, according to PJM: 1) conditions the initial filing-rights transfer over regional planning from the transmission owners in 1997 on the precise location of the planning protocol; and 2) provides the transmission owners with a right to veto any relocation of the planning provision.

That’s a lot of weight for this definition to bear. PJM attached far more significance to that single cross-reference in the CTOA than it did to dozens of cross- references in its Tariff. To transfer of Schedule 6 into the Tariff, PJM proposed revisions to approximately fifty tariff definitions or sections that would replace references to Schedule 6 of the Operating Agreement with references to the new location of the planning protocol in the Tariff.29 In its section 205 filing to implement those changes, PJM “emphasize[d]” that these modifications were not “substantive.”30 PJM does not explain why an identical reference to Operating Agreement Schedule 6 in a single CTOA definition creates a legal right, while dozens of references in the Tariff are trivial.

28 PJM’s Response to the Deficiency Letter, Docket No. ER24-2338-001, at pp. 6‒7 (Oct. 9, 2024).
29 See PJM Initial Filing, Docket No. ER24-2338 (Jun. 21, 2024).
30 Id. at p. 29; id at p. 31, n. 67. See Attachment A to the filing for the full list of proposed changes.

PDF page 10

10

D.C. Circuit Decisions about Filing Rights Do Not Prevent the Commission from Ordering the Changes Proposed in Questions 12 and 13

In 2024, the utilities warned that if the Commission transfers authority over the planning protocol to the PJM Board without utility consent it would be “exceed[ing] its jurisdiction under FPA section 206.”31 The legal problem, according to the utilities, is that transferring the Members Committee’s filing authority without utility consent would “require the Transmission Owners to cede their filing rights over planning in a manner other than what they voluntarily agreed to.”32 No court decision or Commission order suggests that utilities may so restrain the Commission’s section 206 authority.

Under the Atlantic City cases, the Commission “has no jurisdiction to . . . requir[e] utilities to surrender their rights under § 205 of the FPA to make filings to initiate rate changes.”33  The D.C. Circuit’s limited holding does not award the utilities control over filing rights that they voluntarily gave up by contract. In 2003, following the second Atlantic City decision, the Commission understood that it could act under section 206 to modify a settlement agreement between PJM and the utilities that allocates filing rights, and that it could even grant a party additional filing rights without transmission-owner consent.34 A section 206 order transferring a schedule from the OA to the Tariff is well within the Commission’s authority.

31 Motion for Leave to Answer and Answer of the PJM Transmission Owners, Docket No. ER24-2336, at p. 11 (Aug. 15, 2024).

32 Id.
33 Atlantic City Elec. Co. v. FERC, 329 F.3d 856, 859 (D.C. Cir. 2003); Maine Pub. Utils’ Comm’n v. FERC, 454 F.3d 278, 284 (D.C. Cir. 2006) (“the issue in Atlantic City was limited to the question of whether FERC had jurisdiction . . . to oblige public utilities to cede their rights to make future filings under Section 205.”).
34 PJM Interconnection, et al., 105 FERC ¶ 61,294 at P 33 (2003). Id. at P 33, n. 33.

PDF page 11

11

CONCLUSION
Control over the OA’s schedules is a matter between the Members
Committee, the PJM Board, and the Commission. The utilities’ endorsement via CTOA amendments of any transfer from the OA to the Tariff is legally irrelevant.

/s/ Ari Peskoe

Ari Peskoe
Harvard Electricity Law Initiative
6 Everett St., Suite 4133
Cambridge, MA 02138
617.495.4425
apeskoe@law.harvard.edu
August 21, 2026

PDF page 12

--
-
-
-
97 JUN -2 AH 9: 00
FILING OF THE
PJM SUPPORTING COMPANIES
JUNE 2, 1997
· EC97-38 -000
VOLUME I OF II
ORIGINAL
Harvard Electricity Law Initiative Protest Appendix B - PJM's 1997 Operating Agreement B-1

PDF page 13

-
BRUSSEL$. 8ELGIUM
WARSAW. POLAND
I-IONG KONG
NEW YORK. NEW YORK
ATLANTA. GEORGIA
RICHMOND. VIRGINIA
HUNTON & WILLIAMS
1000 K STREET, N.W.
WASHINGTON, D.C. 20000-1100
TELEPHONE 120219!5!5-1!500
FACSIMILE 1202) 77B-2201
EC97-38 -00011
ARNOLD H. QUINT
BY HAND
Ms. Lois D. Cashell
Secretary
Federal Energy Regulatory Commission
888 First Street, N.E., Room IA
Washington, D.C. 20426
June 2, 1997
Atlantic City Electric Company. et al.
Dear Ms. Cashell:
ORIGINAL
MCLEAN. VIRGINIA
NORF'OLK. VIRGINIA
RALEIGH, NORTH CAROLINA
CHARLOTTE, NORTH CAROLINA
KNOXVILLE, T ENNESSEE
FILE No.: 50943.000002
DIRECT DIAL: (202) 955-I 542
C
r,'
C
L
'­
c:
z
I
N "
::c
I';-?
.::­er
--< •• ,
i •• •::
On December 31, 1996, in Docket Nos. OA97-261-000 and ER97-1082-000, the member companies of the Pennsylvania-New Jersey-Maryland Interconnection (PJM Pool) made a compliance filing to implement the requirements of Order No. 888 for "tight" power pools. In that filing, the PJM member companies committed to make a subsequent filing, following further negotiations with stakeholders, to put in place an Independent System Operator (ISO) for the PJM Pool. The instant filing is made by the PJM Supporting Companies!! pursuant to Sections 203 and 205 of the Federal Power Act to fulfill that prior commitment.

In developing this filing, the Supporting Companies worked with a large group of interested stakeholders in an effort to obtain as much consensus as possible. While complete consensus could not be achieved, two major independent power producers, U.S. Generating 11 Atlantic City Electric Company, Baltimore Gas and Electric Company, Delmarva Power & Light Company, Jersey Central Power & Light Company, Metropolitan Edison Company, Pennsylvania Electric Company (the immediately preceding three utilities being subsidiaries of GPU, Inc.), Pennsylvania Power & Light Company, Potomac Electric Power Company and Public Service Electric and Gas Company.

\;>\1
l'ERC-DOCKETED
JUN 2 1997
NOTE: The
PJM Utilities
filed the OA
Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-2

PDF page 14

HUNTON & WILLIAMS
Ms. Lois D. Cashell
June 2, 1997
Page 2
Company and Cogen Technologies N.J. Venture, and two major power marketers, PanEnergy Trading and Market Services, L.L.C. and Citizens Lehman Power, L.P. (now Citizens Power L.L.C.), have authorized the Supporting Companies to advise the Commission that they are generally supportive of this proposal, subject to their review of the final package as filed. Each party has reservations about certain provisions and may offer comments on or propose alternative treatment of these provisions in separate pleadings. For example, Citizens continues to have questions about the use of locational marginal pricing. In addition, Allegheny Electric Cooperative, Inc. has indicated to the Supporting Companies that this filing is, in its opinion, preferable to the principal alternatives presented during the stakeholder process and will advise the Commission of its remaining reservations in a separate pleading.

The Supporting Companies are submitting the following documents pursuant to Section 205 of the Federal Power Act and 18 C.F.R. § 35.13 (1997):

1. Amended and Restated Operating Agreement of PJM Interconnection, L. L. C., dated as of June 2, 1997 (Operating Agreement);

2. Transmission Owners Agreement dated as of June 2, 1997 (Transmission
Owners Agreement);
3. PJM Open Access Transmission Tariff (PJM Tariff); and
4. Reliability Assurance Agreement Among Load Serving Entities in the PJM Control Area dated as of June 2, 1997 (Reliability Assurance Agreement).

Attachment A hereto is a complete list of the documents provided. Nothing in this filing is intended to modify any existing contracts between the Supporting Companies and any other parties.

I. Objectives of the Instant Filing
The December 31 compliance filing, which was accepted by the Commission by Order dated February 28, 1997,l! included (i) changes in the PJM Interconnection Agreement to facilitate the participation of all market participants on a non-discriminatory basis, and (ii) the PJM Open Access Transmission Tariff (PJM Tariff), under which all of the public utilities in the PJM control area offered access to their transmission facilities under <' Mid-Continent Area Power Pool, 78 FERC 161,203 (1997) (February 28 Order). NOTE: The

PJM Utilities
filed the OA
Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-3

PDF page 15

Ms. Lois D. Cashell
June 2, 1997
Page 3
HUNTON & WILLIAMS
non-pancaked rates and on terms that tracked the Commission's pro forma tariff. On April 1, 1997, a filing was made to further modify the PJM Interconnection Agreement, converting it into an Operating Agreement for a limited liability company (PJM Interconnection, L.L.C.) in order to permit an independent board of directors to exercise oversight over the day-to-day operations of the PJM Pool.

This filing builds on the December 31 and April 1 filings, making only those additional changes necessary to accomplish the following objectives:

1. Establish an ISO That Satisfies the Commission's Principles. Although the December 31 and April 1 filings provided for expanded participation in the PJM Pool and enhanced the independence of the PJM Pool's operator, formerly known as the PJM Interconnection Association Office, those filings did not purport to establish an ISO. This filing modifies the governance provisions of the Operating Agreement to ensure that the Office of the Interconnection, subject to the oversight of an independent PJM Board of Managers (PJM Board), will independently administer the day-to-day operations of the PJM Pool, satisfying the Commission's criteria for ISOs set forth in Order No. 888, as clarified in Atlantic City Electric Co. et al., 77 FERC 161,148 (1996) (November 13 Order).l! The revised governance provisions are a direct result of discussions among the Supporting Companies and other stakeholders. The Operating Agreement establishes an ISO with responsibility for system operations, administration of the PJM Tariff, and regional transmission planning. No stakeholder or industry segment has the ability to control the ISO' s functions or to prevent the ISO from acting. Moreover, the ISO will have a governing board (the PJM Board) that is independent of any industry segment, and will have complete responsibility for supervision and oversight of the day-to-day operations of the PJM control area. In addition, for those few matters that come before the members for action, the voting rights continue to be structured so that no one industry segment can either force or block action. These provisions, together with the continuing requirements of the Federal Power Act related to any change in the governing agreements and tariff, provide a system of checks and balances that will assure non-discriminatory, open access transmission service throughout the PJM control area.

The Operating Agreement also has been modified to modernize outdated provisions of the original PJM Agreement and to clarify the responsibilities of the ISO and the parties under the Operating Agreement.

,, Attachment B to this Transmittal Letter demonstrates how the Supporting Companies' proposal complies with each ISO requirement and addresses each of the concerns that was identified in the November 13 Order.

Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-4

PDF page 16

AMENDED AND RESTATED
OPERATING AGREEMENT
OF
PJM INTERCONNECTION, L.L.C.
Dated June 2, 1997
Harvard Electricity Law Initiative Protest Appendix B - PJM's 1997 Operating Agreement B-5

PDF page 17

1. 39 Related Parties … 7 1 .40 Reliability Assurance Agreement … 7 1.41 Sector Votes … 7 1.42 State … 7 1.43 System … 7 1.44 Transmission Facilities … 7 1.45 Transmission Owner … 7 1.46 Transmission Owners Agreement … 8 1.47 User Group … 8 1.48 Voting Member … 8 1.49 Weighted Interest … 8 -

2. FORMATION, NAME; PLACE OF BUSINESS … 8 2.1 Formation of LLC; Certificate of Formation … 8 2.2 Name of LLC … 9 2.3 Place of Business … 9 2.4 Registered Office and Registered Agent … 9

3. PURPOSES AND POWERS OF LLC … 9 3 . 1 Purposes … 9 3.2 Powers … 9

4. EFFECTIVE DATE AND TERMINATION … 10 4 .1 Effective Date and Termination … 10 4.2 Governing Law … 10

5. WORKING CAPITAL AND CAPITAL CONTRIBUTIONS … 10
5.1 Funding of Working Capital and Capital Contributions … 10 5.2 Contributions to Association … 11

6. TAX STATUS AND DISTRIBUTIONS … 11 6.1 Tax Status … 11 6.2 Return of Capital Contributions … 11

6. 3 Liquidating Distribution … 11
7. PJM BOARD … 12 7 .1 Composition … 12 7 .2 Qualifications … 12 7 .3 Term of Office … 12 7 .4 Quorum … 13 7 .5 Operating and Capital Budgets … 13 7.5.1 Finance Committee … 13 7.5.2 Adoption of Budgets … 13 7.6 By-laws … 14 7.7 Duties and Responsibilities of the PJM Board … 14

8. MEMBERS COMMITTEE … 16 -

8.1 Sectors … 16
8. l. l Desi.gnati.on … 16 8.1.2 Related Parties … 16

8. 2 Representatives … 16 8.2.1 Appointment … 16 ii

Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-6

PDF page 18

8.2.2 Regulatory Authorities … 16 8.2.3 Initial Representatives … 17 8.2.4 Change of or Substitution for a Representative … 17 8.3 Meetings … 17 8.3.1 Regular and Special Meetings … 17 8.3.2 Attendance … 17 8.3.3 Quorum … 18 8.4 Manner of Acting … 18 8.5 Chair and Vice Chair of the Members Committee … 18 8.5.1 Selection and Term … 18 8.5.2 Duties … 19 8.6 Other Committees … 19 8.7 User Groups … 19 8.8 Powers of the Members Committee … 19

9. OFFICERS … 20 9.1 Election and Term … 20 9.2 President … 20

9. 3 Secretary … 20 9 .4 Treasurer … 21 9.5 Renewal of Officers; Vacancies … 21 9.6 Compensation … 21

10. OFFICE OF THE INTERCONNECTION … 21 10 .1 Establishment … 21 10.2 Processes and Organization … 21 10.3 Confidential Information … 22 10.4 Duties and Responsibilities … 22

11. MEMBERS … 24 11.1 Management Rights … 24 11.2 Other Activities … 24 11.3 Member Responsibilities … 24 11.3.1 General … 24 11.3.2 Facilities Planning and Operation … 25 11.3 .3 Electric Distributors … 26 11.3.4 Reports to the Office of the Interconnection … 27 11.4 Regional Transmission Expansion Planning Protocol … 27

11. 5 Member Right to Petition … 27 11.6 Membership Requirements … 28

12. TRANSFERS OF MEMBERSHIP INTEREST … 29
13. INTERCHANGE … 29 13.1 Interchange Arrangements with Non-Members … 29 13.2 Energy Market … 29

14. METERING … 1-ſ 14.1 Installation, Maintenance and Reading of Meters … 29 14.2 Metering Procedures … 29 14.3 Integrated Megawatt-Hours … 30 iii

Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-7

PDF page 19

14.4 Meter Locations … 30
15. ENFORCEMENT OF OBLIGATIONS … 30 15 .1 Failure to Meet Obligations … 30 15.1.1 Termination of Market Buyer Rights … 30 15.1.2 Termination of Market Seller Rights … 30 15.1.3 Payment of Bills … 30 15.2 Enforcement of Obligations … 31 15.3 Obligations to a Member in Default … 31 15.4 Obligations of a Member in Default … 32 15.5 No Implied Waiver … 32

16. LIABILITY AND INDEMNITY … 32 16.1 Members … 32 16.2 LLC Indemnified Parties … 32 16.3 Worker' Compensation Claims … 34 16 .4 Limitation of Liability … 34 16.5 Resolution of Disputes … 34 16.6 Gross Negligence or Willful Misconduct … 34 16.7 Insurance … 34

17. MEMBER REPRESENTATIONS, WARRANTIES AND COVENANTS … 35
17 .1 Representations and Warranties … 35 -

17 .1. 1 Organization and Existence … 35 17.1.2 Power and Authority … 35 17 .1.3 Authorization and Enforceability … 35 17.1.4 No Government Consents … 35 17 .1.5 No Conflict or Breach … 35 17.1.6 No Proceedings … 36 17.2 Municipal Electric Systems … 36

17. 3 Survival … 36
18. MISCELLANEOUS PROVISIONS … 36 18 .1 Transmission Owners Rights … 36 18.2 Fiscal and Taxable Year … 37 18.3 Reports … 37 18.4 Bank Accounts; Checks, Notes and Drafts … 37 18.5 Books and Records … 37 18.6 Amendment … 38

18. 7 Interpretation … 39 18.8 Severability … 39 18.9 Force Majeure … 39 18 .10 Further Assurances … 39 18.11 Seal … 39 18 .12 Counterparts … 40 J 8. J3 Costs of Meetings … 41) 18.14 Notice … 40 18.15 Headings … 40 18.16 No Third-Party Beneficiaries … 40 IV

Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-8

PDF page 20

1.3 Related PJM Agreements . ..................................................................... I
2. PURPOSES AND OBJECTIVES ....................................................................... I 2.1 Common and Uniform Procedures … 1 2.2 Interpretation … 1

3. NEGOTIATION AND MEDIATION … 2 3.1 When Required … 2 3 . 2 Procedures … 2 3.2.1 Initiation … 2 3.2.2 Selection of Mediator … 2 3.2.3 Advisory Mediator … 2 3.2.4 Mediation Process … 3 3.2.5 Mediator's Assessment … 3 3.3 Costs … 4

4. ARBITRATION … 4 4.1 When Required … 4 4.2 Binding Decision … 4 4.3 Initiation … 4 4.4 Selection of Arbitrator(s) … 4 4.5 Procedures … 5 4.6 Summary Disposition and Interim Measures … 5 4.6.1 Lack of Good Faith Basis … 5 4.6.2 Discovery Limits … 5 4.6.3 Interim Decision … 5

4. 7 Discovery of Facts … 5 4.7.1 Discovery Procedures … 5

4. 7 .2 Procedures Arbitrator … 6
4. 8 Evidentiary Hearing … 6
4. 9 Confidentiality … 6
4. 9 .1 Designation … 6 4.9.2 Compulsory Disclosure … 7 4.9.3 Public Information … 7 4.10 Timetable … 7 4.11 Advisory Interpretations … 7 4.12 Decisions … 8 4.13 Costs … 8 4.14 Enforcement … 8

5. ALTERNATE DISPUTE RESOLUTION COMMITTEE … 8 5.1 Membership … 8 5.1.1 Representatives … 8 5.1.2 Term … 9 5.2 Voting Requirements … 9 5.3 Officers … 9 5 .4 Meetings … 9

5. 5 Responsibilities … 9 SCHEDULE 6 -

REGIONAL TRANSMISSION EXPANSION PLANNING PROTOCOL .. 1
ix
Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-9

PDF page 21

1. REGIONAL TRANSMISSION EXPANSION PLANNING PROTOCOL … 1
1.1 Purpose and Objectives … 1 1.2 Conformity with NERC and MAAC Criteria … 1

1. 3 Establishment of Committees … 1
1. 4 Contents of the Regional Transmission Expansion Plan … 2
1. 5 Procedure for Development of the Regional Transmission Expansion Plan … 2 1.5.1 Commencement of the Process … 2 1.5.2 Development of Scope, Assumptions and Procedures … 3

1.5.3 Scope of Studies … 3 1.5.4 Supply of Data … 3 1.5.5 Coordination of the Regional Transmission Expansion Plan … 3

1.5.6 Development of the Recommended Regional Transmission Expansion Plan3
1. 6 Approval of the Final Regional Transmission Expansion Plan … 4
1. 7 Obligation to Build … 5 1.8 Relationship to the PJM Control Area Open Access Transmission PJM Tariff … 5 SCHEDULE 7 - UNDERFREQUENCY RELAY OBLICATIONS AND CHARGES … 1

1. UNDERFREQUENCY RELAY OBLIGATION … 1 1.1 Application … 1

1. 2 Obligations … 1
2. UNDERFREQUENCY RELAY CHARGES ......................................................... I
3. DISTRIBUTION OF UNDERFREQUENCY RELAY CHARGES … 2
3.1 Share of Charges … 2 3.2 Allocation by the Office of the Interconnection … 2 SCHEDULE 8 -DELEGATION OF RELIABILITY RESPONSIBILITIES … 1

1. DELEGATION … 1
2. NEW PARTIES ............................................................................................ I
3. IMPLEMENTATION OF RELIABILITY ASSURANCE AGREEMENT … 1
SCHEDULE 9 - EMERGENCY PROCEDURE CHARGES … 1
1. EMERGENCY PROCEDURE CHARGE ............................................................ I
2. DISTRIBUTION OF EMERGENCY PROCEDURE CHARGES ................................ I
2. I Complying Parties … 1 2.2 All Parties … 2 X

Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-10

PDF page 22

-
-
-
-
•
shall distribute to the Members for their information final annual budgets for the following fiscal year not later than 60 days prior to the beginning of each fiscal year of the LLC. 7 .6

By-laws.
To the extent not inconsistent with any provision of this Agreement, the PJM Board shall adopt such by-laws establishing procedures for the implementation of this Agreement as it may deem appropriate, including but not limited to by-laws governing the scheduling, noticing and conduct of meetings of the PJM Board, selection of a Chair and Vice Chair of the PJM Board, action by the PJM Board without a meeting, and the organization and responsibilities of standing and special committees of the PJM Board. Such by-laws shall not modify or be inconsistent with any of the rights or obligations established by this Agreement. 7.7

Duties and Responsibilities of the PJM Board.
In accordance with this Agreement, the PJM Board shall supervise and oversee all matters pertaining to the Interconnection and the LLC, and carry out such other duties as are herein specified, including but not limited to the following duties and responsibilities:

i) ii)
As its primary responsibility, ensure that the President, the other officers of the LLC, and Office of the Interconnection perform the duties and responsibilities set forth in this Agreement, including but not limited to those set forth in Sections 9.2 through 9.4 and Section 10.4, in a manner consistent with (A) the safe and reliable operation of the Interconnection, (B)

the creation and operation of a robust, competitive, and
non-discriminatory electric power market in the PJM Control Area, and (C) the principle that a Member or group of Members shall not have undue influence over the operation of the Interconnection;

Select the Officers of the LLC;
iii) Adopt budgets for the LLC;
iv) Approve the Regional Transmission Expansion Plan in accordance with the provisions of the Regional Transmission Expansion Planning

Protocol set forth in Schedule 6 of this Agreement.
v) vi)
On its own initiative or at the request of a User Group as specified herein, submit to the Members Committee such proposed amendments to this Agreement or any Schedule hereto, or a proposed new Schedule, as it may deem appropriate;

Petition FERC to modify any provision of this Agreement or any
Schedule or practice hereunder that the PJM Board believes to be unjust, unreasonable, or unduly discriminatory under Section 206 of the Federal Power Act, subject to the right of any Member or the Members to

intervene in any resulting proceedings;
vii) Review for consistency with the creation and operation of a robust, competitive and non-discriminatory electric power market in the PJM Control Area any change to rate design or to non-rate terms and

14
Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-11

PDF page 23

-
-
-
conditions proposed by Transmission Owners for filing under Section 205 of the Federal Power Act.

viii) If and to the extent it shall deem appropriate, intervene in any proceeding at FERC initiated by the Members in accordance with Section 1 l.5(b), and participate in other state and federal regulatory proceedings relating to the interests of the LLC;

ix) Review, in accordance with Section 15.1.3, determinations of the Office of the Interconnection with respect to events of default;

x) Assess against the other Members in proportion to their Weighted Interest an amount equal to any payment to the Office of the Interconnection, including interest thereon, as to which a Member is in default;

xi) Establish reasonable sanctions for failure of a Member to comply with its obligations under this Agreement;

xii) Direct the Office of the Interconnection on behalf of the LLC to take appropriate legal or regulatory action against a Member (A) to recover any unpaid amounts due from the Member to the Office of the Interconnection under this Agreement and to make whole any Members subject to an assessment as a result of such unpaid amount, or (B) as may otherwise be necessary to enforce the obligations of this Agreement;

xiii) Resolve claims by a Member that the Reliability Committee established by the Reliability Assurance Agreement has exercised its responsibilities in a manner inconsistent with the creation and operation of a robust, competitive and non-discriminatory electric power market in the P JM Control Area, upon due consideration of the views of the Member and of the Reliability Committee, and of the need to preserve the reliability of electric service in the PJM Control Area.

xiv) Solicit the views of Members on, and commission from time to time as it shall deem appropriate independent reviews of, (A) the performance of the PJM Interchange Energy Market, (B) compliance by Market Participants with the rules and requirements of the PJM Interchange Energy Market, and (C) the performance of the Office of the Interconnection under performance criteria proposed by the Members Committee and approved by the PJM Board; and

xv) Terminate a Member as may be appropriate under the terms of this Agreement.

15
Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-12

PDF page 24

-
-
-
8.5.2 Duties.
The Chair shall call and preside at meetings of the Members Committee, and shall carry out such other responsibilities as the Members Committee shall assign. The Chair shall cause minutes of each meeting of the Members Committee to be taken and maintained, and shall cause notices of meetings of the Members Committee to be distributed. The Vice Chair shall preside at meetings of the Members Committee in the absence of the Chair, and shall otherwise act for the Chair at the Chair's request.

8.6
Other Committees.
(a) The Members Committee may form, select the membership, and oversee the activities, of an Operating Committee, a Planning Committee, and an Energy Market Committee as standing committees, and such other committees, subcommittees, task forces, working groups or other bodies as it shall deem appropriate, to provide advice and recommendations to the Members Committee or to the Office of the Interconnection as directed by the Members Committee.

(b) The Members Committee shall elect representatives to the Alternate Dispute Resolution Committee as specified in the PJM Dispute Resolution Procedures. 8.7

User Groups.
(a) Any five or more Members sharing a common interest may form a User Group, and may invite such other Members to join the User Group as the User Group shall deem appropriate. Notification of the formation of a User Group shall be provided to all members of the Members Committee.

(b) The Members Committee shall create a User Group composed of representatives of bona fide public interest and environmental organizations that are interested in the activities of the LLC and are willing and able to participate in such a User Group.

(c) Meetings of User Groups shall be open to all Members and the Office of the Interconnection. Notices and agendas of meetings of a User Group shall be provided to all Members that ask to receive them.

(d) Any recommendation or proposal for action adopted by affirmative vote of three-fourths or more of the members of a User Group shall be circulated by the Office of the Interconnection to the representatives on the Members Committee and shall be considered by the Members Committee at its next regular meeting occurring not earlier than 30 days after the circulation of such notice.

( e)
If the Members Committee does not adopt a recommendation or proposal
submitted to it by a User Group, upon vote of nine-tenths or more of the members of the User Group the recommendation or proposal may be submitted to the PJM Board for its consideration in accordance with Section 7.7(v).

8.8
Powers of the Members Committee.
The Members Committee, acting by adoption of a motion as specified in Section 8.4, shall have the power to take the actions specified in this Agreement, including: 19

Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-13

PDF page 25

i) Elect the members of the PJM Board;
ii) In accordance with the provisions of Section 18.6 of this Agreement,
amend any portion of this Agreement, including the Schedules hereto, or
create new Schedules, and file any such amendments or new Schedules
with FERC or other regulatory body of competent jurisdiction;
iii) Terminate this Agreement; and
iv) Provide advice and recommendations to the PJM Board and the Office of
the Interconnection.
9.1
Election and Term.
9. OFFICERS
The officers of the LLC shall consist of a President, a Secretary and a Treasurer. The PJM Board may elect such other officers as it deems necessary to carry out the business of the LLC. All officers shall be elected by the PJM Board and shall hold office until the next annual meeting of the PJM Board and until their successors are elected. Any number of offices may be held by the same person, except that the offices of the President and Treasurer may not be held by the same person.

9 .2
President.
The PJM Board shall appoint a President and Chief Executive Officer of the LLC (the "President"). The President shall direct and supervise the day-to-day operation of the LLC, and shall report to the PJM Board.

The President shall be responsible for directing and
supervising the Office of the Interconnection in the performance of the duties and responsibilities specified in Section 10.4. The President shall execute bonds, mortgages and other contracts requiring a seal, under the seal of the LLC, except where required or permitted by law to be otherwise signed and executed and except where the signing and execution thereof shall be expressly delegated by the board to some other officer or agent of the LLC. In the absence of the President or in the event of his or her inability or refusal to act, and if a vice president has been appointed by the PJM Board, the Vice President (or in the event there be more than one Vice President, the Vice Presidents in the order designated by the PJM Board in its Minutes) shall perform the duties of the President, and when so acting, shall have all the powers of and be subject to all the restrictions upon the President. The Vice President shall perform such other duties and have such other powers as the PJM Board may from time to time prescribe.

9 .3
Secretary.
The Secretary shall attend all meetings of the PJM Board and record all the proceedings -

of the meetings of the PJM Board in a minute book to be kept for that purpose and shall perform like duties for the standing committees or special committees when required. He or she shall give, or cause to be given, notice of all special meetings of the PJM Board, and shall perform such other duties as may be prescribed by the PJM Board or President, under whose supervision he or she shall be. He or she shall have custody of the corporate seal of the LLC, 20

Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-14

PDF page 26

-
-
-
-
-
-
-
-
-
-
-
-
shall request such Members as the President shall deem appropriate to participate in such processes and organization.

All such processes and organization shall be carried out in
accordance with all applicable code of conduct or other functional separation requirements of FERC.

10.3
Confidential Information.
The Office of the Interconnection shall comply with the requirements of Section 18. 17 with respect to any proprietary or confidential information received from or about any Member.

10.4 Duties and Responsibilities.
The Office of the Interconnection, under the direction of the President as supervised and overseen by the PJM Board, shall carry out the following duties and responsibilities, 111 accordance with the provisions of this Agreement:

i) Administer and implement this Agreement;
ii) Perform such functions in furtherance of this Agreement as the PJM Board, acting within the scope of its duties and responsibilities under this Agreement, may direct;

iii) Prepare, maintain, update and disseminate the PJM Manuals;
iv) Comply with MAAC and NERC operation and planning standards, principles and guidelines;

v) Maintain an appropriately trained workforce, and such equipment and facilities, including computer hardware and software and backup power supplies, as necessary or appropriate to implement or administer this Agreement;

vi) Direct the operation and coordinate the maintenance of the facilities of the Interconnection used for both load and reactive supply, so as to maintain reliability of service and obtain the benefits of pooling and interchange consistent with this Agreement and the Reliability Assurance Agreement;

vii) Direct the operation and coordinate the maintenance of the bulk power supply facilities of the Interconnection with such facilities and systems of others not party to this Agreement in accordance with agreements between the LLC and such other systems to secure reliability and continuity of service and other advantages of pooling on a regional basis;

viii) Perform interchange accounting and maintain records pertaining to the operation

of the
PJM
Interchange
Energy
Market and
the
Interconnection;
ix) Notify the Members of the receipt of any application to become a Member, and of the action of the Office of the Interconnection on such application, including but not limited to the completion of integration of 22

Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-15

PDF page 27

a new Member's system into the PJM Control Area as specified m Section l l.6(f);

x) Calculate the Weighted Interest of each Member;
xi) Maintain accurate records of the sectors in which each Voting Member is entitled to vote, and calculate the results of any vote taken in the Members Committee;

xii) Furnish appropriate information and reports as are required to keep the Members regularly informed of the outlook for, the functioning of, and results achieved by the Interconnection;

xiii) File with FERC on behalf of the Members any amendments to this Agreement or the Schedules hereto, any new Schedules hereto, and make any other regulatory filings on behalf of the Members or the LLC necessary to implement this Agreement;

xiv) At the direction of the PJM Board, submit comments to regulatory authorities on matters pertinent to the Interconnection;

xv) Consult with the standing or other committees established pursuant to Section 8.6(a) on matters within the responsibility of the committee;

xvi) Perform operating studies of the bulk power supply facilities of the Interconnection and make such recommendations and initiate such actions as may be necessary to maintain reliable operation of the Interconnection;

xvii) Accept, on behalf of the Members, notices served under this Agreement; xviii)

Perform those functions and undertake those responsibilities transferred to it under the Transmission Owners Agreement, including (A) direct the operation of the transmission facilities of the parties to the Transmission Owners Agreement, (B) administer the PJM Tariff, and (C) administer the Regional Transmission Expansion Planning Protocol set forth as Schedule 6 to this Agreement.

xix) Perform those functions and undertake those responsibilities transferred to it under the Reliability Assurance Agreement, as specified in Schedule 8 of this Agreement.

xx) Monitor the operation of the PJM Control Area, ensure that appropriate Emergency plans are in place and appropriate Emergency drills are conducted, declare the existence of an Emergency, and direct the operations of the Members as necessary to manage, alleviate or end an Emergency;

xxi) Incorporate the grid reliability requirements applicable to nue-\e-.;1 generating units in the PJM Control Area planning and operating principles and practices; and

23
Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-16

PDF page 28

party or by which it or any of its properties is bound, or constitutes or will constitute a default thereunder or will result in the imposition of any lien upon any of its properties. 17.1.6 No Proceedings.

There are no actions at law, suits in equity, proceedings or claims pending or, to the knowledge of the Member, threatened against the Member before any federal, state, foreign or local court, tribunal or government agency or authority that might materially delay, prevent or hinder the performance by the Member of its obligations hereunder. 17 .2 Municipal Electric Systems.

Any provisions of Section 17 .1 notwithstanding, if any Member that is a municipal electric system believes in good faith that the provisions of Sections 5. l(b) and 16.1 of this Agreement may not lawfully be applied to that Member under applicable state law governing municipal activities, the Member may request a waiver of the pertinent provisions of the Agreement. Any such request for waiver shall be supported by an opinion of counsel for the Member to the effect that the provision of the Agreement as to which waiver is sought may not lawfully be applied to the Member under applicable state law. The PJM Board shall have the right to have the opinion of the Member's counsel reviewed by counsel to the LLC. If the PJM Board concludes that either or both of Sections 5.l(b) and 16.1 of this Agreement may not lawfully be applied to a municipal electric system Member, it shall waive the application of the affected provision or provisions to such municipal Member. Any Member not permitted by law to indemnify the other Members shall not be indemnified by the other Members. 17 .3

Survival.
All representations and warranties contained in this Section 17 shall survive the execution and delivery of this Agreement.

18. MISCELLANEOUS PROVISIONS
18.1
Transmission Owners Rights.
Neither the PJM Board nor the Members Committee shall take any action which has the effect of modifying or limiting the following rights and obligations of Transmission Owners, which are hereby reserved to the Transmission Owners; provided, however, that the rights and obligations of the Transmission Owners set forth below shall be exercised in a manner consistent with applicable obligations under the Federal Power Act and FERC's rules and regulations thereunder:

(a) The right at any time of Transmission Owners individually or collectively to file pursuant to Section 205 of the Federal Power Act for any change in rates and charges for transmission or an ancillary service that it deems necessary to recover its transmission revenue requirements for providing service under the PJM Tariff.

(b) The right of Transmission Owners individually or collectively to adopt and implement procedures to protect their electric facilities from physical damage or to prevent injury or damage to persons or property.

36
Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-17

PDF page 29

-
-
-
-
-
-
-
-
(c) The right of Transmission Owners individually or collectively to build, acquire, sell, dispose, retire, merge or otherwise transfer or convey all or any part of its or their assets, including but not limited to any Transmission Facilities, such right to include, but not be limited to, the right, individually or collectively, to terminate the relationship with the LLC in connection with the creation of a transmission company to own and/ or operate the Transmission Facilities of the Transmission Owners or any of them.

(d) The ability of Transmission Owners individually or collectively to take whatever actions it or they deem necessary to fulfill its or their obligations under local, state or federal law.

(e) The right of any Transmission Owner to withdraw from this Agreement in accordance with its provisions.

18.2 Fiscal and Taxable Year.
The fiscal year and taxable year of the LLC shall be the calendar year.
18.3
Reports.
Each year prior to the Annual Meeting of the Members, the PJM Board shall cause to be prepared and distributed to the Members a report of the LLC's activities since the prior report.

18.4 Bank Accounts; Checks, Notes and Drafts.
(a) Funds of the LLC shall be deposited in an account or accounts of a type, in form and name and in a bank(s) or other financial institution(s) which are participants in federal insurance programs as selected by the PJM Board. The PJM Board shall arrange for the appropriate conduct of such accounts. Funds may be withdrawn from such accounts only for bona fide and legitimate LLC purposes and may from time to time be invested in such short-term securities, money market funds, certificates of deposit or other liquid assets as the PJM Board deems appropriate. All checks or demands for money and notes of the LLC shall be signed by any officer or by any other person designated by the PJM Board.

(b) The Members acknowledge that the PJM Board may maintain LLC funds in
accounts, money market funds, certificates of deposit, other liquid assets in excess of the insurance provided by the Federal Deposit Insurance Corporation, or other depository insurance institutions and that the PJM Board shall not be accountable or liable for any loss of such funds resulting from failure or insolvency of the depository institution.

(c) Checks, notes, drafts and other orders for the payment of money shall be signed by such persons as the PJM Board from time to time may authorize. When the PJM Board so authorizes, the signature of any such person may be a facsimile.

18.5
Books and Records.
(a) At all times during the term of the LLC, the PJM Board shall keep, or cause to be kept, full and accurate books of account, records and supporting documents, whic\\ <,,\\all reflect, completely, accurately and in reasonable detail, each transaction of the LLC. The books of account shall be maintained and tax returns prepared and filed on the method of accounting determined by the PJM Board. The books of account, records and all documents 37

Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-18

PDF page 30

-
-
-
-
and other writings of the LLC shall be kept and maintained at the principal office of the Interconnection.

(b) The PJM Board shall cause the Office of the Interconnection to keep at its principal office the following:

i) A current list in alphabetical order of the full name and last known business address of each Member, the Weighted Interest of each

Member, and the Members Committee sector of each Voting Member;
ii) A copy of the Certificate of Formation and the Certificate of Conversion, and all Certificates of Amendment thereto;

iii) Copies of the LLC's federal, state, and local income tax returns and reports, if any, for the three most recent years; and

iv) Copies of the Operating Agreement, as amended, and of any financial statements of the LLC for the three most recent years.

18.6 Amendment.
(a) Except as provided by law or otherwise set forth herein, this Agreement, including any Schedule hereto, may be amended, or a new Schedule may be created, only upon: (i) submission of the proposed amendment to the PJM Board for its review and comments; (ii) approval of the amendment or new Schedule by the Members Committee, after consideration of the comments of the PJM Board, in accordance with Section 8.4, or written agreement to an amendment of all Members not in default at the time the amendment is agreed upon; and (iii) approval and/or acceptance for filing of the amendment by FERC and any other regulatory body with jurisdiction thereof as may be required by law. If and as necessary, the Members Committee may file with FERC or other regulatory body of competent jurisdiction any amendment to this Agreement or to its Schedules or a new Schedule not filed by the Office of the Interconnection.

(b) Notwithstanding the foregoing, an applicant eligible to become a Member in accordance with the procedures specified in this Agreement shall become a Member by executing a counterpart of this Agreement without the need for amendment of this Agreement or execution of such counterpart by any other Member.

( c)
Each of the following fundamental changes to the LLC shall require or be deemed to require an amendment to this Agreement and shall require the prior approval of FERC:

i) Adoption of any plan of merger or consolidation;
ii) iii)
Adoption of any plan of sale, lease or exchange of assets relating to all, or substantially all, of the property and assets of the LLC;

Adoption of any plan of division relating to the division of the LLC into two or more corporations or other legal entities;

iv) Adoption of any plan relating to the conversion of the LLC into a stock corporation;

38
Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-19

PDF page 31

v) Adoption of any proposal of voluntary dissolution; or
vi) Taking any action which has the purpose or effect of the adoption of any plan or proposal described in items (i), (ii), (iii), (iv) or (v) above.

18. 7 Interpretation.
Wherever the context may require, any noun or pronoun used herein shall include the corresponding masculine, feminine or neuter forms. The singular form of nouns, pronouns and verbs shall include the plural and vice versa.

18.8
Severability.
Each provision of this Agreement shall be considered severable and if for any reason any provision is determined by a court or regulatory authority of competent jurisdiction to be invalid, void or unenforceable, the remaining provisions of this Agreement shall continue in full force and effect and shall in no way be affected, impaired or invalidated, and such invalid, void or unenforceable provision shall be replaced with valid and enforceable provision or provisions which otherwise give effect to the original intent of the invalid, void or unenforceable provision.

18.9
Force Majeure.
No Member shall be liable to any other Member for damages or otherwise be in breach of this Agreement to the extent and during the period such Member's performance is prevented by any cause or causes beyond such Member's control and without such Member's fault or negligence, including but not limited to any act, omission, or circumstance occasioned by or in consequence of any act of God, labor disturbance, act of the public enemy, war, insurrection, riot, fire, storm or flood, explosion, breakage or accident to machinery or equipment, or curtailment, order, regulation or restriction imposed by governmental, military or lawfully established civilian authorities; provided, however, that any such foregoing event shall not excuse any payment obligation. Upon the occurrence of an event considered by a Member to constitute a force majeure event, such Member shall use due diligence to endeavor to continue to perform its obligations as far as reasonably practicable and to remedy the event, provided that no Member shall be required by this provision to settle any strike or labor dispute. 18.10 Further Assurances.

Each Member hereby agrees that it shall hereafter execute and deliver such further instruments, provide all information and take or forbear such further acts and things as may be reasonably required or useful to carry out the intent and purpose of this Agreement and as are not inconsistent with the terms hereof.

18.11 Seal.
The seal of the LLC shall have inscribed thereon the name of the LLC, the year of its organization and the words "Corporate Seal, Delaware." The seal may be used by causing it or a facsimile thereof to be impressed or affixed or reproduced or otherwise. 39

Harvard Electricity Law Initiative Protest
Appendix B - PJM's 1997 Operating Agreement
B-20