AD26-7-000 · 2026-08-21 · PSEG CompaniesPSEG Energy Resources & Trade LLCPSEG Power LLC, Public Service Electric and Gas Company

Post-Technical Conference Comments of PSEG Companies re PJM Governance and Stakeholder Reform

PDF page 1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Governance and Stakeholder Reforms

Docket No. AD26-7-000

POST-TECHNICAL CONFERENCE COMMENTS OF
THE PSEG COMPANIES

I. Introduction
The PSEG Companies appreciate the opportunity to provide comments in this proceeding following the July 23, 2026 PJM Governance Reform technical conference (“July technical conference”).  These comments address the questions posed in the Commission’s July 30 “Notice Requesting Post-Conference Comment.”1

As both a founding member and significant Transmission Owner (“TO”) in PJM, PSEG offers a unique and informed perspective on PJM’s flawed governance structure.  As we have emphasized in this proceeding, and as the Commission has recognized, the current effort to effectuate governance changes in PJM is not, and cannot be, an academic exercise or one that only addresses “low hanging fruit.”  In this regard, not all changes are created equal; for example, whether all or only certain PJM Board meetings are open to the public is not as significant from a governance reform perspective as deciding who should have filing rights or how votes should be taken or how to establish clear and workable rules around the future role of the states in resource adequacy decision-making.

Given the magnitude of the resource adequacy problem facing PJM, governance changes must be meaningful and advance better outcomes across the RTO – measured by (i) long-term

1 Notice Requesting Post-Conference Comment, Docket No. AD26-7 (July 30, 2026).

PDF page 2

2

system reliability for customers; (ii) stable and sustainable market rules; (iii) a bold, empowered and accountable PJM leadership and Board; and (iv) and a role for the states that reflects their fundamental responsibility for resource adequacy.  Specifically, we support the following as part of a comprehensive effort to revise PJM governance rules:

• Amending the Consolidated Transmission Owners Agreement (“CTOA”) and the PJM Operating Agreement (“OA”) to move regional transmission planning rules into PJM’s Tariff, thereby empowering PJM to make regional planning decisions;

• Revising the current voting rules to either (i) reflect members’ actual stake in, and accountability for, PJM outcomes or (ii) employ full advisory voting;

• Establishing enhanced accountability for PJM senior management and for its Board, which may include clear and transparent performance metrics and third-party evaluations of Board and management performance conducted on a regular cadence; and

• Granting states a clear, defined role in PJM resource adequacy decisions to reflect their primary legal responsibility in this area, which could entail “jump ball” filing rights on matters pertaining to resource adequacy.

We look forward to continuing to participate in shaping PJM governance rules as part of this proceeding, including as part of the upcoming Commission Alternative Dispute Resolution (“ADR”) process.2  With the fundamental objective of advancing better long-term outcomes at PJM, we offer the following responses to the Commission’s questions:

2 See PJM Governance and Stakeholder Reforms, Docket No. AD26-7, Notice Regarding Dispute Resolution Procedures (Aug. 10, 2026).

PDF page 3

3

II. QUESTIONS
PJM Board Independence
1) Should Board members’ terms be extended to five or more years?
Answer: Yes
Comments: With the caveat that, in our view, the length of Board member terms is not a root cause of the current problems PJM is facing, there is a benefit to giving Board members sufficient time in their roles to acquire necessary expertise so that they can effectively understand the challenges facing the PJM region and provide meaningful direction to PJM leadership.

2) Should there be a maximum number of years that a Board member may serve (e.g., 10 years)?

Answer: Yes
Comments:  Establishing a term limit for Board members should encourage bold, independent thinking and fresh perspectives on PJM’s ongoing challenges.

3) Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region?

Answer: Yes
Comments: It is appropriate to consider a multitude of factors when evaluating candidates for the PJM Board.  These factors could include (i) residency; (ii) other “significant ties” to the region;

(iii) knowledge of PJM operations and/or markets; and (iv) other requirements to help select Board members with requisite expertise and independent decision-making.

4) Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?

PDF page 4

4

Answer: Yes
Comments: The existing two-year cooling-off period may make it difficult to find qualified Board members.  Having rules in place that limit the available pool of Board candidates is counter-productive, particularly given the current challenges facing PJM.

5) Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders?

Answer: Yes
Comments: We support appropriately bounded enhancements that will enable stakeholders to better understand the PJM Board’s decision-making process and to bolster confidence in this process.

6) In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?

Answer: Yes
Comments: As explained in response to Question 5 above, it is important for PJM stakeholders to be able to understand Board decisions.  Therefore, at a minimum the Board should be required to explain its reasoning.  As part of the upcoming ADR process, PJM and its stakeholders should discuss whether making Board votes public would chill decision-making at the Board level or whether it instead makes sense to publicize these votes given that Members Committee votes are publicly recorded.

7) In order to increase transparency, should some Board meetings be open or available to the public?

Answer: Yes

PDF page 5

5

Comments: There is a balance that needs to be struck between establishing needed transparency and avoiding chilling independent Board decision-making.  As such, this question merits consideration as part of the upcoming ADR process.

8) Should PJM’s governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest?

Answer: This question requires further consideration as to whether adding this responsibility is needed on top of PJM’s existing, FERC-approved responsibilities and whether/how “serving the public interest” would be defined in this context.

Comments:  In Order No. 2000, the Commission established the following requirements for an RTO: independence from market participants; a region of sufficient scope and configuration to permit the RTO to effectively perform its required functions and to support efficient and nondiscriminatory power markets; possession of operational authority for all transmission facilities under the RTO's control; and exclusive authority to maintain short-term reliability.3 Significantly, Order No. 2000 did not include a “public interest” requirement governing RTO responsibilities.

PJM, which became a FERC-approved RTO in 2001,4 is not a regulator but is instead a public utility under the Federal Power Act, subject to Sections 205 and 206 of the Federal Power Act.  Both statutory provisions require that public utility jurisdictional rates and services must be

3 Reg'l Transmission Orgs., Order No. 2000, FERC Stats. & Regs. ¶ 31,089 (1999) (cross-referenced at 89 FERC ¶ 61,285), order on reh'g, Order No. 2000-A, FERC Stats. & Regs. ¶ 31,092 (2000) (cross- referenced at 90 FERC ¶ 61,201), aff'd sub nom. Pub. Util. Dist. No. 1 of Snohomish Cty. v. FERC, 272 F.3d 607 (D.C. Cir. 2001). 4 PJM Interconnection, L.L.C., et al., 96 FERC ¶ 61, 061 (2001), order on reh’g, 101 FERC ¶ 61,345 (2002).

PDF page 6

6

“just and reasonable.”5  These provisions do not superimpose a “public interest” standard on top of the “just and reasonable” standard.

Under the PJM Operating Agreement, PJM’s core responsibilities include (1) ensuring the safe and reliable operation of the PJM Region; (2) establishing and operating a “robust, competitive, and non-discriminator electric power markets in the PJM Region;” and (3) ensuring that “a member shall not have undue influence over the operation of the PJM Region.”6  Each of these core elements aligns with its responsibilities under Order No. 2000 and its FERC-approved governing documents.

PJM’s May 2026 whitepaper on market design reforms, entitled “Powering Reliability Through Market Design,” illustrates the challenges that occur when PJM seeks to make decisions through a nebulous “public interest” lens rather than through a lens that focuses on its core functions.  In our view, it simply creates indecision.  Rather than presenting a recommended market design to address the ongoing and critical resource adequacy problem, PJM’s whitepaper states that decisions on future market design “belong to the people and institutions with democratic accountability for their consequences – to state regulators and legislatures, to FERC, to consumers and the advocates who represent them.”7  What this really means is that PJM is not focusing on discharging its core, FERC-approved responsibilities but is instead creating decisional paralysis by trying to ascertain what regulators, legislators, consumers and “advocates” believe is in the “public interest.”

5 16 U.S.C. §§ 824d and 824e.
6 See Operating Agreement, Section 7.7(i).
7 See PJM’s May 6, 2026 Whitepaper entitled “Powering Reliability Through Market Design” at 1 (available at  20260506-powering-reliability-through-market-design.pdf) (“PJM May 2026 Whitepaper”).

PDF page 7

7

There are a myriad of fundamental questions and challenges that would flow from overlaying an ill-defined “public interest” standard on top of PJM’s responsibilities.  A few examples:

• Given PJM’s Order No. 1920-required 20-year transmission planning cycle, how would the “public interest” be measured in that context?  More fundamentally, what do “public interest” outcomes look like in the Regional Transmission Expansion Process (“RTEP”) process where there are significant upfront capital costs associated with infrastructure projects but long-term reliability and economic benefits?

• What is a “public interest” outcome in the capacity or energy markets, and who gets to decide that and over what time frame?

• Would the overlay of a “public interest” lens on planning, operations and markets decisions ultimately result in a less reliable system?

We are not suggesting that acting in the “public interest” should be ignored, as it cannot be ignored.  From the Transmission Owner perspective, we are a fully regulated utility tasked with providing reliable customer service at just and reasonable rates.  We make reliability and cost effectiveness a central consideration in all of our decision-making.  However, we challenge the notion that PJM should be tasked with ownership of a “public interest” standard.  Asking PJM to morph from a public utility to a “quasi-regulator” is establishing a role for PJM that is outside of its FERC-determined authority and, most importantly, will not produce better outcomes at PJM.  Instead, it will bog down PJM decision-making even further, and inhibit bold, independent, timely and decisive action.

9) Should state representatives have at least one voting member on the Nominating Committee?

PDF page 8

8

Answer: Yes
Comments: Given the states’ responsibility for resource adequacy, we support a more formal role for the states in PJM governance as pertains to resource adequacy.  While that role can take many forms, it must be linked to the broader goal of improved outcomes in PJM in the areas of reliable system planning and stable, well-functioning markets, an effective stakeholder process and measurable PJM accountability.  Within that framework, providing state representatives with membership on the Nominating Committee is one avenue to offer the states a concrete “seat at the table” on resource adequacy issues.

10) Should PJM adopt public performance metrics and tie management compensation to their achievement?

Answer: Yes
Comments: As we explained in our pre-technical conference comments, it is important for PJM to be empowered to make independent, difficult and sometimes unpopular but necessary decisions.  We specifically noted the existence of corporate governance principles that PJM and the Board could adopt to foster accountability and responsiveness from PJM leadership to the stakeholders, and clear, transparent performance metrics should be part of the equation.  As an example, we recommend the use of a third party to regularly evaluate the performance and effectiveness of its senior leadership.  Figuring out all of the mechanics of establishing performance metrics and monitoring those metrics is less important at this juncture than engaging in an earnest effort to increase organizational accountability for PJM. Section 205 Filing Rights

11) Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board?

PDF page 9

9

Answer: Yes.  Current PJM voting rules must change; however, our preferred approach would be to equate voting strength with membership responsibility for PJM outcomes, including system reliability.  Our alternative approach would be advisory voting, along with enhanced PJM accountability for its decision making.

Comments: As highlighted in our pre-technical conference comments, PJM’s voting structure no longer works to produce effective outcomes.  The current voting structure should be revised so that votes reflect a member’s actual stake in PJM outcomes, and we have proposed various ways to revise the voting structure accordingly (see our response to Question 16 below).  Alternatively, we understand that other ISOs/RTOs utilize a full advisory voting construct and that one could be adopted by PJM.  Such an approach would shift the ultimate responsibility for decision-making onto PJM.  We are wary of the challenges PJM has faced with its capacity market rules, an area where stakeholder voting is already advisory.  However, we are willing to consider an advisory voting construct in PJM to encourage its independence and decisiveness.  However, this approach must be accompanied by enhanced accountability, including for the PJM Board, so that members have confidence in the decisions PJM is making.

12) Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?

Answer: Yes
Comments: If accompanied by measures to ensure bold, independent and reliability-focused decision-making by PJM, we could consider this change as part of a comprehensive, negotiated resolution.

PDF page 10

10

13) Should PJM have section 205 filing rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?

Answer: Yes
Comments: As we stated in our pre-technical conference comments, PJM is the only RTO that does not have independent Section 205 filing rights over transmission planning, and this undermines PJM’s independence to plan the grid.  Both the CTOA and the OA must be revised to empower PJM to make effective regional planning decisions.  In addition, the PJM Transmission Owners must have audit rights to hold PJM accountable for its performance under the CTOA.

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?

Answer: Yes, as pertains to resource adequacy.  No, as pertains to transmission cost allocation. Comments: Resource adequacy is the most significant problem currently confronting PJM and its stakeholders.  As we noted in our pre-technical conference comments, in contrast to the states PJM has only “indirect responsibility for resource adequacy through its use of market pricing signals,” and “(t)here is a pressing need for clarity on the respective responsibilities between PJM and the states on resource adequacy.”8  Because the states have primary responsibility for resource adequacy, in this limited situation, allowing OPSI to have “jump ball” rights or a comparable mechanism is a logical and appropriate step towards enhanced state accountability on the issue.

8 See PJM Governance and Stakeholder Reforms, Docket No. AD26-7, Pre-Technical Conference Comments of the PSEG Companies at 15 (July 14, 2026) (“PSEG’s July 14, 2026 Pre-Technical Conference Comments”).

PDF page 11

11

At the same time, we do not support state “jump ball” filing rights on transmission cost allocation.  FERC and appellate court precedents have established that public utilities possess statutorily granted Section 205 filing rights with respect to transmission cost allocation, and that these rights cannot be modified or altered without the utility’s voluntary consent.9

15) Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?

Answer: Yes
Comments: A “jump ball” provision (or some other comparable mechanism) for the Members Committee over resource adequacy could provide an appropriate balance to PJM’s filing rights. This is because the Federal Power Act preserves state authority over generation facilities,10 and grants states primary jurisdiction over generation matters such as integrated resource planning utility generation mix, and retail procurement choices.11  Because PJM’s capacity market rules

9 See Atlantic City Electric Co. v. FERC, 329 F.3d 856 (DC Cir. 2003)(“holding that Section 205 of the FPA confers utilities the right to file rates and terms for services rendered, and that FERC cannot require transmission providers to relinquish those statutory rights);  See also Order No. 1920 at P 1363 and P 1430 (“Transmission providers retain ultimate responsibility for transmission planning and as discussed below, they have FPA section 205 filing rights to propose tariff changes to rates, which the Commission cannot deprive them of via this final rule” and “[w]e further clarify that unless voluntarily waived, a transmission provider retains its FPA section 205 filing rights.”); Order No. 1920-B at P 52 (“FPA section 205 expressly provides public utilities with statutory filing rights.”). In Order No. 1920-A, as part of the state engagement process, while the Commission directed public utilities to include as an “attachment” in their Order No. 1920 compliance filing the states’ cost allocation proposal, the Commission strongly emphasized it was invoking its authority under Section 206 of the FPA and was not intruding upon the transmission owners’ section 205 filing rights, emphasizing that “public utilities retain all of their right to file proposed rate changes under FPA section 205.  See Order No. 1920-B at PP 52-53, 55.
10 FPA Section 201(b)(1) (providing that the Commission has jurisdiction over all facilities used for the transmission or sale of electric energy in interstate commerce but “shall not have jurisdiction . . . over facilities used for the generation of electric energy.”).
11 See, e.g., PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 at P 48 (2026) (recognizing the bifurcation of jurisdiction under the FPA and that FERC has “exclusive authority” with respect to the rates, terms, and conditions of transmission service while the FPA “expressly reserves to the states the authority over,”

PDF page 12

12

directly affect state generation decisions, a “jump ball” over resource adequacy properly recognizes these statutorily reserved state rights over generation and resource mix issues.  We would expect, however, that any “jump ball” mechanism would be triggered infrequently, functioning as a tool for accountability and helping to ensure that PJM works effectively with its stakeholders including the states.

As explained above, we do not support a “jump ball” provision with respect to
transmission cost allocation filings.
Stakeholder Process
16) Should the approval threshold in the Members Committee be lowered from two-thirds sector-weighted voting?

Answer: Yes
Comments: PJM’s voting structure results in asset owners with responsibility for customer reliability having a significantly diluted vote. Sector-weighted voting must change to reflect the current membership composition, voting behaviors (including “sector blocking” that occurs when two of the five sectors vote together under the two-thirds construct) and the daunting challenges PJM is facing.  There are multiple approaches that may be considered, ranging from a realignment of voting interests to reflect member responsibilities/accountabilities12 to an advisory voting construct.  In addition, revising the current senior voting committee threshold to a lower value (e.g., NYISO employs a 58% threshold for Management Committee votes) would

among other things, retail sales as well as “facilities used for the generation and distribution of electricity.”).

12 See PSEG’s July 14, 2026 Pre-Conference Comments at 9-11 (discussing proposed changes to the voting structure to reflect members’ actual economic and operational stake in PJM outcomes, such as matching voting interest with member responsibilities under the default cost allocation methodology contained in Section 15.2.2 of the OA).

PDF page 13

13

avoid the sector blocking issue and help to at least mitigate asset owner “dilution of vote” concerns.

17) Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?

Answer: No
Comments: Although PSEG’s vote constitutes only about 1.5% of the total vote in PJM senior standing committees, it only accounts for 0.4% of the vote in the lower committees where affiliate voting is employed.  We do not view affiliate voting as a significant issue that needs to be addressed at this time to achieve better outcomes in PJM.

State Participation
18) In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’ representatives?

Answer: Yes, subject to comments below
Comments: We are less concerned with the exact number of regional state committees that are in place and more concerned that any committee(s) established to address resource adequacy have clearly defined roles and responsibilities vis-à-vis those of PJM and the transmission owners. Absent that clarity, additional voices from the states in a new state representative group will lead to confusion and delay.

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes?

Answer: Yes, subject to comments below

PDF page 14

14

Comments: Noting the response to the prior question concerning clearly defined roles and responsibilities, we would support a formal voting role for state representatives in the PJM stakeholder process with respect to resource adequacy.  The PJM states have authority to address resource adequacy through the planning of generation and a vested interest in ensuring that, to the extent they continue to rely on PJM’s markets, rules for those markets are transparent and will procure sufficient supply to maintain reliability.  However, OPSI – or other state representatives – cannot have a voting role over transmission cost allocation unless voluntarily agreed to by the transmission owners since this would contravene established precedent bestowing exclusive Section 205 filing rights over transmission cost allocation on the PJM transmission owners.13

20) Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation?

Answer: Yes, with respect to resource adequacy.  No, with respect to transmission cost allocation.

Comments: Under the current rules, PJM is under no specific obligation to consult with OPSI in a manner that is unique relative to other stakeholders.  Given the states’ responsibility for resource adequacy, however, it may make sense for PJM to consult with OPSI before it makes a Section 205 filing addressing resource adequacy.  PJM and OPSI would need to develop a workable and efficient process for consultation.  We do not support formal consultation with OPSI with respect to transmission cost allocation filings (over which the Transmission Owners, not PJM, have decision-making authority).  At the same time, the transmission owners will

13 See Atlantic City Electric Co. v. FERC, 329 F.3d 856 (DC Cir. 2003).  See also Order No. 1920 at P 1430 (“We further clarify that unless voluntarily waived, a transmission provider retains its FPA section 205 filing rights.”).

PDF page 15

15

continue to work collaboratively with OPSI – as is currently occurring in the context of the Order 1920 PJM Area Relevant State Entities Committee (PARSEC) process – to ensure that the states fully and timely understand any future cost allocation changes and the impacts to customers.

Respectfully submitted,

 Jodi L. Moskowitz
Jodi L. Moskowitz
Vice President – Law, Deputy General Counsel &
RTO Strategy Officer
PSEG Services Corporation
80 Park Plaza, T20
Newark, NJ 07102
(973) 985-7958
Jodi.Moskowitz@PSEG.com
On behalf of the PSEG Companies

Dated: August 21, 2026
Newark, New Jersey