Post-Conference Comments of Advanced Energy United re the technical discussion of Governance and Stakeholder Reforms in the PJM Interconnection region on…
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Governance and
)
Docket No. AD26-7-000
Stakeholder Reforms
)
)
POST-CONFERENCE COMMENTS OF ADVANCED ENERGY UNITED
Advanced Energy United (“United”)1 appreciates the opportunity to provide post-
conference comments following the Federal Energy Regulatory Commission’s (“FERC” or
“Commission”) technical discussion of Governance and Stakeholder Reforms in the PJM
Interconnection (“PJM”) region on July 23, 2026. The Commission should be commended for
facilitating a constructive and candid exchange of ideas and for setting a clear plan for the region to take swift and decisive action.
The comments below expand upon pre-conference comments submitted by United in this
docket, which outlined our perspective on the root causes of the challenges PJM faces and offered recommendations with respect to the role of states, the PJM Board, and PJM
stakeholders.2 United’s primary objective in this proceeding is to ensure that PJM retains its role
1 Advanced Energy United is a national association of businesses that are making the energy we use secure, clean and affordable. Advanced Energy United is the only industry association in the United States that represents the full range of advanced energy technologies and services, both grid-scale and distributed. Advanced energy includes energy efficiency, demand response, energy storage, wind, solar, hydro, nuclear, electric vehicles, and more. The comments expressed in this filing represent the position of Advanced Energy United but may not represent the views of any particular member.2 Comments of Advanced Energy United re PJM Governance and Stakeholder Reforms, Docket No. AD26-7-000 (July 15, 2026). (“United Pre-Conference Comments”)
PDF page 2
2
as the independent grid operator for the region it currently serves. Despite current challenges in the PJM region, we remain confident that the RTO model is the best platform to foster innovation and competition, and thus to deliver value added and reliable electricity. But we also recognize that for PJM to play that role going forward, trust in PJM as an institution and in the markets it operates must be restored. Changes to governance and the stakeholder process are critical to restoring this trust, but will not be sufficient; they must be paired with a renewed commitment to transparent, fair, and functional markets that foster robust investment through enhanced market and regulatory certainty. Governance reforms can either serve to bolster this commitment to markets or cast further doubt on its durability. We must ensure that reforms pursued through this process achieve the former.
United’s comments below seek to strike a balance between objectives that could be seen as competing:
• Ensuring that the PJM board and leadership are disciplined in setting priorities and completing reforms on schedule, but also more open to exploring new ideas and solutions;
• Maintaining the critical role of stakeholders in informing PJM’s actions without allowing incumbent stakeholder interests to stall beneficial reforms in favor of maintaining the status quo; and
• Strengthening opportunities for states to weigh in on priorities and outcomes at PJM that impact their citizens while avoiding chaotic or undue political
interference that would undermine market certainty.
Carefully calibrated governance and stakeholder process changes can and must keep these objectives in balance.
PDF page 3
3
Since United has already shared our general perspectives on PJM’s governance and stakeholder process in pre-conference comments, below we focus primarily on responding to the post-conference questions raised by the Commission in its July 30, 2026 Notice Requesting Post- Conference Comment (“Notice”).3
I. COMMENTS
The Commission’s Notice requests that respondents “indicate the PJM member sector to which your company or organization belongs.”4 As stated in pre-conference comments, Advanced Energy United is a national trade association that represents a wide range of market participants in the PJM region and beyond. United itself is an “Associate” member of PJM, which means we pay a nominal annual fee and participate in PJM stakeholder meetings, but do not cast votes or belong to a sector. Our member companies span multiple sectors of PJM membership, primarily the Generation Owner and Other Supplier sectors. United’s membership also includes companies that are not yet PJM market participants, but that aspire to be in the future, subject to either expansion of their business into the region or implementation of market reforms that remove barriers to participation.
A. PJM Board Independence
Questions/Comments
Yes No
1) Should Board members’ terms be extended to five or more years?
X
Comments:
There is a significant learning curve associated with service on the PJM Board, given the technical complexity of RTO operations, planning procedures, market design, and the interplay between reliability and market rules. New Board members generally require substantial time simply to become well versed enough in the issues to be meaningfully engaged and to challenge the decisions of RTO leadership. Longer terms would allow Board members to
3 Notice Requesting Post-Conference Comment, Docket No. AD26-7-000 (July 30, 2026). (“Notice”)4 Notice at 3.
PDF page 4
4Questions/CommentsYes No
deliver more value after advancing up this learning curve, therefore extending the period during which the organization benefits from an experienced, well-informed Board. Terms that are too long, on the other hand, remove the opportunity to replace disengaged or ineffective board members, and may serve as a deterrent to some prospective Board members not willing to make a longer upfront commitment to serve PJM. In light of the benefits and drawbacks of longer terms, five years is a reasonable term length, whereas PJM’s proposed nine year Board term is too long.5 If Board terms are extended, there must be consideration of how longer terms would interact with other proposed reforms—particularly term limits.
2) Should there be a maximum number of years that a Board member may
serve (e.g., 10 years)?
X
Comments:
Term limits can be a useful tool for ensuring turnover, guarding against directors becoming too closely aligned with incumbent management or entrenched market participants, and creating opportunities to refresh the Board’s mix of skills and perspectives over time. Extending terms to five years and setting a two-term limit (i.e., 10 years total) would be a reasonable approach. At the same time, a rigid cap could force out a Board member who has become particularly effective. If a term limit is imposed, PJM should consider a mechanism to override the limit to extend the term of a particularly effective Board member where there is a demonstrated case that continuity of that member's service is in the best interest of PJM and its stakeholders.
3) Should the Board member qualification rules be revised to provide a
preference for some Board members that reside in the PJM region?
X
Comments:
While there is valid underlying logic to the idea of a residency preference, the priority in identifying Board candidates should be to find individuals with the right mix of qualifications, expertise, and independence, and adding a residency preference risks undermining those goals. PJM’s existing conflict-of-interest and independence restrictions already narrow the eligible candidate pool, and adding a residency requirement risks narrowing it further. Furthermore, a residency requirement should not be necessary to ensure that Board members have the best outcomes for the PJM region as their top priority; Board members’ fiduciary and statutory obligations, not their address, should be the operative check on their decision-making. Outside perspective is a genuine asset to the Board, so if a residency preference is added, it should apply to some seats rather than the Board as a whole to avoid robbing the Board of expertise from other regions and even other countries with different market structures. We would have no concern with a residency preference used only as a tie-breaker among similarly qualified finalists.
Separately, if PJM’s Board qualification criteria are going to be reopened, we would suggest
5 PJM, FERC Mediation Term Sheet, https://www.pjm.com/-/media/DotCom/committees- groups/committees/mc/2026/20260819/20260819-item-08---1-ferc-mediation-term-sheet.pdf (“PJM Term Sheet”), at 2.
PDF page 5
5Questions/CommentsYes No
adding a preference that at least one Board member have expertise in energy transition and grid innovation, given the pace of technological change affecting the PJM footprint.6
4) Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?
X
Comments:
Having Board members who understand the industry in sufficient depth to meaningfully challenge and engage with PJM leadership on substantive issues is critical to effective governance. The current two-year cooling-off period, while well-intentioned, meaningfully narrows the pool of candidates with recent, hands-on industry experience. Relaxing the restriction, even modestly, should help expand the pool of eligible, well-qualified candidates without unduly compromising Board independence. A one-year cooling-off period would be an appropriate middle ground to allow for eligible candidates that are not too closely aligned with a member perspective.
5) Should restrictions on Board communications be relaxed to enable more
communication between the Board and stakeholders?
X
Comments:
It is preferable for Board members to have greater direct exposure to the commercial realities and practical implications of PJM’s rules, as well as visibility into new innovations, technologies, and ideas emerging among stakeholders. Expanded communication between the Board and stakeholders, with guardrails to preserve Board independence and avoid improper influence, would promote exactly this kind of exposure and should result in a better-informed, more engaged Board. United supports further discussion as to what guardrails must be put in place.
6) In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?
X
Comments:
Greater transparency and a requirement to “show its work” will, at minimum, increase stakeholder and public confidence in the Board’s decision-making; the requirement to offer such public explanation may also sharpen the Board’s reasoning. For example, it has been extremely helpful to stakeholders to see the Board’s explanation and reasoning in connection with Critical Issue Fast Path (CIFP) decisions. That practice has improved stakeholder
6 PJM’s Operating Agreement at Section 7.2 currently states, “ Of the nine Board Members, four shall have expertise and experience in the areas of corporate leadership at the senior management or board of directors level, or in the professional disciplines of finance or accounting, engineering, or utility laws and regulation, one shall have expertise and experience in the operation or concerns of transmission dependent utilities, one shall have expertise and experience in the operation or planning of transmission systems, and one shall have expertise and experience in the area of commercial markets and trading and associated risk management.”
PDF page 6
6Questions/CommentsYes No
understanding of, and confidence in, the Board’s decision-making process.
7) In order to increase transparency, should some Board meetings be open or
available to the public?
X
Comments:
Public Board meetings would be most beneficial if they are used as a forum between stakeholders and the Board, as they are in SPP, where Board meetings are used to review and vote on all revision requests. Those revision requests that are more controversial are generally allocated extra discussion time to allow stakeholders to share their arguments with the Board; before a final vote, Board members can choose to share how they will vote and explain their reasoning. Making some Board meetings open to the public is also a no regrets reform: it costs little, increases the visibility of the Board to stakeholders and the public, and is consistent with a broader push toward greater transparency.
8) Should PJM’s governing documents be revised to explicitly state that the
responsibility of PJM and its Board is to serve the public interest?
X
Comments:
While PJM and its Board should act in accordance with the public interest, adding a public interest responsibility into PJM’s governing documents is not a necessary revision, as PJM already has a duty—which FERC has an independent obligation to enforce—to ensure that PJM’s rates are just and reasonable and not unduly discriminatory, and that PJM's operations maintain reliability. Faithful execution of those duties is consistent with serving the public interest. A freestanding “public interest” mandate is susceptible to being interpreted or invoked in ways that go beyond PJM’s and the Board’s existing statutory obligations, potentially justifying actions or interventions that undermine market certainty and confidence and that are ultimately inconsistent with PJM’s role. If a public interest provision were to be adopted, its intent must be a clearly defined, and PJM should offer an explanation of why and how such a mandate is not covered under the existing obligations of PJM and FERC.
9) Should state representatives have at least one voting member on the
Nominating Committee?
X
Comments:
Allowing states to participate and vote in the Nominating Committee would appropriately reflect the important role states have in ensuring PJM’s success, and the impact that PJM’s decisions have on outcomes at the state level. Giving states a seat on the Nominating Committee would also increase confidence in the integrity of the Board selection process by exposing states to this closed process. However, states should be granted one, or at maximum two, voting member(s) on the Nominating Committee. Adding more than two state votes to the eight seats on the Nominating Committee risks introducing a perception of undue political influence into the process. There is strong precedent for an RTO to include states in this way; ISO-NE and MISO both include states as voting members but limit the number of votes
PDF page 7
7Questions/CommentsYes No
available to states.7
10) Should PJM adopt public performance metrics and tie management
compensation to their achievement?
Comments:
This proposal could be beneficial or could have unintended consequences, depending heavily on which public performance metrics are adopted and how they are measured. For example, tying compensation to public performance metrics could inadvertently reinforce risk aversion, which is already generally well rewarded. Tying compensation to performance could also promote more short-term thinking among management, when many beneficial RTO initiatives require a long-term view that may not pay off within a single compensation cycle. Rather, compensation could be tied to accomplishment of annual goals detailed in the RTO’s strategic plan, like what is done in MISO.8 Should this reform be adopted, it will be important to ensure that any resulting metrics support a shift toward a culture that embraces innovation and new tools and technologies and promotes good outcomes in the long-term as well as the near-term.
B. Section 205 Filing Rights
Questions/Comments
Yes No
11) Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board?
X
Comments:
In United's experience, a purely advisory stakeholder process sidelines the legitimate concerns of market participants—ultimately resulting in a more contentious debate when a proposal reaches the Commission. Stakeholders bring valuable perspective on the commercial and practical realities of proposed changes that PJM management and the Board do not always have direct visibility into. Listening to these concerns supports an investable and reliable market; proposals that are not workable in practice tend to generate downstream problems regardless of how sound they look on paper. Additionally, policies with stakeholder support are more durable, and less prone to legal challenges or significant changes from either stakeholders or leadership. While stakeholder perspectives can still be shared in an advisory
7 ISO-NE's Joint Nominating Committee includes 1 out of roughly 14 seats representing the 6 New England States. MISO’s Nominating Committee is comprised of two representatives of the Advisory Committee, which includes State representatives; while there is no guaranteed seat for states, state representatives are eligible to be appointed to the Nominating Committee as any other Advisory Committee member. See, Chrisopher Parent, Katherine Fisher, William Cotton, and Cali Clark, Governance Structure and Practices in the FERC-Jurisdictional ISOs/RTOs, at 3- 12, 4-10, (Feb. 2021).8 MISO, 2026 Short-Term Incentive Plan Proposed Metrics (Dec. 9, 2025). https://cdn.misoenergy.org/20251209%20Human%20Resources%20Committee%20of%20the%20BOD%20Item%2 004b%202026%20Short-Term%20Incentive%20Plan730306.pdf
PDF page 8
8Questions/CommentsYes No
process, it becomes much easier for the RTO to brush them aside. Relegating stakeholders to a purely advisory role would change the entire tenor of the stakeholder process and allow PJM management and the Board to ignore stakeholder concerns whenever they choose, even when they are broadly shared across the stakeholder body.
That said, United is sympathetic to concerns that the incumbent-dominated stakeholder process can be biased toward maintaining the status quo. Resistance to change can result in stalling or blocking reforms that would enhance competition or facilitate new market entry, thereby undermining reliability and just and reasonable rates. Rather than preventing stakeholder logjams by making the process purely advisory, we would propose the following targeted solutions to ensure progress is made while preserving a substantive stakeholder role:
•
Change the voting process to reduce the ability of a small set of market participants to block beneficial proposals, and to prevent outright blocks of proposals at the lower committees before consideration by the full stakeholder body;
•
Re-examine and consider reforms of the sectors to ensure meaningful participation of non- incumbent interests—as NEPOOL did through the creation of its Alternative Resources sector, which gave dedicated representation to renewable generation, distributed generation, and load response interests that might otherwise have been underrepresented;
•
Eliminate the complex “solutions matrix” to simplify and streamline the stakeholder feedback process, and consider instead a simpler "amendment" process, as used in ISO- NE, to increase the likelihood of alignment among PJM members;
•
Introduce discipline into the agenda setting and schedule of stakeholder discussions via an annual work plan administered by PJM, and stronger PJM management of the stakeholder process; and
•
Ensure that stakeholders have "jump ball" filing rights in areas where they do not have direct Section 205 filing rights, as discussed further below.
12) Should PJM have section 205 filing rights over the energy market and
ancillary services unencumbered by the requirement to obtain approval of
two-thirds of the Members Committee?
X
Comments:
For all the reasons above, United does not support “unencumbering” PJM of its obligation to work with stakeholders. If PJM moves in this direction, any expansion of PJM's unilateral Section 205 filing rights over the energy market and ancillary services must be paired with jump ball rights for stakeholders, to avoid effectively converting the stakeholder process into a purely advisory one in this area.
13) Should PJM have section 205 filing rights over Regional Transmission
Expansion Planning (RTEP) unencumbered by the requirement to obtain
approval of two-thirds of the Members Committee?
X
PDF page 9
9Questions/CommentsYes No
Comments:
Transmission planning is a core role of the RTO, and it is critical that the planning process be oriented toward outcomes that are efficient, cost-effective, competitive, and aligned with regional needs. Removing the input of the Members Committee and granting section 205 filing rights to PJM may appear consistent with those goals, but would instead grant outsize influence to transmission owners, who have a direct financial stake in the outcome of RTEP. By virtue of the threat to withdraw from PJM, TOs wield enormous influence over PJM’s decisions, independent of their voting share. Indeed, PJM’s own polling on proposed governance changes indicates that TOs are overwhelmingly supportive of transferring 205 rights over RTEP to PJM, while the end use customer sector is nearly unanimously opposed. This breakdown indicates that TOs generally view this shift as favorable to their interests while consumers do not see it as a means to improve outcomes for the region.9 PJM has also not identified a specific issue or reliability need that was stalled by the Members Committee in RTEP matters. In fact, PJM was the first region to submit Order No. 1920 regional compliance. Removing section 205 filing rights from the Members Committee would do little to speed up the planning process, and would remove important stakeholder feedback that will otherwise be expressed at FERC.
Regardless of who has 205 rights over RTEP, United agrees with the Independent Market Monitor’s (“IMM”) argument that TO influence must be kept in check and supports the IMM’s call for a clearly defined process and set of requirements governing transmission owner departure from PJM.10 Without a defined process for leaving PJM, a TO’s departure could create such upheaval that it could “bring an end to PJM as it currently exists.”11 This looming threat gives TOs an unparalleled influence over the decision making process, and places PJM in the delicate position of having to appease TOs while trying to maintain broad stakeholder support. A defined exit process would diminish this leverage, while also ensuring that PJM and its remaining members are not harmed in the event a transmission owner departs.
14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a
supermajority of OPSI agrees on an alternative proposal?
Comments:
States have a clear role and interest in both resource adequacy and transmission cost allocation. United does not take a position on granting OPSI jump ball rights over these issues at this time, and looks forward to reviewing the perspectives of states and other stakeholders on this issue as part of this proceeding.
9 PJM, Governance and Stakeholder Process Poll Results, https://www.pjm.com/-/media/DotCom/committees- groups/committees/mc/2026/20260819/20260819-item-10---1-governance-and-stakeholder-process-poll-results.pdf, at 18.10 Comments of the Independent Market Monitor for PJM, Docket No. AD26-7-000, at 3.11 Id. at 13.
PDF page 10
10Questions/CommentsYes No
15) Should the Members Committee have “jump ball” filing rights over the
portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?
X
Comments:
As discussed above, stakeholders bring critical perspective on market rules and planning processes that should not be ignored. Granting the Members Committee “jump ball” rights is one way to ensure that stakeholder perspectives are not just acknowledged, but meaningfully taken into account. Stakeholder jump-ball rights in ISO-New England have been an effective mechanism to: (1) incentivize ISO-NE to work proactively with stakeholders to resolve their concerns with its proposals before filing, and (2) encourage stakeholders to work together to build consensus around solutions to concerns rather than simply opposing proposals. Without jump ball rights, the Commission is only presented one proposal that must meet the relatively low bar of “just and reasonable.” Allowing more parties to file will give the Commission the ability to decide which proposal is more “just and reasonable.” Alternatively, the fact that stakeholders have jump ball rights does not necessarily result in a jump ball filing at FERC, but rather ISO-NE’s adoption of stakeholder-supported amendments. United believes a similar dynamic would benefit PJM's stakeholder process.
A “jump ball” mechanism would be beneficial in any portion of the tariff where PJM has 205 filing rights, but will be particularly important if stakeholder filing rights are reduced elsewhere in connection with other reforms.12 If PJM's own unilateral filing rights expand, jump ball rights for stakeholders should be correspondingly enhanced in their place, to preserve a meaningful stakeholder check on PJM’s proposals.
C. Stakeholder Process
Questions/Comments
Yes No
16) Should the approval threshold in the Members Committee be lowered from two-thirds sector-weighted voting?
12 See Questions 12 and 13.
PDF page 11
11Questions/CommentsYes No
Comments:
While the two-thirds threshold sets a high bar to reach consensus that may block some beneficial proposals, it also appropriately protects against advancement of reforms that raise legitimate stakeholder concerns. Prior to lowering the threshold, PJM should take all possible steps to address stakeholder gridlock through mechanisms that would create stronger pathways and incentives for stakeholder alignment, such as:
• PJM taking greater control over the stakeholder timeline to force stakeholder alignment, e.g., by making clear that it will file under section 206 by a certain date if stakeholder agreement is not reached;
• Introducing an annual work plan process to align upfront on what needs to be accomplished in a given year;
• Improving and streamlining the “solutions matrix” process by adopting a simpler “amendment” process, as used in ISO-NE, to increase the likelihood of alignment among PJM members;
• Fixing the CIFP process that gives stakeholders no incentive to converge, since the Board reviews every package regardless of support; to fix this issue, a preliminary vote could be used to narrow the field to the top two or three stakeholder proposals before the final CIFP vote, so fewer options means less-diluted votes and clearer alignment.
17) Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?
Comments:
United does not have input on this question at this time.
D. State Participation
Questions/Comments
Yes No
18) In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’
representatives?
X
Comments:
United supports giving states a better-defined and stronger role at PJM,13 which may help restore trust in market outcomes, and welcomes participation by governors’ representatives and state legislators’ representatives. However, United strongly recommends, to the extent possible, consolidating these perspectives under the umbrella of a single regional state entity.
13 Pre-Conference Comments, at 6.
PDF page 12
12Questions/CommentsYes No
We are encouraged by PJM’s initial proposal “to enhance OPSI to include in a bicameral structure for both the state commissions and the executive branches of each state” and to support additional funding for the expanded OPSI.14
The core benefit of a single regional state entity, rather than multiple, is the consolidation of state input and the pooled resources and support necessary for states to have meaningful engagement. Creating two or more separate state entities risks introducing multiple, potentially conflicting state voices on the same issues, ultimately diluting rather than strengthening the impact of state input.
Further, the notion that these two groups would naturally divide their focus—with governors’ representatives weighing in on strategic, big-picture issues and utility commissioners focusing on implementation details—will likely be difficult to sustain in practice. There is too much topic overlap and interaction to create and sustain clearly defined lanes; and a single issue will often require both kinds of input at once.
State representation as a single entity, rather than multiple separate bodies, could encompass representatives from governors' offices and/or state legislators, in addition to state commissioners. NESCOE (the New England States Committee on Electricity) is a good model to follow in this regard, as it brings together utility commissioners and gubernatorial appointees to represent the interests of the six New England states in a single, well-resourced organization.15 Both governors'/legislators' offices and state utility commissions bring valuable, and different, perspectives and the aim should be to capture both. OPSI should be better resourced, allowing for a permanent staff in a single organization to more efficiently equip the states to reach consensus and engage meaningfully with PJM's stakeholder process.16 PJM’s initial proposal is consistent with these observations.
In any scenario, individual states and bodies within states retain their right to lobby PJM directly and to file at the Commission directly under Section 206, regardless of how a collective state entity or entities are structured.
To the extent the states themselves cannot align on forming a single entity, United respectfully requests that, at a minimum, any resulting multiple state groups be closely coordinated, act together wherever relevant and possible, and have clearly defined and non-overlapping roles and responsibilities.
19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional
transmission cost allocation) in addition to the consumer advocate votes?
X
Comments:
United is supportive of efforts to uplift the voices and perspectives of states, but did not hear
14 PJM Term Sheet, at 3.15 New England States Committee on Electricity, About NESCOE- Regional States Committee (Last Accessed Aug. 21, 2026). https://nescoe.com/about-nescoe/16 United Pre-Conferenced Comments at 8.
PDF page 13
13Questions/CommentsYes No
any real interest in states having a formal stakeholder vote, including from the states themselves.
Giving states a formal vote within the stakeholder process risks putting state perspectives through the same sector-based filter as all other stakeholder perspectives, which may dilute rather than amplify the impact of state voices. In cases where the states have been able to reach their own consensus position, this should not simply be factored in as a 1/5 or 1/6 vote. A state vote folded into the ordinary stakeholder process would carry no more weight than any other single sector's vote, notwithstanding the states’ unique regulatory role and interest in outcomes like resource adequacy and cost allocation.
A formal state vote in the stakeholder process also risks inserting politics directly into the stakeholder process in a way that is ultimately more likely to undermine investor confidence in the markets rather than promote more durable market outcomes.
If states express interest in having voting rights in the stakeholder process, one model to look at would be SPP’s Regional State Committee (“RSC”). The RSC has one designated commissioner from each state regulatory commission having jurisdiction over an SPP member; any issues that pertain to resource adequacy and transmission cost allocation ultimately go to the RSC for a final vote. While commissioners get voting rights at the RSC, they do not vote with members at the Market and Operations Policy Committee—equivalent to PJMs MRC/MC.17
20) Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation?
X
Comments:
PJM's proactive consultation with OPSI should be increased across the board, and in particular on issues related to resource adequacy and transmission cost allocation, where states have a direct and well-established interest. As PJM develops its strategic planning process to produce an annual work plan, PJM should also be required to consult with OPSI on the priorities reflected in that work plan, so that state input is incorporated upstream—at the stage where priorities are being set—rather than only at the point of a specific filing.
II. CONCLUSION
Advanced Energy United appreciates the opportunity to weigh in on next steps for the Commission, the PJM states, PJM stakeholders, and PJM itself to consider as the region pursues
17 SPP Bylaws Section 7.2. https://www.spp.org/documents/13272/current%20bylaws%20and%20membership%20agreement%20tariff.pdf.
PDF page 14
14
improvements to governance and the stakeholder process. We appreciate the Commission’s bias toward action, and remain optimistic that governance reforms will contribute to a more affordable, reliable, fair, and competitive PJM.
Respectfully submitted,
/s/ Caitlin Marquis
Caitlin Marquis, Managing Director
Jon Gordon, Senior Director
Mike Haugh, Director
Kelsey Koenig, Policy Associate
Advanced Energy United
1801 Pennsylvania Ave. N.W., Suite 410
Washington, D.C. 20006
cmarquis@advancedenergyunited.org
jgordon@advancedenergyunited.org
mhaugh@advancedenergyunited.org
kkoenig@advancedenergyunited.org