AD26-7-000 · 2026-08-21 · Shell Energy North America (US), L.P.
Post-Technical Conference Comments of Shell Energy North America (US), L.P. re PJM Governance and Stakeholder Reforms
PDF page 1
Page 1 of 2
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Governance and Stakeholder Reforms
)
Docket No. AD26-7-000
)
POST-TECHNICAL CONFERENCE COMMENTS OF
SHELL ENERGY NORTH AMERICA (US), L.P.
Shell Energy North America (US), L.P. (“Shell Energy”)1 submits these comments on the
Staff-led technical conference held on July 23, 2026, in the above-referenced docket.2 Shell Energy appreciates this opportunity the Federal Energy Regulatory Commission (“FERC” or
“Commission”) has created for stakeholders to collaborate on enhancements to PJM’s governance and stakeholder process. PJM has made meaningful progress over the past year in enhancing
transparency and stakeholder engagement. Further reforms should be evaluated based on whether they improve decision-making, allow appropriate checks and balances, and support the regulatory certainty needed to promote investment and maintain reliability at just and reasonable rates.
I. COMMENTS
Shell Energy appreciates the Commission’s consideration of PJM governance and supports
efforts to improve decision making, transparency, and accountability. At the same time,
1 Shell Energy is one of the largest traders of electricity, natural gas, and environmental products in North America and actively participates in wholesale electric markets across North America, including markets administered by PJM. In addition, Shell Energy has affiliates that invest in, own, and develop storage, natural gas, clean energy resources, supply retail power to customers, and are commercial and industrial end users. While Shell Energy is a Member of PJM’s Other Supplier Sector, it is unique in that it represents most lines of businesses within the Other Supplier Sector and other PJM sectors.2 PJM Governance and Stakeholder Reforms, Notice Requesting Post-Conference Comment, Docket No. AD26-7- 000 (July 30, 2026).
PDF page 2
Page 2 of 3
governance reform should not be viewed as a substitute for addressing the underlying market challenges confronting PJM.3
In September 2023, Shell Energy urged PJM to undertake a broader examination of
investment barriers and future market design, noting that regulatory uncertainty, administrative complexity, rule intervention, and declining forward-market liquidity were undermining investor confidence.4 Since then, PJM has increasingly recognized the need for a more holistic assessment of resource adequacy and market design.5
While many of the governance proposals under consideration are motivated by resource
adequacy concerns, reliability depends on investment decisions driven by expectations across the full revenue stack, including capacity, energy, and ancillary services revenues.6 Resource adequacy therefore cannot be viewed in isolation from broader market design.
The central question in this proceeding is not simply whether PJM’s governance structure should change, but whether any reforms will help produce a transparent, durable, and investable market framework capable of maintaining reliability at just and reasonable rates. Governance reforms should facilitate timely decision-making while preserving stakeholder engagement, accountability, and regulatory certainty. Equally important, they should maintain the checks and
3 See Meeting the Challenge of Resource Adequacy in Regional Transmission Organization and Independent System Operator Regions, Docket No. AD25-7-000, Shell Energy Comments at 6 nn.8-10, 12 (May 21, 2025) (“Shell Energy Resource Adequacy Comments”) (describing challenges of PJM market); Docket No. AD25-7-000, Shell Energy Post-Technical Conference Comments at 2-3 nn. 9-10 (June 27, 2025) (“Shell Energy Post-Technical Conference Resource Adequacy Comments”) (describing challenges of PJM market adjustments, complaints, and retroactive changes).4 See Letter from Shell Energy North America (US), L.P. to the PJM Board of Managers regarding Critical Issue Fast Path Capacity Market Reforms and Looking Beyond (Sept. 18, 2023).5 See PJM’s Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment To Support Durable Reliability (May 6, 2026) (“PJM’s Holistic Market Review”).6 See Shell Energy Resource Adequacy Comments at 3-5 (discussing revenues needed to overcome investment hurdle rates as shown in Figure 1. Revenue Stack Example of Various Resource Types”); see also Shell Energy Post- Technical Conference Comments at 5 n.17.
PDF page 3
Page 3 of 4
balances that promote durable outcomes and confidence in the stakeholder process. Governance reforms can improve efficiency; lasting success, however, will require PJM to remain independent and focused on market outcomes that support investment, liquidity, and resource adequacy. Governance reform should complement, not distract from, the broader effort to strengthen market design and address the region’s underlying reliability and cost-allocation challenges.
II. APPENDIX RESPONSES
The responses below reflect these principles and focus on reforms that improve decision- making and preserve stakeholder accountability, market transparency, and confidence in PJM’s long-term reliability objectives and market framework.
PJM Board Independence
1. Should Board members’ terms be extended to five or more years?
Governance research and board governance best practices support periodic board renewal and recognize that long tenure can diminish independence, critical oversight, and the introduction of new perspectives. While no single tenure limit has been shown to be universally optimal, many organizations establish an outer limit of approximately six to nine years of continuous board service. 7 Multi-year staggered terms, like those in effect in PJM, are preferred over a single lengthy term.8 Staggered renewable terms provide periodic opportunities to assess engagement, performance, and continued fit. They also promote board continuity through staggered turnover and reduce the risk of multiple directors departing simultaneously.
7 See Sterling Huang & Gilles Hilary, Zombie Boards: Board Tenure and Firm Performance, 56 Journal of Accounting Research 1285 (2018); BoardSource, Leading with Intent: BoardSource Index of Nonprofit Board Practices at 33, 74 (2021); BoardSource, Board Term Limits (2024).
8 See BoardSource, Leading with Intent: BoardSource Index of Nonprofit Board Practices at 33, 74 (2021); BoardSource, Board Term Limits (2024).
PDF page 4
Page 4 of 5
2. Should there be a maximum number of years that a Board member may serve (e.g., 10 years)?
Industry practice generally supports term limits, while allowing limited discretion in exceptional circumstances to justify service beyond term limits (e.g. term limit waivers for MISO Board members Barbara Krumsiek and Todd Raba in 2025). PJM’s current governance framework achieves this balance through staggered three-year terms and a five-term maximum (15 years). As discussed in Response 1, regular re-election cycles provide opportunities to assess performance, engagement, independence, and continued fit, while preserving valuable institutional knowledge and continuity. As a result, PJM’s existing approach appropriately balances board refreshment with long-term effectiveness.
3. Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region?
While familiarity with the PJM region is beneficial, expertise is not contingent on current residence. The primary qualifications for Board service should remain independence, expertise, and governance capability. Residency within the footprint may be considered a positive factor but should not be a mandatory qualification that could unnecessarily limit the pool of potential candidates.
4. Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?
This change would potentially increase the pool of candidates. Prospective Board members should remain subject to PJM’s conflict-of-interest and independence requirements, including restrictions on financial interests in and business relationships with PJM Member companies and their affiliates.
PDF page 5
Page 5 of 6
5. Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders?
The current ex parte communication framework appropriately protects the Board’s independence and helps prevent undue influence. PJM has made progress in expanding opportunities for Board engagement through forums such as at the end of Members Committee meetings. Additional engagement should be pursued within the existing framework.
6. In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?
PJM has made significant progress on transparency through Board letters and other communications. The Board should continue to enhance transparency by explaining the rationale for its decisions, including insight into differing views considered during deliberations, and why its views may have switched over time. Public disclosure of individual Board member votes raises separate concerns. It could increase the risk of lobbying, undue influence, or retaliation directed at individual members, making robust ex parte protections even more important. Board performance should be assessed based on the integrity of its process, decision-making, and engagement; not on whether stakeholders agree with a particular outcome.
7. In order to increase transparency, should some Board meetings be open or available to the public?
Select Board meetings or meeting segments should be open to the public to increase transparency and demonstrate that stakeholder and public concerns are being considered. However, confidential or market-sensitive discussions should remain closed to ensure effective governance.
PDF page 6
Page 6 of 7
8. Should PJM’s governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest?
PJM and its Board advance the public interest by ensuring reliability, just and reasonable rates, and well-functioning competitive markets. PJM members invest in and provide the infrastructure and risk management necessary to help achieve these outcomes. Any such revision should clearly define the term and avoid creating ambiguity that could allow PJM’s core responsibilities to be deprioritized in favor of particular stakeholder or policy preferences.
9. Should state representatives have at least one voting member on the Nominating Committee?
Consumer interests are already represented by the End Use Consumer sector’s voting seat, so the purpose and responsibilities of a state representative seat must be clearly structured to support PJM’s overall interests rather than those of any individual state or policy agenda. Because the Nominating Committee Code of Conduct requires its members to act in the best interests of PJM, the selection criteria for any state representative should be transparent, objective and designed to promote independence from political considerations.
10. Should PJM adopt public performance metrics and tie management compensation to their achievement?
Transparent, publicly reported performance metrics that are tied to management compensation would enhance accountability and align management incentives with PJM’s core responsibilities.
Section 205 Filing Rights
11. Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board? An advisory stakeholder process may improve PJM’s ability to act more quickly, but
PDF page 7
Page 7 of 8
it should not be adopted if PJM also receives exclusive Section 205 filing rights. The stakeholder process serves important functions beyond producing votes, including vetting proposals, identifying unintended consequences, improving filings, and encouraging compromise before issues reach FERC. If stakeholder votes are merely advisory and PJM has sole authority to file under Section 205, stakeholders may have little incentive to invest in consensus-building and instead reserve their efforts for privately lobbying of PJM staff and litigation before FERC.
The MISO Resource Availability and Need (RAN) proceeding illustrates this concern. In 2021, stakeholders overwhelmingly supported a motion requesting that MISO delay its filing and implementation schedule. MISO ultimately chose not to follow the stakeholder recommendation and proceeded with its filing after only a limited delay.9 This example demonstrates how an advisory process can leave stakeholders with influence, but little practical ability to shape the outcome when management disagrees.
Accordingly, stakeholder voting should become advisory only if stakeholders are provided a meaningful “jump-ball” right to bring alternative proposals before FERC. Providing meaningful jump-ball rights helps ensure that stakeholder engagement continues to improve proposals, identify unintended consequences, and produce more durable market reforms.
12. Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?
9 See Midcontinent Independent System Operator, Inc., Filing to Include Seasonal and Accreditation Requirements for the MISO Resource Adequacy Construct, Docket No. ER22-495-000 at 22 (filed Nov. 30, 2021) (proceeding with filing after stakeholders overwhelmingly supported motion requesting later filing date and delayed implementation schedule).
PDF page 8
Page 8 of 9
PJM should have unencumbered Section 205 filing rights over the energy and ancillary services markets provided stakeholders are afforded meaningful “jump ball” rights that allow FERC to consider stakeholder-supported alternative proposals. This approach supports timely decision-making, creates an important governance check, and maintains incentives for stakeholders to build consensus. As reforms across capacity, energy, and ancillary services markets are considered as part of PJM’s Holistic Market Review, a consistent legal framework would improve regulatory certainty and investment across the full revenue stack.
13. Should PJM have section 205 filing rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?
As with energy and ancillary services, PJM should have unencumbered Section 205 filing rights over RTEP provided stakeholders have meaningful “jump ball” rights that allow alternative proposals to be presented to FERC. Otherwise, exclusive filing authority would concentrate authority in PJM and reduce an important check and balance within PJM’s governance framework.
The Commission recently considered related issues in EL24-119, ER24-2336, and ER24-2338. While FERC rejected the specific proposal before it, the proceedings highlighted the importance of carefully balancing PJM independence, stakeholder participation, and governance accountability. As discussed in Response 11, the 2021 MISO Resource Availability and Need (RAN) proceeding further illustrates the importance of preserving meaningful stakeholder checks. Having a mechanism for stakeholders to advance alternative proposals to FERC would help maintain confidence in the stakeholder process and encourage continued investment in consensus building.
PDF page 9
Page 9 of 10
14. Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?
OPSI should not receive separate jump-ball rights. If additional state participation is warranted, OPSI could advance proposals through the stakeholder process on the same footing as other stakeholder proposals considered by the Members Committee.
15. Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?
The Members Committee should have meaningful jump-ball rights when a
supermajority of stakeholders approves an alternative proposal in areas where PJM has Section 205 filing authority. Similar to the NEPOOL framework in ISO-NE, the Members Committee should be able to advance stakeholder supported alternative proposals to FERC, which would allow PJM to independently file the proposal it believes is necessary to fulfill its responsibilities.
Jump-ball rights promote stakeholder engagement, encourage consensus-building, and provide an important governance check without granting stakeholders veto authority over PJM filings. They also ensure that FERC can evaluate competing proposals on their merits when consensus cannot be reached.
As PJM considers coordinated reforms across the capacity, energy, and ancillary service markets, reserving meaningful jump-ball rights will help maintain confidence in the stakeholder process while ensuring that broader market reforms benefit from a robust record before the Commission.
PDF page 10
Page 10 of 11
Stakeholder Process
16. Should the approval threshold in the Members Committee be lowered from two-thirds sector-weighted voting?
Any reduction in the Members Committee approval threshold should be limited to 60% sector-weighted voting (three sectors). This would improve efficiency while preserving the need for broad stakeholder support and maintaining an important governance check on PJM’s Section 205 authority. To the extent PJM has unilateral Section 205 filing rights over portions of the Tariff or Operating Agreement, the approval threshold is arbitrary.
17. Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?
Applying affiliate voting restrictions consistently across all committee levels would improve the consistency and perceived fairness of the stakeholder process. While no voting structure perfectly aligns voting power with stakeholder interests and deployed capital, this could allow removal of layers of committees that often encumber the stakeholder process. PJM could also consider a representative voting model like those used in ERCOT and MISO, where elected sector representatives vote on behalf of their sectors at the highest levels of the stakeholder process. Such an approach could encourage greater consensus-building within sectors and improve the efficiency of stakeholder decision-making.
State Participation
18. In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’ representatives?
Rather than creating a second state representative organization, FERC should consider whether OPSI could be expanded to incorporate additional state perspectives. OPSI already provides a coordinated regional forum for state utility regulators within the PJM footprint.
PDF page 11
Page 11 of 12
Creating a separate organization for governors’ representatives and/or legislators could lead to duplicative processes, conflicting recommendations, and additional governance complexity. If FERC concludes that broader state participation is warranted, a more effective approach may be to expand OPSI’s role in a manner similar to NESCOE in New England. Such a structure could provide a single forum for utility regulators, governors’ offices and other state energy policymakers to coordinate and engage with PJM, while preserving each state’s independent authority to advocate for its own positions before PJM and FERC.
19. Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes?
Allowing state voting rights to a subset of topics would create unnecessary complexity and likely lead to disputes over which issues qualify for state participation. If additional state involvement is warranted, strengthening OPSI’s consultative role, similar to NESCOE's role in New England, would provide a clearer and more effective mechanism for state engagement than creating a new voting class within the stakeholder process.
20. Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation?
PJM should consult with OPSI before making Section 205 filings on these issues. Such consultation would ensure state regulators have a formal opportunity to provide input, like the role stakeholder consultation plays through the Members Committee. New England’s experience with NESCOE demonstrates the value of structured state engagement while preserving RTO and state independence.
PDF page 12
Page 12 of 13
III. CONCLUSION
Shell Energy appreciates the opportunity to provide these comments. As PJM considers coordinated reforms across capacity, energy, and ancillary services, governance changes should prioritize timely decision-making, meaningful stakeholder engagement and appropriate checks and balances. A governance framework that balances efficiency, accountability, and transparency will be better positioned to support investment, maintain confidence in PJM markets, and enable durable market reforms that support reliability over the long term.
Ultimately, governance reform should be evaluated based on whether it helps PJM maintain reliability, support just and reasonable rates, and advance a transparent, durable and investable market framework.
PDF page 13
Page 13 of 14
Shell Energy looks forward to continuing to work constructively with the Commission, PJM, and stakeholders to advance durable solutions to the region’s market design and reliability challenges.
Respectfully Submitted,
/s/ Sean Chang
___________________________
Sean Chang
Director, Regulatory Affairs
Shell Energy North America (US), L.P.
1000 Main Street, Level 12
Houston, TX 77002
(713) 230-3340
Sean.Chang@shell.com
/s/ Jennifer Fletcher
___________________________
Jennifer Fletcher
Director, Regulatory Affairs
Shell Energy North America (US), L.P.
1050 K Street NW, Suite 700
Washington, DC 20001
(858) 323-6606
Jennifer.Fletcher@shell.com
/s/ Shaela Collins
___________________________
Shaela McNulty Collins
Senior Power Policy Adviser, Corporate Relations
Shell USA, Inc.
1050 K Street NW, Suite 700
Washington DC 20001
(508) 523-0378
Shaela.Collins@shell.com
Dated: August 21, 2026
PDF page 14
Page 14 of 14
CERTIFICATE OF SERVICE
I hereby certify that I have this day electronically served the foregoing document on each person designated on the official service list compiled by the Secretary of the Federal Energy Regulatory Commission in this proceeding.
Dated at Washington, D.C., this 21st day of August 2026.
/s/ Jennifer Fletcher
Jennifer Fletcher