AD26-7-000 · 2026-08-21 · Office of the Ohio Consumers' Counsel
Comments of the Office of the Ohio Consumers’ Counsel re the reforms to the governance of PJM Interconnection, L.L.C
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Governance and Stakeholder Reforms
)
)
Docket No. AD26-7-000
COMMENTS
BY
OFFICE OF THE OHIO CONSUMERS’ COUNSEL
Maureen R. Willis
Ohio Consumers’ Counsel
Angela D. O’Brien
Deputy Consumers’ Counsel
Office of the Ohio Consumers’ Counsel
65 East State Street, Suite 700
Columbus, Ohio 43215
Telephone: (614) 466-9531
angela.obrien@occ.ohio.gov
Denise C. Goulet
McCarter & English, LLP
1301 K Street, N.W.
Suite 1000 West
Washington, D.C. 20005
(202) 753-3400
dgoulet@mccarter.com
Special Counsel to the Ohio Office of the Attorney General for the Office of the Ohio Consumers’ Counsel
PDF page 2
i
TABLE OF CONTENTS
PAGE
I. INTRODUCTION … 1
II. REFORMS TO PJM GOVERNANCE STRUCTURE … 3
A. PJM governance must expressly recognize affordability and the public interest … 3
B. Independent cost oversight on transmission projects is needed … 4
C. Enhancing the PJM Attachment M-3 Supplemental Project process … 6
D. Transparency for PJM meetings … 10
III. STATE PARTICIPATION … 10
IV. STAKEHOLDER PROCESS … 11
A. Consumers need meaningful cost information before PJM makes decisions … 11
B. Stakeholder voting should prevent affiliate voting from overwhelming consumer
interests … 13
C. PJM voting should be transparent … 14
V. PJM BOARD INDEPENDENCE … 14
VI. SECTION 205 FILING RIGHTS … 15
VII. CONCLUSION … 17
PDF page 3
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Governance and Stakeholder Reforms
)
)
Docket No. AD26-7-000
COMMENTS
BY
OFFICE OF THE OHIO CONSUMERS’ COUNSEL
I. INTRODUCTION
The Office of the Ohio Consumers’ Counsel (“OCC”), on behalf of Ohio’s residential utility consumers, respectfully submits these comments regarding reforms to the governance of PJM Interconnection, L.L.C. (“PJM”).
The Federal Energy Regulatory Commission’s (“FERC” or “Commission”) examination of PJM governance is both timely and necessary. Under the Federal Power Act, FERC is responsible for protecting consumers from rates, terms, and conditions of wholesale electric service that are unjust and unreasonable. Yet the institutional structure through which PJM develops the rules governing wholesale markets, resource adequacy, and transmission planning gives the consumers who ultimately pay those costs remarkably little leverage in the processes and decisions that produce them. That is problematic on many fronts.
That imbalance matters. PJM serves approximately 67 million consumers across 14 jurisdictions. But those consumers are represented in the PJM stakeholder process by only 14 statutory consumer advocate votes—one for each jurisdiction. At the Standing Committee and Senior Task Force level, those consumer advocates constitute approximately 1.3 percent of potential voters. Even at the Markets and Reliability Committee (“MRC”) and Members
PDF page 4
2
Committee (“MC”), where sector-weighted voting applies, consumer advocates account for only a small portion of the voting influence.
Meanwhile, entities with direct financial interests in PJM market rules and transmission decisions comprise much of PJM’s membership and exercise substantial influence over the development of those rules. The result is a fundamental structural problem: many of the entities voting on proposals governing wholesale electricity markets and transmission investment have a financial interest in the revenues those rules produce. At the same time, residential consumers who ultimately pay the resulting charges, have comparatively little ability to shape those proposals.
FERC should address that imbalance as a central component of PJM governance reform. But there is more to be done.
Governance reform should not merely redistribute authority among PJM’s existing institutional actors. It should make PJM more accountable to the public that it serves. That requires, at minimum, making affordability and the public interest an express component of PJM’s responsibilities, implementing consumer safeguards for transmission planning, strengthening the voices of statutory consumer advocates, improving transparency and cost oversight, and ensuring that any expansion of the PJM Board’s authority is accompanied by meaningful safeguards protecting consumers.
OCC’s responses to the Commission’s specific list of questions attached to the Notice Requesting Post-Conference Comment issued in this docket on July 30, 2026, are appended as Attachment A to these comments.
PDF page 5
3
II. REFORMS TO PJM GOVERNANCE STRUCTURE
A. PJM governance must expressly recognize affordability and the public
interest.
PJM performs functions that profoundly affect the affordability and reliability of electricity service for over 67 million Americans. Its capacity market, energy markets, and transmission planning processes produce billions of dollars in costs that ultimately flow through to consumers’ electric bills. These electric transmission and supply charges comprise 60 to 70% of an Ohio household’s electricity bill, all pass-through charges from FERC and PJM.1 Yet affordability is not embedded in PJM’s governance structure. Unlike reliability – which PJM expressly calls its “primary responsibility,” – affordability is not treated as a comparable institutional obligation. PJM instead points to the states to address the retail impact of rising wholesale costs.2
Reliability is indispensable. But reliability cannot mean reliability at any cost. The Federal Power Act’s consumer-protection mandate requires rates to be “just and reasonable.” Energy markets and transmission planning should produce reliable service efficiently and at reasonable cost.
PJM’s governing documents should expressly require PJM and its Board to act in the public interest and to consider affordability alongside reliability. This should be a substantive obligation, not an aspirational statement. PJM should be required to evaluate the consumer cost consequences of material proposals and major Board decisions. A governance structure that measures reliability consequences but does not meaningfully measure and consider consumer
1 Public Utilities Commission of Ohio, Ohio Utility Rate Survey (June 2026).2 PJM Interconnection, L.L.C., Docket Nos. EL 25-49-000 and -001, Informational Report, Exhibit A at 2 (Jan. 20, 2026) (“PJM must be conscious of the affordability challenges facing the 67 million consumers in our footprint today. There is much that our states can be doing to contend with the higher wholesale costs at the retail level.”) (citation omitted).
PDF page 6
4
cost consequences falls far short of providing just and reasonable rates for consumers. Affordability should accordingly become an institutional responsibility against which PJM’s performance can be measured.
B. Independent cost oversight on transmission projects is needed.
Transmission deserves particular attention in the form of an Independent Transmission Monitor. Transmission charges can account for up to 20% of an Ohio household’s electricity bill.3
PJM consumers face substantial and growing transmission costs. From 2017 through 2025, Ohio transmission project costs have ballooned with over $16.4 billion in costs, with supplemental projects accounting for 66% of those projects, $10.8 billion. 4 These huge transmission bills to Ohio consumers emanate from massive transmission investment and the cost allocation methodologies used to collect that investment in regional and supplemental transmission projects.
Ohio consumers’ experience with supplemental transmission projects demonstrates the need for independent transmission oversight. Under PJM’s existing framework, supplemental projects are not subject to PJM review for need, prudence or cost-effectiveness. Yet the costs are recovered from consumers through FERC-jurisdictional transmission rates.
In Ohio, no one is filling that gap by reviewing these projects for prudence, need, or cost- effectiveness before consumers are required to pay for them. OCC’s 2023 complaint to FERC highlighted the magnitude of the problem: based on data through 2022 available at the time of that filing, Ohio utilities had added to local transmission infrastructures over approximately six
3 PUCO, Ohio Utility Rate Survey (June 2026). 4 Sourced from PJM State of Ohio Infrastructure Reports 2017-2025.
PDF page 7
5
years nearly $6 billion in supplemental project costs that were not reviewed by any regulatory authority for need, prudence or cost-effectiveness. This problem keeps growing. Supplemental Projects continue to make up the bulk of annual investment in transmission infrastructure. This regulatory gap creates precisely the wrong incentive – utilities can pursue substantial transmission investment without the meaningful, independent scrutiny that should precede the imposition of monopoly costs on captive consumers. The persistence of that gap also demonstrates why governance reform cannot rely on existing institutions to correct themselves. OCC filed its complaint in September 2023 asking FERC to remedy the lack of regulatory oversight and requested expedited treatment because additional projects and costs would continue accumulating while the complaint remained unresolved. True to form, subsequent supplemental transmission spending has continued to increase. From 2023 to 2025, an additional $4.3 billion has been spent on Ohio supplemental transmission projects, bringing the total since 2017 to over $10 billion. Nearly three years after filing the complaint, FERC still has not ruled on OCC’s Complaint. Docket No. EL23-105-000 remains on the Commission’s list of pending complaints.
Yet there is no transmission equivalent of PJM’s Independent Market Monitor providing comprehensive, independent scrutiny of transmission planning incentives, costs, and outcomes. That gap is especially troubling for transmission projects receiving limited regional scrutiny, including transmission-owner Supplemental Projects that are proliferating in Ohio. The existing structure can create incentives favoring locally planned, cost-of-service transmission investment over regional solutions that may provide broader benefits or greater efficiency. Consumers ultimately bear the consequences of those incentives through their electric bills.
PDF page 8
6
An independent transmission monitor would help close this accountability gap by providing ongoing, independent scrutiny of the need, alternatives and costs associated with transmission investment – including Supplemental Projects. This would replace the current process where consumers must rely on after-the-fact challenges to formula transmission rates while billions of dollars in costs continue to be incurred. An independent transmission monitor should be structurally independent from PJM and transmission owners and should have sufficient access to information to conduct meaningful analysis.
Independent oversight would not replace PJM’s planning responsibilities, existing state oversight authority or the Commission’s jurisdiction. It would provide FERC, states, consumer advocates, and stakeholders with an independent source of information needed to determine whether billions of dollars in transmission investment are prudent, efficient, and beneficial to consumers.
C. Enhancing the PJM Attachment M-3 Supplemental Project process.
The growth in AI load interconnection requests is driving the need for improved local and Supplemental Project transmission planning processes. Although the Supplemental Projects are not directly governed by the requirements of FERC Order No. 1920, the Commission’s recent actions reflect an increasing emphasis on transparent planning processes, meaningful stakeholder participation, cost-effective analyses, and well-supported planning records. Those essential elements are lacking in the present PJM process.
In Order No. 1920, the Commission concluded that more forward-looking and
transparent transmission planning is necessary to ensure that transmission investments remain just and reasonable over the long term. While that rule principally addresses long-term regional transmission planning, the policy objectives it advances – including transparency, robust
PDF page 9
7
planning assumptions, and meaningful stakeholder engagement—are equally relevant to customer-driven supplemental transmission projects.
Importantly, Order No. 8905 required similar transparency, robust planning assumptions and meaningful stakeholder engagement in the local transmission planning process. In PJM, Supplemental Projects are part of the local planning process and must be planned in a manner that encompasses these principles.
The PJM Attachment M-3 planning process for local transmission projects and Supplemental Projects embrace some, but not all these principles. OCC recognizes that FERC accepted the current PJM Attachment M-3 local transmission planning process in 2020 but notes that FERC has more recently questioned whether that process is sufficient in its April 2022 Supplemental Notice of Technical Conference in Docket No. AD22-8-000. That Notice states: The purpose of this conference is to explore measures to ensure
sufficient transparency into and cost effectiveness of local and
regional transmission planning decisions, including: (1) the role of
cost management measures in ensuring the cost-effective
identification of local transmission needs (e.g., planning criteria)
and solutions to address identified local transmission and regional
reliability-related transmission needs; and (2) cost considerations
and the processes through which transmission developers recover
their costs to ensure just and reasonable transmission rates.6
Although FERC did not require changes to the local and Supplemental Project transmission planning process in Order No. 1920, it clearly left the door open for improvements in that process.
5 Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, 118 FERC ¶ 61,119 at P 3, FERC Stats. & Regs. ¶ 31,241 (2007) (“Order No. 890”), order on reh’g, Order No. 890-A, 121 FERC ¶ 61,297, FERC Stats. & Regs. ¶ 31,261 (2007) (“Order No. 890-A”); order on reh’g, Order No. 890-B, 123 FERC ¶ 61,299 (2008); order on reh’g, Order No. 890-C, 126 FERC ¶ 61,228 (2009).
6 Transmission Planning and Cost Management, Docket No. AD22-8-000, Supplemental Notice of Technical Conference at 1, (July 22, 2022).
PDF page 10
8
In a move toward creating greater transparency around that process, FERC recently issued show-cause orders directing several public utility transmission providers, including PJM in Docket No. EL26-67-000, to explain why aspects of their local and Supplemental Project transmission planning processes remain just and reasonable under the Federal Power Act. These proceedings reflect FERC’s movement toward a broader regulatory focus on transparency, justification, cost-effectiveness and oversight of local and Supplemental Project transmission investments.
These show cause proceedings reinforce the importance of ensuring that local and Supplemental transmission projects are supported by demonstrated need, prudent engineering, transparent planning assumptions, project cost-effectiveness and a planning record sufficient to permit meaningful stakeholder review before significant investments are undertaken. These elements are missing from the current PJM Attachment M-3 planning process.
Customer-driven project presentations to the Sub-regional RTEP committee and the TEAC committee should include additional information regarding the basis for projected load growth. Without disclosing confidential commercial information, transmission owners should identify the extent to which projected customer demand is supported by executed service agreements, meaningful development milestones, or other objective indicators demonstrating the likelihood that the projected load will materialize.
Transmission owners should be more fully discussing alternatives considered during project development. For projects presented at the Solutions stage, stakeholders should understand not only the preferred solution but also the principle alternatives evaluated, the reasons those alternatives were not selected, and whether phased implementation, equipment upgrades, operational changes, or other lower-cost options were considered.
PDF page 11
9
Transmission owners should also address substantive stakeholder comments as projects advance through subsequent stages of the M-3 process. OCC is not suggesting that transmission owners be required to provide formal written responses to every comment. However, a brief discussion during subsequent TEAC presentations explaining whether significant stakeholder concerns were considered and, where appropriate, how they were addressed, would strengthen the planning record and improve stakeholder confidence in the process.
PJM and transmission owners should at a minimum provide information requested by stakeholders during these processes about specific planned projects. To date, despite several requests by OCC for information as part of the July and August Attachment M-3 stakeholder processes in PJM, PJM and the Ohio transmission Owners still have not provided substantive responses to OCC’s requests for information regarding specific projects.7 Those questions seek information related to the planning assumptions, alternatives considered and cost-efficiency of certain identified proposed Supplemental Projects in Ohio.
Finally, OCC encourages continued dialogue among PJM, transmission owners, states, consumer advocates, and other stakeholders regarding the evolution of Supplemental Project transmission planning, especially where those local transmission projects may be related to large load and Artificial Intelligence data centers. This customer-driven transmission investment represents a significant and growing component of transmission development throughout the PJM region, both in the Regional Transmission Expansion Planning process and in the Attachment M-3 Supplemental Project planning process. As planning practices continue to evolve, regular stakeholder discussions regarding transparency, planning assumptions, customer commitments, and cost responsibility will help ensure that the M-3 process provides meaningful
7 See Attachment B.
PDF page 12
10
opportunities for stakeholder participation while supporting timely, reliable, and cost-effective transmission planning.
D. Transparency for PJM meetings.
Transparency in PJM meetings and decision-making is essential. PJM makes decisions that have enormous consequences for the over 67 million consumers who pay electric bills. Decisions affecting capacity and energy costs, transmission investment, market rules, and reliability should not be developed through closed-door discussions or processes that leave consumers and their representatives unable to understand who advocated for outcomes and why. Open meetings, accessible materials, meaningful opportunity for public and consumer participation, and a clear record of the basis for PJM’s decisions would promote accountability and public confidence. It would also help ensure that consumer affordability and broader public interest receive meaningful consideration alongside the interests of PJM’s market participants. The Board’s deliberations and decision-making should, whenever practicable, occur in meetings open to stakeholders and the public, with limited exceptions only where confidentiality is legally or commercially required.
III. STATE PARTICIPATION
State participation must be formalized- but state representation cannot substitute for consumer representation.
PJM governance reform should substantially strengthen the role of the states and the role of consumer advocates. FERC should recognize an important distinction: strengthening the “state voice” is not synonymous with strengthening the consumer voice.
State utility commissions, governors, legislators, environmental agencies, economic- development officials, and statutory consumer advocates perform different functions. State commissions may balance reliability, utility financial integrity, economic development,
PDF page 13
11
environmental requirements, and other statutory considerations. Governors and legislatures likewise balance numerous competing public-policy objectives. Statutory consumer advocates have a different responsibility: protecting utility consumers, including residential consumers, from excessive, unjust and unreasonable utility costs.
Those unique consumer interests often overlap with the states’ interests, but they are not identical. Consumer advocates may agree with their state commissions on one issue and disagree on another. PJM governance reform should preserve those independent perspectives rather than subsuming consumer representation within a generalized category of “state interests.” Accordingly, FERC should strengthen the role of both representative voices in the processes. OPSI should receive meaningful jump-ball filing rights where a sufficiently broad consensus of states supports an alternative to a PJM proposal. While the Commission has provided for such filing rights in the context of cost allocation proposals for long-term regional transmission projects in Order No. 1920, no similar rights exist for the Order No. 1000 and Order No. 890 regional and local transmission planning processes. PJM should also be required to consult formally with OPSI before any major section 205 filings, including significant resource- adequacy and transmission planning and cost allocation filings. At the same time, statutory consumer advocates should retain an independent and meaningful role throughout PJM governance, including in the stakeholder process and in the selection of PJM Board members.
IV. STAKEHOLDER PROCESS
A. Consumers need meaningful cost information before PJM makes decisions.
PJM cannot credibly claim that its processes produce cost-effective outcomes if neither decision-makers nor stakeholders are routinely provided with information about what the
PDF page 14
12
proposals will cost consumers. Cost analysis should become an ordinary part of PJM governance
– a part that is freely and timely shared with interested parties, including consumer advocates. For material proposals advancing to the MRC or MC, PJM should provide a reasonable assessment of expected cost impacts sufficiently early for stakeholders to use that information in evaluating competing proposals. The analysis need not – and often cannot – predict costs with precision. But uncertainty is not a justification for providing no analysis. PJM routinely analyzes complicated questions involving reliability, resource adequacy, market behavior, and system conditions under uncertain future assumptions. Consumer cost consequences deserve comparable institutional attention.
Cost information would improve not only consumer protection but decision-making itself. Stakeholders could evaluate whether incremental reliability benefits justify incremental costs, compare alternatives on a more informed basis, and identify proposals that accomplish the same objective at lower consumer cost.
FERC should require PJM to institutionalize meaningful and transparent cost-impact analysis. FERC also should require PJM and the transmission owners to provide answers to specific questions from stakeholders, including consumers advocates, about identified projects during the stakeholder process. Such questions include information regarding cost analyses, planning assumptions, alternatives considered and other cost impact data. There should be consequences for PJM’s and/or the transmission owners’ failure to respond to such specific questions about identified projects. In the absence of any realistic process for challenging the prudence, need for and cost-efficiency of local or Supplemental Projects in the formula transmission rate challenge process, consumers must have access to information regarding these projects during the transmission planning stage before construction begins.
PDF page 15
13
B. Stakeholder voting should prevent affiliate voting from overwhelming
consumer interests.
PJM’s stakeholder process should facilitate genuine consensus rather than allow entities with numerous affiliates to dominate the early stages of policy development. Ohio illustrates how PJM’s affiliate-voting rules dilute the consumer voice at the committees where proposals are developed.
OCC, the statutory representative of 4.5 million residential households, receives one vote to represent Ohio’s residential utility consumers. Utilities participate through corporate families with numerous PJM affiliates. For example, Ohio Power Company is part of the AEP corporate family, which includes multiple transmission, generation, and energy affiliates. Ohio Edison is part of the FirstEnergy corporate family. Duke Energy Ohio participates alongside other Duke affiliates. At Standing Committees and Senior Task Forces, where affiliate voting is permitted, these corporate families can potentially exercise many multiple votes while OCC has one. That distinction is particularly important because the detailed work of designing PJM rules often occurs at Standing Committees and Senior Task Forces before proposals reach the Markets and Reliability Committee (MRC) or the Members Committee (MC). While the MRC and MC may be governed by weighted sector voting requirements, the same is not true of the other Standing Committees and Task Forces. This can permit supply-side or other commercial interests to advance proposals without meaningful support from those who represent the consumers responsible for paying the resulting costs. That is fundamentally unfair. By the time proposals reach sector-weighted voting at the MRC and MC, it may be too late for consumer interests to meaningfully shape their design. Those interests may instead be left primarily with the ability to vote no on a proposal developed without their meaningful participation.
PDF page 16
14
FERC should encourage PJM to address this structural problem by extending sector- weighted voting, or comparable protections against affiliate-vote dominance, to Standing Committees and Senior Task Forces. Doing so would not silence any sector but rather would levelize the playing field for all stakeholder interests. It would encourage those submitting proposals to attract support across sectors earlier in the development process, when compromise can meaningfully affect their substance.
C. PJM voting should be transparent.
PJM should also disclose how individual member companies vote throughout the stakeholder process. Entities participating in PJM are voting on matters that affect more than their private commercial interests. They participate in developing rules affecting the reliability and cost of electricity service for approximately 67 million consumers.
Aggregate voting results provide insufficient accountability and can impede consensus- building. When a proposal narrowly fails, stakeholders should be able to identify the concerns preventing agreement and determine whether modifications could produce broader support. Transparency would also eliminate inconsistent disclosure obligations. Some utilities may already be required under state law to disclose PJM votes, while others are not. In contrast, public consumer advocates operate under public-records requirements. PJM-wide disclosure would establish a uniform standard that could easily be followed. Individual member votes should be publicly available at all material levels of the stakeholder process.
V. PJM BOARD INDEPENDENCE
PJM Board reform should increase public accountability while preserving board independence.
Any expansion of Board authority should be accompanied by greater Board
accountability.
PDF page 17
15
First, the Board’s required expertise should include meaningful experience with state regulation and consumer interests. PJM should include Board members who understand how wholesale market and transmission decisions ultimately appear on consumers’ retail electric bills.
Second, the process for selecting Board members should include greater state and consumer participation. The Nominating Committee should include representation designated by states as well as a statutory consumer advocate. Consumers should not depend upon occasional rotation within the End-Use Customer Sector for representation in selecting the individuals who ultimately exercise enormous authority over costs paid by those consumers. Third, Board decision-making should be substantially more transparent. Board votes on significant matters should be disclosed, and the Board should provide meaningful explanations for consequential decisions. Appropriate portions of Board meetings should also be open or otherwise made available to stakeholders and the public.
Transparency should not, however, come at the expense of independence. FERC should not relax appropriate restrictions on private communication between individual Board members and interested market participants. Greater transparency in Board deliberations provides a better means of increasing accountability than expanding private access.
VI. SECTION 205 FILING RIGHTS
FERC should not expand the PJM Board’s Section 205 authority without corresponding consumer and state safeguards.
The Commission should proceed cautiously before expanding or limiting the PJM Board’s unilateral filing authority under section 205 of the Federal Power Act. The relevant question is not simply whether other RTO boards possess broader section 205 authority. The question is whether expanding or limiting authority to PJM’s Board, under PJM’s existing
PDF page 18
16
governance structure, would produce decision-making that better protects consumers and results in just and reasonable rates.
More importantly the Commission has already spoken on the concept of limiting the Board’s existing filing rights related to transmission planning. In Docket Nos. ER24-2336, ER24-2338 and EL24-119, the Commission rejected efforts by the Transmission Owners to provide themselves with extensive, unilateral veto rights with respect to the transmission planning process. In those cases, PJM and the Transmission Owners proposed to move the planning process rules from the PJM Operating Agreement to the PJM Open Access Transmission Tariff and the Consolidated Transmission Owners’ Agreement. FERC found that such action would provide the Transmission Owners with undue influence over the transmission planning process.8 The D.C. Circuit Court of Appeals affirmed the Commission’s rulings just two months ago.9 There is no reason to revisit these very recent decisions.
At a minimum, PJM’s governing documents should first be revised to establish affordability and the public interest as express Board responsibilities. States and consumer advocates should also receive meaningful “jump ball” filing rights that allow a sufficiently broad consensus to present an alternative proposal to the Commission.
Providing FERC with competing proposals would not displace the Commission’s
ultimate responsibility to determine what is just and reasonable. Instead, it would ensure that the Commission hears a meaningful alternative from governmental entities responsible for protecting consumer interests.
8 PJM Interconnection, L.L.C., 189 FERC ¶ 61,181(2024), order denying reh’g, 192 FERC ¶ 61,051 (2025).9 PJM Transmission Owners v. FERC, No. 25-1064 (D.C. Cir. June 5, 2026) (per curiam).
PDF page 19
17
VII. CONCLUSION
The Commission should evaluate PJM governance reform from the perspective of the consumers whom the Federal Power Act ultimately protects. The fundamental problem is not simply whether authority resides with PJM’s Members Committee, its Board, or another institutional actor. The problem is whether PJM’s governance structure produces transparent, accountable, cost-conscious decisions consistent with just and reasonable rates. At the present time, PJM’s governance structure is not doing the job.
The reforms discussed in these OCC comments would not guarantee that every PJM decision produces the outcome preferred by consumers, states, market participants, or any other constituency. The reforms would, however, make it substantially more likely that decisions affecting tens of millions of consumers are made through a process that gives weight to affordability, provides meaningful public accountability, and supplies the Commission with the information and competing perspectives necessary to fulfill its responsibility under the Federal Power Act to protect consumers from unjust and unreasonable rates.
PDF page 20
18
Respectfully submitted,
/s/ Maureen R. Willis
Maureen R. Willis (0020847)
Ohio Consumers’ Counsel
Angela D. O’Brien (0097579)
Deputy Consumers’ Counsel
Office of the Ohio Consumers’ Counsel
65 East State Street, Suite 700
Columbus, Ohio 43215
Telephone: (614) 286-7549
angela.obrien@occ.ohio.gov
Denise C. Goulet
McCarter & English, LLP
1301 K Street, N.W.
Suite 1000 West
Washington, D.C. 20005
(202) 753-3400
dgoulet@mccarter.com
Special Counsel to the Ohio Office of the Attorney General for the Office of the Ohio Consumers’ Counsel
PDF page 21
19
CERTIFICATE OF SERVICE
I hereby certify that a copy of the foregoing Comments was served via electronic transmission upon all parties of record on the Commission’s official service list in this proceeding on this 21st day of August 2026.
/s/ Maureen R. Willis
Maureen R. Willis
Ohio Consumers’ Counsel
PDF page 22
ATTACHMENT A
Office of the Ohio Consumers’ Counsel Response to Commission Questions in Notice Requesting Post-Conference Comments
PJM Board Independence
Questions/Comments
Yes
No
1) Should Board members’ terms be extended to five or more years?
X
Comments: Longer terms for Board members could help ensure a more knowledgeable Board with a longer-term perspective that is less susceptible to stakeholder pressure. However, terms should not be too long to reduce accountability to Members (including consumer advocates) and make it more difficult to influence the Board when change is needed.
2) Should there be a maximum number of years that a Board member may serve (e.g., 10 years)?
X
Comments: While a longer term may promote Board independence and allow members to develop greater institutional knowledge, a single term greater than five years without the possibility of reelection would likely reduce accountability to Members and make the Board too insulated from Member feedback. Some opportunity for periodic reevaluation of Board performance better balances independence with accountability. Periodic refreshment in the board is a benefit.
3) Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region?
X
Comments: While Board members must act in the interests of the PJM region as a whole, residing within the region helps ensure they remain connected to the affordability and reliability concerns experienced by the consumers ultimately served by PJM. Regional familiarity strengthens understanding of consumer impacts and state policy.
4) Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?
X
Comments: The two-year cooling-off period helps preserve the Board’s independence by reducing conflicts of interest arising from recent employment with PJM Members. A cooling off period is required in Ohio when it comes to both the state consumer advocate and the PUCO commissioners.
5) Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders?
X
Attachment A
Page 1 of 5
PDF page 23
Questions/Comments
Yes
No
Comments: FERC should not relax appropriate restrictions on private communications between individual Board members and interested market participants. Greater transparency in Board deliberations provides a better means of increasing accountability than expanding private access.
6) In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?
X
Comments: To promote transparency, Board votes on significant matters should be disclosed, and the Board should provide meaningful explanations for consequential decisions.
7) In order to increase transparency, should some Board meetings be open or available to the public?
X
Comments: Appropriate portions of Board meetings should be open or otherwise made available to stakeholders and the public. The Board’s deliberations and decision-making should, whenever practicable, occur in meetings that are open to stakeholders and the public, with limited exceptions only where confidentiality is legally or commercially required.
8) Should PJM’s governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest? X
Comments: PJM should expressly recognize in governing documents its obligation to serve the public interest and consider affordability as well as reliability of service for consumers in the region.
9) Should state representatives have at least one voting member on the Nominating Committee?
X
Comments: States should have representation on the Nominating Committee. It promotes balanced governance and broader public accountability.
10) Should PJM adopt public performance metrics and tie management
compensation to their achievement?
X
Comments: Tying PJM management compensation to achievement and public performance metrics could result in PJM management focusing on reliability at all costs to the detriment of consumers who must pay high rates for transmission service. Energy markets and transmission planning should produce reliable service efficiently and at reasonable cost.
Attachment A
Page 2 of 5
PDF page 24
Section 205 Filing Rights
Questions/Comments
Yes
No
11) Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board?
X
Comments: The stakeholder process should not be reduced to one that is merely advisory. The stakeholder process should provide an important mechanism for ensuring that a broad range of perspectives, including those representing residential consumers- are meaningfully considered in decisions affecting reliability, markets, and costs. Before reducing the role of stakeholders, confidence is needed that stakeholder input is consistently reflected in decision-making and that departures from stakeholder recommendations are transparent and well explained. Having a meaningful stakeholder process promotes accountability, transparency, and better outcomes for consumers.
12) Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?
X
Comments: Expanding PJM’s section 205 filing rights without obtaining approval from two-thirds of the Members Committee could provide PJM or certain stakeholder sectors with too much power. As noted in OCC’s comments, in Docket Nos. ER24-2336, ER24-2338 and EL24-119, the Commission rejected efforts by the Transmission Owners to provide themselves with extensive, unilateral veto rights with respect to the transmission planning process. In those cases, PJM and the Transmission Owners proposed to move the planning process rules from the PJM Operating Agreement to the PJM Open Access Transmission Tariff and the Consolidated Transmission Owners’ Agreement. FERC found that such action would provide the Transmission Owners with undue influence over the transmission planning process. The D.C. Circuit Court of Appeals recently affirmed the Commission’s rulings.
13) Should PJM have section 205 filing rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?
X
Comments: Expanding PJM’s section 205 filing rights without obtaining approval from two-thirds of the Members Committee could provide PJM or certain stakeholder sectors with too much power. As noted in OCC’s comments, in Docket Nos. ER24-2336, ER24-2338 and EL24-119, the Commission rejected efforts by the Transmission Owners to provide themselves with extensive, unilateral veto rights with respect to the transmission planning process. In those cases, PJM and the Transmission Owners Attachment A
Page 3 of 5
PDF page 25
Questions/Comments
Yes
No
proposed to move the planning process rules from the PJM Operating Agreement to the PJM Open Access Transmission Tariff and the Consolidated Transmission Owners’ Agreement. FERC found that such action would provide the Transmission Owners with undue influence over the transmission planning process. The D.C. Circuit Court of Appeals recently affirmed the Commission’s rulings.
14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?
X
Comments: OPSI should receive meaningful jump-ball filing rights where a sufficiently broad consensus of states supports an alternative to a PJM proposal. While the Commission has provided for such filing rights in the context of cost allocation proposals for long-term regional transmission projects in Order No. 1920, no similar rights exist for the Order No. 1000 and Order No. 890 regional and local transmission planning processes. PJM should also be required to consult formally with OPSI before any major section 205 filings, including significant resource-adequacy and transmission planning and cost allocation filings. Consumer advocates should also receive meaningful “jump ball” filing rights that allow a sufficiently broad consensus to present an alternative proposal to the Commission.
15) Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?
X
Comments: Permitting the Members Committee to have “jump ball” filing rights over the PJM Board could result in improper influence by certain stakeholder sectors over resource adequacy, transmission planning and cost allocation filings.
Stakeholder Process
Questions/Comments
Yes
No
16) Should the approval threshold in the Members Committee be lowered from two-thirds sector-weighted voting?
Comments:
Attachment A
Page 4 of 5
PDF page 26
Questions/Comments
Yes
No
17) Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?
X
Comments: PJM’s current affiliate-voting rules at the lower-level committees unfairly dilute the consumer voice at the committees where proposals developed. As explained in OCC’s Comments, Consumer Advocates of the PJM states collectively have 14 total votes at the lower-level committees, accounting for only 1.3 percent of the vote.
State Participation
Questions/Comments
Yes
No
18) In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’ representatives?
X
Comments: OCC supports an additional state representative group in addition to OPSI provided there is no duplication of state efforts and no dilution of the consumer advocacy roles of members of the Consumer Advocates of the PJM States.
19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? X
Comments: Providing state representatives with an informational voting role in the PJM stakeholder process would improve transparency without altering stakeholder voting rights.
20) Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation? X
Comments: Requiring PJM to consult with OPSI in this manner would provide great transparency. In addition, this is required by FERC Order 1920-A.
Attachment A
Page 5 of 5
PDF page 27
65 E. State St., Suite 700 ⋅ Columbus, Ohio 43215 ⋅ 614-466-8574 ⋅ www.occ.ohio.gov Maureen Willis
Ohio Consumers’ Counsel
Cheryl Grossman
Board Chair
STAKEHOLDER COMMENTS AND INFORMATION REQUESTS OF THE OHIO
OFFICE OF THE CONSUMERS' COUNSEL
Regarding Supplemental Transmission Projects Presented at the July 7, 2026, PJM Transmission Expansion Advisory Committee Meeting
I. Introduction
The Ohio Office of the Consumers' Counsel (OCC) appreciates the opportunity to submit these Comments and Information Requests regarding the supplemental transmission projects presented by American Electric Power (AEP), FirstEnergy ATSI (ATSI), Duke Energy Ohio (DEOK), and AES Ohio (AES) at the July 7, 2026, meeting of the PJM Transmission Expansion Advisory Committee (TEAC).
OCC submits these comments in support of the purposes of PJM's M-3 Supplemental Project Process. As reflected in PJM Manual 14B, the Regional Transmission Expansion Planning Process is intended to promote transparency, facilitate meaningful stakeholder participation, and improve transmission planning through the early identification and evaluation of planning assumptions, transmission needs, proposed solutions, and local transmission plans. Transparency during the M-3 process benefits transmission owners, PJM, regulators, and consumers by promoting informed discussion regarding planning assumptions, project need, alternatives, and anticipated consumer impact. OCC’s comments are intended to further these objectives by requesting information necessary for stakeholders to meaningfully evaluate customer-driven supplemental transmission projects.
OCC supports prudent transmission investment necessary to maintain a reliable and resilient transmission system. At the same time, transmission investments are long-lived assets whose costs ultimately may be borne by consumers. Accordingly, transmission planning should remain transparent, data-driven, and consistent with the principle that costs should follow cost causation. These Comments and Information Requests are consistent with OCC's longstanding interest in ensuring that supplemental transmission projects are supported by transparent planning assumptions, demonstrated need, prudent engineering, and appropriate consumer protections. Nothing in these comments is intended to address the merits of any pending regulatory proceeding. Rather, OCC seeks to ensure that the project-specific record developed through the M-3 process is as complete and transparent as possible.
Attachment B
Page 1 of 14
PDF page 28
July 16, 2026
Page 2 of 13
65 E. State St., Suite 700 ⋅ Columbus, Ohio 43215 ⋅ 614-466-8574 ⋅ www.occ.ohio.gov
II. The Supplemental Transmission Projects
A. FirstEnergy ATSI – Need No. ATSI-2026-048
OCC appreciates FirstEnergy's presentation of Need No. ATSI-2026-048. Because this project is being presented during the Needs stage of the M-3 process, OCC's comments are directed to whether the identified operational issue has been sufficiently documented to support advancement to the Solutions phase.
Unlike the other Ohio presentations, ATSI's project is not customer driven. Rather, FirstEnergy identifies an operational limitation associated with maintenance outages on the Chamberlain- Harding 345-kV S-21 transmission line caused by terminal equipment limitations. To facilitate meaningful stakeholder review, OCC respectfully requests additional information regarding the following.:
1. The operational significance of the identified limitation, including how frequently the maintenance condition occurs and whether it has resulted in operational restrictions, congestion, or reliability concerns.
2. The applicable planning criteria supporting the identified need and whether the project is intended to address reliability, operational flexibility, asset management, or a combination of these objectives.
3. The expected operational benefits that would result from addressing the identified limitation.
4. As this project advances to the Solutions stage, the alternatives considered, including equipment replacement, operational measures, maintenance practices, and other lower-cost options before more extensive transmission facilities are proposed.
5. Estimated customer benefits and expected project costs once potential solutions are identified.
OCC appreciates that ATSI identified the specific operational issue prompting the project and encourages continued transparency as engineering alternatives are developed.
B. American Electric Power – Need No. AEP-2026-AP007
OCC appreciates AEP's presentation of Need No. AEP-2026-AP007. Because this project is at the Needs stage of the M-3 process, OCC's comments focus on whether AEP has adequately Attachment B
Page 2 of 14
PDF page 29
July 16, 2026
Page 3 of 13
65 E. State St., Suite 700 ⋅ Columbus, Ohio 43215 ⋅ 614-466-8574 ⋅ www.occ.ohio.gov demonstrated that a transmission need exists and whether sufficient information has been provided to allow stakeholders to meaningfully evaluate that need.
AEP's presentation identifies a request for 1,000 MW of new customer load in Boyd County, Kentucky, by the fourth quarter of 2028 as the basis for the identified transmission need. Because this project is in the Needs stage, OCC respectfully requests additional information regarding:
1. The planning assumptions supporting the projected 1,000 MW customer load.
2. Whether the requesting customer has executed a binding service agreement or achieved other significant development milestones.
3. Whether AEP evaluated scenarios in which the requested load is delayed, reduced, or does not materialize.
4. The specific transmission planning criteria, thermal limitations, voltage concerns, or other system conditions giving rise to the identified need.
5. Whether the identified need would continue to exist under more conservative customer load assumptions.
6. Whether transmission facilities located within Ohio are expected to be constructed or upgraded to accommodate service to the Kentucky customer and, if so, whether Ohio consumers may bear any portion of the resulting transmission costs.
7. Does PJM and/or the transmission owner have any information as to whether the prospective load interconnection customer has submitted similarly sized project proposals in other locations on that transmission owner’s system, or in other transmission zones.
8. Has PJM and/or the transmission owner conducted any analyses of the extent to which existing loads need the expansions being considered for the large load interconnection to serve their needs now or in the future. If so, please provide that information. Because this project appears to arise from a specific customer request rather than existing reliability concerns, OCC also requests an explanation of how future transmission investments associated with this need will be planned and funded consistent with cost-causation principles.
Attachment B
Page 3 of 14
PDF page 30
July 16, 2026
Page 4 of 13
65 E. State St., Suite 700 ⋅ Columbus, Ohio 43215 ⋅ 614-466-8574 ⋅ www.occ.ohio.gov
C. Duke Energy Ohio – Need No. DEOK-2026-004
OCC appreciates Duke Energy Ohio's presentation of Need No. DEOK-2026-004. Because this project is being presented during the Needs stage of the M-3 process, OCC's comments focus on whether Duke has adequately demonstrated the need for additional transmission facilities and provided sufficient information for stakeholders to evaluate that need.
Duke Energy Ohio's presentation indicates that a customer previously requesting approximately 500 MW of load near Trenton, Ohio, now plans to increase its requested service by an additional 300 MW beginning in 2028.
Accordingly, OCC requests additional information regarding:
1. The basis for the revised customer load forecast and what has changed since the prior need presentation.
2. Whether the additional load reflects expansion by the same customer or additional customer development.
3. The level of customer commitment supporting the revised forecast, including executed service agreements and development milestones.
4. The specific transmission planning criteria demonstrating the need for additional transmission facilities.
5. Whether the identified need remains under lower customer load assumptions.
6. Whether future transmission facilities can be developed in phases corresponding to demonstrated customer commitments.
7. Does PJM and/or the transmission owner have any information as to whether the prospective load interconnection customer has submitted similarly sized project proposals in other locations on that transmission owner’s system, or in other transmission zones.
8. Has PJM and/or the transmission owner conducted any analyses of the extent to which existing loads need the expansions being considered for the large load interconnection to serve their needs now or in the future. If so, please provide that information.
Attachment B
Page 4 of 14
PDF page 31
July 16, 2026
Page 5 of 13
65 E. State St., Suite 700 ⋅ Columbus, Ohio 43215 ⋅ 614-466-8574 ⋅ www.occ.ohio.gov Because the identified need appears to arise from the expansion of a specific customer request, OCC also requests an explanation of how resulting transmission investments will be planned and funded consistent with cost-causation principles and how existing residential consumers will be protected from costs attributable primarily to serving new large-load customers.
D. AES Ohio – Solution Presentations
OCC appreciates AES Ohio's presentation of proposed solutions for customer-driven transmission needs in the vicinity of the Fayette, Clinton, and Stuart substations. Because these projects are at the Solutions stage of the M-3 process, OCC's comments focus on whether the selected transmission facilities represent prudent, appropriately sized, and cost-effective solutions to the identified needs.
AES Ohio presented proposed transmission solutions associated with customer-driven projects in the Fayette, Clinton, and Stuart areas. These projects are supported by projected customer requests reaching approximately 1.5 GW near Fayette, 500 MW near Clinton, and 1.3 GW near Stuart. AES proposes approximately $589.8 million in transmission investment, including new 345-kV transmission lines, substation expansions, capacitor installations, and customer delivery facilities. Because these projects are in the Solutions stage, OCC respectfully requests additional information regarding:
1. The basis for concluding that the proposed facilities represent the most prudent and cost- effective solution to the identified needs.
2. The extent to which the projected customer demand is supported by executed service agreements or other significant development milestones.
3. Whether the proposed facilities have been appropriately sized based upon reasonably certain customer demand.
4. Whether portions of the proposed projects can be constructed in phases corresponding to demonstrated customer commitments.
5. The alternatives evaluated, including phased implementation, operational alternatives, equipment upgrades, and lower-cost transmission configurations.
Attachment B
Page 5 of 14
PDF page 32
July 16, 2026
Page 6 of 13
65 E. State St., Suite 700 ⋅ Columbus, Ohio 43215 ⋅ 614-466-8574 ⋅ www.occ.ohio.gov
6. Does PJM and/or the transmission owner have any information as to whether the prospective load interconnection customer has submitted similarly sized project proposals in other locations on that transmission owner’s system, or in other transmission zones.
7. Has PJM and/or the transmission owner conducted any analyses of the extent to which existing loads need the expansions being considered for the large load interconnection to serve their needs now or in the future. If so, please provide that information.
While AES identified several transmission alternatives for the Fayette and Clinton projects, OCC requests additional information regarding the comparative cost and performance of those alternatives.
For the Stuart project, AES identified "Alternatives: N/A." OCC requests an explanation of why no alternatives analysis was performed or presented.
Finally, because these projects appear to be undertaken primarily in response to customer requests, OCC requests an explanation of how resulting transmission investments will be funded in a manner consistent with cost-causation principles and how existing residential consumers will be protected from bearing costs attributable primarily to serving new large-load customers. AES’s presentation relies on aggregated "customer requests" measured in hundreds or thousands of megawatts. Yet we are not being provided with sufficient information to evaluate the likelihood that those requests will materialize. As customer-driven transmission investments become larger and more frequent, OCC encourages PJM and transmission owners to develop standardized reporting identifying the maturity of customer requests, the level of contractual commitment supporting forecasted load, and the assumptions used in evaluating forecast uncertainty. Such information is essential to meaningful stakeholder review and to protecting consumers from the costs of transmission investments that may ultimately prove unnecessary.
General Policy Discussion
The recent increase in requests for large-load service—including data centers, advanced manufacturing facilities, and other energy-intensive customers—is resulting in substantial transmission investment throughout Ohio. Meaningful stakeholder review depends upon understanding not only the magnitude of projected customer load but also the certainty supporting those forecasts.
Attachment B
Page 6 of 14
PDF page 33
July 16, 2026
Page 7 of 13
65 E. State St., Suite 700 ⋅ Columbus, Ohio 43215 ⋅ 614-466-8574 ⋅ www.occ.ohio.gov
1. The Need for Standardized Reporting
OCC encourages PJM and transmission owners to provide standardized reporting identifying: (1) projected load attributable to native load, ordinary growth, and large-load customers; (2) whether customer load is supported by executed service agreements or other binding commitments; (3) customer development milestones; (4) anticipated in-service schedules; (5) sensitivity analyses for delayed or cancelled projects; and (6) whether facilities can be phased as customer commitments mature.
2. The Need for Transparency
Customer-driven supplemental transmission projects differ in important respects from traditional reliability-driven transmission projects. Historically, many supplemental projects were developed to address aging infrastructure, equipment replacement, operational flexibility, or identified reliability violations based on existing system conditions. By contrast, customer-driven projects are often initiated in anticipation of substantial future load growth associated with one or more specific customers seeking new or expanded electric service. As a result, these projects frequently depend upon assumptions regarding the timing, magnitude, and certainty of future customer demand rather than existing system deficiencies. That distinction makes transparency regarding planning assumptions, customer commitments, forecast certainty, and project timing particularly important. Without sufficient information regarding those underlying assumptions, stakeholders cannot meaningfully evaluate whether the proposed transmission investment is appropriately timed, appropriately sized, or reasonably necessary to serve the anticipated customer load. The projects presented at the July 7, 2026 TEAC meeting illustrate this distinction. Three of the four Ohio projects were driven primarily by anticipated customer load growth, while one addressed an operational limitation on the existing transmission system. OCC's comments reflect those differences by applying a common set of planning principles while recognizing that the information necessary to evaluate customer-driven projects is not identical to that required for traditional reliability or operational projects.
3. The Value of Phased in Construction in Customer-Driven Transmission Planning As customer-driven supplemental transmission projects continue to increase in size and complexity, transmission owners should, where practical, evaluate whether proposed facilities can be developed in phases that correspond with demonstrated customer demand. Phased implementation is a well- established planning approach that allows infrastructure to be expanded as customer development progresses while maintaining the flexibility necessary to provide reliable electric service. Attachment B
Page 7 of 14
PDF page 34
July 16, 2026
Page 8 of 13
65 E. State St., Suite 700 ⋅ Columbus, Ohio 43215 ⋅ 614-466-8574 ⋅ www.occ.ohio.gov For projects driven by anticipated future load growth, phased construction may reduce the risk of premature investment if projected customer demand is delayed, reduced, or ultimately does not materialize. Rather than requiring the construction of facilities sized for the maximum projected load at the outset, phased implementation can allow transmission owners to provide service as customer commitments become more certain and system needs evolve. This approach can reduce the likelihood that consumers will bear the costs of transmission facilities that exceed what is reasonably necessary to serve actual demand.
Accordingly, OCC encourages transmission owners to discuss, as part of the M-3 process, whether phased implementation was considered during project development, the engineering and economic factors supporting the selected approach, and how the proposed construction schedule aligns with anticipated customer development. Providing this information will improve transparency, strengthen the planning record, and enhance stakeholder confidence that proposed investments are appropriately timed and appropriately sized for reasonably certain customer demand. Considering phased implementation where feasible does not delay necessary infrastructure or discourage economic development. Rather, it reflects prudent utility planning by aligning the pace of infrastructure investment with the pace of demonstrated customer demand, thereby reducing the potential for existing consumers to bear the costs of facilities constructed significantly in advance of need, or that may be excess capacity if the AI loads fail to show up as projected.
III. Federal Regulatory Context
The projects presented at this meeting arise during a period of significant evolution in federal transmission planning policy. The growth in AI load interconnection requests is driving the need for improved local and Supplemental Project transmission planning processes that account for the potential cost impact of these local projects. Although the Supplemental Projects presented through PJM’s M-3 process are not directly governed by the requirements of FERC Order No. 1920, the Commission’s recent actions reflect an increasing emphasis on transparent planning processes, meaningful stakeholder participation, cost-effective analyses, and well-supported planning records. In Order No. 1920, the Commission concluded that more forward-looking and transparent transmission planning is necessary to ensure that transmission investments remain just and reasonable over the long term. While that rule principally addresses regional transmission planning, the policy objectives it advances – including transparency, robust planning assumptions, and meaningful stakeholder engagement—are equally relevant to customer-driven supplemental transmission projects. Importantly, Order No. 890 required similar transparency, robust planning assumptions and meaningful stakeholder engagement in the local transmission planning process. In Attachment B
Page 8 of 14
PDF page 35
July 16, 2026
Page 9 of 13
65 E. State St., Suite 700 ⋅ Columbus, Ohio 43215 ⋅ 614-466-8574 ⋅ www.occ.ohio.gov PJM, Supplemental Projects are part of the local planning process and must be planned in a manner that encompasses these principles.
The PJM Attachment M-3 planning process for local transmission projects and Supplemental Projects embrace some, but not all of these principles. OCC recognizes that FERC accepted the current PJM Attachment M-3 local transmission planning process in 2020, but notes that FERC has more recently questioned whether that process is sufficient in its April 2022 Notice of Technical Conference in Docket No. AD22-8-000. That Notice states that:
The purpose of this conference is to explore measures to ensure sufficient
transparency into and cost effectiveness of local and regional transmission
planning decisions, including: (1) the role of cost management measures in
ensuring the cost-effective identification of local transmission needs (e.g., planning criteria) and solutions to address identified local transmission and regional reliability-related transmission needs; and (2) cost considerations and the processes through which transmission developers recover their costs to
ensure just and reasonable transmission rates.
It is this cost effectiveness obligation that is missing from the current PJM Attachment M-3 planning process.
Although FERC did not require changes to the local and Supplemental Project transmission planning process in Order No. 1920, it clearly left the door open for improvements in that process. In a move toward creating greater transparency around that process, FERC recently issued show- cause orders directing several public utility transmission providers, including PJM in Docket No. EL26-67-000, to explain why aspects of their local and Supplemental Project transmission planning processes remain just and reasonable under the Federal Power Act. OCC recognizes that the new show cause proceedings do not control the disposition of the projects presented here. However, these proceedings reflect FERC’s movement toward a broader regulatory focus on transparency, justification, cost-effectiveness and oversight of local and Supplemental Project transmission investments.
These show cause proceedings reinforce the importance of ensuring that local and Supplemental transmission projects are supported by demonstrated need, prudent engineering, transparent planning assumptions, project cost-effectiveness and a planning record sufficient to permit meaningful stakeholder review before significant investments are undertaken.
Attachment B
Page 9 of 14
PDF page 36
July 16, 2026
Page 10 of 13
65 E. State St., Suite 700 ⋅ Columbus, Ohio 43215 ⋅ 614-466-8574 ⋅ www.occ.ohio.gov
IV. Consumer Protection Principles
As supplemental transmission planning increasingly responds to requests from individual large-load customers rather than traditional reliability needs, several principles should guide the evaluation of proposed transmission investments.
First, transmission projects should be supported by a clearly demonstrated need based on objective and transparent planning analyses. Stakeholders should have sufficient information to understand the assumptions underlying projected customer demand, the degree of certainty associated with those forecasts, and the planning criteria giving rise to the identified need. Without this information, stakeholders cannot meaningfully evaluate whether proposed facilities are necessary or appropriately sized.
Second, transmission investments should reflect prudent utility planning. Proposed solutions should be supported by reasonable engineering analyses, consideration of feasible alternatives, and where appropriate, opportunities for phased implementation that correspond to demonstrated customer commitments. Particularly for projects involving substantial capital investment, prudent planning requires balancing the need to provide timely service to new consumers with the responsibility to avoid premature, unnecessary or potentially abandoned infrastructure investments that may ultimately be borne by existing consumers.
Third, transmission investments should be developed and implemented in a manner consistent with longstanding regulatory principle of cost causation. Consumers should have confidence that investments undertaken primarily to accommodate new large-load customers are planned and funded in a manner that appropriately assigns costs to those AI customers, rather than shifting those costs to existing residential and small business consumers.
Finally, meaningful stakeholder participation is essential to maintaining confidence in the transmission planning process. The M-3 process should provide an opportunity for stakeholders to review proposed transmission needs and solutions before significant investment decisions are finalized. That opportunity is meaningful only if stakeholders are provided sufficient information to understand the basis of proposed projects and if substantive stakeholder comments are thoughtfully considered as projects advances through the planning process.
These principles are not intended to impede or delay needed transmission investment. Rather, they are intended to ensure that customer driven transmission projects are supported by transparent planning assumptions, prudent engineering, meaningful stakeholder review, and appropriate consumer protections. As transmission planning continues to evolve in response to unprecedented large-load growth, adherence to these principles will strengthen confidence in the M-3 process and Attachment B
Page 10 of 14
PDF page 37
July 16, 2026
Page 11 of 13
65 E. State St., Suite 700 ⋅ Columbus, Ohio 43215 ⋅ 614-466-8574 ⋅ www.occ.ohio.gov help ensure that transmission investments are reliable, cost-effective, and fair to the consumers who ultimately fund the electric system.
V. Enhancing the M-3 Supplemental Project Process
OCC appreciates PJM's efforts to improve transparency and stakeholder engagement through the M-3 Supplemental Project Process. As supplemental transmission planning evolves to address unprecedented growth in customer-driven load, there are opportunities to further strengthen the process while preserving the flexibility transmission owners need to respond to emerging system needs.
OCC recommends that future customer-driven project presentations include additional information regarding the basis for projected load growth. Without disclosing confidential commercial information, transmission owners should identify the extent to which projected customer demand is supported by executed service agreements, meaningful development milestones, or other objective indicators demonstrating the likelihood that the projected load will materialize. Providing stakeholders with a better understanding of forecast certainty would improve confidence that proposed transmission investments are appropriately timed and sized.
OCC encourages transmission owners to more fully discuss alternatives considered during project development. For projects presented at the Solutions stage, stakeholders should understand not only the preferred solution but also the principal alternatives evaluated, the reasons those alternatives were not selected, and whether phased implementation, equipment upgrades, operational changes, or other lower-cost options were considered. Such information would improve transparency and strengthen stakeholder confidence that the selected solution represents the most prudent investment. OCC recommends that PJM encourage transmission owners to address substantive stakeholder comments as projects advance through subsequent stages of the M-3 process. OCC is not suggesting that transmission owners be required to provide formal written responses to every comment. However, a brief discussion during subsequent TEAC presentations explaining whether significant stakeholder concerns were considered and, where appropriate, how they were addressed would strengthen the planning record and improve stakeholder confidence in the process. Finally, OCC encourages continued dialogue among PJM, transmission owners, states, consumer advocates, and other stakeholders regarding the evolution of supplemental transmission planning. Customer-driven transmission investment represents a significant and growing component of transmission development throughout the PJM region. As planning practices continue to evolve, regular stakeholder discussions regarding transparency, planning assumptions, customer Attachment B
Page 11 of 14
PDF page 38
July 16, 2026
Page 12 of 13
65 E. State St., Suite 700 ⋅ Columbus, Ohio 43215 ⋅ 614-466-8574 ⋅ www.occ.ohio.gov commitments, and cost responsibility will help ensure that the M-3 process continues to provide meaningful opportunities for stakeholder participation while supporting timely, reliable, and cost- effective transmission planning.
VI. Looking Forward
The comments submitted herein are intended not only to address the specific supplemental transmission projects presented at the July 7, 2026 TEAC meeting, but also to contribute to the continued evolution of a transparent, well-supported, and consumer-focused supplemental transmission planning process.
OCC recognizes that the electric industry is experiencing unprecedented changes driven by rapid load growth, technological advancement, and increasing demand for electric service from data centers, advanced manufacturing facilities, and other large energy users. Transmission owners and PJM face the significant challenge of planning for this growth while maintaining system reliability and providing timely service to new customers.
At the same time, these changing conditions reinforce—not diminish—the importance of prudent planning, transparency, and meaningful stakeholder participation. Customer-driven supplemental transmission projects increasingly involve investments measured in billions of dollars and infrastructure that may remain in service for decades. Such investments warrant planning assumptions and project development processes that provide stakeholders with sufficient information to understand the basis for the proposed investment and evaluate whether it is appropriately timed, appropriately sized, and consistent with sound utility planning practices. The M-3 Supplemental Project Process can provide an important opportunity for stakeholders to contribute constructively to transmission planning before significant investment decisions are finalized. The effectiveness of that process, however, depends upon stakeholders receiving sufficient information to evaluate identified transmission needs, proposed solutions, and the assumptions supporting those decisions.
The OCC supports responsible transmission investment that maintains reliability, accommodates appropriate economic development, and protects consumers from unnecessary costs. Increased transparency and continued stakeholder engagement will strengthen confidence in the supplemental planning process and improve the quality of transmission planning decisions for the benefit of all stakeholders.
Attachment B
Page 12 of 14
PDF page 39
July 16, 2026
Page 13 of 13
65 E. State St., Suite 700 ⋅ Columbus, Ohio 43215 ⋅ 614-466-8574 ⋅ www.occ.ohio.gov OCC appreciates PJM's continued commitment to stakeholder engagement and looks forward to continued participation in the M-3 Supplemental Project Process as transmission planning continues to evolve.
VII. Conclusion
OCC appreciates the opportunity to submit these Comments regarding the supplemental transmission projects presented at the July 7, 2026 TEAC meeting. The Office recognizes the importance of timely transmission planning and supports investments that are necessary to maintain reliable electric service and accommodate responsible economic growth.
The observations and recommendations contained in these comments are intended to support the objectives of the M-3 Supplemental Project Process by encouraging greater transparency, strengthening the planning record, and facilitating informed stakeholder participation before significant transmission investments advance through the planning process.
Accordingly, OCC respectfully requests that PJM include these comments in the planning record for the referenced projects and encourage the applicable transmission owners to address the issues and requests for information raised here during the next stage of the M-3 process. Doing so will enhance stakeholder confidence in the planning process and promote more informed transmission planning decisions.
Respectfully submitted,
Maureen Willis
Ohio Consumers' Counsel
Office of the Ohio Consumers' Counsel
Attachment B
Page 13 of 14
PDF page 40
65 E. State St., Suite 700 ⋅ Columbus, Ohio 43215 ⋅ 614-466-8574 ⋅ www.occ.ohio.gov Maureen Willis
Ohio Consumers’ Counsel
Cheryl Grossman
Board Chair
FOLLOW UP TO STAKEHOLDER COMMENTS AND INFORMATION REQUESTS OF
THE OHIO OFFICE OF THE CONSUMERS' COUNSEL
Regarding Supplemental Transmission Projects Presented at the July 7, 2026, PJM
Transmission Expansion Advisory Committee Meeting
Request for Responses to Stakeholder Questions Regarding Ohio Supplemental Projects At the Needs and Solutions meeting held last month, the Office of the Ohio Consumers' Counsel ("OCC") submitted several questions regarding proposed Ohio supplemental transmission projects. To date, those questions have not been addressed.
OCC respectfully requests that the applicable Transmission Owners provide written responses to the outstanding questions before these projects proceed further in the planning process. The questions concern matters central to evaluating the proposed projects, including the basis for the identified need, underlying load forecast assumptions, customer commitments, consideration of alternatives, project scope, timing, and expected consumer cost impacts.
Providing responses will promote a complete and transparent planning record and facilitate meaningful stakeholder participation in PJM's planning process. Because the costs of supplemental transmission projects are ultimately borne by electricity consumers, stakeholders should have access to the information necessary to understand and evaluate the justification for the proposed investments.
OCC notes that this request is separate from, and is not intended to address the merits of, any pending regulatory proceeding. However, the absence of responses to stakeholder questions underscores the importance of transparency and a well-developed record for supplemental transmission projects. Written responses will help ensure that stakeholders and decision-makers have information to assess whether the proposed projects represent prudent, cost-effective solutions to the identified system needs. Accordingly, OCC requests that the outstanding questions and the corresponding written responses be included in the planning record prior to further consideration of these projects.
Respectfully submitted,