ER26-3380-000 · 2026-08-21 · CPV Power Holdings, LP
Motion to Intervene and Comments of CPV Power Holdings, LP re PJM Interconnection, L.L.C.’s 07/31/2026 filing
PDF page 1
DCACTIVE-88550388.31
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3380-000
Motion to Intervene and Comments of CPV Power Holdings, LP
Pursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) Rules of Practice and Procedure,1 CPV Power Holdings, LP (“CPV”) moves to intervene and comment on the July 31, 2026 filing by PJM Interconnection, L.L.C. (“PJM”) in the above-captioned proceeding.2 In the RBP Proposal, PJM proposes revisions to the PJM Open Access Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load Serving Entities to implement the Reliability Backstop Procurement (“RBP”) framework—a one-time mechanism for procuring new capacity to address PJM’s resource adequacy shortfalls.
I. SUMMARY
CPV supports the RBP Proposal and believes it is a critical step toward restoring resource adequacy in the PJM region. PJM is facing a significant capacity shortfall as observed by the 2028/29 Base Residual Auction, which fell 6,831 MW short of the Reliability Requirement. Load forecasts indicate that this shortfall is expected to grow considerably over the next 5–10 years, primarily driven by large load additions and data center growth. The RBP is a necessary and timely response to this growing resource adequacy challenge.
CPV participated throughout the months-long Critical Issues Fast Path (“CIFP”) proceeding that culminated in the RBP Proposal and appreciates PJM’s efforts to develop a necessary and timely response to the resource adequacy shortfalls facing the PJM region. The
118 C.F.R. §§ 385.212 and 385.214 (2025).
2PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads” (July 31, 2026) (“RBP Proposal”).
PDF page 2
DCACTIVE-88550388.32
RBP Proposal combines feedback from the diverse group of parties that participated in the CIFP to yield an overall package that aims to protect ratepayer interests while still providing the decisive action that the moment calls for.
A confluence of conditions in recent years, including interconnection queue delays, significant increases in equipment and development costs, supply chain constraints, and extended construction durations, has made bringing new generation resources online increasingly difficult. Despite these conditions, companies including CPV have continued to develop new generation projects, many of which are in the late stages of development and have the potential to enter construction in the near term. Absent immediate action to facilitate the financing and construction of these late-stage projects, it is unlikely that new generation will be built at the scale necessary to keep pace with expected load growth. The RBP Proposal will use gating criteria to evaluate sponsor credentials and development progress and determine which are most likely to enter service, while distinguishing between advanced and more speculative projects. The selection process will then select projects in least-cost order, subject to prioritization based on expected in-service dates,3 and provide them with the long-term commitments needed in today’s environment to enable them to reach financial close, commence construction, and ultimately reach commercial operations.
While supportive of the RBP Proposal, in reviewing PJM’s July 31, 2026, filing in this proceeding, CPV identified one issue with the gating criteria language that requires clarification to avoid causing confusion about the gating requirements, inadvertently narrowing the pool of
3Given the significant weight placed on expected in-service dates in the RBP selection process, rigorous application of the gating criteria will be particularly important to ensure that proposed commercial operation dates are realistic and projects are assigned to the appropriate Delivery Year. Otherwise, the selection methodology could result in a significantly higher-cost project being selected based on a perceived timing advantage that ultimately may not materialize, with little or no corresponding reliability benefit.
PDF page 3
DCACTIVE-88550388.33
eligible projects, and undermining the effectiveness of the procurement. Specifically, the site control requirement of the RBP’s gating criteria applicable to RBP Sell Offers, set forth in Attachment DD § 18.5(f)(i)(2), appears to contain a drafting error that could unintentionally exclude projects currently in PJM’s interconnection queue that have already satisfied applicable site control requirements under existing Tariff provisions. CPV does not believe PJM intended this result and proposes a narrow revision to the Tariff language to clarify its intended application. With this limited clarification, CPV respectfully urges the Commission to act by, and accept the RBP Proposal and Tariff changes subject to a compliance filing effective, September 29, 2026, as PJM requested.4
II. MOTION TO INTERVENE
CPV and its affiliates develop, own, and operate electric generating facilities that participate in the PJM markets. PJM’s RBP Proposal and associated Tariff changes will directly and substantially affect CPV and its affiliates. Accordingly, CPV has a direct and substantial interest in the outcome of this proceeding that no other party can adequately represent. CPV’s participation is in the public interest, and it respectfully requests that the Commission grant this timely filed motion to intervene.
III. COMMENTS
Although CPV generally supports the RBP Proposal, it respectfully submits the following comments addressing one discrete issue: PJM’s proposed site control requirement applicable to RBP Sell Offers.
4RBP Proposal at 2–4.
PDF page 4
DCACTIVE-88550388.34
Under the RBP Proposal, a seller must satisfy certain gating criteria to submit a valid RBP Sell Offer for RBP UCAP MW.5 Among those criteria, PJM proposes to require a seller to provide evidence of 100% site control in Attachment DD § 18.5(f)(i)(2) of its proposed Tariff changes:
Evidence of 100% Site Control for each of the Generating Facility (including the location of the main step-up transformer), the Interconnection Facilities, and the Interconnection Switchyard (as defined in the PJM Manuals) for a term of at least three years from the date of submission of the Application.6
As discussed below, CPV has identified two related aspects of this provision that warrant clarification to avoid unnecessarily narrowing the pool of eligible sellers and undermining the effectiveness of the RBP.
The proposed section 18.5(f)(i)(2) requires a seller to demonstrate site control for a term of at least three years from the date of submission of the “Application.” The Tariff’s existing definition of Application, however, has no connection to the RBP.7 Notably, PJM does not use the term “Application” in the RBP Proposal to describe a seller’s submission; instead, PJM consistently uses “RBP Sell Offer” to describe the mechanism by which sellers offer to sell RBP Resources. This strongly indicates that PJM intended to reference the date of submission of the RBP Sell Offer.8
Second, as drafted, the proposed section 18.5(f)(i)(2) does not appear to account for sellers with generation projects currently active in PJM’s interconnection queue that have already
5See RBP Proposal at 71–74; Proposed Tariff, Attachment DD, § 18.5(f)(i).6RBP Proposal at 73, n.189; Proposed Tariff, Attachment DD, § 18.5(f)(i)(2).7See RBP Proposal at 1, n.1 (“Capitalized terms not otherwise defined herein have the meaning as defined in the Tariff, Amended and Restated Operating Agreement of PJM [], RAA, and Consolidated Transmission Owners Agreement [].”); see PJM Tariff, Part 1, § 1, Definitions – Application (“‘Application’ shall mean a request by an Eligible Customer for transmission service pursuant to the provisions of the Tariff.”).8The RBP Sell Offer is defined as “an offer to sell RBP Resources in the Reliability Backstop Procurement.” RBP Proposal at 46, n.122; Proposed Tariff, Definitions – RBP Sell Offer.
PDF page 5
DCACTIVE-88550388.35
satisfied the applicable site control requirements under PJM’s existing Tariff. PJM’s existing interconnection procedures require generation project developers to demonstrate site control as a condition of advancing through the queue.9 Requiring such developers to separately satisfy a new three-year requirement on limited notice could impose an unnecessary additional burden on sellers that have already demonstrated to PJM’s satisfaction that they possess the requisite site control for their generating facility and related infrastructure under PJM’s existing generator interconnection procedures, and risks disqualifying advanced projects from the RBP.
For example, projects in Transition Cycle #1 and Transition Cycle #2, which have
reached advanced stages of the interconnection process , have already demonstrated site control as a prerequisite to their continued advancement through the queue. Yet under section 18.5(f)(i)(2) as currently proposed, these projects could inadvertently be excluded from participation in the RBP based solely on the discrepancies between the two sets of site control requirements. Such an outcome would unnecessarily limit the pool of eligible resources, contrary to the RBP’s stated objective of selecting resources “most likely to go into service and provide needed capacity.”10 Based on this objective, and the extensive discussions during the CIFP proceeding, CPV does not believe that this was PJM’s intent with the site control gating criteria.119See Tariff, Part VII, Subpart A, section 302 (explaining that a developer in PJM’s Transition Cycle must meet numerous site control requirements throughout the interconnection process); id. at Part VIII, Subpart A, section 302 (explaining that a developer in PJM’s regular cycle must meet numerous site control requirements throughout the interconnection process).10RBP Proposal at 71.11See PJM Interconnection, L.L.C., CIFP – Reliability Backstop Procurement – Options and Packages Matrix – Updated, Row 13, Selection Process (June 29, 2026) (providing, as part of PJM’s proposal, “Evidence of site control consistent with PJM Tariff Part VII, Subpart A, Section 302, and PJM Tariff Part VIII, Subpart A, Section 402”) (“RBP Options Matrix”), available at https://www.pjm.com/committees-and-groups/cifp-rbp.
PDF page 6
DCACTIVE-88550388.36
To remedy these concerns, CPV respectfully requests that the Commission direct PJM to submit revisions to section 18.5(f)(i)(2) in a compliance filing,12 as follows: For projects without an active queue position, eEvidence of 100% Site Control for each of the Generating Facility (including the location of the main step-up transformer), the Interconnection Facilities, and the Interconnection Switchyard (as defined in the PJM Manuals) for a term of at least three years from the date of submission of the Application RBP Sell Offer.
This limited revision would preserve PJM’s site control requirement for projects without active queue positions while recognizing that projects already in the interconnection queue are subject to existing site control requirements under the Tariff. The revision would therefore clarify the requirement by using terminology applicable to the RBP Proposal and avoid unintentionally excluding advanced projects without altering the overall design of the RBP Proposal.
IV. COMMUNICATIONS
Please address all notices and communications regarding this proceeding to the following persons who are also designated for service in this proceeding:
Jonathan Odell
Executive Vice President and General Counsel
Competitive Power Ventures, Inc.
8403 Colesville Road, Suite 915
Silver Spring, MD 20910
Tel: (240) 723-2300
jodell@cpv.com
Deborah A. Carpentier
Kathy Lowrey
Crowell & Moring LLP
600 Fifth Street, NW
Washington, DC 20001
Tel: (202) 624-2857
dcarpentier@crowell.com
klowrey@crowell.com
12PJM consents to the Commission using its authority under NRG Power Marketing, LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017) to “modify and/or sever any element of the proposed Tariff and RAA language to the extent necessary . . . .” RBP Proposal at 3.
PDF page 7
DCACTIVE-88550388.37
V. CONCLUSION
For the foregoing reasons, CPV respectfully requests the Commission to grant its requests herein, and to act on PJM’s RBP Proposal by, and accept the related Tariff changes, subject to a compliance filing, effective, September 29, 2026, as requested by PJM..
Respectfully submitted,
August 21, 2026
/s/ Deborah A. Carpentier
Deborah A. Carpentier
Kathy Lowrey
Crowell & Moring LLP
600 Fifth Street, NW
Washington, DC 20001
Tel: (202) 624-2857
dcarpentier@crowell.com
klowrey@crowell.com
Counsel for CPV Power Holdings, LP
CERTIFICATE OF SERVICE
I hereby certify that on this 21st day of August, 2026, a copy of the foregoing document has been electronically served upon each person designated on the official service list in this proceeding.
/s/ Kathy Lowrey
Kathy Lowrey