AD26-7-000 · 2026-08-21 · East Kentucky Power Cooperative, Inc.

Post-Technical Conference Comments of East Kentucky Power Cooperative, Inc. re PJM Governance and Stakeholder Reforms

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Governance and
)
Docket No. AD26-7-000
Stakeholder Reforms
)

POST-TECHNICAL CONFERENCE COMMENTS OF
EAST KENTUCKY POWER COOPERATIVE, INC.

East Kentucky Power Cooperative, Inc. (“EKPC”) appreciates the opportunity to offer these post-technical conference comments, including responding to the questions posed by the Commission.

EKPC integrated into PJM in 2013. EKPC is a generation and transmission owning cooperative that serves 16 distribution owner-member cooperatives. EKPC is in the Transmission Owner sector of the PJM membership. EKPC actively engages in the PJM stakeholder process, including working across sectors to achieve consensus on contentious matters. Most recently, EKPC co-sponsored the Reliability Backstop Procurement proposal that achieved a two-thirds, sector-weighted super-majority vote.1 Although there are examples where the PJM membership has been challenged to come to consensus, developing an appropriately structured Reliability Backstop Procurement was not one. Of course, this is a key component to addressing the biggest challenge facing the PJM region

1 A proposal co-sponsored by EKPC, Buckeye Power, Dominion Energy, Duke Energy Ohio, Duke Energy Kentucky, Duquesne Light Company, Exelon, Old Dominion Electric Cooperative, PPL Electric Utilities Corp., Southern Maryland Electric Cooperative, and the Data Center Coalition (called the “Coalition” Reliability Backstop Procurement (RBP) Proposal). The Coalition RBP Proposal is available here: 20260630-item-02f---joint-edcs-and-data-center-coalition---rbp---executive-summary.pdf.

PDF page 2

2
and, despite the complexity of the issues involved, EKPC helped to forge a consensus when PJM was unable to do so.

It is EKPC’s view that the current resource adequacy challenge in the PJM region may partially be attributed to PJM’s failure to act appropriately and timely with respect to matters within the Commission’s jurisdiction where PJM currently has the authority to make filings under Section 205 of the Federal Power Act. However, EKPC firmly believes that the current resource adequacy challenge is primarily driven by the failure of retail choice states to impose appropriate requirements on those who serve retail load within their state.2 In other words, those states have allowed: 1) existing load to be served by reliance on PJM’s short-term markets; and 2) new load to connect to the system without requiring adequate power supplies to serve them. These state policies have effectively encouraged leaning on the wholesale power markets at a period in time when large amounts of dispatchable generation resources have been retired without replacement. Moreover, policy makers in some of these states have condemned the PJM markets and the PJM Board and leadership for rapid escalations in retail energy prices when the negative impacts of their own state policies have adversely impacted the wholesale capacity market via increased RPM Capacity Market prices.

EKPC fundamentally disagrees with how some have framed the challenge – that the crisis was caused by flaws in PJM’s governance and ineffective stakeholder process. The

2 See Letter from Don Mosier (EKPC CEO) to DOE Sec’y Wright and FERC Chairman Swett, dated August 6, 2026. Mr. Mosier’s letter is made available here: https://elibrary.ferc.gov/eLibrary/filedownload?fileid=DE6EEFA0-9BE5-C0BF-9D32-9FF2CA500000.

PDF page 3

3
status quo cannot solely be attributed to PJM’s action or lack of action. While there are certain changes at PJM that would be constructive and appropriate to consider at this time to best ensure the region as a collective body navigates through this challenge successfully, care must be exercised to not institutionalize politization in PJM’s governance and bulk power grid operations.

A key theme in written and oral comments arising from the Technical Conference was that there should be a clear delineation of responsibilities between PJM and the “states” to achieve resource adequacy and ensure it will persist into the future. In EKPC’s view, a clear delineation of roles and responsibilities to ensure resource adequacy (and associated accountability to faithfully execute those roles to fulfill those responsibilities) is the most critical thing that must be accomplished under the Commission’s leadership through the Alternative Dispute Resolution process that the Commission initiated. Only then may strategic action plans be developed by the states and PJM to ensure that their respective efforts work in concert, not conflict, with the overall resource adequacy objective. Collaboration between the federal authorities and state authorities through this effort must result in clarity about what needs to happen in the thirteen states and District of Columbia comprising the PJM region and how those actions mesh with, and harness, the benefits of the wholesale power markets administered by PJM. This must happen regardless of whether any specific additional role or responsibility be considered for states in the PJM governance or stakeholder process. Governors’ offices, state legislators and state commissions have been engaged in this Technical Conference, but primarily led by leaders in those states where the requirement to own and operate generation adequate is divorced

PDF page 4

4
from the obligation to meet customer load. Those are the various state entities that must act in their retail realm to ensure alignment with the overarching resource adequacy objective and action is undertaken to ensure there is no unreasonable leaning on the wholesale power markets. Ironically, the states with the greatest need to assure that their states achieve affordable energy rates are the very states calling for wholesale reform of PJM’s governance, despite the fact that it is their own state policies that have created the affordability concern. In some instances, state laws or state commission regulations will need to be revised. It would be appropriate to receive commitments that those actions will be assessed and undertaken before pressuring PJM to alter a governance structure that, historically, has worked relatively well. Indeed, that should be a condition of any state body being granted any specific role or responsibility in PJM’s governance or stakeholder process.

EKPC offers its perspective on the questions below and appreciates that the Commission recognizes that these questions are inter-related and not exhaustive. EKPC also offers an observation that potential acceptance of certain changes below would be conditioned on other changes simultaneously being made.

PJM Board Independence

Questions/Comments
Yes No
1) Should Board members’ terms be extended to five or more years?
X

Comments: EKPC supports extending the term to 5 years. PJM is complex and the decisions that the PJM Board is tasked to make require sufficient expertise that sharpens over time and experience. Additionally, the result of Board decisions may not fully come to bear within the three-year term of a Board member. It is appropriate to have a time horizon that more likely ensures that a

PDF page 5

5

Questions/Comments
Yes No
Board member will experience the longer-term outcome of decisions made.
2) Should there be a maximum number of years that a Board member may serve (e.g., 10 years)?

X

Comments: If a Board member has effectively discharged their responsibilities, there should be no Operating Agreement imposed limit on terms or years of service. However, as a self-policing effort, it is appropriate for the Board to impose term and age limits through their bylaws as the PJM Board currently does.

3) Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region? X

Comments: It is appropriate to require some tie to the region, being a resident or relevant work experience. However, requiring residency during Board service term should not be a requirement. It may limit qualified candidates who otherwise had experience that satisfies the intention of a residency requirement.

4) Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?

X

Comments: A cooling off period is necessary to address actual or perceived conflicts of interest. A 2-year cooling off period reduces the candidate pool. A 1- year cooling off period would be appropriate and is consistent with state and federal lobbying rules and state and federal employment rules.

5) Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders?

X

Comments: The ex parte rules are intended to reinforce independence and transparency. Relaxing them will disadvantage smaller, less-resourced market participants and shift stakeholder efforts from striving to achieve stakeholder consensus to striving to influence Board decisions. This concern would be heightened should additional FPA Section 205 filing rights be afforded to the PJM Board. To the extent the term “stakeholders” encompasses states, it is appropriate for the PJM Board to meet with OPSI, as it does today. To have impact on what governing document changes are filed with the Commission, however, the OPSI consensus position should be injected into the stakeholder process to be deliberated with those who own the assets, make financial decisions based on the PJM rules. Such entities must fully understand the technical impacts of the proposals on their businesses. Members like EKPC owe a fiduciary duty as

PDF page 6

6

Questions/Comments
Yes No
well as obligation to provide safe, adequate and reliable service to its owner- members who serve end-consumers. It is imperative that EKPC have an effective opportunity to weigh in on potential changes that may impact its ability to meet its obligations.

6) In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?

X

Comments: The tally of “yeas” and “nays” would be beneficial to understand the level of consensus on positions. However, it is not necessary to report individual Board member voting positions. Revealing individual votes may increase the potential for ex parte lobbying efforts targeting individual Board members, which may compromise the Board’s independence. Additionally, it would be beneficial for the membership to understand the factors the Board considered in explaining its reasoning for decisions involving changes to PJM governing documents. The Board makes numerous decisions, including those affecting PJM employees and PJM operations. Those decisions do not need to be reported publicly or explained publicly.

7) In order to increase transparency, should some Board meetings be open or available to the public?

X

Comments:
8) Should PJM’s governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest?

X

Comments: PJM’s purpose is to ensure reliability at the lowest reasonable cost. It necessarily needs focus on engineering and economics. Whereas, a “public interest” standard necessarily involves broader factors, including those outside of PJM’s authority.

PJM may only be charged with responsibilities that are consistent with the Federal Power Act. To the extent that the concept of public interest were limited to that embodied in the Federal Power Act, an appropriately caveated reference may be considered.

However, even such caveats are insufficient to address the elephant in the room. Resource adequacy is the most significant challenge for the region to overcome. Including a reference to “public interest,” while ignoring the fact that PJM does not possess all the authorities necessary to accomplish it, would likely further subject PJM to political pressure and out-weighted criticism. Only upon establishing a clear delineation of, and accountability for, roles and

PDF page 7

7

Questions/Comments
Yes No
responsibilities between PJM and the states/DC to ensure resource adequacy would it be appropriate to consider inserting “public interest” (caveated to ensure that it is framed in the context of the Federal Power Act) in the PJM governing documents. PJM’s governing documents also would need to reflect the accountability that the states/DC have agreed to assume. Otherwise, PJM would be upheld to a standard that its authorities alone cannot satisfy. Imposing such a significant legal standard would likely require authorization by Congress.

9) Should state representatives have at least one voting member on the Nominating Committee?

X

Comments: This question is unclear. There are at least 3 bodies of state government engaged in the governance discussions: state commissions, governors, and state legislators. This could be read to assume that one representative for each state, or one representative of each of these 3 bodies. Or both.

10) Should PJM adopt public performance metrics and tie management compensation to their achievement?

X

Comments: This question is unclear. If it is suggesting that a public interest standard could be translated to metrics for performance against which management would be assessed, it is unclear how that could be done. Whereas, PJM’s Operating Agreement currently charges the PJM Board to ensure reliability as well as non-discriminatory, competitive wholesale markets. Those objectives should be tied to management performance metrics.

Section 205 Filing Rights

Questions/Comments
Yes No
11) Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board?

X

Comments: For the stakeholder process to be advisory, the PJM Board would have Section 205 filing rights over every governing document and stakeholder votes would not result in any Section 205 filings, including “jump ball” filings. Additionally, to the extent that the TOA-AC may be considered part of the stakeholder process, it would be inappropriate to suggest that the asset owners who came together to enable the formation of PJM to not have a say in changes to the foundational agreement that governs the rules and responsibilities turned

PDF page 8

8

Questions/Comments
Yes No
over to PJM and those retained by the Transmission Owners.
12) Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain

approval of two-thirds of the Members Committee?

X

Comments: The current challenge is resource adequacy. PJM currently has Section 205 rights over its Tariff and the Reliability Assurance Agreement. Those are the operative governing documents to address the current challenge.

13) Should PJM have section 205 filing rights over Regional
Transmission Expansion Planning (RTEP) unencumbered by the
requirement to obtain approval of two-thirds of the Members
Committee?
X

Comments: Providing PJM with Section 205 rights over the RTEP protocol must be conditioned on appropriate dispute resolution procedures being established. As noted above, EKPC owes a duty to its owner-members and must comply with state regulations. It must have a meaningful opportunity to ensure that its perspectives are considered before changes that may impact its ability to plan its system are filed with the Commission.

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?

X

Comments: The PJM members (not OPSI), acting with a sector-weighted supermajority, should be afforded “jump ball” rights over resource adequacy. Transmission cost allocation filing rights must remain with the Transmission Owners as they need the ability to ensure that their cost to build and maintain the transmission system may be recovered. To the extent, however, that OPSI achieves a super-majority consensus on issues affecting resource adequacy or transmission cost allocation, they should be afforded the opportunity to present those perspectives to the PJM membership (for resource adequacy matters) or TOA-AC (for transmission cost allocation matters) and have those perspectives fully considered as proposals are being developed. Their input should be included and considered as part of the deliberative process, not something that occurs alongside or outside the deliberative process. In this way, OPSI may influence and essentially drive consensus to support a “jump ball” filing but not in and of themselves submit a “jump ball” filing. We believe this suggestion is consistent with the “jump ball” structure between NEPOOL and ISO New England.

PDF page 9

9

Questions/Comments
Yes No
15) Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?

X

Comments: See above comment.

Stakeholder Process

Questions/Comments
Yes No
16) Should the approval threshold in the Members Committee be lowered from two-thirds sector-weighted voting?

X

Comments:
17) Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?

X

Comments:

State Participation

Questions/Comments
Yes No
18) In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’ representatives?

X

Comments: Having multiple channels for state voices likely would result in confusion for PJM and for the membership. It would be difficult to determine which voice should be considered if the voices expressed conflicting views. The state perspective is valuable but should be channeled to best enable actionable impact. Ultimately, it would be important to consider the role and responsibility of any state group in order to determine the appropriateness of a particular configuration of state representatives for purposes of influencing outcomes affecting PJM and its ability to satisfy its mandate under the Operating Agreement consistent with the Federal Power Act. As noted above, EKPC urges clarity in the delineation of roles and responsibilities (and accountability to fulfill those responsibilities) between PJM and the states regarding resource adequacy.

PDF page 10

10

Questions/Comments
Yes No
19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes?

X

Comments: There should be an opportunity for OPSI to insert its consensus view on matters under deliberation in the PJM stakeholder process. That should be a structured role enabling the offering of proposals, offering feedback on other’s proposals, asking questions, and seeking analysis or information. This, however, should not be a formal voting role. EKPC supports the approach used in New England.

20) Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation?

X

Comments: There should be no explicit requirement that PJM consult with OPSI before it be permitted to submit a Section 205 filing with the Commission. However, it would be a good practice that PJM staff consult with OPSI throughout the process in which the proposal is being developed. As noted in the response above, the New England model would invite the OPSI to engage directly in the stakeholder process so that the stakeholders too have a meaningful opportunity to engage with the ideas initiated by OPSI. Transparency and efficiency are reinforced by including OPSI in the process. Creating an entirely separate process for engaging OPSI would conflict with transparency and efficiency objectives.

PDF page 11

11
EKPC appreciates the opportunity to submit the foregoing comments in response to the Commission’s questions. EKPC looks forward to continued dialogue on the important topics discussed herein.

Respectfully submitted,

Denise R. Foster Cronin
Chief Compliance Officer and Senior Vice
President
East Kentucky Power Cooperative, Inc.
4775 Lexington Road, P.O. Box 707
Winchester, KY 40392-0707
Tel.: 859-745-9615
denise.cronin@ekpc.coop

On Behalf of
East Kentucky Power Cooperative, Inc.

/s/ Daniel E. Frank

Daniel E. Frank
Allison E.S. Salvia
Kelly A. Cuthbertson
Eversheds Sutherland (US) LLP
700 Sixth St., N.W., Suite 700
Washington, DC 20001-3980
Tel.: 202-383-0100
danielfrank@eversheds-sutherland.com
allisonsalvia@eversheds-sutherland.com
kellycuthbertson@eversheds-sutherland.com

Counsel for
East Kentucky Power Cooperative, Inc.

Dated: August 21, 2026

PDF page 12

Certificate of Service

I hereby certify that I served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, DC this 21st day of August, 2026.

Kelly A. Cuthbertson

Kelly A. Cuthbertson